153
CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE RISK INDICATOR FOR RENEWABLE ENERGY PROJECTS SCHOOL OF ENGINEERING ADVANCED MECHANICAL ENGINEERING MSc Academic Year: 2013 - 2014 Supervisor: Dr Athanasios Kolios June 2014

CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

CRANFIELD UNIVERSITY

THOMAS BRINDLEY

SINGLE SCORE RISK INDICATOR FOR RENEWABLE ENERGY PROJECTS

SCHOOL OF ENGINEERING ADVANCED MECHANICAL ENGINEERING

MSc Academic Year: 2013 - 2014

Supervisor: Dr Athanasios Kolios June 2014

Page 2: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …
Page 3: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

CRANFIELD UNIVERSITY

School of Engineering Advanced Mechanical Engineering

MSc

Academic Year 2013 - 2014

THOMAS BRINDLEY

Single Score Risk Indicator for Renewable Energy Projects

Supervisor: Dr Athanasios Kolios

June 2014

This thesis is submitted in partial fulfilment of the requirements for the degree of Advanced Mechanical Engineering

© Cranfield University 2014. All rights reserved. No part of this publication may be reproduced without the written permission of the

copyright owner.

Page 4: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …
Page 5: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

i

ABSTRACT

Single score risk indicators will enable various renewable energy projects to be

simultaneously evaluated with the aim of selecting projects with minimum risk

for further development. This thesis explores a number of different multi-criteria

decision making analysis methods for optimum allocation of risk resources.

A comprehensive risk register for the offshore renewable wind energy sector is

performed using failure mode and effects analysis. These risks are separated

by project phase and categorised using PESTLE analysis.

A Fuzzy TOPSIS program is generated to optimise a selection of 18 risks

chosen to be ranked against 9 engineering criteria. 5 Decision makers with

backgrounds in management, risk and offshore engineering provide linguistic

responses to the risk matrix.

Keywords: Fuzzy TOPSIS, FMECA, MCDM, Risk Analysis, PESTLE

Page 6: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …
Page 7: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

iii

ACKNOWLEDGEMENTS

I would like to thank Willis Insurance and Dr Athanasios Kolios for their

guidance in writing this report.

I would also like to thank my colleagues who have provided support throughout

this thesis and academic year.

Page 8: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

iv

TABLE OF CONTENTS

ABSTRACT ......................................................................................................... i ACKNOWLEDGEMENTS................................................................................... iii LIST OF FIGURES ............................................................................................. vi LIST OF TABLES ............................................................................................... vi LIST OF EQUATIONS ....................................................................................... vii GLOSSARY ...................................................................................................... viii 1 INTRODUCTION ......................................................................................... 1

1.1 Background ........................................................................................... 1

1.2 Motivation .............................................................................................. 1 1.3 Aims and Objectives.............................................................................. 1 1.4 Thesis Structure .................................................................................... 2

1.5 Limitations ............................................................................................. 4 2 LITERATURE REVIEW – Sections 1- 4 ...................................................... 4

2.1 Section 1 - Stakeholders ....................................................................... 4 2.1.1 What are stakeholders? .................................................................. 4

2.1.2 Stakeholder PESTLE Analysis........................................................ 5 2.2 Decision Makers .................................................................................. 13

2.2.1 What are Decision makers? .......................................................... 13 2.2.2 Expert specialities utilised ............................................................. 13

2.3 Section 2 - Alternatives ....................................................................... 13

2.3.1 What are Alternatives? ................................................................. 14

2.3.2 Alternatives PESTLE Analysis ...................................................... 14 2.3.3 Alternatives selected for the risk matrix ........................................ 38

2.4 Criteria ................................................................................................. 41 2.4.1 What are Criteria? ......................................................................... 41 2.4.2 Criteria Identification ..................................................................... 41 2.4.3 Risk Matrix .................................................................................... 44

2.5 Section 3 - MCDA Selection ................................................................ 46 2.5.1 AHP .............................................................................................. 46

2.5.2 MAFMA ......................................................................................... 48 2.5.3 FMEA ............................................................................................ 54 2.5.4 Fuzzy Logic Methods .................................................................... 56

2.5.5 TOPSIS ........................................................................................ 57 2.5.6 MCDA Evaluation ......................................................................... 60

2.6 Section 4 – Preference Elicitation ....................................................... 60 3 Methodology – Section 5 ........................................................................... 63

3.1 Theory ................................................................................................. 63 3.1.1 Fuzzy TOPSIS method ................................................................. 63

3.2 Computation ........................................................................................ 66 3.2.1 User Input ..................................................................................... 66 3.2.2 Calculations .................................................................................. 67

3.2.3 Outputs ......................................................................................... 69 3.2.4 Obtaining results ........................................................................... 69 3.2.5 Questionnaire ............................................................................... 69

3.3 Validation and verification ................................................................... 70

Page 9: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

v

3.3.1 Case Study 1 ................................................................................ 70

3.3.2 Case Study 2 ................................................................................ 71 4 Results ...................................................................................................... 74

4.1 Fuzzy TOPSIS output with closeness coefficient ................................ 74 5 Sensitivity analysis – Section 6 ................................................................. 76

5.1 Weight stability Intervals ...................................................................... 76

5.1.1 Scenario 1 – Safety Conscious ..................................................... 76 5.1.2 Scenario 2 – Eco-Environmental .................................................. 78 5.1.3 Scenario 3 – Socio-economic ....................................................... 79 5.1.4 Scenario 4 - Engineering Longevity .............................................. 81

5.2 Sensitivity in alternative ratings ........................................................... 82

5.2.1 Individual change .......................................................................... 83 5.2.2 Group change - Cost criteria ......................................................... 84

5.2.3 Group change - Benefit criteria ..................................................... 86 5.2.4 Group change - Solution ............................................................... 88

6 Analysis and Discussion............................................................................ 89 6.1 Analysis ............................................................................................... 89

6.1.1 Program structure ......................................................................... 89 6.1.2 Decision maker Responses .......................................................... 89

6.2 Discussion ........................................................................................... 92 6.2.1 General ......................................................................................... 92 6.2.2 Program ........................................................................................ 93

7 Conclusion – Section 7.............................................................................. 95

7.1 Further Work ....................................................................................... 96 REFERENCES ................................................................................................. 97 APPENDICES ................................................................................................ 100

Appendix A Literature Review ................................................................. 100 Appendix B Methodology ......................................................................... 105 Appendix C Results ................................................................................. 121

Appendix D Digital Information ................................................................ 139

Page 10: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

vi

LIST OF FIGURES

Figure 1-1 ........................................................................................................... 2 Figure 2-1 ......................................................................................................... 10 Figure 2-2 ......................................................................................................... 17 Figure 2-3 ......................................................................................................... 49

Figure 6-1 ......................................................................................................... 92 Figure 7-1 ....................................................................................................... 101 Figure 7-2 ....................................................................................................... 106 Figure 7-3 ....................................................................................................... 107

Figure 7-4 ....................................................................................................... 108 Figure 7-5 ....................................................................................................... 108 Figure 7-6 ....................................................................................................... 109

Figure 7-7 ....................................................................................................... 109 Figure 7-8 ....................................................................................................... 110 Figure 7-9 ....................................................................................................... 110 Figure 7-10 ..................................................................................................... 111

Figure 7-11 ..................................................................................................... 112 Figure 7-12 ..................................................................................................... 113

Figure 7-13 ..................................................................................................... 114 Figure 7-14 ..................................................................................................... 115

LIST OF TABLES

Table 2-1 .......................................................................................................... 12 Table 2-2 .......................................................................................................... 16 Table 2-3 .......................................................................................................... 45

Table 2-4 .......................................................................................................... 48 Table 2-5 .......................................................................................................... 56

Table 3-1 .......................................................................................................... 70 Table 3-2 .......................................................................................................... 71

Table 3-3 .......................................................................................................... 70 Table 3-4 .......................................................................................................... 71 Table 3-5 .......................................................................................................... 71 Table 3-6 .......................................................................................................... 71 Table 3-7 .......................................................................................................... 71

Table 3-8 .......................................................................................................... 72 Table 3-9 .......................................................................................................... 72 Table 3-10 ........................................................................................................ 72 Table 3-11 ........................................................................................................ 72 Table 3-12 ........................................................................................................ 72

Table 3-13 ........................................................................................................ 73

Table 3-14 ........................................................................................................ 73

Page 11: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

vii

Table 3-15 ........................................................................................................ 73

Table 3-16 ........................................................................................................ 73 Table 3-17 ........................................................................................................ 73 Table 3-18 ........................................................................................................ 73 Table 4-1 .......................................................................................................... 74 Table 4-2 .......................................................................................................... 75

Table 5-1 .......................................................................................................... 78 Table 5-2 .......................................................................................................... 79 Table 5-3 .......................................................................................................... 80 Table 5-4 .......................................................................................................... 82 Table 5-5 .......................................................................................................... 84

Table 5-6 .......................................................................................................... 86 Table 5-7 .......................................................................................................... 87

Table 7-1 ........................................................................................................ 122 Table 7-2 ........................................................................................................ 123 Table 7-3 ........................................................................................................ 125 Table 7-4 ........................................................................................................ 126

Table 7-5 ........................................................................................................ 129 Table 7-6 ........................................................................................................ 130

Table 7-7 ........................................................................................................ 133 Table 7-8 ........................................................................................................ 134 Table 7-9 ........................................................................................................ 137

Table 4-10 ...................................................................................................... 138

LIST OF EQUATIONS

Equation 2-8 ..................................................................................................... 55

Equation 2-1 ..................................................................................................... 58 Equation 2-2 ..................................................................................................... 58

Equation 2-3 ..................................................................................................... 58

Equation 2-4 ..................................................................................................... 58

Equation 2-5 ..................................................................................................... 59 Equation 2-6 ..................................................................................................... 59 Equation 2-7 ..................................................................................................... 59 Equation 3-1 ..................................................................................................... 63 Equation 3-2 ..................................................................................................... 64

Equation 3-3 ..................................................................................................... 64 Equation 3-4 ..................................................................................................... 64 Equation 3-5 ..................................................................................................... 65 Equation 3-6 ..................................................................................................... 65 Equation 3-7 ..................................................................................................... 65

Equation 3-8 ..................................................................................................... 65

Page 12: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

viii

GLOSSARY

MCDM Multi-criteria Decision Makers

LCOE Levelized Cost of Energy

FMEA/ PC-FMEA/ LC-FMEA Failure Mode and Effects Analysis/ Priority cost FMEA/ Life Cost FMEA

EU European Union

PESTLE Political, Economic, Social, Legal and Environmental

MCDA Multi-criteria decision analysis

GIB Green Investment Bank

RES Renewable Energy Sector

OWF Offshore wind farm

DECC Department of Energy and Climate Change

HAWT Horizontal Axis Wind Turbine

VAWT Vertical Axis Wind Turbine

ROI Return on Investment

IMF International Monitory Fund

CO2 Carbon Dioxide

GHG Green House Gases

MW/ GW Mega Watts/ Giga Watts

R&D Research and Development

RE Renewable Energy

NREL National Renewable Energy Laboratory

NERC National Environmental Research Council

CAPEX Capital Expenditure

OPEX Operational Expenditure

FEED Front End Engineering Design

ALARP As Low as Reasonably Practical

CI Consistency Index

Page 13: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

ix

AHP/ FAHP Analytic Hierarchal Process/ Fuzzy Analytic hierarchal process

TOPSIS Technique for Order Preference subject to Similarity to Ideal Solution

RPN Risk Prioritisation Number

O S D Occurrence, severity, detection

DM Decision Maker

MAFMA Multi-Attribute Failure Mode Analysis

MTTF Mean Time To Failure

MTBF Mean Time Between Failure

PIS/ FPIS Positive Idea Solution Fuzzy PIS

NIS/ FNIS Negative Idea Solution Fuzzy NIS

CRTF Cost reduction taskforce

MAUT

Multi-attribute Utility Theory

DSS

Decision support system

Page 14: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …
Page 15: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

1

1 INTRODUCTION

1.1 Background

Risk analysis is used in industry as method of balancing the predicted

profitability with the risk of investment. The evaluation method characterises the

costs and problems likely encountered within a project and compares with the

probability of success.

One subject area used for the evaluation of projects is a field call multi-criteria

decision making analysis (MCDM). This topic comprises of a range of

optimisation methods for risk and criteria.

1.2 Motivation

Renewable energy has become more popular in the wake of international

mandates to reduce carbon dioxide emissions in the EU. A number of varying

designs and intended locations have led to the requirements for the use of a

MCDM analysis to evaluate a number of different designs for funding further

development.

1.3 Aims and Objectives

This project aims to identify new criteria to be used in conjunction with current

FMECA methodology for evaluating project risks and failure modes. This is then

applied to a MCDM analysis optimisation method ranking the failure modes to

optimise resource allocation. Risk ranking will then be used to create a single

metric that can be used to evaluate the predicted success of an offshore

renewable energy project.

A risk register is required to evaluate the extensive range of risks throughout the

project (separated by phase).

Page 16: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

2

1.4 Thesis Structure

Figure 1-1 shows the structure of the thesis, separated into seven sections.

Figure 1-1

[1]

The offshore wind renewable energy sector will be used for the implementation

of the selected MCDA method. ‘Regional data’ and ‘other’ from Figure 1-1 have

Page 17: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

3

been combined to form a PESTLE analysis which will be used to evaluate the

second and third tier in this design methodology. Selection of MCDA method

will include a review of current techniques utilised in the energy sector

(including where appropriate worked examples illustrating the methodology).

Introduction

Literature review

Section 1:

Stakeholders

Decision Makers

Section 2:

Alternatives

Criteria

Section 3:

Selection of Multi-criteria decision analysis Method

Section 4:

Preference Elicitation

Methodology

Results

Section 5:

Model Application

Sensitivity Analysis

Section 6:

Weight Stability Intervals

Sensitivity In Alternative Ratings

Page 18: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

4

Analysis and Discussion

Conclusion and Further Work

Section 7:

Consensus

Proposal for Further Work

References

Appendices

1.5 Limitations

The project is only concerned with the offshore wind energy sector. Examples of

offshore risks are utilised to prove the validity of the proposed methodology

(examples from industry are not considered in the evaluation). The project will

not involve any dynamic study of risk.

2 LITERATURE REVIEW – Sections 1- 4

2.1 Section 1 - Stakeholders

2.1.1 What are stakeholders?

A stakeholder is a person, group or organisation with a vested interest in an

organisation.

One of the key principles in stakeholder identification is the premise of

inequality, their influence and priorities greatly impact their contribution (or

hindrance) to a project. Offshore wind energy has a large variety of

stakeholders with varying agendas. The stakeholder analysis is performed from

the viewpoint of the organisation implementing change.

Page 19: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

5

Since stakeholders are not equal, each of the stakeholders must be analysed

with respect to their position on the project (goal) and their impact influence.

The stakeholders have a large range of criteria objectives which requires a

multi-criteria analysis to be carried out within each sector. The comprehensive

PESTLE analysis (Political, Economic, Social, Technological, and Legal and

Environmental factors) provides a framework to categorise stakeholders thus

enabling multi-criteria analysis.

Stakeholders exist for each of these headings; investors, legislators,

environmentalists and engineers etc. The pestle analysis is used to establish a

framework for risk management with organisations following BS ISO

31000:2009 (section 4.3.1 part a) [2]. Sections 4.3.6 and 4.3.7 discus risk

consolidation which involves categorising numerous sources of risk into a single

risk measure (risk evaluation 5.4.4).

Section 4.3.7 relates to external stakeholders, which are likely to be the

shareholders and board members who would have the final decision for funding

projects, this is the area this report will investigate how a single risk indicator

can be used to expedite informed decision making.

2.1.2 Stakeholder PESTLE Analysis

2.1.2.1 Political

Arguably the largest stakeholder in the production of offshore wind energy is the

UK government, who pledged to make Britain a world leader in offshore

renewable energy ahead of the EU directive for renewable energy. Other

member states of the EU are also stakeholders for the offshore wind industry,

due to attempts to diversify sources of renewable energy.

The Kyoto protocol binds countries in the UN (an international stakeholder) to

meeting targets for the reduction of greenhouse emissions by 2020, Article 2 of

the Kyoto Protocol to the United Nations Framework Convention on Climate

Page 20: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

6

Change states that countries should promote the development and use of novel

forms of renewable energy [3].

The crown estate owns a majority of land within 12 miles of the British coast

and as such offshore installations within this area must with the crown estate

regulations and specifications. This enables the crown estate to influence

decisions in the operation of all wind energy projects operating within their

territory.

The government backed scheme for the Green Investment Bank (GIB) has

committed £461million to two of Britain’s largest wind farms (31st March 2014)

[4]. Government commitment to the development of the offshore energy sector

is critical for the industry to receive commercial funding; otherwise the high

CAPEX required to enter the market would lead to lower competitors, a high

LCOE, resulting in a low profit margin. Once the infrastructure is in place

offshore energy will become more economically viable. The coalition

government has pledged to work on this in 2010 [5].

The current economic climate has influenced the government’s position on

funding allocated to the RES, a reduction of 10% - £400m from the annual

budget was approved by the DECC and HM treasury in May 2013 [6]. The

national debt is held by the IMF which is an international organisation to

underwrite the risk of the British economy. The IMF exercises control over a

nation’s expenditure, recommending courses of action and so is an indirect

quasi-Political/ Economical stakeholder in Renewable energy.

The high capital expenditure for the development of offshore wind farms

requires government subsidies to lower the LCOE. Offshore wind is much more

reliable (than onshore) and is comprised of 3 mainstream designs; HAWT,

VAWT and Helical VAWT. The numbers of industrial stakeholders for these

designs vary, but the most widely accepted design is the HAWT.

2.1.2.1.1 Local government involved with offshore renewable energy

Page 21: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

7

Operational OWF sites; Cumbria, Morray Firth, Northumberland, Merseyside,

Suffolf, Essex, Kent, Lincolnshire, Denbighshire, Conwy, Norfolk, North

Yorkshire, Dumfries and Galloway.

Commissioned OWF sites; East Anglia, Teesside and the Irish sea (multiple

currently undefined councils).

Figure 2-1 and Table 2-1 contain some key political stakeholders identified by

George Read (2013) [7] and ‘Best practice guidelines for offshore consultancy’

[8] correspondingly.

2.1.2.2 Economic

Economics stakeholders mostly consist of government funding agencies, banks

and insurance agencies. An insurance broker underwrites risks involved with

offshore wind energy and so require in depth knowledge of the risk environment

in order to manage financial implications. Willis Insurance is a significant

stakeholder in the renewable energy sector and was the third largest insurance

broker in the world when measured by revenues in 2013 [9].

Commercial banks are concerned with the return on investment (ROI) of the

industrial sectors they make loans to. High risks to reward industries are not

usually permitted loans or if they are, they have high interest rates applied to

offset the risk of company bankruptcy.

The green investment bank was set up to fund emerging technology to reduce

emissions from Britain in order to keep to the EU environmental initiative to cut

the CO2 production by 34% by 2020. Another initiative by the GIB is ‘15% of all

energy consumed generated from green sources by 2020’, the bank has a total

of £3.8bn to invest with 80% priority to accomplishing its key objectives [10].

There are a few evaluation criteria that all offshore wind projects are required to

meet in order to secure funding from the GIB, these are;

- Creating a reduction in GHG emissions

- Improving the efficiency of renewable energy capture.

Page 22: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

8

- To protect or improve the natural environment.

- To protect or encourage biodiversity.

- Promotion of environmental sustainability – for example creating an

offshore electrical grid [10].

Offshore technology must be economically competitive with the current

technology in the market to be fully accepted by the consumer. The bottom line

for the average consumer is the price of electricity and so the consumer will be

only interested in a low cost alternative electrical generation. The overall

financial power the consumers have on the implementation of renewable energy

means the consumer is a stakeholder in their own right. Some companies have

approached this issue with surveys to find out the social (and hence financial

intention) response to developing the renewable energy sector.

The high LCOE for the offshore wind sector has been recognised by the DECC

on the renewable ‘roadmap’, they have responded with the creation of the

offshore wind cost reduction taskforce (CRTF) to highlight the actions required

to reduce cost down to £100/ MWh by the 2020 deadline. The taskforce was

directed by the RenewableUK Chairman: Andrew Jamieson, and found that the

target was attainable if 28 changes were made to the sector [11].

Figure 2-1 contains some key economical stakeholders identified by George

Read (2013) [7].

2.1.2.3 Social

National and international initiatives have seen increasing support for 'low

carbon' technologies. Since global warming and the effects of emissions have

been widely publicised, there has been an increase in the desire for recycled or

‘Green products’. This intention extends beyond the food industry and is starting

to influence a social demand for sustainable energy production.

Environmentalist organisations are examples of social organisations that are

stakeholders in offshore RE. Recreational clubs and societies that operate on or

near to proposed OWF sites are also stakeholders.

Page 23: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

9

Onshore and offshore wind turbines have faced opposition from the ‘Not in My

Back Yard’ - NIMBY group with reasons ranging from damaging the aesthetics

of the area, to the disruption of the architecture of the area. Their potential for

the disruption of development requires them to be included in the stakeholder

analysis.

Figure 2-1 and Table 2-1 both contain social stakeholders identified by George

Read (2013) [7] and ‘Best practice guidelines for offshore consultancy’ [8]

respectively.

2.1.2.4 Technological

The technological stakeholders in offshore wind are composed of both

regulating bodies and technology providers in the subject field. A list of

operators, developers and manufacturers are shown below.

Development of technology

UK Technology: VESTAS, REpower, Siemans.

Irish Technology/ emerging companies: GE Wind Energy.

Manufacture

The Leshy Energy, Scottish and Southern, E.ON Renewables, DONG Energy,

SSE Renewables, Vattenfall, Centrica, Siemans, RWE NPower Renewables,

Scira Offshore, EDF-EN.

Operators/ Owners

Centrica, DONG Energy, SKM, Blyth offshore windfarm Ltd, SSE Renewables,

Vattenfall, E.ON Renewables, Masdar, NWP offshore Ltd, Statoil (50%)

Statkraft (50%), EDF-EN, Barrow offshore, Stadtwerke München, Gwynt y Môr.

Page 24: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

Figure 2-1 shows a breakdown of stakeholders through PESTLE analysis by

George Read [7]:

Figure 2-1

2.1.2.5 Legal

The European commission is one of the main stakeholders for the production of

offshore wind. They produce the directives which the member states must

legally abide by. Regulatory bodies provide legally binding directives for the

implementation; one example is the use of health and safety.

Figure 2-1 contains some legal stakeholders for the offshore energy sector

identified by George Read (2013) [7].

Page 25: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

Legal stakeholders for the offshore industry include; the Marine Management

Organisation (MMO), Infrastructure Planning Commission (IPC) [12] and

various law firms specialising in corporate and copyright law.

2.1.2.6 Environmental

The energy sector accounts for 27% of the total CO2 production in Britain and

in the year 2010, 156 metric tonnes of carbon dioxide equivalent [13] were

produced. The drive to reduce emissions relies heavily on the ability to de-

carbonise electrical generation in the UK. The government has set an initiative

to cut the production of CO2 by 2/3 by 2030, since the CO2 producing plants

will be decommissioned, the renewable energy sector is expected to be able to

support 30% of electrical generation by 2020 to be on target. Currently

accounting for 3GW the offshore wind sector is expected to reach a mean

predicted production of 18GW with an interquartile range of 18GW by 2020.

NERC (National Environmental Research Council) is a stakeholder for the

environmental sector and progressively monitors the introduction of renewable

energy devices have on marine and offshore wildlife. The meteorological

society is an important stakeholder who helps determine high yield areas for

offshore wind.

Figure 2-1 and Table 2-1 both contain environmental stakeholders identified by

George Read (2013) [7] and ‘Best practice guidelines for offshore consultancy’

[8] respectively.

Page 26: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

Table 2-1

[8]

2.1.2.7 Force Majeure of Economic, Social, or Political Developments

Change in government policy in the near term is unlikely, since the green

agenda enforced by the European Union. However change is possible if this

connection is broken. The next EU vote is in 2014, and if it passes then we can

guarantee no changes in policy until 2019. The British government has its own

independent set of targets for environmental protection and will safeguard the

recycling business even if the connection with the EU is broken. Independent

member state targets can be abandoned without consequence providing they

are greater than the EU targets.

Scottish independence could ensure that the green agenda is maintained since

the SNP energy policy on renewables is a key agenda for the party. However

fluctuation in confidence of the Scottish currency could affect costing

projections.

Page 27: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

2.2 Decision Makers

2.2.1 What are Decision makers?

Decision Makers are administrators who are able to rate alternatives against a

range of criteria within their speciality.

Decision makers are used in multi-criteria decision analysis to optimise the

performance, allocation of funding or time to a part product or system. Decision

makers have different levels of experience in their speciality; therefore including

more decision makers increases the accuracy of the ratings. The decision

makers were chosen based on their experience in; risk, offshore technology or

the renewable energy sector.

2.2.2 Expert specialities utilised

Contribution Breakdown;

Insurance: 0

Risk: 1

Offshore expert: 2

Engineering Project Managers: 2

A total of 5 decision makers contributed to rating the alternatives and criteria.

2.3 Section 2 - Alternatives

The alternatives identified will be used to demonstrate the Fuzzy MCDM

method separated by; design construction, and operation and decommissioning

phases of an offshore wind farm project.

Page 28: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

14

2.3.1 What are Alternatives?

Alternatives are the options available for optimisation; they could be

manufacturers, contractors, etc. The identification of risks and failure modes will

provide the list of alternatives to be used in the fuzzy MCDM method.

2.3.2 Alternatives PESTLE Analysis

2.3.2.1.1 Political

2.3.2.1.1.1 International

The impact assessment proposal for a directive of the European parliament and

of the council amending Directive 2009/28/EC on the promotion of use of

energy from renewable energy sources prevents membership countries from

creating a biofuel sector for the Renewable Energy Directive that exceeds 10%

of the targets set for 2020 (European Commission (2013) [14]). This is an

attempt to reduce the greenhouse emissions that are released in combustible

fuels; this also prevents edible crop land from being used for the production of

fuel. The Renewable Energy Directive sets out to produce 20% of its energy

from renewable energy sources by 2020 [15]. This initiative is designed to

reduce foreign energy dependency, cut greenhouse emissions and create an

innovation revolution in the energy sector, hence reducing unemployment in the

EU.

The European Commission (2013) [14] report (page 6) evaluated the progress

and capacity to achieve the EU 2020 targets show that only one of the

alternative energy sources is on target (Photovoltaic cells). Alternative energy

sectors show lower than predicted progress for onshore/ offshore wind, biofuels

and biomass. The wind energy sector is expected to contribute 213GW of

electrical generation in member states with 44GW to be produced from offshore

wind energy along with 169GW from onshore wind. A total of 140TWh of

electricity is planned to be generated from offshore wind power across the EU.

The 2013 report postulates that infrastructure difficulties and reduction in

national effort will prevent the objective being accomplished.

Page 29: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

15

A policy brief released by the European University Institute titled ‘A new EU

technology policy towards 2050: which way to go? [16]’ looks into the effect

both strong and weak carbon prices will have on the future of European Energy

policy. There are 3 options available;

1. To continue and extend the 2020 policies through to 2050.

2. In the event of a strong carbon price, the current technologies will be

extended along with the creation of a common platform for open

information exchange to support investors and their decision making.

3. In a weak carbon market, optimisation will be performed to find the most

cost effective portfolio of RE technology.

In the event of each of the three scenarios, offshore wind energy will likely play

a large role in energy policy through till 2050 due to its popularity over onshore

wind energy both in terms of energy efficiency and aesthetics. Offshore

electrical grid development will be one of the key infrastructure problems faced

in meeting 2020 targets.

2.3.2.1.1.2 National

The British government wishes to lead the way in reducing greenhouse

emissions and has set an independent target of 30% reduction of carbon

dioxide emissions of the 1990 level by the year 2020 [5]. It plans to accomplish

this through a diverse portfolio of renewable energy sources including the

promotion of marine energy. The government also pledged to produce an

offshore electricity grid in order to encourage private investment in offshore

energy.

2.3.2.1.2 Economical

The oil and gas reserves in the North Sea provided the UK with shelter from the

economic sanctions applied to countries without energy security by Russia (and

other oil producing nations) up until the end of the 20th century. Renewable

energy in the form of offshore renewable has the potential to extend this

independence until 2050 (at which point a transition to a hydrogen economy

using 4th gen nuclear power stations is expected). If the government supports

Page 30: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

16

the creation of a supply chain to service the offshore wind industry, the UK

economy could benefit between £6 and 8 billion of annual revenue with 70 000

jobs created by 2020 [17]. The change in design and size of OWF has the

greatest impact on the economic viability of the sector; this is addressed in

section 2.2.2.4. A cost based sensitivity analysis on offshore wind energy by

NREL evaluated how changes in turbine design affected the cost of energy. The

results are shown below in Table 2-2;

Table 2-2

[18]

Figure 2-2 (Matthias Finger (2013) [19]) depicts of the state of the energy

industry in 2011, and shows that while ranked joint 4th with respect to overall

investment capital, wind energy has the second highest corporate funding

behind Hydrogen/ Fuel Cell technology. His report highlights how corporate

funding provides 70% of the overall R&D budget for non-nuclear low carbon

renewable energy. This would suggest that wind energy has a considerable

stake in the competitive energy market and filtering mechanisms need to be

adopted to select highest performing designs and most optimum design

solutions.

Page 31: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

17

Figure 2-2

[19]

The academic paper [20] highlights how investment in offshore renewable

energy must initially be backed by the government in order for private

investment to follow. It concludes that the lack of private investment in offshore

technology is attributable to a combination of; the infancy of the sector creating

a high risk - low ROI environment, combined with the economic downturn (in

general investment) caused by the recession.

Competing renewable energy sectors pose a risk to offshore wind funding, for

example hydropower provides a more reliable source of energy with higher

energy density; however the variation in design and efficiency places high ROI

on potential investors (a similar limitation found in offshore wind).

The levelized cost of energy (LCOE) for offshore wind is significantly higher

than the current blend of energy sources. This poses a risk to the future

implementation of the technology since consumers want to minimise the

financial implications of switching to sustainable energy sources. The LCOE

influences the levels of; subsidies afforded to the industry from the government,

and taxation applied to commercial venders to encourage economic viability.

Page 32: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

18

2.3.2.1.3 Social

Social response to offshore wind generation has been quite varied. Some of the

key concerns expressed by the public are identified in the journal

‘Understanding public responses to offshore wind power’ (Haggett, C. (2011)

[21]) and are condensed into 5 concepts; Visual Impact, Local context and

place attachment, the disjuncture between local and global, Relationships with

outsiders and finally Planning and participation.

Social risks can stem from project implementation phase in the form of; Human

Error, poor vertical and horizontal collaboration within the company, reduced

communication in the project, retaining/ risk of losing skilled employees,

complacency in job leading to risk of non-detection of failures/ faults, and finally

disruption to teamwork social collaboration.

2.3.2.1.4 Technological

Offshore turbine technology can be separated into 5 subsections; Foundation,

Tower, Blades, Drivetrain and (Grid and substation). Technology used for

onshore wind has been applied to the offshore environment to perform a

preliminary analysis. Offshore technology used for oil and gas (such as

foundation structures for oil drilling rigs) can provide a wealth of experience

(and risks) for developments of increasing water depth and distance from shore.

2.3.2.1.4.1 Foundation

Most (96%) of the current offshore wind energy is extracted from locations not

exceeding 40m, leading to the almost universal use of monopile foundations.

This is expected to expand to include the use of jacket foundations in the next 5

years with implementation planned for two sites in Fife, Scotland (Higgins, P.

and Foley, A. (2014) [22]). These new platforms encounter new forms of risks to

Page 33: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

19

implementation and maintenance which can be adapted from known risks in oil

and gas industry.

2.3.2.1.4.2 Tower

Specialist coatings and standards have been developed for the towers of

offshore turbines to minimise the corrosive effect of the salt water, in an effort to

reduce the risk associated with material failure (see Chapter 2.3.3). Current

limitations to the size of tower sections prevent the tower from being

constructed from a single piece and so sections of 30 -40m are transported to

the area of deployment [22]. As the infrastructure develops it is hoped that the

single tower structures can be transported to deployment – this will reduce the

strength requirements (by minimising stress concentration points where the

sections are combined) and help minimise risk associated with material failure.

A key legislation directive specifies a 22m gap between the minimum height of

the blade and the peak yearly water height. This minimises the risk associated

with collision by enabling small craft clearance from the blades [22].

2.3.2.1.4.3 Aerofoil

The lift generated by an aerofoil intensifies as the length increases and so the

blade diameter is directly proportional to the power output. Current designs

allow for diameters up to 120m with a majority of currently installed turbines

around or below 66m. The largest blade diameter planned for the UK is 171m

and will be manufactured by Samsung heavy industries for deployment in Fife,

Scotland [22]. These improvements in materials, size and output power

increase the number of both known and unknown risks. The cost sensitivity

analysis results shown in Table 2-2 (Chapter 2.3.2.1.2) highlight the economic

benefits arising from the increase in size of offshore turbines.

Advances in the manufacture of turbine blades in the areas of reinforcement

and self-healing materials are increasing the design life span and reducing the

risks involved in transportation. 3D printing of the aerofoils is predicted to

reduce costs and increase competition in the energy market.

Page 34: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

20

2.3.2.1.4.4 Drivetrain

Improvements in the design and materials used for offshore wind turbines

include the use of superconducting materials to reduce the mass of the

generator and increase efficiency. This however is balanced against the

increase in cost and risks resulting from the requirements of coolant required for

the superconducting materials. The prototype for this new design is expected to

be commercially available in 2020 [23].

2.3.2.1.4.5 Grid and substation

Substations are electrical transformers that are based on the sea bed with costs

up to £50 million; the risk of failure can have high cost and environmental

consequences. They are used to transform electrical power from DC to AC thus

preventing loss from line resistance in the grid. Both the grid and substation can

exert negative electro-magnetic effects on the surrounding environment [24].

2.3.2.1.5 Legal

Consent or planning permission can create legal risks when delays in the

consent affect the economic viability.

Creation of network of conservation sites from [25] states that offshore

conservation sites need to be defines such that offshore technology cannot

build on sites within a given distance (especially when drilling monopiles into the

seabed [26]).

2.3.2.1.6 Environmental

A report compiled to find the ecological risks associated with offshore wind [27]

found that the construction phase in deployment had the highest ecological

damage risk. The report finds that securing the foundations produced high

levels of noise pollution when the monopile foundation was used (since it is

Page 35: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

21

required to be drilled into the seabed). It was highlighted that other foundations

were available which would have much less of an impact on the environment

(such as gravity based support structures). The impact to the wildlife from

stressors varies with age, where 1% of younger marine wildlife may be injured,

and 1% of the developed cod vulnerable to injury or even death. Seasonal

changes in wildlife populations led to periods of increased risk, the Ecological

Risk Assessment concluded that maintenance (such as cable trenching) be

postponed until June (if planned to start in December) to minimise distress to

spawning marine wildlife.

Another study researched the affects the offshore wind farms (OWF) had on the

surroundings [26] and found that monopiles caused disruption to the sediment

and substrate along with changing currents in the local area. It also highlighted

how marine bird populations could reduce from impacts with the OWF, Noise

and vibration from the turbine is unsettling for fish and marine mammals. These

are considered environmental risks of offshore wind.

It was highlighted that the foundations provided artificial structures favourable to

some aquatic species. A study was conducted on the seal (one of these aquatic

species) by attaching GPS units to seals and monitoring their interaction with

OWFs [28] which proved that the structures were beneficial for this marine

mammal.

Page 36: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

22

2.3.2.2 Comprehensive Risk Register separated by project phase

2.3.2.2.1 Planning/ Design

PESTLE breakdown of risk register

Political Economical Social Technological Legal Environmental

Greater levels

of onshore

turbine

commissioning

[29]

Greater level of

optimisation

during FEED

[29]

Encourage Vertical

Collaboration [29]

Increase project

design life [29]

Improvements in

jacket design and

design standards

[29]

Greater level of

geophysical and

geotechnical

surveying [29]

Global

recession and

uncertainty of

future economy

[21]

Fishing communities –

incentive schemes [21]

Engineering design

uncertainty [21]

Availability of

design standards

and certification

guidelines [21]

Unknown

environmental

impacts (force

majeure) [21]

Commercial and

recreational boating [21]

Supply chain [21]

Insurer risk [21] Emergency [21] services Reliability

Page 37: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

23

(component &

system) [21]

CAPEX [30] Tourism [21] Grid connection

[21]

UN not

supporting

future

renewable

energy

developments

[21]

Feasibility [30] Public acceptance [21] Design variability

based on depth

and conditions [21]

Environmental

impact

assessments [21]

Social groups being

ignored/not being

involved [21]

Fragmented

industry (no widely

accepted

configuration) [21]

Commitment to

legally bound

renewable targets

[21]

Strategic

environmental

assessments [21]

Current high

cost of

technology [21]

Project Complexity and

communication [31]

System efficiency

on array scale

development [21]

Licensing [21]

Government cut

backs in

spending for

Financial – Low

return on

investment

Offshore structures less

visible and so there is

less size restriction

Foundations,

turbines, grid

Planning

permission [21]

Wind, wave and

current – impact on

structure and

Page 38: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

24

renewables [21] (ROI) [31] based on planning

restrictions (from NIMBY

campaign) [30]

connection [31] activities [31]

Local content –

requirement for

x% of final

product sourced

locally [30]

Procurement

difficulties for

sourcing

materials [30]

Feasibility [30] Overlooking details

of legislation [21]

Corrosion of

structure changing

the localised

composition of the

seawater – and

effect on wildlife

[30]

Loss of

management or

staff through

political

reasoning

(internal

company

politics) [30]

Drop in demand for

electricity [30]

Superior

technology making

offshore wind

redundant – e.g.

significant

breakthrough in

solar efficiency [30]

Copyright

infringement [30]

Subsurface

conditions –

geohazards, scour,

accretion [31]

Page 39: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

25

Forbid contracts

with foreign

companies –

forbid

techniques

used [30]

Price of

electricity in

current market

[30]

Human Error Units of

measurement (SI

or Metric) [30]

Standards required

for country of

installation [30]

1/3 generation

capacity from

renewable mix

in offshore wind

(British target)*

[30]

Introduction of

multi‐variable

optimisation of

array layouts

[29]

Public’s willingness to

pay more for energy to

reduce emissions [30]

Corrosion [30]

Transferability of

knowledge from

similar industries

[21]

Standard

Industry Risk

Encourage Horizontal

Collaboration [29]

Array cable system

design for

Widen range of

working conditions

Protected marine

life migration

Page 40: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

26

Register

template [29]

redundancy [29] for support

structure

installation [29]

patterns [30]

Shout about

success ‐ push

good news case

studies [29]

Incentivise early

site

investigation

and FEED work

[29]

Public image – linking to

popularity [30]

Step change in

wake modelling

science and

certainty [29]

Standardisation of

support structure

selection and

design [29]

Wake effect on

coastline (based

on proximity to

shoreline) [30]

20% final

energy

production - EU

targets for

2020* [30]

Initial funding –

Private and

government

incentives [30]

effects on employment

(other than the purely

economic) [32]

Delay [30] Improvements in

array cable

standards and

client spec [29]

Page 41: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

27

2.3.2.2.2 Construction

PESTLE breakdown of risk register

Political Economical Social Technological Legal Environmental

Shout about

success ‐ push

good news case

studies [29]

Instigate step‐

change in WTG

manufacturing

quality [29]

Encourage Vertical

Collaboration [29]

Standardise site

investigation

technical

requirements [29]

Standardise

Contract Forms

[29]

Standardisation of

offshore

transmission

assets [29]

Health and safety

of the workforce

(both at sea and

associated land

areas), other users

of the sea, and

local communities

and members of

the public [32]

Environmentalists

causing delays [21]

Social groups Acute noise-

Page 42: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

28

delaying/stopping

a project [21]

related impacts

during construction

phase (driving,

drilling and

dredging

operations) [24]

Difference in

regional political

support within the

UK [21]

Incentivise early

site investigation

and FEED work

[29]

Effects of

environmental

changes on local

residents

(including visual,

noise and traffic)

[32]

Primary industries

in place to supply

necessary parts.

[30]

Compliance with

relevant standards

from country of

operation [30]

Generation of

polluted sediments

during construction

and their re-

suspension [24].

Effect on leisure

pursuits [32]

Human Error [30] Units of

Measurement (SI

or Imperial) [30]

Disturbance during

exploration,

construction and

maintenance [24]

Job creation in Overheads for Communication Delay [30] Manufacturing

Page 43: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

29

local area and

positive secondary

employment –

rejuvenating

communities [30]

delay in

construction phase

[30]

problems –

multinational

companies/

contracts may

have problems

with

miscommunication

[30]

carbon footprint to

be mitigated over

working lifespan

[30]

Encourage

Horizontal

Collaboration [29]

Improvements in

workshop

verification testing

[29]

Transportation of

parts kept to a

minimum to reduce

component carbon

footprint. [30]

Page 44: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

30

2.3.2.2.3 Installation

PESTLE breakdown of risk register

Political Economical Social Technological Legal Environmental

Shout about

success ‐ push

good news case

studies [29]

Cost of hiring

specialist marine

vehicles for

installing turbine

[30]

Encourage Vertical

Collaboration [29]

Optimisation of

array cable

installation

vessels, tools and

methods [29]

Standardise

treatment of

Uncontrollable

Risk [29]

Improvements in

range of lifting

conditions for

blades [29]

Visual Impact [32] Delay [30] Check contract

times and location

specified in

contract including

overhead costs

[30]

Noise pollution [30]

Encourage

Horizontal

Collaboration [29]

Improvements in

the installation

process for space‐

Improvements in

weather

forecasting [29]

Page 45: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

31

frames [29]

Archaeological

heritage [32]

Heavy lifts,

collision

(installation,

visiting or passing

vessels) and

damage [31]

health and safety

of the workforce

(both at sea and

associated land

areas), other users

of the sea, and

local communities

and members of

the public [32]

Turbine installation

disruption [32]

Transport – marine

aviation,

accommodation.

[31]

Water quality and

pollution incidents

during installation

and maintenance

[32]

Human Error [30] Improvements in

range of cable

installation working

Health and safety

– working at

height, confined

Carbon footprint

with transportation

[30]

Page 46: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

32

conditions [29] space, electrical

and mechanical

working, structural

failings, fire, vessel

transfer,

evacuation and

rescue, diving [31]

Anchoring &

mooring [21]

Short-term

environmental

damage [21]

Page 47: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

33

2.3.2.2.4 Operation

PESTLE breakdown of risk register

Political Economical Social Technological Legal Environmental

Shout about

success ‐

push good

news case

studies [29]

Instigate step‐

change in WTG

design for

reliability / O&M

[29]

Encourage

Vertical

Collaboration

[29]

Improvements in

personnel

access from

transfer vessel to

turbine [29]

Improvements

in personnel

transfer from

land base to

turbine location

[29]

Improvements in weather forecasting

[29]

Impact of anchorage, or the ‘artificial

reef effect’[24]

Number of

offshore

turbines

contributing to

national grid

[30]

Effects on

fisheries and

other users of

the sea [32]

Sea and air

navigation.

[32]

Interfaces –

land, port,

marine, aviation

[31]

Security Threats

– physical,

cyber [31]

Electromagnetic interference and

temperature rise from subsea power

transmission cables[24]

Competitiveness

with traditional

energy sources

[30]

Encourage

Horizontal

Collaboration

[29]

Autonomous

health

monitoring [30]

Warning lights

for low flying

aircraft. [30]

Impact - Sedimentary, biological,

visual, fishing, navigation [31]

Page 48: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

34

OPEX [30] Improved

monitoring for

vibration

reduction in

structure [30]

Designated

areas and

proximity of

protected areas

[32]

Marine habitats and benthic (seabed)

communities [32]

Bathymetry, sediment transport

paths, bedforms, scouring, mixing,

turbidity. Changes in wave and tidal

current characteristics [32]

Fish resources, migration patterns,

nursery areas [32]

Marine mammals – distribution,

disturbance, displacement, impacts

of noise and vibration [32]

Noise, vibration, lighting [32]

Collision from wildlife [30]

Long-term environmental damage

[21]

Page 49: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

35

2.3.2.2.5 Maintenance

PESTLE breakdown of risk register

Political Political Political Political Political Political

Communication to

upper level

management [30]

Instigate step‐

change in WTG

design for reliability

/ O&M [29]

Encourage Vertical

Collaboration [29]

Improvements in

personnel access

from transfer

vessel to turbine

[29]

Improvements in

personnel transfer

from land base to

turbine location

[29]

Improvements in

weather

forecasting [29]

Human Error [30] Weld/ Material

defect [30]

Vibration Damage

[30]

OPEX [30] Complacency in

job leading to

missed risks [30]

Increase in

autonomous

sensing for failure

[30]

Changes to

regulation

governing working

at heights [30]

Environmental

impact detection

more closely

monitored [30]

Introduction of

turbine condition‐

based

Encourage

Horizontal

Improvements in

jacket condition

Subsidence [30]

Page 50: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

36

maintenance [29] Collaboration [29] monitoring [29]

Instigate step‐

chain in

Investment Risk

[29]

Teamwork [30] Change in system

affecting overall

time spent (on

repairs) in the

offshore structure.

[30]

Health and safety

law being updated

(learning from

incidents) [30]

Storm [30]

Indirect

environmental

damage [21]

Page 51: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

37

2.3.2.2.6 Decommissioning

PESTLE breakdown of risk register

Political Political Political Political Political Political

Shout about

success ‐ push

good news case

studies [29]

Budgeting for

successful removal

over the planned

lifecycle. [30]

Encourage Vertical

Collaboration [29]

Similar to

installation

(technologically)

adjusted for time.

[30]

Compliance with

shipping and

disposal laws [30]

Cost in material

decomposition

(carbon fibre or

glass fibre-epoxy),

Transportation [30] Change in strength

of currency [30]

Evaluation of

lifetime vs energy

production [30]

Reduction in

recoverable scrap

metal value

relative to

purchase. [30]

Encourage

Horizontal

Collaboration [29]

Development of

new restrictions

regarding disposal

[30]

Impacts during

physical

decommissioning

(particularly with

the use of

explosives) [24]

This is not an exhaustive analysis.

Page 52: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

38

2.3.3 Alternatives selected for the risk matrix

A risk matrix is a table that enables decision makers to compare alternatives

(risks) against a range of criteria. A selection of risks shall be selected from the

risk register and used to represent how mitigation of failure modes (risks) can

be optimised through a MCDA method.

A key risk in the design and implementation phase is in copyright infringement

along with standards. Legislation for the design and implementation of

engineering projects in European countries require that the work must be

performed under specific standards to be insured. These standards ensure that

the design and particularly the implementation of the project adheres to a strict

health and safety protocol and ensures that the product will have either minimal

local impact (ALARP) or sufficient strength to withstand certain extreme

scenarios within its design parameters.

Health and safety policy is constantly changing and adapting with new offshore

incidents. This ensures that the risk to human life is minimised when new risks

are discovered (lowering force majeure). This change in policy can drastically

affect the design of offshore structures, and while offshore turbines are not

manned all year round they required to facilitate the needs of the maintenance

staff. Upgrading an existing offshore structure to comply with changing

standards can be very expensive and so this is an important risk to consider.

The economic principle of supplying the sustainable energy is based on fixed or

increasing market wholesale price for the project to be profitable. Therefore

fluctuations (especially decreases) in the wholesale cost of energy can

significantly affect the bottom line of this industry. Variations in the cost of

carbon based fuel have a huge impact on the investment and competitiveness

of renewable technology. Shale gas is expected to lead to a drop in energy

prices over the coming decade and will likely affect the market for offshore wind

assuming emissions taxes (and Carbon Capture and Storage technology costs)

are not able to offset these changes to the wholesale energy price.

Page 53: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

39

The EU has legally binding objectives to be met by 2020 and 2050 with regard

to the use and contribution of renewable energy. Member states also have their

own objectives and policies (usually exceeding the EU general objective).

Changes in national political policy for RE, brought about by the public’s

influence over politicians and reluctance to increasing energy costs, will impact

both commercial and government investment of the RE sector and so presents

a risk to the financial stakeholders invested in offshore wind.

Carbon friendly technologies (or technologies with increased efficiency) are

entitled to tax subsidies which encourage commercial competition by ensuring a

profit margin for emerging technologies. The government benefits from this by

meeting greenhouse gas reduction targets from the EU. (Higgins, P. and Foley,

A. (2014)) [33] Stated that the UK policy on government subsidies for wind

energy shall increase from £135/ MWh to £140/ MWh until 2019. This increase

is designed to promote the construction of further wind energy farms to meet

the EU Directive 2009/28/EC. Without these subsidies the initial development

and production of offshore wind turbines would not be viable. Changes to this

policy in the future will affect the profit margin of the venture.

Material failure is a component of all offshore structures which is attributed to

harsh environmental conditions coupled with the high cost of using corrosion

proof materials. Material failure can occur from faults in the manufacture

(welding) process, from the corrosive action of the salt water or from vibration at

the natural frequency of the support material. The corrosive failure mode is

linked to the design life and will be considered as a separate failure mode.

Delay can occur throughout the project lifespan; this can lead to financial and/

or non-financial consequences. Delay can be seen as consequence of deadline

mismanagement and is an important risk to monitor to ensure the project is

progressing according to schedule.

A reduction in Carbon emissions within the transport sector is required by

Directive 2009/28/EC. This has resulted in the formation of a carbon footprint

Page 54: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

40

that is attached to all products throughout the manufacture and deployment

phases (recycling in decommissioning can offset the value).

There is a high emphasis to minimise the carbon footprint attached to the

production of renewable energy equipment such that the carbon footprint per

kilowatt hour is far below competing RE technologies. This can be achieved by

creating the infrastructure to produce the components of the turbines closer to

deployment location. This will boost the local economy and create jobs in the

energy sector.

Global warming is having an adverse effect on the predictability of

environmental conditions. This means that changes to the weather (and

climate) can produce excessive loading beyond the designed specifications

leading to failure.

Communication breakdown within the hierarchal structure of the company can

lead to top tier management uncourting important stakeholders that could

hinder the progress of the project. Therefore miscommunication and

management must be addressed as (separate) serious risks that can hinder

project completion.

Automated detection systems are often used in the maintenance phase to

monitor structural and performance characteristics and the failure of such

systems will significantly impact the level of associated risk.

Force majeure is the term denoted to risks that are unknown and so can be

considered project failure uncertainty. This can have high financial implications

despite an exhaustive failure mode analysis of the project.

Impacts from aerial wildlife can damage the turbines reducing their

performance; this can also affect the number and species of aerial wildlife in the

area. This can be caused by changes in migration patterns from global

warming. The effect of marine life migration must also be considered; however

this risk shall be performed separately as it’s a different cause of disruption.

Page 55: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

41

Energy storage and transfer are major risks in offshore wind technology. An

article from Risktec (RISKworld, (2014) [34]) identifies cabling as the most

significant failure, resulting in the highest number of insurance claims from

offshore wind.

Supply chain problems can impose a significant risk to the development of

offshore wind installations. This can be compounded when there are few

manufacturers that are able to provide the specialized components leading to

waiting lists and contributing to project delay.

2.4 Criteria

2.4.1 What are Criteria?

To enable evaluation of a project for the optimisation of a part, product or

system, the parameters of optimisation are required to filter the performance

characteristics of the options available (alternatives). These parameters form

the criteria used in MCDA. Criteria are the conditions which the alternatives can

be effectively compared with one another.

2.4.2 Criteria Identification

The number of criteria that are required is dependent on the types of failures

expected for the project. This method aims to categorise predicted risk

scenarios to form the criteria. This will help identify the most critical failure

modes.

Failure mode and effects analysis uses three main criteria used to develop a

risk prioritisation number; these are occurrence, severity and detection. The

main aim is to link the probability of occurrence with the severity or

consequence of failure, the detection criteria is added to account for risk of non-

detection. Each of these factors has its own rating scale, all denoted by a 1-10

scale. This scaling system has been criticised due to information about the

contribution of each factor being lost in the calculation of the risk prioritization

number. Some methods chosen to combat the crisp scaling system have

Page 56: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

42

included variations of fuzzy number ranges to prevent the repetition of RPN

values.

There has been much criticism on the subject of criteria used to develop a

representative and cumulative risk number for a part, component or system.

The three criteria used in FMEA were determined to enable sufficient

information in the operational lifespan for maintenance to be able to perform

their role effectively. The goal of this project is to determine the role additional

criteria can have on the overall communication of failure and risk information.

Failures in a system will impact different areas of the business with varying uses

for the information required. For example the maintenance crew need to know

the specifics of what parts to replace and when this needs to be accomplished

by, the management require information on cost of replacement/ repair and how

to manage/ optimise the funding necessary to keep the system at optimal

performance. Insurance requires estimations on the cost of failure and the cost

associated with downtime caused by failure (as well as indirect costs such as

customer satisfaction/ loss in customer purchase).

2.4.2.1 Case Study

A few of the key criteria (common to offshore operation) shall now be explored

using the deep-water horizon accident in 2010 as a case study.

The deep-water horizon Gulf of Mexico accident in 2010 started with an initial

topside gas explosion which killed 11 people.

“The accident involved a well integrity failure, followed by a loss of hydrostatic

control of the well. This was followed by a failure to control the flow from the

well with the blowout preventer (BOP) equipment, which allowed the release

and subsequent ignition of hydrocarbons. Ultimately, the BOP emergency

functions failed to seal the well after the initial explosions.” [35]

Page 57: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

43

This resulted in an oil spill estimated at 4.9 million barrels into the sea; the spill

was finally halted after 87 days due to the remote location and great depth of

the seabed. BP was fined $32.7 billion for damages to coastlines and sea life,

$14 billion was spent on the response from BP with further commitments to

monitor environmental damage.

There was a direct loss of profit from the spill and clean-up, and an indirect cost

to the shareholder price as the company’s reputation was damaged causing a

reduction in customer demand. This contributes to the criteria associated with

failure in terms of direct and indirect financial cost. The loss of life associated

with the incident is a critical criterion that needs to be accounted for from a

health and safety perspective. One way to prevent future failure is to build

redundancy options into the system. This reduces the risk at this level however

will only be cost effective at high risk parts of the system.

In summary from the case study the following criteria have been shown to be

applicable to the offshore environment; Direct/ indirect cost of failure, Failure

impact on environment, Fatality associated with failure and Redundancy/

Mitigation.

Risk to business can be categorised by financial and non-financial. Financial

risk has been covered in the ‘cost of failure’ criteria; non-financial risk needs to

be defined and quantified.

The report by CFO Research (2012) [36] explains how non-financial risk can be

separated into 3 separate phases; Performance and competitiveness,

Information Management and (legal, liability and compliance).

These non-financial risks take many forms and are composed of but not limited

to; political, Operational, economic climate, vendor/ supplier failure to meet

company performance criteria, company reputation, ability to retain experienced

staff, loss of private competitive (or personal) data, environmental restrictions

(bad weather or disasters), compliance with standards and legislation, copyright

infringement and customer perception.(CFO Research. (2012)) [36].

Page 58: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

44

Detectability is a criterion that enables the maintenance staff to convey the

difficulty in performing checks on certain failure modes. This can lead to the use

of automated detection systems as a method of redundancy in maintenance.

The operational lifespan of a turbine is dependent on an effective maintenance

scheme along with the intended design life. The cumulative effect of failure

modes can cause a reduction in the operational lifespan and so the operational

lifespan of wind turbines must be compared with their intended design life to

identify causes of force majeure.

2.4.3 Risk Matrix

In conclusion we have a total of 18 risks and 9 criteria that shall be used to

populate the risk matrix;

Page 59: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

45

Criteria Alternatives

1 Component failure 1 Bird impacts

2 Design life 2 Carbon footprint

3 Detectability 3 Change in electricity costs

4 Direct/ Indirect cost of

failure 4 Change in environmental conditions

5 Fatalities 5 Change in government position on

subsidies

6 Impact on environment 6 Change in Health and safety

7 Redundancy/ Mitigation 7 Change in RE Policy

8 Risk to business - non-

financial 8

Communication to upper level

management

9 Tonnes of CO2 avoided

per year 9 Delay

10 Energy storage and transfer

11 Failure of automated detection

systems

12 Force Majeure

13 Human Error

14 Legislation

15 Marine life migration

16 Material failure

17 Miscommunication

18 Supply chain problems

Table 2-3

Page 60: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

46

2.5 Section 3 - MCDA Selection

Changes in consumer desire and increased competition have caused

manufacturers specialise (in reliability, durability, cost, and other criteria) within

their respective fields. The creation of new products requires input from these

supporting manufacturers (alternatives) and stakeholders (defining criteria) to

compete financially with rivals.

Optimisation of alternatives and the stakeholder specified criteria must be

performed to ensure maximum performance within a specified budget. The

influence or ‘weight’ of each of the stakeholders (and their criteria) must be

accounted for against the desired goal of project completion.

2.5.1 AHP

2.5.1.1 Literature

The analytic hierarchal process determines relative importance of criteria

required to achieve the goal, utilising the pair-wise ranking process for criteria

and alternatives.

The pair-wise ranking consists of comparing the relative importance of two

criteria. This ranking system is based on a 1- 9 scale, where 9 indicates high

relative importance and 1 indicates equal importance (R.W. Saaty, (1987) [37]).

Inconsistencies in response is one of the limitations to this method, therefore a

consistency index (CI) is calculated to check the variation of the individual’s

responses. A CI of 0 would suggest that there is no variance and the person

has no difficulty in ranking all criteria. The AHP method is flexible, allowing a

variance of 0.1, meaning that controlled levels of uncertainty are allowable in

the ranking of criteria.

To illustrate the process of AHP an example was generated for the purchase of

an eco-friendly vehicle. The decision maker ranked the relative importance of 4

criteria (environmental friendliness, motorway performance, engine type and

Page 61: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

47

price) against one another. The results of the example are shown in Appendices

A.1.1.

2.5.1.2 Analytic hierarchy process method

To make a decision in an organised way to generate priorities we need to decompose the decision into the following steps.

1. State the goal of the project and place on the highest tier.

2. Identify alternatives and assign to the lowest tier, state the criteria that the alternatives are to be measured against and assign to intermediate tier.

3. Perform pairwise comparisons on each of the alternatives with respect to

the criteria on the tier above.

4. Normalise the pairwise comparison of the criteria and then average with respect to each element to find the associated weighting.

5. Create scale for each of the alternatives utilising the maximum or minimum values dependent on ideal solution, then normalise scale. Multiply normalised scale by the associated weighting for each criterion to give the overall score for each alternative with respect to criteria.

6. Sum the overall scores for each alternative and rank maximum to minimum.

7. Perform consistency calculation on weighted criteria to check CI is less than 0.1.

2.5.1.3 Limitations

The relative weighting of criteria to achieve the goal will change when

conducted by different individuals; this will also create variance in the

consistency index. The synergetic productivity from teamwork should positively

influence (minimise) the consistency index.

The AHP process does not account for rank reversal – the concept that

critical criteria can change with time (especially in an emergency). Additional

criteria will require re-calculation to ensure that the CI does not change (note

that the RI increases with increasing criteria allowing for a small deviation in

Page 62: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

48

pair-wise comparisons with respect to new criteria). The relative increase in

deviation in consistency allowable is shown in Saaty's Consistency Index Table

(Table 2-4).

Table 2-4

[38]

If consistency is maintained when adding new criteria, the rank of the

criteria should not change dramatically (assuming that the new criteria are not

dependant on current criteria).

The main limitation to the AHP process is the requirement for pairwise

comparison with previous criteria/ alternatives when new criteria/ alternatives

are added. This can be costly with projects involving large arrays of both

alternatives and criteria.

2.5.2 MAFMA

2.5.2.1 MAFMA Literature

M.Braglia (Feb, 2000) [39] identified a few shortcomings of the FMEA method:

- Implementation timing

- Creating unbiased teams

- Coordination

- Doesn’t consider important criteria (cost etc.)

- Linguistic variation – need for fuzzy definitions

Page 63: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

49

In a review of previous literature the MAFMA paper found that cost evaluation

should be carried out simultaneously and not in parallel. This was based on the

understanding that the criteria would be weighted later on in the AHP method.

Simple multiplication of risk criteria (o, s and d) was not determined to be

representative of the relative importance manufacturers assigned to each of the

evaluation criteria. Quantification of failure modes was found to be difficult

especially when the criteria were linked (for example product failure eroding

customer satisfaction).

Multi-attribute Failure Mode Analysis utilises the Analytic Hierarchal Process

setting out the alternatives as the base level, the second tier represents the

range of criteria from the risk prioritisation number (occurrence, severity and

detectability) and combines with the predicted cost. The second level can be

made more inclusive if other criteria are wished to be considered also. The top

tier comprises of the cause of failure selection and is represented as the project

goal in AHP. The 3 tier system is used in order to select the type of failure the

product will most frequently encounter. Each of the criteria can be weighted in

order of preference; these weightings are then used to find the least disruptive

alternative for selection. The method utilises the strengths of the AHP method

where both qualitative and quantitative information can be compared either

individually or combined.

Figure 2-3

Page 64: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

50

[40]

Each of the failure criteria (occurrence, severity and detection) was assigned

ranges of applicability for each of the scores. Occurrence was defined as the

mean time between failures and was quantifies on a time-scale ranging from 3

months to 10 years. Detectability was determined on a 1 to 10 scale and

categorised by; visibility, detectability (both directly and using automated

sensors) and time between inspection. Finally severity was determined using a

1 to 10 scale where an accident requiring more than 3 days off work was ranked

highly (legal stipulation from both government agency and insurance coverage).

This method of restricting the definition of each of the criteria was determined to

eliminate confusion in linguistic terminology while avoiding the use of fuzzy

logic.

The use of the AHP system to quantify criteria weighting enables a sensitivity

analysis to be performed. The sensitivity analysis shows how the variation in the

decision maker’s response to criteria weighting will affect the combined risk

ranking.

G. Carmignani (2009) [41] further develops the use of the AHP method to

prioritise high RPN scores and correlate to cost mitigation due to corrective

actions. This is called the priority cost failure mode and effects analysis.

The main aims of the academic paper were set out to characterise the three

original criteria, differentiate between equal values and correlate cost to all

risks.

In order to characterise o, s and d, the scale (traditionally based on a 1-10

system) needs to be changed. For severity the scale is linked to the economic

impact associated with the severity of the incident, it is hence calculated as the

hours of lost production multiplied by the potential hourly profit. This method of

cost based quantification enables domino affects to be identified with greater

ease.

The occurrence scale of 1-10 is replaced with a frequency figure relating

to a fixed quantity of time for example 1000hrs of operational time. Detection is

Page 65: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

51

calculated from the cost of implementing a maintenance system multiplied by

the associated effectiveness. An advantage term is then calculated by

deducting the total potential loss with modification from the total current loss

associated with the failure mode.

This cost of implementation (calculated from the mean hourly cost

multiplied by the hours consumed by each action) is then deducted from the

advantage term to find the total profitability of pre-emptive intervention. The four

criteria are then used to create a graph of total current loss verses potential

profitability, this gives a visual representation to high priority cases and

highlights economic potential for prioritisation.

2.5.2.2 Limitations

Limitations highlighted to the method include variations in sensitivity

through the decision makers rating, the method is highly sensitive to variations

in cost estimates and highlights the need to verifiable facts and figures used.

This can be seen to be problematic from the point of view of the decision

makers (who inevitably have varying experiences of expected costs); this is a

fundamental problem in the field of multi-criteria decision making. The term

profitability needs to be concisely defined since it can relate to profitability

before and after tax etc. If equal weighting are applied to the three values for

occurrence, severity and detection, then this new method doesn’t provide a

sensitivity analysis and increase the sensitivity of the cost criteria in the model.

The method of evaluation of the PC-FMEA is of the same form as

analytic hierarchal process. This method is also reflected in the research carried

out by Braglia (2000). The alternatives are represented by system (or product)

faults, and are prioritised based on the 4 evaluation criteria to reach the goal of

selecting what faults to correct within strict budget limitations.

2.5.2.3 LC-FMEA Literature

Rhee S. J and Ishii, K (2003) [42] produced the academic paper ‘Using cost

based FMEA to enhance reliability and serviceability’. This aimed to assign cost

Page 66: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

52

based quantification to the FMEA methodology in the hopes to make the

severity of the failure mode (denoted by the risk prioritisation number) easier to

understand over a range of different departments.

Some of the shortcomings identified in the paper include; Detectability

register should be separated by design phase such that confusion over the

ability to detect and the risk of non-detection can be eliminated. The three

scales used to determine the RPN are independent of one another and

therefore distances between their products will not supply any additional

information for prioritisation.

The proposal of a Life-Cost based FMEA has a more rigorous framework

of identifying failure in the associated phase of operation (design, manufacture

or installation). A cycle of continued design modifications is performed prior to

manufacture utilising an experienced manufacture team to identify design flaws

and work with the design team (before mass scale production) with the intention

that the design can be adapted for ease of manufacture. The data gathered at

this phase is used to from the origin and detection inputs to the method. This

however can have its own limitations the most apparent is the requirement for a

product to be in the design phase (or have extended knowledge of design and

implementation) to carry out the methodology effectively. In other words it

cannot be implemented on existing manufacture to improve performance.

The method outputs a term called failure cost which relates to the

associated cost of detection and reparative measures to return the part or

system back to optimum performance. The failure cost is broken down into

labour cost, material cost and opportunity cost (downtime loss of potential

earnings). To determine the sensitivity to input criteria, a sensitivity analysis is

performed using Monty Carlo simulation with triangular distribution (5% lower

bound, 50% mean and 95% upper bound).

Unfortunately both methods (MAFMA and PC-FMEA) inherit the limitations

highlighted in AHP section 1.1.1. Some of the most prevalent limitations are;

Page 67: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

53

- When new faults or alternative failure modes are discovered, the process

of pairwise comparisons and alternative evaluations must be recalculated

(although he extensive support from software available somewhat

mitigates this problem).

- The failure modes must be evaluated and quoted for different modes of

operation since rank reversal is not possible in AHP.

- Failure modes that are dependent on one another are difficult to

categorise and evaluate using this format.

The life cost based FMEA differs from PC-FMEA in the way the cost term is

calculated, where LC-FMEA chooses to focus on the cost of a failure mode to

represent risk severity and PC-FMEA aims to use the cost calculations to find

the maximum benefit from preventative maintenance to optimise fund allocation.

LC-FMEA uses a much less complicated method of deriving the input terms

(based on MTBF and MTTF data), which places the methodology much closer

to the original FMEA calculation. This has advantages over PC-FMEA and

MAFMA such that limitations within the AHP structure are omitted. Hybrid

methodologies between these methods may produce a much more flexible and

reliable form for FMEA.

Sachdeva, A., Kumar, D. and Kumar,P. (2009) [43] broadens some of the terms

to include other factors for example severity can be broken down into

maintainability, spare parts and cost. The paper aims to improve the confidence

in each of the O S and D terms such that the FMEA method can be improved.

The terms are broken down into 6 components and given scores on a 1 to 9

scale. These 6 scores are then combined to be used in the final evaluation to

give a fully representative RPN.

2.5.2.4 Limitations

A limitation to this method is its similarity to the previous FMEA method where

the products can still be repeated (since crisp numbers are used).

Page 68: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

54

2.5.3 FMEA

2.5.3.1 Literature

FMEA stands for Failure mode and effects analysis. It is utilised in evaluating

the performance of parts, components or systems in both working life and

design phase. FMECA is an adaption to the original FMEA method and

incorporates a critical assessment. This critical assessment is used to create a

risk prioritisation number (RPN), and evaluates the subject (part, component or

system) based on the criteria; severity, occurrence and detection. The higher

the RPN number, the more imminent corrective attention is required. The O S D

system translates qualitative terminology into quantitative information to be

used in the calculation and implementation of resources. This combination of

criteria is very general and applicable to a wide range of topics. This project is

concerned with deriving a suitable range of criteria to more effectively evaluate

offshore wind power in the renewable energy sector.

Tables 4, 5 and 6 from [44] show the standardised scales that severity,

occurrence and detection are calibrated to respectively (these are included in

appendices A.1.2).

The academic paper: A. Hadi-Vencheh, M. Aghajani (2013) [45]

researches extensively the effect of incorporating the relative weighting system

used in TOPSIS (see section 1.1.2) with fuzzy logic (to aid decision makers)

such that relative importance of occurrence, severity and detectability can be

determined. In the long term this can provide information on how to optimise

funding to reduce the RPN of each failure mode in the system.

A fuzzy number is one which accounts for a range of values. The

distribution and occurrence of this range is referred to as the membership

function. The membership function is normalised with respect to the mode.

Alpha-level sets are the range of values determined for the linguistic fuzzy

terms used to derive relative weighting. The alpha-level sets can be set at any

value between 0 and 1.

Page 69: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

55

2.5.3.2 Method:

1. Define the content of the part, component or system being analysed.

Identify all possible methods of failure or hindrance and the environment

in which they occur.

2. Characterise the optimum operational conditions of part, component or

system, such that a state of failure can be easily identifiable.

3. Characterise the three values of occurrence, severity and detectability

with respect to repair, maintenance, logistics, etc.

4. Calculate the risk prioritisation number for the system failures.

5. Plan and implement steps to mitigate areas of high risk.

6. Create an effective maintenance schedule to reduce failure probability.

US MIL-STD-1629A [46] states that the risk prioritisation number can be

calculated as:

tC Pm

Equation 2-1

Where Cm is the criticality number for failure mode m, β is the conditional

probability of loss, α is the failure mode ration, λp is the part failure rate and t is

the time scale.

British Standard defines the calculation of the RPN as Severity multiplied

by probability of occurrence. This can be extended to incorporate the criteria of

detectability to ensure that the maintenance schedule is not underdeveloped in

the design phase.

2.5.3.3 Limitations

Liu, H., Liu, L., Liu, N. (2013) [47] identified of 11 shortcomings of FMEA (in a

review of academic papers relating to MCDM analysis) which are shown in

Table 2-5.

Page 70: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

56

Table 2-5

[47]

Some of the key considerations from this list are; the relative importance of O, S

and D terms, the individuality of the RPN, Interdependencies of failure modes

and the variations in risk evaluations.

2.5.4 Fuzzy Logic Methods

Fuzzy methods for multi-criteria decision making are used to enable decision

makers (experts in the field of study) to characterise linguistic terms into a

numerical range consisting of a lower bound, average, and an upper bound.

The fuzzing of classical (crisp) values creates a level of security for failure

modes or consequences unseen in the evaluation prior to operation, and

decreases the sensitivity to DM input. Using fuzzy numbers also increases the

Page 71: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

57

range of possible outcomes from the analysis – solving one of the core

problems identified in FMECA.

Fuzzy numbers combine vague descriptions and uncertainty with subjective

investor preference and expert knowledge to enable multi-criteria decision

making analysis [48].

2.5.5 TOPSIS

2.5.5.1 Literature

TOPSIS is the technique for order of preference by similarity to ideal solution.

The method involves calculating two values; the positive ideal solution

(maximum benefit and minimum cost = A*), along with the negative ideal

solution (minimum benefit with maximum cost = A-). The MCDM methodology

was created by Hwang and Yoon in1981 [49].

TOPSIS aims to translate qualitative and quantitative information into a

geometrical problem, optimising criteria with respect to weighting (cost to

benefit ratio).

The consistency index function from the Analytic Hierarchal Process can

be used to find if the decision makers used are consistent with their response to

the criteria weighting. This can be achieved through the pair wise comparison

process shown in chapter 2.5.1.2.

The degree of separation is calculated next, this relates the normalised

alternatives to both the positive and negative ideal solutions. This is used to find

the relative (geometric) closeness to ideal solution such that the alternatives

can be ranked by preference. The alternatives are ranked in descending order –

the higher the rank, the more suitable to the objective the alternative is.

Page 72: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

58

2.5.5.2 Method

Step 1 – Normalize the decision matrix

Create a decision matrix consisting of the m alternatives and n criteria, and

normalise using the formula below

m

j

ij

ij

ij

f

fr

1

2

Equation 2-2

Where fij is the ith criterion function for the alternative Aj (j=1,..., m; i=1,..., n).

Step 2 – Create the weighted normalized decision matrix vij

ijiij rwv

Equation 2-3

Where wi is the ith criterion (or attribute) weight and

n

i iw1

.1

Step 3 - Calculate ideal and negative-ideal solutions

Isolate the benefit criteria from the cost criteria and assign maximum and

minimum alternative values respectively. Thus the ideal solutions (A∗) and the

negative-ideal solutions (A−) are calculated as:

)''|(min),'|(max,..., **

1

* IivIivvvA ijjijjn

Equation 2-4

)''|(max),'|(min,...,1 IivIivvvA ijjijjn

Equation 2-5

Where I’ represents benefit criteria, and I’’ represents cost criteria.

Page 73: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

59

Step 4 – Distance measures

Using the n-dimensional Euclidean distance, the distance between each

alternative and the ideal solution is given as:

n

i

iijj vvD1

2** )(

Equation 2-6

Similarly for the negative-ideal solution:

n

i

iijj vvD1

2)(

Equation 2-7

Step 5 - Calculate closeness coefficient (to the ideal solution)

The relative distance between the alternative aj with respect to A∗ is given by:

)( *

*

jj

j

jDD

DC

Equation 2-8

Step 6 - Rank the Alternatives

Utilise the closeness coefficient to rank the alternatives in decreasing order.

Highlight the most optimum solution identified by the MCDA method (the

maximum C*j value).

2.5.5.3 Limitations

One of the limitations to TOPSIS is the high sensitivity to fluctuations in cost

which is valued highly (since it can convey the risk in a universally accepted

scale) and considered equal to the combination of all other benefits. In some

Page 74: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

60

industries (such as aerospace, and nuclear energy), safety criteria outweigh the

cost implications and as such this method is less applicable.

2.5.6 MCDA Evaluation

The AHP example highlighted the strengths of using weighted criteria to allow

prioritisation of resources – something fundamental to balancing stakeholders

with varying project influence. MAFMA took this further and incorporated the

three evaluation criteria from FMEA with cost in series (as opposed to parallel).

This enables both engineering analysis and cost based evaluation (for

management) to be carried out simultaneously. AHP and MAFMA do not allow

for rank reversal and are hence inappropriate for evaluating offshore

engineering; where varying weather conditions can change the weighting of the

criteria and hence cause rank reversal.

FMECA provides the base criteria used for universal engineering evaluation

using quantitative rating scales. These scales have been proven ineffective in

translating the relative state (repetition in RPN) and hence priority of resources.

This requires the use of fuzzy number theory to increase the quantity of

possible number combinations, allowing the result to be representative. TOPSIS

combines the use of weighted criteria with cost evaluation and allows rank

reversal to take place, and therefore is the most useful MCDA method for

offshore wind application. Using fuzzy numbers for the weighting will prevent

number repetition and hence a Fuzzy TOPSIS MCDA method shall be utilised

for the offshore wind example.

2.6 Section 4 – Preference Elicitation

Preference elicitation is the process of evaluating decision maker response.

DSS are systems that support decision makers and offer an array of

tools to scrutinise their decision. Two commonly used methods for preference

elicitation are derived explicitly and implicitly which relate to absolute

measurement and pair-wise comparison respectively [50].

Page 75: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

61

Explicit preference elicitation is based on absolute scales to enable the

decision makers to understand the direct consequence of decision. Implicit

elicitation uses pair-wise comparisons to find relative weights (to better

apprehend preference) and is subjective to decision maker’s personal

experience. Implicit evaluation makes the DM think more carefully about how

the alternatives interconnection, however require more comparisons to be made

in relation to the explicit method.

One method for passive pattern recognition (used in targeted

advertisements) collects previous decisions to provide a preference profile. This

can be applied to explicit responses to evaluate consistency in ranking by

comparing answers specified with the profile predicted results in for future

ranking. This study requires only one response from each of the decision

makers, therefore as a preliminary analysis passive pattern recognition will not

be considered.

The criticality analysis of FMECA utilises explicit elicitation for ranking

failure modes. Conversely MAUT, MAFMA and AHP use implicit pair-wise

comparisons to rank alternatives.

TOPSIS and Fuzzy TOPSIS both use explicit elicitation; the offshore wind

energy sector has many criteria for a range of purposes and fluctuating

numbers of risks, and so implicit evaluation is not suitable for the reasons

highlighted in chapter 2.5.1.3.

Page 76: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …
Page 77: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

63

3 Methodology – Section 5

3.1 Theory

3.1.1 Fuzzy TOPSIS method

Fuzzy TOPSIS uses triangular fuzzy numbers to translate qualitative information into

quantitative range as an alternative to the use of ‘crisp’ numbers in TOPSIS.

Fuzzy triangular numbers are comprised of a lower bound, middle bound and upper

bound.

When normalising the fuzzy decision matrix with respect to cost, the minimum cost

term is the numerator and the triangular fuzzy number is inversed such that (min

cost/ max cost) = lower bound etc.

It is common practice to use scales consisting of 7 independent linguistic terms,

increasing the number of linguistic terms does not significantly improve the

confidence in the combined ratings. As such 7 terms have been specified for both

alternative and criteria scales. The fuzzy logic triangular scale proved to be most

universally accepted in literature and hence was selected for the fuzzy calculations.

The Fuzzy TOPSIS Method is given below;

A triangular fuzzy number has 3 terms (α1, α2, α3) and is defined by the membership

function µα(x);

.

,

,

,0

,

,

,0

)(

3

32

21

1

32

3

32

1

x

x

x

x

x

x

x

Equation 3-1

Step 1: Select evaluation criteria and form a team of decision makers.

Page 78: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

64

Step 2: Allocate appropriate linguistic terms to the criteria weighting and alternative

ranking scales.

Step3: Average the criteria weights (wj) to find the average fuzzy weight of criterion

(Cj), and then aggregate the decision maker’s ratings (rij) into a matrix under to the

alternative Ai and criterion Cj.

n

w

C

n

j

j

j

1

Equation 3-2

Step 4: Build the fuzzy decision and criteria weight matrices, and then normalise with

respect to the criteria designation of either benefit (Equation 3-3) or cost (Equation 3-

4) to get the normalised fuzzy decision matrix (rij).

;,,,***

Bjc

c

c

b

c

ar

j

ij

j

ij

j

ij

ij

ij

ij cc max* If j ϵ B;

Equation 3-3

;,,, Cja

a

b

a

c

ar

ij

j

ij

j

ij

j

ij

iji

j aa min If j ϵ C;

Equation 3-4

Step 5: Multiply Cj by rij to find the weighted normalised fuzzy decision matrix.

Step 6: Specify the Fuzzy positive and negative ideal solutions either from the

criteria weighting, using zero and one, or the maximum and minimum possible

values from the decision maker ratings rij.

Step 7: Find the separation between the FPIS/ FNIS and the weighted normalised

fuzzy numbers.

Page 79: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

65

Let α = (α1, α2, α3) and β = (β1, β2, β3) be two different fuzzy triangular numbers, the

distance between α and β is defined as;

].)()()[(3

1),( 2

33

2

22

2

11 d

Equation 3-5

Step 8: Sum both separation values (FPIS and FNIS) independently for each

alternative (equations 3-6 and 3-7 respectively), and then use to find the closeness

coefficient (equation 3-8).

n

j

dd1

** ),( , ,,.....2,1 mi

Equation 3-6

n

j

dd1

),( , ,,.....2,1 mi

Equation 3-7

,*dd

dCC

,,.....2,1 mi

Equation 3-8

Step 9: Use the score from the closeness coefficient to rank the alternatives in

descending order.

Page 80: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

66

3.2 Computation

3.2.1 User Input

The excel program is based on a linked cell format. This enables the program to

quickly output new answers when new data is entered. The program was designed

to allow a maximum of 25 decision makers, 30 criteria and 20 alternatives (a risk

matrix of 600 inputs); however this can be tailored to the client’s specifications at a

later date and will be used in this report for proof of concept.

The program requires input of the criteria weightings from the decision makers (see

Figure 7-3) along with the associated cost or benefit indicator in the form of C or B

respectively (Figure 7-4).

Next the alternatives are ranked against one another with respect to the criteria, in

each of the 30 matrices representing the 30 possible criteria. The standard format

was to list the alternatives in the rows and the decision makers in the columns

(Figure 7-5).

Triangular fuzzy numbers were used to translate the qualitative ratings into

quantitative information to be used the calculation phase. This enabled a higher

range of outcomes compared with normal ‘crisp’ values.

There is the possibility for the user to change the linguistic terms. This was achieved

through the use of named matrices in the calculations tab in conjuncture with a

lookup function which searches the linguistic terms stated by the decision makers in

the two tables (rating and weighting scales).

Two examples were completed to demonstrate the flexibility in this regard (see

chapter 3.3: validation). Separate tables were generated for the weighting of the

criteria and rating of the alternatives. This enables the user to change the scaling of

the fuzzy numbers used to suit their specific style without changing the outcome. The

two scaling systems used for examples 1 and 2 are shown in Figures 7-6 and 7-7

respectively. These scales can however be changed (provided fuzzy triangular

numbers are used) to suit the user if the scales provided are not satisfactory. The

Page 81: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

67

tables are named datasets in the calculation phase and lookup functions are used to

perform calculations, enabling change in scale.

While the alteration is only a factor of 10 between the scales, alternative scale

systems can be generated without changing the outcome providing these changes

are applied only to the ratings scale. The weightings scale is not normalised and so

will change the outcome when calculating the distances between fuzzy numbers. To

enable the user to control the fuzzy scale used for weighting, input cells were added

to the user interface and linked to the fuzzy positive and negative ideal solutions in

the calculations tab. This means that when changing the weighting scale, the user

needs to change the FPIS and FNIS to the maximum and minimum values

expressed in the new weighting scale.

In summary, the following inputs are required from the user;

3.2.1.1 Compulsory inputs;

- Criteria Weighting.

- Define the criteria optimisation process; either cost or benefit criteria.

- Enter the ratings of alternatives against criteria specified by the decision

makers

3.2.1.2 Optional inputs;

- Enter any changes to the alternative rating scale

- Enter any changes to criteria weighting scale and hence update FPIS and

FNIS inputs accordingly.

An image of the format of the tool is included in Appendix B.1.1. The red boxes

indicate inputs, green indicate criteria and grey are the solution; all calculations are

carried out on a separate sheet that is hidden from view/ modification.

3.2.2 Calculations

The calculations are generated in a separate tab that will be locked off on completion

of the project.

Page 82: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

68

Initially the program generates the fuzzy triangular number from the linguistic term

specified for criteria weighting. This is then averaged to find the average fuzzy

number for weighting, shown in Figure 7-8.

The calculations required extrapolation of this data and for simplicity of calculation

and programming the index function was used to transpose the matrix (swapping

rows with columns). This is an effective and more efficient form of using the look up

function described for the scaling earlier. Figure 7-9 shows the new format for the

decision matrix.

The transposed matrix is then used for the generation of the fuzzy triangular

numbers for each linguistic term respectively. In the same manner as for the criteria,

the average fuzzy rating is calculated for the alternatives for each criterion. This

phase required error management such that lookup functions would be able to

search data in the calculation phase easily (the IFERROR operator was used to

achieve this in conjunction with the blank cell function “”). Figure 7-10 shows an

extract from the averaged fuzzy ratings for the alternatives. The criteria optimisation

designation (minimum or maximum ideal solution) is shown in the cost/ benefit

column.

The normalisation procedure was then performed where the maximum or minimum

value (for each criterion) was extracted based on whether the criterion was

designated a B (benefit) or C (Cost) term in the User interface respectively. This was

then used to normalise the fuzzy numbers using the fuzzy TOPSIS normalisation

formula for cost or benefit. The max/ min column uses the benefit or cost allocation

to find the largest part of the maximum fuzzy number ( *

jc ) or smallest part of the

minimum fuzzy number (

ja ) respectively. The normalised results are shown in

Figure 7-11.

The weighted normalised fuzzy decision matrix was then calculated by multiplying

the average fuzzy weighting (figure 7-8) with the normalised fuzzy decision matrix

(Figure 7-11). This is shown in Figure 7-12.

The fuzzy positive idea solution is usually set at 1 and fuzzy negative ideal solution

at 0 and this remains true for both the examples; however the option to change them

Page 83: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

69

has been added to the user interface to allow changes in the criteria weighting scale.

Figure 7-13 shows the ideal solutions and the calculation of the distance values

between the ideal solutions.

These are then summed for to find the closeness coefficient using the formula from

fuzzy TOPSIS method. The results are then sorted into descending order and the

alternatives ranked for the output.

3.2.3 Outputs

The output from the calculations tab are sorted according to their closeness

coefficient and ranked accordingly. The closeness coefficient is included to highlight

the difference between the alternatives; other alternatives can be useful if key

stakeholders object to the top ranked solution. The output is shown in the user

interface (Figure 7-14).

3.2.4 Obtaining results

Combining FMEA and Fuzzy TOPSIS enables the system failure modes to be

ranked (with respect to the criteria weighting) to find the highest risk alternative. The

literature review revealed 18 potential failure modes that can affect the performance

of offshore wind turbines. This was not an exhaustive list, however were chosen to

demonstration the implementation of the method. Criteria were chosen to represent

a wide array of failure modes and were designated either a cost or benefit term

indicating the type of optimisation to be performed on the criteria.

To enable evaluation of the failure modes against the designated criteria, a

questionnaire was created for the input of the evaluation data by decision makers.

3.2.5 Questionnaire

The decision makers from chapter 2.2 were asked to fill out a questionnaire to

compare the relationship the risk alternatives has with the criteria allocated. The

questionnaire can be found in Appendices B.1.2.

Page 84: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

70

3.3 Validation and verification

To ensure the program completes the intended task, two case studies were taken

from literature for validation of program.

3.3.1 Case Study 1

Source: Extensions of the TOPSIS for group decision-making under fuzzy

environment by Chen-Tung Chen [51]

The numerical example provided in this paper, envisaged using fuzzy TOPSIS to

help filter potential employees to a software company. This paper was chosen for

two reasons;

1. It uses different scales for the weighting of criteria and rating of alternatives.

2. All of the criteria used in the example are for a benefit optimisation (testing the

ability of the program to optimise on one type of criteria).

The benefit criteria chosen are as follows; Emotional Steadiness, Oral

communication skills, personality, past experience and finally self-confidence.

Tables (3-1) – (3-6) are extracts from the program and show the inputs taken from

the example;

Enter Attribute Weighting by decision maker (linguistic value)

DM1 DM2 DM3 DM4

G1 H VH MH

G2 VH VH VH

G3 VH H H

G4 VH VH VH

G5 M MH MH

Table 3-1

DM ratings for alternatives against criteria

G1 DM1 DM2 DM3

X1 MG G MG

X2 G G MG

G2 DM1 DM2 DM3

X1 G MG F

X2 VG VG VG

X3 MG G VG

Table 3-3

Page 85: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

71

Table 3-2

X3 VG G F

G3 DM1 DM2 DM3

X1 F G G

X2 VG VG G

X3 G MG VG

Table 3-4

G4 DM1 DM2 DM3

X1 VG G VG

X2 VG VG VG

X3 G VG MG

Table 3-5

G5 DM1 DM2 DM3

X1 F F F

X2 VG MG G

X3 G G MG

Table 3-6

The scale used for weighting of the criteria and rating of the alternatives can be

found in Appendix B.1.2 (Figure 7-7).

These inputs were then processed and gave the following output;

Output

CC Rank

0.765332 X2

0.701821 X3

0.638032 X1

Table 3-7

These were then compared with the results from the academic paper which were;

CC1 = 0.62, CC2 = 0.77, CC3 = 0.71. There is a small degree of separation between

the results which may have been caused by rounding errors in their solution;

however the rank of the three alternatives remains unchanged.

3.3.2 Case Study 2

Source: Constructing Project selection using Fuzzy TOPSIS approach by Yong-tao

Tan, Li-yin Shen et al [52].

A company is researching a number of subcontractors using a list of 9 criteria to

evaluate them. The criteria in order are as follows; Profitability, difficulty, relationship

Page 86: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

72

with owner, need for work, resources and capabilities, keenness of competitors,

competitors’ competitiveness, project execution risk and finally financial risk. Criteria

2, 6, 7, 8 and 9 are allocated for cost criteria optimisation, whereas 1, 3, 4 and 5 are

assigned to benefit optimisation.

The criteria are assigned the weightings shown in table (3-8) using a fuzzy rating

scale with a range between 1 and 0 (Appendix B.1.2).

Enter Attribute Weighting by decision maker (linguistic value)

DM1 DM2 DM3 DM4

G1 H H VH

G2 M MH M

G3 H H MH

G4 H MH M

G5 VH H H

G6 M MH MH

G7 H H H

G8 H MH MH

G9 MH H H

Table 3-8

G2 DM1 DM2 DM3

X1 MG F MG

X2 F F MG

X3 MG F F

Table 3-9

G3 DM1 DM2 DM3

X1 F F F

X2 F F MP

X3 F F MG

Table 3-10

G4 DM1 DM2 DM3

X1 F F MG

X2 G MG G

X3 MG MG MG

Table 3-11

G5 DM1 DM2 DM3

X1 G MG MG

X2 F F F

X3 MG MG MG

Table 3-12

Page 87: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

73

The ratings for the alternatives are entered separately on tables (9 through 17)

respectively.

DM ratings for alternatives against criteria

G1 DM1 DM2 DM3

X1 VG VG G

X2 F F MG

X3 F MG F

Table 3-17

The scale used to rate the alternatives is on Figure7-6, Appendix B.1.2.

The program was able to calculate the closeness criteria and hence rank the

alternatives which are shown in table (3-18).Using the input data above and the

fuzzy TOPSIS method, the excel program derived the following solutions:

Output

CC Rank

0.544246 X3

0.496368 X1

0.466551 X2

Table 3-18

The academic paper listed the solutions as CC1 = 0.496, CC2 = 0.467 and CC3 =

0.544. This proves that both the calculations and ranking formula are able to perform

the calculations over an array of different inputs to a high degree of accuracy.

G6 DM1 DM2 DM3

X1 G F MG

X2 MG MG MG

X3 F F F

Table 3-13

G7 DM1 DM2 DM3

X1 G MG MG

X2 G MG F

X3 F F F

Table 3-14

G8 DM1 DM2 DM3

X1 MG MG MG

X2 F F MG

X3 F F F

Table 3-15

G9 DM1 DM2 DM3

X1 MG F F

X2 F MG MG

X3 F F F

Table 3-16

Page 88: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

74

4 Results

Expert responses can be found in appendix C.

4.1 Fuzzy TOPSIS output with closeness coefficient

Table 4-1 links the designation code for the alternatives with the corresponding

linguistic alternative from the questionnaire.

X1 Legislation

X10 Carbon footprint

X2 Human Error

X11 Change in environmental conditions

X3 Delay

X12 Marine life migration

X4 Change in Health and safety

X13 Communication to upper level management

X5 Material failure

X14 Bird impacts

X6 Volatility in wholesale energy costs

X15 Force Majeure

X7 Change in government position on subsidies

X16 Failure of automated detection systems

X8 Change in RE Policy

X17 Energy storage and transfer

X9 Failure of information transfer

X18 Supply chain

Table 4-1

The following table is the output from the Fuzzy TOPSIS program with respect

to the five decision makers. The closeness coefficient is used to rank the terms

in descending order. The most critical failure mode identified related to the

damage or change to wildlife caused by marine migration followed by the supply

chain problems associated with the wind turbines.

Page 89: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

75

Output

Closeness Coefficient

Rank Corresponding Linguistic term

1 0.254152 X12 Marine life migration

2 0.246818 X18 Supply chain

3 0.236966 X8

Change in Renewable Energy Policy

4 0.231433 X10 Carbon footprint

5 0.206862 X5 Material failure

6 0.206277 X1 Legislation

7 0.205712 X17 Energy storage and transfer

8 0.203197 X13

Communication to upper level management

9 0.199203 X6 Volatility in wholesale energy costs

10 0.188499 X14 Bird impacts

11 0.188377 X7

Change in government position on subsidies

12 0.179115 X16

Failure of automated detection systems

13 0.1692 X9 Failure of information transfer

14 0.150115 X15 Force Majeure

15 0.144312 X11

Change in environmental conditions

16 0.136967 X3 Delay

17 0.13542 X2 Human Error

18 0.106854 X4 Change in Health and safety

Table 4-2

Page 90: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

76

5 Sensitivity analysis – Section 6

TOPSIS has the advantage of assigning weights to the evaluation criteria

enabling the project managers to optimise resource allocation based on

personal preference parameter prioritisation. The data displayed in the results

section is not representative of the Renewable Energy sector as a whole and so

can only be considered as semi-quantitative information. This means that a

larger decision maker sample is required in order to reach a group consensus.

Figure 1-1 shows where a sensitivity analysis should be performed.

5.1 Weight stability Intervals

The results were collected from 5 decision makers which is a small sample, this

would suggest high sensitivity within decision maker responses; we are

interested in the correlation between a single DM’s input and its effect on the

output.

The criteria have a linear relationship with the closeness coefficient and hence

this would suggest that maximising or minimising the criteria would change the

ranking of alternatives that have high ratings. Large changes in single criteria

are unlikely to occur, however large changes in groups of criteria weight would

suggest a societal change in priority. Therefore a sensitivity analysis shall focus

on the cost of implementation potential future policies will have based on the

current ranking.

5.1.1 Scenario 1 – Safety Conscious

An example could include a society with a high value of life. Resources would

be concentrated on minimising human interaction with OWFs by increasing

reliance on automated maintenance systems. This would result in the weighting

associated with redundancy/ mitigation (G7) and fatalities (G2) would be

maximised.

The combined affect this change would have on the prioritisation of resources

relative to the initial findings are shown below;

Page 91: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

77

Rank Number

G2 and G7 Maximised

Original rank position

Current rank Rank Change

1 X12 X18 1

2 X18 X12 -1

3 X8 X8 0

4 X10 X10 0

5 X5 X5 0

6 X1 X13 2

7 X17 X1 -1

8 X13 X6 1

9 X6 X17 -2

10 X14 X16 2

11 X7 X14 -1

12 X16 X7 -1

13 X9 X15 1

14 X15 X9 -1

15 X11 X2 2

16 X3 X11 -1

17 X2 X3 -1

Page 92: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

78

18 X4 X4 0

Total rank change: 9

Table 5-1

A safety conscious society would impose the second largest cost of

implementation from change in risk rank.

5.1.2 Scenario 2 – Eco-Environmental

Another example could be of a society who becomes extremely eco-

environmentally friendly; this would influence the risk weighting of all

environmental criteria – maximising emphasis on detectability (G6) and tonnes

of carbon dioxide avoided per year (G9). Similarly these design parameters are

considered below;

Rank Number

G1, G6 and G9 Maximised

Original rank position

Current rank

Rank Change

1 X12 X18 1

2 X18 X12 -1

3 X8 X10 1

4 X10 X8 -1

5 X5 X1 1

6 X1 X13 2

7 X17 X5 -2

8 X13 X17 -1

Page 93: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

79

9 X6 X6 0

10 X14 X14 0

11 X7 X7 0

12 X16 X16 0

13 X9 X9 0

14 X15 X11 1

15 X11 X15 -1

16 X3 X2 1

17 X2 X3 -1

18 X4 X4 0

Total rank change: 7

Table 5-2

Scenario 2 has the second lowest rank change, demonstrating a lower cost of

execution than both scenarios 1 and 4.

5.1.3 Scenario 3 – Socio-economic

The third condition could involve a business orientated society where business

image and profitability is most crucial. This would maximise non-financial risk to

business (G3) and Direct/ Indirect cost of failure (G5);

Rank Number

G3 and G5 Maximised

Original rank position

Current rank

Rank Change

Page 94: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

80

1 X12 X12 0

2 X18 X18 0

3 X8 X8 0

4 X10 X10 0

5 X5 X17 2

6 X1 X5 -1

7 X17 X1 -1

8 X13 X13 0

9 X6 X6 0

10 X14 X14 0

11 X7 X7 0

12 X16 X16 0

13 X9 X9 0

14 X15 X15 0

15 X11 X11 0

16 X3 X3 0

17 X2 X2 0

18 X4 X4 0

Total rank change: 2

Table 5-3

Page 95: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

81

The rank change score of 2 indicates that there is little change to the current

model and therefore a low cost of implementation.

5.1.4 Scenario 4 - Engineering Longevity

The final scenario considered is the future where the lifespan of the turbine is

most important, by maximising the priority to component failure (G4) and design

life (G8);

Rank Number

G4 and G8 Maximised

Original rank position

Current rank

Rank Change

1 X12 X8 2

2 X18 X10 2

3 X8 X12 -2

4 X10 X18 -2

5 X5 X5 0

6 X1 X13 2

7 X17 X17 0

8 X13 X1 -2

9 X6 X16 3

10 X14 X6 -1

11 X7 X7 0

12 X16 X14 -2

13 X9 X9 0

Page 96: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

82

14 X15 X15 0

15 X11 X3 1

16 X3 X11 -1

17 X2 X2 0

18 X4 X4 0

Total rank change: 10

Table 5-4

Scenario 4 had the highest rank change, with 10 of the alternatives changing

position. This high rank change suggests that the current solution and this new

proposed scenario is vastly different, indicating a high cost of implementation.

While each of these four scenarios is plausible, a combination of these factors

is likely to influence the future direction of the wind energy sector.

5.2 Sensitivity in alternative ratings

The method used for calculating the weighted normalised fuzzy matrix produces

a linear relationship between changes in criteria weight and the closeness

coefficient.

A sensitivity analysis on how small changes in alternative ratings influence the

closeness coefficient will produce a more complete picture of the importance of

individual ratings. This information will help identify the recommended number

of decision makers required to classify risks/ failure modes and their relative

priority in the offshore wind sector.

Page 97: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

83

5.2.1 Individual change

The normalisation process is very sensitive to changes. Equations 3-3 and 3-4

are used to perform optimisation on the averaged fuzzy ratings matrix. When

the criterion is specified as cost, the minimum aij (the smallest part of the fuzzy

number) with respect to that criterion becomes crucial in ascertaining the

complexity of the correlation between input and output. If the change in rating is

not significant then the change in output will be limited to the alternative

changed.

An example would be;

X3, G1, DM1 - increased from P to MP

Original Rank

Position Current Rank

Closeness

coefficient Rank Change

X12 X12 0.2542 0

X18 X18 0.2468 0

X8 X8 0.237 0

X10 X10 0.2314 0

X5 X5 0.2069 0

X1 X1 0.2063 0

X17 X17 0.2057 0

X13 X13 0.2032 0

X6 X6 0.1992 0

Page 98: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

84

X14 X14 0.1885 0

X7 X7 0.1884 0

X16 X16 0.1791 0

X9 X9 0.1692 0

X15 X15 0.1501 0

X11 X11 0.1443 0

X3 X3 0.1362(01) 0

X2 X2 0.1354 0

X4 X4 0.1069 0

Total Rank Change: 0

Table 5-5

The change in the closeness coefficient is highlighted in the table. The original

score from the results section was 0.136967 compared with the altered rating

giving a new CC value of 0.136201 (a minimal change in the individual term –

as predicted). Rank changes can occur when individual changes are made,

however this depends on the initial proximity to other CC values.

5.2.2 Group change - Cost criteria

However if the change in rating creates a new averaged fuzzy aij value below all

other alternative ratings, the outcome for all values in the criterion will be

altered. For a rating modification to be considered large, the separation from

other DMs in the same criterion must be 2 or higher (dependent on a low

variance in decision maker response). A significant alternative is one in which a

small change will result in a change in rank of the maximum (cij) or minimum

(aij) average fuzzy number.

Page 99: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

85

Rank Number

DM1 – G3 – X12 reduced from MP to P

Original rank position

Current rank

Closeness Coefficient

Rank Change

1 X12 X12 0.254152 0

2 X18 X18 0.246818 0

3 X8 X8 0.236966 0

4 X10 X10 0.231433 0

5 X5 X5 0.206862 0

6 X1 X1 0.206277 0

7 X17 X17 0.205712 0

8 X13 X13 0.203197 0

9 X6 X6 0.199203 0

10 X14 X7 0.188377 1

11 X7 X16 0.179115 1

12 X16 X14 0.188499 -2

13 X9 X9 0.1692 0

14 X15 X15 0.150115 0

15 X11 X11 0.144312 0

16 X3 X3 0.136967 0

17 X2 X2 0.13542 0

18 X4 X4 0.106854 0

Page 100: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

86

Total Rank Change: 2

Table 5-6

The initial average aij value for cost criteria 3, alternative number 12, was 0.064.

The decision maker 1 response was changed from MP to P resulting in the

average aij term to reduce to 0.046. This led to decreases in all 18 closeness

coefficients; averaging a 1.72%, and ranging from 0.30% to 7.54% compared

with the initial result. The change in CC resulted in a rank change, moving two

alternatives up and two down in their rank.

Two rank changes can result from a change to a single rating in the decision

matrix.

5.2.3 Group change - Benefit criteria

Conversely if the change in average fuzzy number breaches the initial

maximum value (Cij) and the criterion optimisation designation is for benefit,

then similarly the values of all normalised alternative fuzzy numbers within that

criterion will change accordingly.

The example for the benefit criterion is given in Table 5-7.

X15, G7, DM1 increase from MG to VG

Original Rank

Position Current Rank

Closeness

coefficient Rank Change

X12 X12 0.254 0

X18 X18 0.2461 0

X8 X8 0.2364 0

Page 101: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

87

X10 X10 0.2313 0

X5 X5 0.2061 0

X1 X1 0.2057 0

X17 X17 0.2052 0

X13 X13 0.2025 0

X6 X6 0.199 0

X14 X7 0.1881 1

X7 X14 0.1879 -1

X16 X16 0.1782 0

X9 X9 0.1689 0

X15 X15 0.1514 0

X11 X11 0.1442 0

X3 X3 0.1366 0

X2 X2 0.1349 0

X4 X4 0.1065 0

Total Rank Change: 1

Table 5-7

The alternative chosen created an original cij value of 0.96; the increase in the

rating value gave the new cij value of 0.98. This correspondingly changed the

rank order by one place. The lack of benefit criteria prevented any more

influential examples being used. The small change in final rank despite an

Page 102: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

88

increase of 2 places in rating indicates a low variance within the ranking of the

criteria.

5.2.4 Group change - Solution

One solution to get around the dilemma of high sensitivity is to increase the

number of decision makers in the analysis. This will reduce the sensitivity to

large changes in alternative ratings by a single decision maker, by lowering the

overall contribution of each of the ratings. This will also enable a higher level of

confidence in the risk rating, since it is expected that each of the alternative

responses will fall in a narrow range – outputting a normal distribution with a low

variance (an inversely proportionate relationship between variance and

confidence).

Page 103: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

89

6 Analysis and Discussion

6.1 Analysis

6.1.1 Program structure

The examples used for validation of the TOPSIS program both used

combinations of linguistic risk ratings that precluded any of the average fuzzy

numbers for alternatives from containing zero terms. The results from the 5

decision makers highlighted a fault in the rating scales. When poor and very

poor correlation ratings were allocated by all decision makers, zero terms in the

averaged fuzzy rating scales prevented the normalisation process for cost

optimised criteria (this can be seen in Equation 3-4 in chapter 3).

In order to circumvent this error, the scale was changed such that the minimum

coefficient of the fuzzy number was at most 1% of the peak value in the scale.

This prevented a zero coefficient from occurring in the criteria normalisation

while having little effect on the overall results.

This problem was limited to the rating of alternatives since the criteria weighting

is not normalised, and so the limits of the criteria are linked to the FPIS and

FNIS scales.

6.1.2 Decision maker Responses

The results from the decision makers were analysed, giving the ranking shown

in Table 4-12. The largest risk was interference from or to marine life migration,

this was unexpected (volatility in wholesale energy costs was expected to be

the highest, but subsequently ranked 9/18). One of the reasons why this risk

was selected as the largest potential hindrance to the installation and operation

of OWFs could be the overwhelming number of government and non-

government stakeholders for the protection of offshore wildlife.

The second highest risk was from the supply chain, this can be expected since

delays or failure to produce the equipment is highly problematic in developing

Page 104: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

90

industries; where alternative companies for sourcing parts/ reducing costs are

scarce. Change in renewable energy policy ranked third, indicating the influence

politics has on the future development of the sector. This could also have been

influenced by modern developments in shale gas (in the UK) which could

promise to bring down carbon fuel costs (and reduce the political need for

energy independence – through renewables).

Carbon footprint was ranked 4th which was expected. There is an increasing

interest in minimising carbon dioxide emissions and so carbon taxes are applied

to all products which either directly or indirectly expelled CO2 during their

production and transportation. Material Failure is an always present risk when

planning for offshore development and was ranked 5th accordingly.

Improvements in both design and material behaviour aim to make the failure of

these structures more predictable, to ensure adequate maintenance.

Legislation is required in the production of all engineering sectors to ensure the

product is built within strict limits for allowable risks. This is to prevent damage

to the environment or injury to humans operation on or around the structures.

This was ranked 6th above energy storage and transportation (which is currently

under construction with the aim of promoting commercial offshore installations).

This project aims to improve communication between the engineers (to convey

risks) to upper level management (and accountants). This project risk was

ranked 8th overall by the decision makers.

Volatility in wholesale energy costs was expected to rank higher since it directly

influences the (already narrow) profit margin to make the sector feasible.

Current high cost of energy may keep the production of offshore wind viable into

the near future; however changes in alternative energy source costs may harm

future investment in the sector.

The risk of bird impacts had two sides to it; environmental from loss of bird life

and structural damage to the aerofoils. As such it was collaboratively ranked

10th place, ahead of change in government position on subsidies at 11th.

Page 105: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

91

Failure of automated detection systems slightly outranked failure of information

transfer most likely from the reliance of the detection systems where visual

inspection is difficult. Information transfer should be maintained if the correct

standards are adhered to.

Force majeure (unknown risk) and change is environmental conditions ranked

14th and 15th respectively. Delay, human error and change in health and safety

were the three lowest rated risks associated with offshore wind. Each of these

terms were expected to rank higher, however delay is more of a generic term

and hence more specific causes for delay (problems with supply chain) are

rated higher. Human error is currently being reduced to a minimum with designs

re-checked before sent for production, and is controlled autonomously and

hence reducing human interaction. Changes to health and safety is likely

however only in the medium to long term, if human interaction is designed out of

the maintenance process, health and safety (for maintenance) will no-longer be

important. There is little impact changes in policy can have on the final 5 risks

ranked (and hence their position in the ranking).

It is important to remember that these surveys capture a snapshot in time for

predicted risks faced by offshore wind. The information provided should be re-

generated at all phases of the project, to ensure the appropriate action for the

risk faced at any particular time.

Figure 6-1shows the trend in the output data, a linear regression line has been

added to indicate the relationship between rank and closeness coefficient. The

linear relationship shows that there is little to no skew in the output data,

suggesting that changes to the inputs should have a proportionate impact on

the ranking of the alternatives.

Page 106: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

92

Figure 6-1

6.2 Discussion

6.2.1 General

This thesis has explored concepts from failure mode and effects analysis and

applied them to a multi-criteria decision making method to enhance problem

solving for risk in the offshore wind energy sector.

The validity of the results for use in the offshore industry would require further

input from relevant stakeholders identified in the literature review. These include

but are not limited to; Academic institutions, insurance brokers, banking,

government officials and a wider array of experts from the offshore renewable

sector.

The selection of risks and failure modes extracted from the risk register were

able to prove that optimisation of resource allocation to risks through the use of

multi-criteria analysis is possible. The next step in the process of method

validation to enable a group consensus will require the method being applied in

a range of scenarios (for example as a cost optimisation tool for banking or a

benefit analysis for insurance brokers). The ability to reach group consensus is

0

0.05

0.1

0.15

0.2

0.25

0.3

0 5 10 15 20

Clo

sen

ess

Co

eff

icie

nt

Rank

Variation in closeness coefficient with respect to rank

Distribution of End Results

Linear (Distribution of EndResults)

Page 107: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

93

dependent on the flexibility of the program to meet the requirements of a range

of industries.

6.2.2 Program

Both the criteria and alternatives were chosen to be representative for

application to multiple phases in offshore wind. In reality, these should be

broken down and evaluated as separate individual phases to ensure risks are

not overlooked or under evaluated.

The results expressed in this thesis are an indication of how a full scale

evaluation of how multi-criteria analysis can be applied to the ranking and

prioritisation of risks and failure modes in offshore wind. The number and type

of failure modes/ risk can be changed to suit the project phase. Some

evaluation criteria are required in all areas of project implementation (such as

costs). The variation in rank of these common criteria should provide a basis to

correlate different risk criteria metrics to assign relative importance when

evaluating the combined project risk.

Kutlu, A. C. and Ekmekçioğlu, M. (2012) [53], provided an analysis using a

combination of FAHP and fuzzy TOPSIS to evaluate the three risk criteria used

in failure mode and effects criticality assessment. The closeness coefficients

produced from this study were of the same order of magnitude as the results

obtained in this study. It was decided that AHP would not be used within this

thesis based on limitations preventing rank reversal and the increase in the time

taken for decision makers to rate on an implicit scale system. This study

contained more than twice the number of alternatives and it was concluded that

AHP works best from a small number of comparisons.

Sachdeva, A. and Kumar, D. and Kumar,P. (2009) [54], doubled the number of

evaluation criteria used in FMECA to enable comparisons with cost, safety and

spare parts for a more in-depth evaluation of the resources available to improve

the maintenance phase. Direct explicit scales were used where the MTBF was

Page 108: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

94

separated into duration in terms of months to characterise the occurrence rate.

This study decided not to restrict the ranges for the evaluation criteria to be as

inclusive of varying aspects of the risk evaluation as possible. The sensitivity

analysis (chapter 5) attempted to provide insight into the variation in potential

futures and the effect on the cost of implementation based on current ranking.

This found that designing for both long (wind turbine) life and increased

restrictions on safety would create the greatest cost of implementation relative

to the two other potential future scenarios. These future scenarios link to the

additional criteria used in [54].

The program was designed for application in the insurance industry. The next

step to be performed for the program is to ascertain the maximum number of

alternatives that are expected for any particular phase of a project (since

projects are insured by project phase).

Page 109: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

95

7 Conclusion – Section 7

The project aimed to implement a program capable of taking multiple inputs and

creating a verifiable and representative single metric for renewable energy

projects to be compared against one another.

The project goal is achievable by finding common risk areas throughout the

renewable energy industry (such as cost, design life, energy yield, etc.) and

comparing the top ranked alternatives within each of the energy sectors

respectively. The difference between these energy sectors will always induce

some ambiguity in risk caused by the lack of compatibility of risk evaluation

criteria.

A variety of risks were found in each of the project phases, and the

understanding/ experience of the decision makers changed was indicated by

variance in response. Selecting criteria for the evaluation of risks was difficult

and was hence generalised for simplicity. The evaluation criteria chosen were

not ideal for all risks faced in OWFs; therefore further analysis by project phase

is required.

Assigning project risk is a dynamic process, in which risk results are only

applicable for a limited time step (before external changes influence the risk

rank). This constant rank change is one of the key reasons why TOPSIS was

used in preference to AHP (which does not allow for rank reversal).

The use of fuzzy TOPSIS enabled a far greater range of outcomes effectively

eliminating the problems related to number repetition. The cause of repetition

stemmed from the use of crisp numbers to generate the RPN in the FMECA

method (which was criticised in the literature review). The ability to select new

criteria and apply a relative weighting in TOPSIS solved the difficulties in the

generation of a representative outcome for resource allocation (an extension to

the three criteria used to generate the RPN). The use of explicit linguistic values

to rate the alternatives minimised the decision maker’s response time (which

lowers the project cost).

Page 110: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

96

The normalisation process enabled changes in the numerical range of the

scales which were used to translate the qualitative linguistic ratings into

quantitative fuzzy numbers for the alternatives. It was found that changes to the

quantitative scales for the weighting of criteria could be achieved by allowing

the user to assign the fuzzy positive/ negative ideal solutions the same limits as

the new weighting scale. These changes make the program more flexible and

hence applicable to bespoke applications.

7.1 Further Work

One future prospect would obtain decision maker results for risk matrices

generated by project phase and measure the cumulative total project risk.

Application of the decision tool to a real world problem will find the accuracy of

the program and characterise its usefulness. When applying the method to a

real world problem, taking several surveys (from decision makers) over the

project lifespan will help identify the dynamic change in risk priorities.

Another dynamic risk analysis could be obtained from asking the decision

makers to rank the alternatives with respect to changing socio-economic

conditions to find the project sensitivity to the business operating climate.

Further work should include running tests involving larger arrays of alternatives,

criteria and decision makers to calculate if there is a 1/n effect on the average

fuzzy rating (where n=number of DMs) relationship between changing a single

rating by one linguistic value. This would enable optimisation to find the

minimum number of DMs required for ambiguities in responses not to

significantly skew the data.

Page 111: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

97

REFERENCES

1. [1] Haralambopoulos, D. A. and Polatidis, H. (2003), "Renewable energy projects: structuring a multi-criteria group decision-making framework", Renewable Energy, vol. 28, no. 6, pp. 964.

2. [2] BS ISO 31000:2009

3. [3] United Nations. (1998). Kyoto Protocol to the United Nations

Framework Convention on Climate Change. United Nations. ( ), p2.

4. [4] The Green Investment Bank. (2014). UK Green Investment Bank invests £461m in the UK offshore wind sector. Available: http://www.greeninvestmentbank.com/news-and-insight/2014/uk-green-investment-bank-invests-461m-in-the-uk-offshore-wind-sector/. Last accessed 1st August 2014.

5. [5] The Coalition Government. (2010). The Coalition: our programme for government. Crown Copyright. (Ref: 401238 / 0), p16.

6. [6] Newton, P. (2013). DECC agrees budget cut with Treasury. Available: http://www.chpa.co.uk/decc-agrees-budget-cut-with-treasury_1430.html. Last accessed 29th July 2014.

7. [7] Kolios, A, Read, G & Ioannou, A. (2014). Application of multi-criteria decisionmaking to risk prioritisation in tidal energy developments. International Journal of Sustainable Energy. ( ), p5.

8. [8] British Wind Energy Association. (2002). Consultation for offshore wind. Best Practice Guidelines. 1 (1), 9.

9. [9] Insurance Information Institute. (2013). World Rankings. Available: http://www.iii.org/publications/online-financial-services-fact-book-2013/world-rankings. Last accessed 12th August 2014.

10. [10] The Green Investment Bank. (2013). Green Investment Policy. Green Investment Bank. ( ), 7.

11. [11] RenewableUK. (2012). Wind Energy in the UK: State of the Industry Report 2012. RenewableUK. ( ), p4.

12. [12] Gibson, E, Howsam, P. (2010). The legal framework for offshore wind farms: A critical analysis of the consents process. Energy Policy. 38 ( ), p4700.

13. [13] Green Investment Bank. (2014). what we do - offshore-wind. Available: http://www.greeninvestmentbank.com/what-we-do/offshore-wind/default.html. Last accessed 10th June 2014.

14. [14] The European Commission. (2013). Renewable energy progress report. The European Commission. ( ), 1-15.

15. [15] European Commission (2013), “The Renewable Energy Directive 2009/28/EC”, SWD(2013) 102 final, pp. 2-6.

16. [16] Matthias Finger et al. (2013). Policy Brief: A New EU Energy Technology Policy. European University Institute. 2013/01 ( ), p1-5.

17. [17] Delay, T and Jennings, T. (2008). Offshore wind power: big challenge, big opportunity Maximising the environmental, economic and security benefits. The Carbon Trust. 1 (1), p90.

Page 112: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

98

18. [18] Dykes, K et al. (2012). Sensitivity Analysis of Offshore Wind Cost of Energy. OFFSHORE WINDPOWER NREL. ( ), 1.

19. [19] Matthias Finger et al (2013), “THINK-Topic9: A new EU Energy Technology Policy towards 2050: Which way to go?”, Seventh Framework Plan, pp. 47

20. [20] Kolios, A and Read, G. (2013). A Political, Economic, Social, Technology, Legal and Environmental (PESTLE) Approach for Risk Identification of the Tidal Industry in the United Kingdom. Energies. 6 ( ), 5026.

21. [21] Haggett, C. (2011), "Understanding public responses to offshore wind power", Energy Policy, vol. 39, no. 2, pp. 503-510.

22. [22] Higgins, P. and Foley, A. (2014), "The evolution of offshore wind power in the United Kingdom", Renewable and Sustainable Energy Reviews, vol. 37, no. 0, pp.603.

23. [23] Higgins, P. and Foley, A. (2014), "The evolution of offshore wind power in the United Kingdom", Renewable and Sustainable Energy Reviews, vol. 37, no. 0, pp.605.

24. [24] Spiropoulou, I., Karamanis, D. and Kehayias, G. "Offshore wind farms development in relation to environmental protected areas", Sustainable Cities and Society, , no. 0, p2-3.

25. [25] The British Government. (2009). Marine and Coastal Access Act 2009 . Crown copyright. 23 (4), p83.

26. [26] Spiropoulou, I., Karamanis, D. and Kehayias, G. "Offshore wind farms development in relation to environmental protected areas", Sustainable Cities and Society, , no. 0, p2.

27. [27] Hammar, L., Wikström, A. and Molander, S. (2014), "Assessing ecological risks of offshore wind power on Kattegat cod", Renewable Energy, vol. 66, no. 0, pp. 414-424.

28. [28] Deborah J.F. Russell, Sophie M.J.M. Brasseur, Dave Thompson, Gordon D. Hastie, Vincent M. Janik, Geert Aarts, Brett T. McClintock, Jason Matthiopoulos, Simon E.W. Moss, Bernie McConnell. Marine mammals trace anthropogenic structures at sea. Current Biology, 2014; 24 (14)

29. [29] Garrad Hassan. (2012). Test & Demonstrate: opportunities for reducing UK offshore wind cost and risk. The Crown Estate. ( ), 2.

30. [30] Richard Green, NicholasVasilakos. (2011). The economics of offshore wind. Energy Policy. 39 ( ), 496-502. Combined with general knowledge.

31. [31] Risktec. (2011). De-Risking Offshore Wind Energy. RISKworld. Issue19 ( ), p5.

32. [32] British Wind Energy Association. (2002). BWEA Best Practice Guidelines. Consultation for offshore wind energy developments. 1 (1), 16.

33. [33] Higgins, P. and Foley, A. (2014), "The evolution of offshore wind power in the United Kingdom", Renewable and Sustainable Energy Reviews, vol. 37, no. 0, pp. 599-612.

Page 113: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

99

34. [34] RISKworld. (2014). De-risking Offshore Wind Energy. Available: http://www.risktec.co.uk/knowledge-bank/technical-articles/de-risking-offshore-wind-power.aspx. Last accessed 10 August 2014.

35. [35] (2013). Deepwater Horizon accident and response. Available: http://www.bp.com/en/global/corporate/gulf-of-mexico-restoration/deepwater-horizon-accident-and-response.html. Last accessed 8th August 2014.

36. [36] CFO Research. (2012). The Finance View of Non-financial Risk for Technology Companies. CFO Publishing LLC. , p4.

37. [37] Saaty, R. W. (1987), "The analytic hierarchy process—what it is and how it is used", Mathematical Modelling, vol. 9, no. 3–5, pp. 161-176.

38. [38] Sharma, B.C. Gandhi, O.P. (2006). RUL assessment of lube oil using AHP and vector projection approach. Available: http://www.emeraldinsight.com/journals.htm?articleid=1558402#idb12. Last accessed 15th June 2014.

39. [39] Braglia, M. (2000), "MAFMA: multi-attribute failure mode analysis", Emeraldinsight, vol. 17, no. 9, pp. 1017--1033.

40. [40] Braglia, M. (2000), "MAFMA: multi-attribute failure mode analysis", Emeraldinsight, vol. 17, no. 9, pp. 1017--1033.

41. [41] Carmignani, G. (2009), "An integrated structural framework to cost-based FMECA: The priority-cost FMECA", Reliability Engineering & System Safety, vol. 94, no. 4, pp. 861-871.

42. [42] Rhee, S. J. and Ishii, K. (2003), "Using cost based FMEA to enhance

reliability and serviceability", Advanced Engineering Informatics, vol. 17,

no. 3–4, pp. 179-188.

43. [43] Sachdeva, A. and Kumar, D. and Kumar,P. (2009), "Multi-factor

failure mode criticality analysis using TOPSIS", Journal of Industrial

Engineering International, Vol.5, mo.8 pp 1--9.

44. [44] BS EN 60812:2006

45. [45] A. Hadi-Vencheh1, M. Aghajani. (2013). Failure mode and effects

analysis: A fuzzy group MCDM approach. Journal of Soft Computing and

Applications. 2013 ( ), 1-14.

46. [46] US MIL-STD-1629A

47. [47] Liu, H., Liu, L. and Liu, N. (2013), "Risk evaluation approaches in

failure mode and effects analysis: A literature review", Expert Systems

with Applications, vol. 40, no. 2, pp. 828-838.

48. [48] Gupta, P, Mehlawat, M, Inuiguchi, M and Chandra, S (2014). Fuzzy Portfolio Optimisation. London: Springer. p61.

49. [49] Hwang, C.L., Yoon K. (1981).Multiple Attribute Decision Making:

Methods and Applications. Springer, Heidelberg

50. [50] Pommeranz, A et al. (2012). Designing interfaces for explicit

preference elicitation: a user-centered investigation of preference

representation and elicitation process. Springerlink. 22 ( ), p 357-397.

Page 114: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

100

51. [51] Chen-Tung Chen. (2000). Extensions of the TOPSIS for group decision-making. Fuzzy Sets and Systems. 114 ( ), p1-9.

52. [52] Yong-tao Tan and Li-yin Shen et al. (2010). Constructing Project selection using Fuzzy TOPSIS approach. Journal of Modelling in Management. 5 (3), pp. 302-315.

53. [53] Kutlu, A. C. and Ekmekçioğlu, M. (2012), "Fuzzy failure modes and effects analysis by using fuzzy TOPSIS-based fuzzy AHP", Expert Systems with Applications, vol. 39, no. 1, pp. 61-67.

54. [54] Sachdeva, A. and Kumar, D. and Kumar,P. (2009), "Multi-factor failure mode criticality analysis using TOPSIS", Journal of Industrial Engineering International, Vol.5, mo.8 pp 1--9.

APPENDICES

Appendix A Literature Review

A.1 MCDM Methods

A.1.1 AHP Example

Page 115: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

1

Figure 7-1

Page 116: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

2

A.1.2 FMECA Tables

Table 4, [44]:

Page 117: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

3

Table 5, [44]:

Page 118: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

4

Table 6, [44]:

Page 119: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

5

Appendix B Methodology

B.1.1 Fuzzy TOPSIS program

Fuzzy TOPSIS User Interface

Page 120: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

6

Figure 7-2

Page 121: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

7

Figure 7-3

Page 122: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

8

Figure 7-4

Figure 7-5

Page 123: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

10

9

Figure 7-6

Figure 7-7

Page 124: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

0

Figure 7-8

Figure 7-9

Page 125: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

1

Figure 7-10

Page 126: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

2

Figure 7-11

Page 127: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

3

Figure 7-12

Page 128: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

4

Figure 7-13

Page 129: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

5

Figure 7-14

Page 130: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

6

B.1.2 Questionnaire

This evaluation is for the offshore

wind renewable energy sector.

Using the scales provided, please

complete the table comparing the

criteria with the risks (alternatives).

Scale for the weighting of criteria:

Qualitative weighting

Linguistic term

VL Very Low

L Low

ML Moderately Low

M Medium

MH Moderately High

H High

VH Very High

Criteria Relative Importance

Weighting Benefit or cost

criteria

Impact on environment Cost

Fatalities Cost

Risk to business - non-financial

Cost

Component failure Cost

Direct/ Indirect cost of failure Cost

Detectability Benefit

Redundancy/ Mitigation Benefit

Design life Benefit

Tonnes of carbon dioxide avoided per year

Benefit

Page 131: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

7

Scale for the ranking of alternatives:

Qualitative rating of

risks

Correlation with

criteria

VP Very Poor

P Poor

MP Moderately Poor

F Fair

MG Moderately Good

G Good

VG Very Good

List of alternatives (from risk register);

Legislation Carbon footprint

Human Error Change in environmental

conditions

Delay Marine life migration

Change in Health and safety Communication to upper level

management

Material failure Bird impacts

Volatility in wholesale energy

costs Force Majeure

Change in government position

on subsidies

Failure of automated detection

systems

Change in RE Policy Energy storage and transfer

Failure of information transfer Supply chain

Page 132: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

8

Risk matrix

Impact on

environment Fatalities

Risk to

business -

non-

financial

Component

failure

Direct/

Indirect

cost of

failure

Detectability Redundancy/

Mitigation

Design

life

Tonnes

of CO2

avoided

per

year

Legislation

Human Error

Delay

Change in

Health and

safety

Material failure

Volatility in

wholesale

Page 133: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

11

9

energy costs

Change in

government

position on

subsidies

Change in RE

Policy

Failure of

information

transfer

Carbon

footprint

Change in

environmental

conditions

Page 134: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

0

Marine life

migration

Communication

to upper level

management

Bird impacts

Force Majeure

Failure of

automated

detection

systems

Energy storage

and transfer

Supply chain

Page 135: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

1

Appendix C Results

C.1 Decision Maker 1

C.1.1 Risk matrix

Impact on environment

Fatalities

Risk to business

- non-financial

Component failure

Direct/ Indirect cost of failure

Detectability

Redundancy/ Mitigation

Design life

Tonnes of

carbon dioxide avoided per year

Legislation VG F MG F G F F F G

Human Error MP G G G G MP MP P P

Delay P P MG MG P P MG MP

Change in Health and

safety

P VG G G F F P P P

Material failure P MG G G MG F MG G P

Volatility in wholesale

energy costs

MG VP G P P MP P MP MG

Change in government position on subsidies

MG P G P F P MP P G

Page 136: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

2

Change in RE Policy

G P F VP F VP F MP VG

Failure of information

transfer

G MG MG G G F MP F F

Carbon footprint

G P F VP F F VP VP VG

Change in environmental

conditions

G MP MG VP MP F VP MP MP

Marine life migration

F VP MP VP VP F VP P P

Communication to upper

level management

G G MG MG F F F G MG

Bird impacts MG P MP P P MG F P VP

Force Majeure G F G P F MP MG P P

Failure of automated detection systems

P G G G G MP G G P

Energy storage and

transfer

G MP MP VP G VP F MP VG

Supply chain

P P VG F VG F F P MP

Table 7-1

Page 137: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

3

C.1.2 Criteria weighting

Criteria Relative Importance

Weighting Benefit or cost criteria

Impact on environment H Cost

Fatalities H Cost

Risk to business - non-financial MH Cost

Component failure M Cost

Direct/ Indirect cost of failure M Cost

Detectability M Benefit

Redundancy/ Mitigation MH Benefit

Design life M Benefit

Tonnes of carbon dioxide avoided per year MH Benefit

Table 7-2

C.2 Decision maker 2

C.2.1 Risk matrix

Impact on

environment Fatalities

Risk to business

- non-

Component failure

Direct/ Indirect cost of

Detectability

Redundancy/ Mitigation

Design life

Tonnes of carbon dioxide

Page 138: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

4

financial failure avoided per year

Legislation G F G F MG F F MG G

Human Error P G G G MG P MP F P

Delay MP MP MG F MG MP MP MG MP

Change in Health and

safety

MP VG G MG MG F MP P P

Material failure P G MG MG MG F F G P

Volatility in wholesale

energy costs

G VP G P P F P MP MG

Change in government position on subsidies

G P G P MG P P MP G

Change in RE Policy

G P F VP MP VP F P G

Failure of information

transfer

G MG F G MG F P F F

Carbon footprint

G MP F VP F F VP P G

Change in environmental

conditions

MG MP G VP MP F VP P P

Marine life migration

F VP P VP P F P P P

Page 139: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

5

Communication to upper

level management

G MG F MG F F F G MG

Bird impacts G MP P P MP G F P VP

Force Majeure G F F VP F MP G P P

Failure of automated detection systems

P MG MG G MG MP MG G P

Energy storage and

transfer

G P P VP MG VP MP MP G

Supply chain

P P G MG VG F MG MP MP

Table 7-3

Page 140: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

6

C.2.2 Criteria Weighting

Criteria Relative Importance

Weighting Benefit or cost criteria

Impact on environment VH Cost

Fatalities H Cost

Risk to business - non-financial H Cost

Component failure M Cost

Direct/ Indirect cost of failure MH Cost

Detectability M Benefit

Redundancy/ Mitigation MH Benefit

Design life M Benefit

Tonnes of carbon dioxide avoided per year M Benefit

Table 7-4

Page 141: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

7

C.3 Decision Maker 3

C.3.1 Risk matrix

Impact on environment

Fatalities

Risk to business - non-financial

Component failure

Direct/ Indirect cost of failure

Detectability

Redundancy/ Mitigation

Design life

Tonnes of carbon dioxide avoided per year

Legislation G G VP MP VP F VP VP G

Human Error VP VG F F VP G VP F VP

Delay VP VP VG VP VP VP VP VP G

Change in Health and safety

VP VG P F VP P VP VP VP

Material failure VP F F VG VG P P G VP

Volatility in wholesale energy costs

VP VP VP VP VG VP VP VP VP

Page 142: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

8

Change in government position on subsidies

VP VP G VP VP VP VP P P

Change in RE Policy

VP VP G VP VP VP VP P P

Failure of information transfer

VP F P G G G VP G VP

Carbon footprint VG VP VP VP VP VP VP G VG

Change in environmental conditions

P MG G VG VG VG VP VG VG

Marine life migration

G VP VP MP VP VP VP VP VP

Communication to upper level management

VP VP P P MP P F P P

Bird impacts F P P G G VP VP F VP

Page 143: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

12

9

Force Majeure VP VP G G G G G G VP

Failure of automated detection systems

G P G VG VG VG MP MP MP

Energy storage and transfer

G MP G P P P P P F

Supply chain P P G G G MP P G G

Table 7-5

Page 144: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

0

C.3.2 Criteria Weighting

Criteria Relative Importance Weighting Benefit or cost criteria

Impact on environment L Cost

Fatalities MH Cost

Risk to business - non-financial H Cost

Component failure VH Cost

Direct/ Indirect cost of failure H Cost

Detectability H Benefit

Redundancy/ Mitigation L Benefit

Design life M Benefit

Tonnes of carbon dioxide avoided per year VH Benefit

Table 7-6

C.4 Decision Maker 4

Page 145: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

1

C.4.1 Risk matrix

Impact on environment

Fatalities

Risk to business - non-financial

Component failure

Direct/ Indirect cost of failure

Detectability

Redundancy/ Mitigation

Design life

Tonnes of carbon dioxide avoided per year

Legislation G F MG F MG F F MG G

Human Error P MG G G MG P MP F P

Delay MP MP MG F MG p MP MG MP

Change in Health and safety

MP VG G MG MG F MP P P

Material failure P G MG MG MG MP F G P

Volatility in wholesale energy costs

G VP G MG P F P MP MG

Change in government position on subsidies

G P MG MP MG P P MP VG

Change in RE Policy

G P F VP MP VP F P VG

Page 146: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

2

Failure of information transfer

G MG F G MG F P F F

Carbon footprint

G MP F VP F MG VP P G

Change in environmental conditions

MG MP G VP MP F VP P MP

Marine life migration

MG VP MP VP P F P P P

Communication to upper level management

G MG F MG F F F G G

Bird impacts G MP MP P MP G F P VP

Force Majeure G F F VP F P G P P

Failure of automated detection systems

P MG MG G MG MP MG G P

Energy storage and

G P P VP MG VP MP MP G

Page 147: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

3

transfer

Supply chain P P G MG VG F MG MP P

Table 7-7

Page 148: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

4

C.4.2 Criteria Weighting

Criteria Relative Importance Weighting Benefit or cost criteria

Impact on environment H Cost

Fatalities M Cost

Risk to business - non-financial M Cost

Component failure ML Cost

Direct/ Indirect cost of failure M Cost

Detectability MH Benefit

Redundancy/ Mitigation MH Benefit

Design life M Benefit

Tonnes of carbon dioxide avoided per year

MH Benefit

Table 7-8

C.5 Decision Maker 5

C.5.1 Risk matrix

Page 149: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

5

Impact on environment

Fatalities

Risk to business - non-financial

Component failure

Direct/ Indirect cost of failure

Detectability

Redundancy/ Mitigation

Design life

Tonnes of carbon dioxide avoided per year

Legislation VG F MG F G F F F G

Human Error MP G G F G MP F F F

Delay F F MG MG P P MG MP

Change in Health and safety

F VG G G F F P P P

Material failure

P MG G G MG F MG G P

Volatility in wholesale energy costs

MG VP G P P MP P MP MG

Change in government position on subsidies

MG P G P F P MP P G

Page 150: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

6

Change in RE Policy

G P F VP F VP F MP VG

Failure of information transfer

G MG MG G G F MP F F

Carbon footprint

G P F VP F F VP VP VG

Change in environmental conditions

G MP MG VP MP F VP MP MP

Marine life migration

F VP MP VP VP F VP P P

Communication to upper level management

G G MG MG F F F G MG

Bird impacts MG P MP P P MG F P VP

Force Majeure

G F G P F MP MG P P

Failure of automated detection

P G G G G F G G P

Page 151: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

7

systems

Energy storage and transfer

G MP MP VP G VP F MP VG

Supply chain P P VG F VG F F P MP

Table 7-9

Page 152: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

13

8

C.5.2 Criteria weighting

Criteria Relative Importance Weighting Benefit or cost criteria

Impact on environment MH Cost

Fatalities ML Cost

Risk to business - non-financial MH Cost

Component failure M Cost

Direct/ Indirect cost of failure M Cost

Detectability M Benefit

Redundancy/ Mitigation M Benefit

Design life M Benefit

Tonnes of carbon dioxide avoided per year

H Benefit

Table 7-10

Page 153: CRANFIELD UNIVERSITY THOMAS BRINDLEY SINGLE SCORE …

139

Appendix D Digital Information

CD 1 contains electronic copies of all the software and documents used in the

thesis.