Upload
scribdstorage
View
212
Download
0
Embed Size (px)
Citation preview
7/26/2019 Cpo Report 2015 Main Report May2015
1/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014I
IntroductionPlanning and Housing CPOs 2003-2014
Compulsory Purchase Orders: 2015 update
7/26/2019 Cpo Report 2015 Main Report May2015
2/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014II 1
Foreword 2
Introduction 4
Planning and Housing CPO Statistics 2012-2014 7
Effectiveness of CPOs
Implementation by Acquiring Authorities 19
Reasons why some CPOs fail
Secretary of State decisions 2009 2014 22
Enabling power and clarity of objectives 23
Technical deficiencies 25
Procedural issues/Withdrawal of Order 27
Housing CPO evidential burden 29
Deliverability/Financial Viability/Alternative Scheme 33
Acquisition by agreement 37
Failure to demonstrate need 38
Not confirmed/Withdrawal by consent 40
Comments on reasons for CPO failure 42
Appendix: Schedule of CPOs 43
Contents
7/26/2019 Cpo Report 2015 Main Report May2015
3/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 32
Foreword
Continued high success rates with both
Planning and Housing Compulsory PurchaseOrders (CPOs) and a recovery in the use ofPlanning CPOs demonstrates howcompulsory purchase assists in drivingurban regeneration and housing renewal.
CPOs are demonstrably an effective
tool in the armoury of local
authorities. As can be seen from our
latest research, Planning CPOs
continue to drive regeneration, and
facilitate development and
redevelopment, particularly in urban
areas. Although levels of usage
remain lower than pre-recession
figures, 2014 saw a significant
recovery in the use of PlanningCPOs, hopefully presaging the
returning economic confidence and
increasing viability of major schemes.
Both Planning and Housing CPOs
have very high success rates. In
broad, headline terms we consider
that it is reasonable to conclude that
95% or more CPOs are actively
confirmed or result in acquisition
by agreement being achieved.
Moreover such rates have been
achieved consistently, year
upon year.
To the extent that the making of
Planning CPOs operates as a proxy
for economic confidence given that
the making of a CPO is often
representative of a key step incommitment by both the public and
private sectors towards a major
development scheme the signs of
renewed development activity are
encouraging. In 2014 58 Planning
CPOs were submitted compared
with 36 in 2013 representing a 61%
increase. Moreover although the hot
spots for use of CPOs remain
London, the Midlands and the North
West, there is evidence that CPOs
are being used nationwide. In
addition, CPOs are used to
assemble site for smaller schemes of
considerable local significance.
For example, 2014 has seen
Planning CPOs made promoting
major schemes such as the retail-led
Whitgift Centre in Croydon, theWatford Health Campus, and
housing-led schemes such as
Barnet LBCs West Hendon
Regeneration Area and Phase 3
of the Edge Hill project made by
Liverpool City Council.
Frank Orr
Legal Director
T: +44 191 279 9086E:frank.orr
@bonddickinson.com
Key contact
Housing CPOs are more likely to
involve acquisition of individual
properties or small groups or
clusters. That they can be aneffective, coordinated tool for
housing regeneration and
improvement is well evidenced by
their use by Burnley Borough
Council, which has utilised Housing
CPOs extensively as part of its
Vacant Property Initiative (VPI),
addressing long-term vacant
property as part of a targeted
approach to housing improvement.
CPOs must of course be used
carefully and proportionately, having
proper regard to the rights of
affected third parties. Acquiring
Authorities must demostrate that
there is a compelling case in the
public interest for a CPO to be
confirmed.
Generally local authorities
possessing compulsory purchase
powers (ie Acquiring Authorities)
use their powers sparingly and most
make only one CPO in any givenyear. There is a small, but not
insignificant, body of Acquiring
Authorities that use their powers
more frequently. This we consider
reflects their positive experience
gained from repeated success with
CPOs and the allocation of
resources such as dedicated
CPO staff.
Our Freedom of Information
enquiries to Acquiring Authorities (for
which we are grateful for the
responses received) suggestshowever that in many cases there is
an absence of an active corporate
memory of how CPOs were used
and what lessons have been
learned. We would fight shy of
suggesting that a statutory register
of CPOs and their outcomes is
required, but it is best practice for an
acquiring authority to review how its
CPOs have been promoted and
whether identified objectives have
been achieved.
As this report goes to press the
Department for Communities and
Local Government and HM Treasury
have jointly instigated consultation
on proposed reform to compulsory
purchase processes. The
consultation reiterates Governments
view that compulsory purchase
powers are an important tool for
assembling land needed to help
deliver social, environmental and
economic change and that usedproperly, compulsory purchase can
contribute towards effective
regeneration.
The consultation also recognises the
need for the compulsory purchase
system to balance interference with
third party rights whilst improving
efficiency and delivery. The
proposals therefore seek to
streamline processes in a number
of ways, including the introductionof timescales for key stages and
decision-making, whist maintaining
fairness to third parties. As this
report identifies compulsory
purchase is an effective tool for
delivering change and regeneration
but there is scope for improving
delivery of properly made CPOs
and that aim of the consultation is
very much to be welcomed.
7/26/2019 Cpo Report 2015 Main Report May2015
4/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 54
Introduction
Among the key messages of the
earlier reports were:
CPOs are a vital tool for
regeneration.
Usage in 2009 was at its lowest
for several years.
Success rates for both Planning
and Housing CPOs were generally
high.
There was a range of reasons,
from technical to evidential, why
some CPOs were not confirmed.
This report updates the statistics
further to the end of 2014 and alsolooks at Secretary of State decisions
between 2009-2014 not to confirm
CPOs, i.e. it seeks to identify the
reasons why CPOs sometimes fail.
In addition, based on information
obtained from Acquiring Authorities,
the report includes initial conclusions
about levels of implementation of
CPOs and commencement of
schemes where sites have been
assembled by CPO.
In 2010, Dickinson Dees LLP (now Bond Dickinson LLP) publisheda detailed review of the use and success of Compulsory PurchaseOrders (CPOs), particularly Planning1and Housing2CPOs. The reportcontained a statistical analysis of the outcomes of CPOs, analysing
how many were confirmed (with or without modification), how manywere not confirmed and how many were treated as withdrawn.It also contained case reviews of the reasons why CPOs were notconfirmed. An update of the statistics was published in 2012.
The statistical report focuses on
Planning and Housing CPOs since
these are by far the most numerous
CPOs made. However, the decision
reviews also include reference to
CPOs made under other powers
where there are notable reasons for
non-confirmation. The key findings of
this report include:
Many local authorities make use of
compulsory purchase powers but
do so sparingly.
Success rates for both Planning
and Housing CPOs remain
consistently high.
In 2013 the use of Planning CPOs
fell to the lowest level since 2003
(the first year covered by this
study), but recovered significantly
in 2014.
Use of Planning Act powers still
remains lower than levels achieved
pre-recession.
There is consistently more
frequent use of Housing Act
powers than Planning Act powers,
with spikes in Housing CPO usage
reflecting targeted programmes of
use by one or two Acquiring
Authorities.
For example, 2013 saw an
increase in the use of Housing Act
powers principally because of
extensive use by a small number
of Acquiring Authorities.
Planning CPOs are more likely to
comprise more complicated
schemes and attract objections
than Housing CPOs;consequently, Planning CPOs on
average take longer than Housing
CPOs to be determined.
Most confirmed CPOs are
implemented by means of General
Vesting Declaration (GVD) as
opposed to using a Notice to
Treat. This vests title in the
Acquiring Authority when
possession occurs.
1. Made under s.226 Town and Country Planning Act 1990
2. Made under s.17 Housing Act 1985
Data derived from Acquiring
Authorities in respect of
implementation is incomplete but
provisionally indicates:
up to 88% of Planning CPOs and
90% of Housing CPOs being
implemented by one or other ofthe statutory methods, or by
agreement in the light of a
confirmed CPO.
at least 56% of Planning CPOs
and 61% of Housing CPOS have
resulted in completed schemes or
schemes that are in progress.
Acquiring Authority derived data
of the timescales involved in the
CPO process is consistent with
DCLG/NPCU data.
The reasons why some CPOs are
not confirmed range from the
technical to evidential and include:
for CPOs generally: technical
drafting errors; the availability of
alternative solutions falling short of
the need for compulsory
acquisition; and failure to
demonstrate that all Order land
was needed
for Housing CPOs: the weight tobe given to an owners ability to
deliver a comparable scheme; the
personal circumstances of an
owner; and the Acquiring
Authoritys failure to put in place
delivery mechanisms for its
preferred scheme
for Planning CPOs: a successful
challenge to the assumptions
underlying the viability of a
proposed scheme; failure to
demonstrate that a CPO was
timely; evidence of planning
impediments; failure to meet the
tests in Circular 06/04; non-
conformity with Local
Development Framework; and
absence of updated evidence
base establishing quantitative
need.
It should also be noted that the
levels of CPOs not confirmed does
not necessarily mean that the CPO
has failed. CPOs are often treated
as not confirmed at the request of
an acquiring authority when
acquisition has occurred by
agreement against the background
of a CPO.
Given that that success rate of
Planning and Housing CPOs
remains high it can be concluded
that they continue to represent a
significant tool available to local
authorities to promote site assembly
and regeneration. We have also
drawn some initial conclusions
based on Acquiring Authority dataas to the extent to which confirmed
CPOs are implemented and the
objectives of the acquiring authority
have been achieved. That field of
study would benefit from further
detailed research.
7/26/2019 Cpo Report 2015 Main Report May2015
5/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 20146 7
Planning and Housing CPO Statistics 2012-2014
Figure 1 shows that:
In 2012:
46 Planning CPOs were submitted
by Local Authorities. That is
almost identical to the 47 Planning
CPOs submitted the previous
year, 2011.
37 Housing CPOs were
submitted, representing a 25%
decrease from the 50 submitted
in 2011.
In 2013:
36 Planning CPOs were
submitted. This is the lowest figure
in all the years covered by this
report, i.e. since 2003. Indeed it is
lower than the 40 submitted in
2009, during the depths of the
recession.
In contrast, 92 Housing CPOs
were submitted the highest level
for ten years. During the years
covered by the survey, only 2004
demonstrates higher levels of
usage.
2012 2013 2014
Planning CPOs
submitted (including
those not determined)
46
(27 opposed)
36
(14 opposed)
58
(31 opposed)
Housing CPOs
submitted (including
those not determined)
37
(13 opposed)
92
(23 opposed)
66
(22 opposed)
Figure 1:
Planning and Housing CPOs submitted 2012-2014 totals
In 2014:
58 Planning CPOs were
submitted. This is a return to 2010
levels and reflects a recovery from
the 36 submitted in 2013.
66 Housing CPOs were
submitted. This is a drop of 29%
from the 92 Orders submitted in
2013 but is in line with the general
levels of usage from 2009-2011.
Moreover, in terms of the longer term
trend, the number of Planning CPOs
submitted post-recession andeconomic downturn continue to be
of a different order to the levels of
usage witnessed 2004-2008.
To the extent that the use of Planning
CPOs can be viewed as a proxy for
economic/redevelopment activity
and in particular as a barometer of
economic confidence, then the
confirmed lower levels of usage are
perhaps unsurprising. What is
unclear is whether there is any
specific underlying reason for the
drop in 2013 to 36 CPOs.
Given the lead-times involved in
preparation of Planning CPOs it
may reasonably be assumed that
the 2013 figures reflect prevailing
economic conditions in 2011-2013
in the UK. Moreover, given the
increase in Planning CPOs in 2014
to a level consistent with all other
years from 2009, it is suggested
that the 2013 should not
necessarily be viewed as indicative
of any longer term trend.
Levels of usage of Housing CPOs
are perhaps less representative ofgeneral economic activity and
more closely tied to access to
public sector funding. As Figure 2
demonstrates, they are more
volatile than Planning CPOs. An
increase in the use of Housing
CPOs can be attributed to a small
number of Councils undertaking
targeted programmes of
improvement. The significant
increase in 2013 to 92 Housing
CPOs would appear to reflect
more extensive use of CPOs by a
number of authorities, notably
Burnley as shown on pages 14
and 15.
7/26/2019 Cpo Report 2015 Main Report May2015
6/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 98
Figure 2:
Planning and Housing CPOs submitted from 01/01/03 to 31/12/14
Figure 3:
Planning and Housing CPOs determined from 01/01/03 to 31/12/14
The change in the numbers of
Planning and Housing CPOs
submitted each year for the period
2003-2014 is illustrated in Figure 2.
In broad terms, the level of usage of
Planning CPOs from 2009-2014
remains down from previous levels
at around three quarters of 2004-
2008 levels. However the
submission in 2014 of 58 planning
CPOs represents a significant
recovery in usage from the previous
years figure of 36 which was the
lowest annual figure in the years
covered by the study.
Whilst the above figures for
submission of CPOs are robust there
have been some difficulties with the
data available in respect of
determination of CPOs. In March
2011, the National Planning
Casework Unit (NPCU) within the
Department for Communities and
Local Government (DCLG) was
established and from May 2012 it
began to have responsibility for
compulsory purchase matters that
had previously been overseen by the
National Unit for Land Acquisition
and Disposal (NULAD). Prior to
that formal handover, it appears that
to a limited degree NPCU operated
in tandem with NULAD. For example,
between 14 March and 31
December 2011, NPCU received
three Housing CPOs for
determination. It is understood that
during that period all other Planning
and Housing CPOs continued to be
handled by NULAD.
The handover from NULAD to NPCU
was completed around 30 April
2012. From that date onwards it is
understood that all Planning and
Housing CPOs have been dealt with
by NPCU.
Planning and Housing CPO Statistics 2012-14(continued)
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Housing
Planning
20
40
60
80
100
In 2012 to the end of April of that
year, NULAD determined 14 Housing
CPOs, whereas NPCU determined
15 Housing CPOs in the rest of the
year. In the same time periods,
NULAD determined 26 Planning
CPOs whereas NPCU determined
18. We would suggest that this data
reflects both NULAD completing the
determination of outstanding CPOs
before it ceased to have such
responsibility and also NPCU taking
a little time to get up to speed with
its new responsibilities.
The level of usage of Housing CPOs,
having been more or less constant
over the past four years, took a
significant upturn in 2013. The profile
of use is shown on pages 14 and 15
in Figure 6. In broad terms it reflects
the making of Housing Act CPOs
once or twice per annum by most of
the authorities using the power and
one authority making extensive use
of it.
20
40
60
80
100
120
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Housing
Planning
7/26/2019 Cpo Report 2015 Main Report May2015
7/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1110
66%64%
67%
14%
4%
4%
7%
9%
7%
9%
3%
2%
26%
18%
Confirmed without modification
(including referred to Acquiring
Authority for confirmation)
Confirmed with modification
Not confirmed
Withdrawn
Other
2012
2014
2013
Figure 4:
How Planning CPOs were determined 2012 2014
Figures 4 and 5 show how Planning
and Housing CPOs, respectively,
were determined from 2012-2014.
For Planning CPOs these figures
denote continuing high rates of
success and indeed an increase in
CPOs recorded positively as havingbeen confirmed. The key points to
note include:
The percentage confirmed without
modification (including those
referred back to Acquiring
Authorities for determination)3was
remarkably consistent: 66% in
2012; 64% in 2013 and 67% in
2014.
This represents a general increase
in the percentage of CPOs
confirmed without modification as
compared with 46% between
2003 and 2009 and 60% in
2010-2011.
Confirmation with modification is
more variable: 9% in 2012; 26%
in 2013 and 18% in 2014.
Whilst confirmation without
modification remains more or less
consistent, as regards the balance
of CPOs, ie CPOs eitherconfirmed with modifications or
not confirmed or withdrawn
respectively, these outcomes
often reflect the submisson of
objections to a CPO.
That where there is an objection
to a CPO, potential outcomes
may include:
modification of an Order as a
result of more active scrutiny and/
or negotiation
not confirmed decisions where a
CPO actively fails in the light of an
objection
acquisition by agreement (with the
CPO subsequently being either
recorded as not confirmed or
withdrawn).
The confirmation with modification
figures in earlier years are: 31%
from 2003-2009; 23% in 2010;
and 12% in 2011.
7% of CPOs in 2013 were
recorded as not confirmed. This
is consistent with 6% (2003-2009)
and 8% (2010).
4% not confirmed in 2014 is
slightly below average. 14% in
2012 is above average. The figure
of 18% for 2011 would appear to
be out of step with t he broad
pattern.
The annual totals of actively
confirmed Planning CPOs were:75% (2012); 90% (2013) (ie both
with and without moderation) and
85% (2014).
3. As per the powers contained in s.14A Acquisition of Land Act 1981
As has been emphasised in
previous reports, the fact that a
CPO is listed as not confirmed
does not necessarily mean that a
CPO should be considered to
have failed. In many cases, it
reflects an acquisition byagreement and request for an
Order to be treated as not
confirmed.
There appears to be greater
consistency and accuracy in the
recording of Planning CPO data
compared with the earlier years
covered by our reports.
Planning and Housing CPO Statistics 2012-14(continued)
7/26/2019 Cpo Report 2015 Main Report May2015
8/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1312
76%
14%
3%3%
3%
9%
6.5%
3%
80%
1.5%
10%
7%
11%
1%1%
69%
Confirmed without modification
(including referred to Acquiring Authority)
Confirmed with modification
Not confirmed
Withdrawn
Inverted
Other
2012
2014
2013
Figure 5:
How Housing CPOs were determined 2012 2014
Figure 5 indicates how Housing
CPOs were determined in 2012,
2013 and 2014. The results for 2013
show a significant increase in usage
of Housing CPOs from the
immediately preceding years and an
increase in the percentage of CPOsconfirmed. In addition, of the CPOs
confirmed there is an increase in the
percentage of CPOs confirmed
without modification. The key points
to note include:
Success rates for Housing CPOs
are consistently high.
Total confirmations (confirmations
both with and without
modification) were 90% (2012);
89% (2013); and 80% (2014).
Confirmations without modification
(76%, 80% and 69% 2012-14)
(including those referred to the
Acquiring Authorities for
determination) are all higher than
averages for previous years for
which data is available: 62%
(2003-2009), 61% (2010) and
68% (2011).
Confirmations with modification.
(14%, 9% and 11% 2012-14)
were all lower than previous yearsdata with one exception: 19%
(2003-2009), 15% (2010) and
12% (2011).
The increase in confirmation
without the need for modification
and the concomitant fall in the
percentage of CPOs confirmed
with modification may indicate
improvements in the technical
standard of Orders and increasedfamiliarity with the statutory and
policy requirements.
The annual totals of CPOs not
confirmed were 3% (2012); 6.5%
(2013) and 7% (2014). The latter
two years were slightly higher than
both the 5% average from 2003-
2009 and 4% and 2% in 2010 and
2011, respectively.
The 3% of Housing CPOs
withdrawn in 2012 and 2013
respectively contrasts with 10%
(2003-2009), 18% (2010) and
16% (2011). In that respect, 10%
of withdrawals in 2014 is more in
line with the historic pattern.
The differentiation between not
confirmed and withdrawn in
respect of Housing CPOs needs
to be treated with caution. We
consider that previously there was
a degree of inconsistency in
recording Orders as either not
confirmed or withdrawn.
Present practice would usually
appear to treat CPOs as not
confirmed where requested to be
treated as withdrawn. It is perhaps
safer to compare the combined
totals of Orders both not
confirmed and withdrawn. For
example, that exercise shows a
reduction from 15% (average2003-2009), 22% (2010) and 18%
(2011) to 6% (2012), 9.5% (2013)
and 17% (2014).
Planning and Housing CPO Statistics 2012-14(continued)
7/26/2019 Cpo Report 2015 Main Report May2015
9/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1514
Figures 6 (a) and (b) indicate how CPO usage is spread across local authorities.
Figure 6a:
Number of local authorities submitting Planning CPOs 2013 2014
Figure 6b:
Number of local authorities submitting Housing CPOs 2013 2014
1 2 3 4 5 6 14 21
NumberofLocalAuthorities
2013
Number of Housing CPOs submitted
2014
0
5
10
15
20
25
30
0
2013
1
Number of Planning CPOs submitted
NumberofLocalAuthorities
2 3 4
5
10
15
20
25
30
2014
In 2013, 31 separate Acquiring
Authorities submitted Planning
CPOs. Of these, 26 made a single
CPO in that year. Three authorities
(Burnley, Birmingham and
Wolverhampton) made two CPOs
and two (Hackney and Rochdale)
made three.
In 2014, 40 separate Acquiring
Authorities submitted Planning
CPOs. Of these, 28 made a single
CPO in that year. Seven authorities
(Barnet, Burnley, Daventry, Hastings,
Birmingham, Lincoln and Watford)
made two CPOs. Four authorities
(Hackney, Ealing, Enfield and
Liverpool) made three CPOs. One
authority (Brent) made four CPOs.
In 2013, 36 separate authorities
submitted Housing CPOs. Nineteen
authorities each made a solitary
CPO. Five authorities (Birmingham,
Doncaster, Leeds, Newham,
Redditch) made two CPOs. Four
authorities (Bradford, Great
Yarmouth, Hounslow,
Wellingborough) made three CPOs.
Bristol made four CPOs. Four
authorities (Derby, Sutton, Wigan,
Wolverhampton) made five CPOs.
Stoke-on-Trent made six CPOs. By
far the most prolific user of Housing
CPO powers was Burnley which in
2013 made 21 separate CPOs.
In 2014, a similar pattern emerges.
Thirty eight separate authorities
submitted Housing CPOs. Twenty
five authorities each made a solitary
CPO. Nine authorities ( Barnet,
Bristol, Broadland, Barking and
Dagenham, East Riding of Yorkshire,
Ipswich, Tendring, Stevenage and
Wolverhampton) made two CPOs.
Three authorities (Derby, Blackburn
with Darwen and Wigan) made three
CPOs. Burnley made 14 CPOs.
Burnley has used Housing CPO
powers extensively as part of its
Vacant Property Initiative (VPI).
This initiative was particularly active
in 2006-2009 and latterly in
2013 -2014 and has been used to
address long-term vacant property
as part of a targeted, cluster
approach to housing market renewal.
It is understood that around 70
properties have been subject to
compulsory purchase in this way.
Planning and Housing CPO Statistics 2012-14(continued)
Those acquired have been
refurbished and sold thereby
bringing the properties back into
use. Proceeds of sales were
recycled back into the VPI.
7/26/2019 Cpo Report 2015 Main Report May2015
10/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1716
Region No. ofCPOssubmittedin 2014
Total number ofCPOs opposed ofthose submitted
No. of CPOsdeterminedin 2014
Confirmedwithmodification
Confirmed withoutmodification(including referred toacquiring authority)
Notconfirmed
GO-East 4 2 3 1 4 -
GO-EastMidlands
2 - 4 - 4 -
GO-London 22 13 16 2 11 2
GO-North East 4 3 2 1 1 -
GO-North West 13 6 6 2 4 -
GO-South East 5 1 3 - 1 -
GO-South West 1 1 2 - 2 -
GO-WestMidlands
4 4 2 1 1 -
GO-YorkshireHumber
3 1 3 1 2 -
Figure 7:
Planning CPOs by region 2014
Region No. ofCPOssubmittedin 2014
Total number ofCPOs opposed ofthose submitted
No. of CPOsdeterminedin 2014
Confirmedwithmodification
Confirmed withoutmodification(including referred toacquiring authority)
Notconfirmed
GO-East 13 4 8 1 5 -
GO-EastMidlands
4 1 4 - 3 -
GO-London 10 3 22 2 14 3
GO-North East 1 1 1 - 1 -
GO-North West 25 5 23 - 20 1
GO-South East 1 1 1 - - 1
GO-South West 5 2 3 - 2 -
GO-WestMidlands
3 2 8 1 6 -
GO-YorkshireHumber
4 3 3 1 2 -
Figure 8:
Housing CPOs by region 2014
Planning and Housing CPO Statistics 2012-14(continued)
The results for 2014 are consistent
with previous findings:
CPO usage continues to be
spread widely but thinly. Many
authorities use CPO powers, but
do so sparingly. In particular it is
unusual for an authority to make
more than one Planning CPO
annually.
Of course, the number of
individual CPOs does not of itself
reflect the scale or nature of the
intervention by an Acquiring
Authority.
In line with previous reports
regionally London and the North
West consistently have the
highest totals of both Planning
and Housing CPOs made.
For Planning CPOs, in London 22
were submitted in 2014
compared with 10 the previous
year. In the North West 13 were
submitted in 2014 compared with
nine in 2013.
For Housing CPOs, in the North
west 25 were submitted in 2014
as against 28 the previous year. In
London 2014 saw 10 submitted
compared with 18 in 2013.
There is otherwise fluctuation
between regions. The 2014
figures show an increase in the
use of Housing CPO powers in
the East region to 13 from four in
2013. The opposite has occurred
in the West Midlands: a fall to
three from 14 in 2013.
A relatively small number of
Councils as noted above in figure
6b account for a significant
proportion of Housing CPOs. With
Planning CPOs the distribution is
more even.
Our earlier findings established
that Planning CPOs are more
likely to generate objections than
Housing Orders. That still remains
the case but there has been an
increase in objections to Housing
CPOs rising to 33% as compared
with 26% in 2013.
Figures7 and 8 provide a breakdown of usage by former Government Office regions for 2014.
In addition to the above data we
have analysed those Orders
submitted in 2012 and 2013 and
determined by the Secretary of State
in terms of how long it takes from
the receipt of the Order and the
Secretary of States decision date.
These are set out overleaf in
Figure 9.
7/26/2019 Cpo Report 2015 Main Report May2015
11/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1918
Effectiveness of CPOs Implementation by Acquiring Authorities
2012 2013
Opposed Unopposed Opposed Unopposed
Planning 323 123 281 97
Housing 296 112 119 63
Figure 9:
Average time (in days) from receipt of CPOs to Secretary of State decision, 2012-2013
Our previous research has focused
on the CPO process up to the
Confirming Authoritys decision.
It is acknowledged however that the
mere fact of whether or not a CPO
has been confirmed has some
limitation as a measure ofeffectiveness of compulsory
purchase as it does not address if
and how implementation occurs.
We have already noted above that
withdrawal or non-confirmation of a
CPO is not necessarily an indication
of failure; more often than not we
would suggest it reflects acquisition
by agreement having been achieved
against the background of a CPO
such that a confirmed Order is no
longer required. Conversely, the
confirmation of a CPO does not
necessarily mean that it will
subsequently be implemented and
all interests acquired. Indeed
following confirmation there are a
number of potential scenarios that
may apply including:
Immediate acquisition by
implementation of the CPO of all
or some land comprised within
the CPO; or
Acquisition by agreement
notwithstanding that the CPO has
been confirmed; or
Delay in acquisition
postponement of implementation
by GVD and/or Notices to Treat;
or
The CPO is never implemented.
Are confirmed CPOs alwaysimplemented?
As regards Planning CPOs in
particular there is a myriad of factors
affecting viability and deliverability,
and therefore, in turn, the speed and
manner in which a CPO may beimplemented by the Acquiring
Authority. We would suggest that
anecdotally there is evidence that
where schemes were conceived
pre-recession but site assembly was
facilitated and concluded by means
of CPO in a wholly different
economic climate then there have
been significant delays in the
implementation of the relevant Order.
Indeed such situations have required
considerable resourcefulness by
CPO practitioners to keep the
implementation window open,
including reliance upon Notices to
Treat rather than GVDs and thereby
effectively extending the window for
taking possession from three years
to six years from the date of
confirmation of CPO powers.
In respect of Housing CPOs,
especially those of single, problem
properties, the situation is often
more straightforward andimplementation frequently proceeds
in good time by disposal of the
property to the market forthwith.
At the Compulsory Purchase
Association conference in 2014, a
question was asked from the floor as
to whether there were any statistical
data about whether CPOs were
successful in the sense of both
being implemented and thereafter
the intended scheme coming to
fruition. Of course it is recognised
that the CPO process of itself cannot
ensure delivery of a scheme per se,
but as a mechanism it uniquely
may facilitate a scheme which
would not otherwise be possible.
We therefore made Freedom ofInformation requests to all Acquiring
Authorities that DCLG data indicated
had made CPOs since 2003,
enquiring as to what steps were
taken post-confirmation and whether
confirmed CPOs were implemented
and the underlying scheme was
delivered. We also sought
information as to how long both the
pre-confirmation process took and
how long it took in total, from
making a CPO to commencement of
the underlying scheme.
The responses were varied but we
have obtained data in respect of
over 800 CPOs upon which we have
based the following observations.
Responses ranged from fully
completed answers to all questions
together with additional details and
analysis on the one hand, to refusal
either to acknowledge that the
authority had made any CPOs or todecline to supply any data on the
grounds of confidentiality on the
other hand. Moreover, the
incomplete nature of many
responses reflects the somewhat
varied nature of Acquiring
Authorities corporate memory
of the reasons why CPOs were
undertaken and the outcomes of
the process. There is presently no
statutory or other obligation on
Acquiring Authorities to keep a
Planning and Housing CPO Statistics 2012-14(continued)
7/26/2019 Cpo Report 2015 Main Report May2015
12/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2120
register of CPOs made and/or
confirmed, or indeed to record the
outputs of the process. We consider
that whilst there would be benefits
from a statutory obligation to keep
a register of CPOs made and their
respective outcomes, these would
not necessarily be proportionate to
the costs involved. However, as a
matter of best practice, Acquiring
Authorities may wish to keep such
a record or register and may wish to
complete a brief lessons learned
report at the conclusion of the CPOprocess reflecting on how the CPO
proceeded and identifying any best
practice issues relevant to future use
of CPO.
On the basis of the data collected
we would make the comments
below.
Figure 10 indicates that, as
practitioners may expect, GVD is the
most common way of implementing
a CPO. There is clear evidence that
the majority of CPOs have been
implemented by means of GVD,
Notice to Treat or a combination of
(i)
GVD
(ii)
NoticestoTreat/
of Entry
(iii)
Combinationof (i) and (ii)
(iv)
Agreement
(v)
Nopossession
taken
(vi)
Unknown
Planning 51.8% 2.6% 11.7% 8.8% 11.4% 13.6%
Housing 69.1% 1.5% 6.2% 6.6% 8.8% 7.6%
Figure 10:
Method of implementation of Planning and Housing CPOs 2003-2014
Figure 11:
Schemes undertaken pursuant to Planning and Housing CPOs 2003-2014
the two. The responses received
indicate that 70% of Planning CPOs
and 77% of Housing CPOs have
been confirmed by means of the
formal, statutory process.
In addition, it is interesting to note
that responses indicated that in
8.8% and 6.6% of Planning and
Housing CPOs, respectively,
possession was obtained by
agreement notwithstanding that a
confirmed CPO was in place. These
figures perhaps need to be treatedwith some caution, however, and are
deserving of further analysis.
Taking the combined totals for
columns (i) (iv) in the above table
represents a positive answer to
whether implementation took place
in respect of 75% of Planning CPOs
and 83% of Housing CPOs.
In addition, upon closer inspection
and enquiry it appears that some
responses stating that no
possession was taken have been in
circumstances where, in fact,
acquisition by agreement had
occurred. Those figures t herefore
also require further examination. The
unknown responses reflect gaps in
the database. If the unknowns are
discounted the figures are 88% of
Planning CPOs and 90% of Housing
CPOs being implemented by the
statutory method or by agreement in
the light of a confirmed CPO.
Figure 11 reflects an attempt to get
to the heart of the question as to the
extent to which Planning and
Housing CPOs result in the deliveryof the intended underlying scheme.
On a positive note, 31% of Planning
CPOs have resulted in completed
schemes together with 25% of
schemes being described as in
progress. In comparison, 50% of
Housing CPO schemes have been
completed, with 11% being in
progress.
Where schemes are described as
not yet commenced that indicates
that it is still envisaged that there is a
likelihood or intention to carry out
the scheme. In contrast, the not
Not yet
commenced
In progress Completed Not
undertaken
Unknown
Planning 14.9% 25.4% 31.1% 15.7% 12.9%
Housing 8.1% 11.1% 49.7% 19.6% 11.5%
Average time (in months) between
CPO made andCPO confirmed
CPO confirmedand possession
Possession andSchemecommencement
Planning 10.82 10.79 9.47
Housing 8.18 9.45 6.18
Figure 12:
Average timescales for implementation of Planning and Housing CPOs 2003-2014
undertaken column reflects those
schemes that will no longer happen
or are unlikely to happen. Around
16% of Planning CPOs and 20% of
Housing CPOs are not undertaken.
From the responses received, it
appears likely that, in terms of
Housing CPOs, some Orders where
the scheme has not occurred have
however resulted in outcomes that
were not anticipated at the outset,
for example by way of sales to third
parties or otherwise, and have
thereby delivered an alternative
scheme.
Figure 11 reflects initial analysis of
the responses received. It is
intended in due course that more
detailed analysis will be undertaken.
In addition, we have calculated the
average timescales for
implementation of Planning and
Housing CPOs from the data
submitted by Acquiring Authorities
as set out at Figure 12 above. These
data are not as fine-grained as the
DCLG/NPCU records of time taken
to process CPOs; the data reflects
the passage of months rather than
days. In broad terms, Figure 12 acts
as a check against the data derived
from the NPCU figures. However, the
correlation between the two sets of
data is striking.
Effectiveness of CPOs Implementation by Acquiring Authorities(continued)
7/26/2019 Cpo Report 2015 Main Report May2015
13/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2322
Enabling power and clarity of objectivesReasons why some CPOs fail Secretary of State decisions 2009 2014
By definition, CPOs are site specific.
Moreover, each CPO stands or falls
on its own merits. An Acquiring
Authority commencing the
compulsory purchase process is well
advised to remind itself of the
Secretary of States requirements in
Circular 06/04 (currently being
revised).
In particular, it should be
emphasised that the onus is
squarely on an Acquiring Authority
to demonstrate that there is a
compelling case in the public interest
for compulsory acquisition. The
decision letters reviewed
demonstrate how the Secretary of
State can be expected to weigh
carefully and balance the competing
public and private interests and to
assess whether the interference
proposed is both proportionate and
necessary.
An Acquiring Authority should bear
in mind that the Secretary of State
will look at each CPO on its own
merits this is not a tick box
exercise. It will therefore need to
apply its mind to particular
circumstances of each case. The
onus is firmly on it to demonstratethat there is a compelling interest in
the public interest and consequently,
notwithstanding the generally high
success rates, there is no room for
complacency. An Acquiring Authority
must therefore clearly identify the
objectives and benefits of its
proposed scheme, demonstrate that
efforts have been made to acquire
by agreement (or reach other
acceptable arrangements for access
to or use of land) and establish a
robust evidential base in order to
establish the need for compulsory
purchase.
Acquisition by agreement
For developers seeking to take
possession of, and develop a site
assembled by means of compulsory
purchase, engagement with the
process is a pre-requisite. For
example, the CPO process requires
efforts to be made to acquire by
agreement. There is some evidence
in decision letters that CPOs have
on occasion been perceived as a
short cut to site assembly, obviating
the need to try to acquire by
agreement. That is an approval
taken at ones peril. A developer will
also be called upon to demonstrate
the likely viability of its s cheme. That
requirement should come as no
surprise and evidence of both
deliverability and, where appropriate,
viability should be advanced.
Objectors opposing schemes should
note that an objection has a
proportionately greater prospect of
success where a Public Inquiry is
held and evidence is forensically
tested. In Housing CPOs, objections
putting forward evidence of
deliverability of renovation or
redevelopment by the existing owner
have proved successful. In Planning
CPOs, as cases below demonstrate,
an Inquiry provides an opportunity to
test an Acquiring Authoritys
assumptions about viability.
The reasons why CPOs can fail as
evidenced by recent Secretary of
State decisions are set out below
under the following headings:
Enabling power and/clarity of
objectives
Technical deficiencies
Procedural issues/withdrawal of
Order
Housing CPOs evidential burden
Planning CPO viability,
deliverability and alternative
schemes
Acquisition by agreement
statutory and policy requirements
Orders not confirmed/withdrawn.
4. Great Yarmouth Borough Council (Land at Hall Road, Hopton-on-Sea, Great Yarmouth, Norfolk) Compulsory Purchase Order 2009 (S125 Local Govt Act 1972 and
S164 Public Health Act 1875. Decision 30 March 2010)
It is essential at the outset to
establish clearly the particular
objectives of a case and therefore
identify the most appropriate power
under which to make a CPO. The
approach of Great Yarmouth
Borough Council and Hopton-on-
Sea Parish Council ultimately was
fatally unclear in respect of both
(Great Yarmouth Borough Council
(Land at Hall Road, Hopton-on-
Sea, Great Yarmouth, Norfolk)
Compulsory Purchase Order
2009)4.
The Order Land in Hopton-on-Sea
on the Norfolk coast comprised 0.4
hectares of woodland covered by a
Tree Preservation Order. It was
adjacent to the local church, bowling
green, a single residence and post
office. Planning applications for
residential development of the site
had previously been refused by the
LPA and on appeal.
The impetus for compulsory
acquisition came from the Parish
Councils desire to manage the site
as a woodland walk/nature reserve.
The Parish Council was also
concerned about the areas untidy
and ill-maintained appearance.
There was an extensive history of
negotiations between the Parish
Council and landowner. Ultimately,
no substantive progress was made
so the Parish Council requested that
the Borough Council make a CPO.
Negotiations recommenced and an
undertaking was given by the
landowner to make reasonable
endeavours to clear, tidy and make
the land safe to the Parish Councils
reasonable satisfaction within a
specified period of a few months
and thereafter maintain it to the
Parish Councils satisfaction. The
CPO was thereupon withdrawn. The
deadline for works was subsequently
extended by six months but by that
time there was little evidence of
progress so a second CPO was
made. In the meantime the area was
fenced off and some works
undertaken by the landowner.
Statutory power
The Order was made pursuant to
S125 of the Local Government Act
1972 (LGA) and S164 of t he Public
Health Act 1875 (PHA). S125 LGA
provides that a District Council may
in certain circumstances
compulsorily acquire land on behalf
of a Parish Council provided the land
is for a purpose for which the Parish
Council is authorised to acquire land.
However, that does not include
matters specified in S124(1)(b) LGA,
namely the benefit, improvement or
development of their area. S164
provides that a local authority may
purchase or take on lease lay outplant improve and maintain lands for
the purpose of being used as public
walks or pleasure grounds
The Secretary of State accepted that
the acquisition of the lands for use
as a woodland walk/nature reserve
fell within the ambit of S164 PHA
and therefore S125 LGA applied but
commented that the Councils desire
to tidy up the site and improve its
scruffy and neglected appearance
and its use by undesirables fell
within the exclusions in S124(1)(b)
LGA and therefore were not matters
which alone would form a proper
basis for a CPO. Likewise, the value
of the woodland in providing a
setting for the church was not a
matter of itself for which the Parish
Council was entitled to seek a CPO.
These may be additional benefits,
as the Council put it, but since t hey
fell outside the powers the Secretary
of State gave them little weight.
The Inspector also noted that the
undertaking that had been accepted
by the Parish Council did not provide
for public access to the land but only
for the land to be cleared, tidied and
made safe. The Inspector
accordingly concluded that
improving the appearance and
maintenance of the land might in fact
be the overriding objective for the
Parish Council. Laudable as that
may be it was not a proper basis for
a CPO under S124(1)(b). The
Inspector therefore concluded that
in considering whether the Order
should be confirmed I have therefore
had regard to the creation of a
woodland walk/nature reserve and
have given little weight to any allied
benefits.
There were additional planning and
evidential objections to the CPO.
Local Plan policy provided support
for the creation of wildlife habitats.
However, the supporting t ext to the
policy stated that the Council would
seek access arrangements to sites.
7/26/2019 Cpo Report 2015 Main Report May2015
14/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2524
Technical deficiencies
The landowner pointed out that no
such access agreement had been
sought. The Inspector noted that the
landowner had not ruled out the
potential for granting a lease and
during the Inquiry a draft lease was
offered albeit one that wasunacceptable to the Council.
Also, the Council argued that there
was a shortfall of 0.84 ha of informal
recreation space/childrens play
space and that the Order Lands
would meet half of that shortfall.
However, the Secretary of State was
sceptical that the woodland would
be suitable for a range of recreational
uses and in any event such uses
would conflict with the proposal as a
nature reserve. Although there was
relatively little accessible woodland
on the coastal fringe, the Order land
had no particular scientific or nature
conservation interest and was in any
event protected by policy from
development and was unlikely to be
lost as a wildlife area.
The Secretary of State thereforeconcluded that a compelling case
had not been made out and the
purposes werent sufficient to justify
interference with the landowners
human rights and that despite there
being no obvious impediments to
the project, the use of compulsory
purchase powers would not be
proportionate.
In this instance, the Borough
Councils case suffered from lack of
clarity as to precisely what it was
that the Parish Council wished to
achieve. Indeed there was arguably
some confusion about the precise
intended use and its benefits. Clearly
there was a tension between nature
reserve and childrens play space
use, for example. This wassignificant because of the Secretary
of States approach to give weight to
the benefits that fall within S164
PHA and not the ancillary or allied
benefits.
The land was suitable as a woodland
walk/nature reserve, but was not of
particular nature conservation
interest. The Secretary of State was
not convinced that land was of the
right type to address the shortage of
recreational space. Moreover a lease
may well have been long enough to
secure a significant proportion of any
benefits and could be available. In
addition no attempt had been made
to secure an access agreement.
It is hard not to have some sympathy
in this instance for the Parish Council
given that it had spent five years
from negotiations first commencing
to progressing the second CPO.
However, if there is an alternative
means of achieving the identified
objectives short of the need for
compulsory acquisition, then careful
consideration should be given to that
alternative. In this instance could a
suitably framed access agreement
have sufficed. In other cases, one
may wish to consider whether
outright acquisition is needed or
whether an easement would be
sufficient.
The Secretary of State will refuse to
confirm a CPO that is demonstrably
technically flawed and not capable
of modification or remedy. Guidance
in Appendix V to Part I of the
Memorandum to Circular 06/04 sets
out the technical requirements. Inaddition the procedural
requirements, for example, as set
out in The Compulsory Purchase
(Inquiries Procedure) Rules 2007 or
The Compulsory Purchase of Land
(Written Representations Procedure)
(Ministers) Regulations 2004, must
be followed. A combination of
technical and procedural errors can
be fatal to a CPO as demonstrated
by two Planning CPOs made by
Mansfield DC (Mansfield District
Council (Brownhill Road) CPO
2010andMansfield District
Council (Bould Street) CPO 2010)5.
The procedural error was that
newspaper notices did not appear in
two successive weeks. The second
notice appeared two weeks after the
first, thereby effectively shortening
the objection period for those who
saw the second notice.
In addition, the Order Maps were
contrary to the Circular in that: they
were undated; they did not contain
street names or house numbers or
local landmarks; and boundaries
were not clearly delineated and
numbering hard to pick out.
Furthermore, the Order Schedule did
not include Table 2 and no signed
certificates had been provided.
There can be no surprise that the
CPOs were rejected on technical
grounds. Although the Secretary of
State may permit some
modifications to a CPO where it is
possible to do so without causing
prejudice to an objector, it isimportant to take care at the outset
to follow both the statutory
requirements and the Secretary of
States requirements as to the form
of an Order.
Checking the draft Order
The NPCU in Birmingham provides a
valuable informal checking service
for draft CPOs. This can be
especially useful not just for complex
Orders, but in allowing fresh eyes to
scrutinise the CPO schedule and
map. Acquiring Authorities are
recommended to make use of the
NPCU.
The limitation on the scope for
modifying an Order is well
demonstrated by a Housing Act
CPO made by the East Riding of
Yorkshire Council (The East Riding
of Yorkshire Council (11
Lansdowne Road, Bridlington)
Compulsory Purchase Order
2009)6.
The Councils Housing CPO case
was well made out. The property
was in disrepair and had partially
collapsed. The Council had
negotiated with the landowner over
a prolonged period of time, had clear
5. Mansfield District Council (Brownhill Road) CPO 2010 (S226(1)(a) TCPA 1990. Decision 17 February 2011)
6. The East Riding of Yorkshire Council (11 Lansdowne Road, Bridlington) Compulsory Purchase Order 2009 (S17 Housing Act 1985. Decision date 22 September2010)
proposals to bring it back into use
and the owner had shown no
commitment to renovation. It is clear
from the decision letter that the
Secretary of State would in all
probability have confirmed the Order
had it not been for a fatal flaw in theCPO.
There were two notable errors:
The CPO Map included part of an
adjoining property in error.
The CPO Map failed to include a
rear single storey extension that
was an integral part of the
dwellinghouse to which the CPO
related. It also omitted the rear
yard to the property.
Consequently, the description of
the area of land in the Schedule
was materially inaccurate.
Modification of the CPO to remove
the land included in error was
possible and caused no prejudice.
However, it was not possible to bring
into the CPO land excluded in error.
Although there was no overall
ambiguity in the Councils intention
that proposed modification was not
consented to by t he objector. The
Secretary of States position is that
he may not, without the consent of
all persons interested, modify a CPO
by adding land not originally included
in the CPO. That is, with the
agreement of the Secretary of State
one may modify a CPO to remove
Enabling power and objectives(continued)
It is hard not to have some sympathyin this instance for the Parish Council
given that it had spent five years fromnegotiations first commencing toprogressing the second CPO. However,if there is an alternative means ofachieving the identified objectives shortof the need for compulsory acquisition,then careful consideration should begiven to that alternative.
7/26/2019 Cpo Report 2015 Main Report May2015
15/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2726
Procedural issues/Withdrawal of Order
land, but one cannot insert land not
originally included in the CPO
without the consent of all affected
parties and acquiescence of the
Secretary of State.
The East Lindsey District Council
(The Gatherums, Louth)
Compulsory Purchase Order
20127would also appear to have not
been confirmed following a request
for withdrawal because of technical
7. East Lindsey District Council (The Gatherums, Louth) Compulsory Purchase Order 2012 (S226(1)(a) TCPA 1990. Decision date 16 October 2012)
In cases where an Acquiring
Authority wishes to withdraw a CPO
because acquisition has been
achieved by agreement, an
application is made to the
determining Secretary of State who
determines that the CPO is notconfirmed. Details of those CPOs
not confirmed/withdrawn in this
way are set out later in this report.
But what happens when an
Acquiring Authority wishes to
withdraw a CPO but there is an
outstanding objector who opposes
the withdrawal? This issue was
addressed in a Planning CPO Order
made by Kings Lynn and West
Norfolk BC (Borough Council of
Kings Lynn and West Norfolk
(Waterfront Regeneration Area,
Land at the Friars) Compulsory
Purchase Order 2009).8The
underlying scheme fell within a
strategic transport route forming part
of mixed-use development within a
wider regeneration area. Kings Lynn
BC sought deferral of a Public
inquiry for six months on grounds
that the economic downturn meant
a review of its regeneration project
was necessary. A statutory objectoropposed the deferral on a number of
grounds; most particularly that his
own development proposals would
be prejudiced by delay. The
Secretary of State refused to
sanction deferral. The Council wrote
to PINS stating that it wished to
withdraw the CPO.
8. Borough Council of Kings Lynn and West Norfolk (Waterfront Regeneration Area, Land at the Friars) Compulsory Purchase Order 2009 (S215 (1)(b) TCPA 1990.
Decision 14 May 2010)
Its stated reasons were: to enable a
review of its Waterfront Regeneration
Area; that an alternative route not
involving the remaining objectors
land had been found for the strategic
transport link (and planning
permission for this alternative routehaving been granted four days
earlier); and to enable funding to be
utilised by a deadline. It was stated
that this request was without
prejudice to making a second Order
because the Councils underlying
purpose had not changed. The
Government Office for London (GOL)
was minded to cancel the Inquiry
and wrote to the Council stating that
in the interests of fairness and
natural justice where an Acquiring
Authority indicated close to an
Inquiry that it no longer wished to
pursue the CPO then remaining
objectors who have reasonably
incurred costs in preparation for the
inquiry should be able to seek an
award of costs against the Acquiring
Authority. GOL also stated that as
you are aware however compulsory
purchase order costs can only be
awarded where an inquiry has taken
place.
Jurisdiction
The Inquiry therefore proceeded.
The Council called no evidence and
instead relied upon its Statement of
Case. There was extensive debate
as to whether an Acquiring Authority
could withdraw a CPO. There was
broad agreement that there is no
express power to do so. However, is
there an implied power? The
objector argued that the Council was
functus officio i.e. it no longer had
the power to act in respect of the
CPO, the CPO baton having been
passed to the Secretary of State to
decide whether it could beconfirmed. It was also contended
that, in this case, the Council had
not in fact passed an appropriate
resolution to withdraw the Order.
The Council relied on the decision in
Persimmon v North Hertfordshire
(2001 1WLR 2393) in respect of the
withdrawal of a Local Plan. It also
argued that if the CPO was not
considered to be withdrawn it would
ask the Secretary of State to confirm
the Order in respect of those plots t o
which there were no objections.
The Inspector noted that, although
the Order fell not under the ambit of
Circular 8/93, but Circular 03/2009,
at Annex E paragraph E6 states:
exceptionally, an Order is not
confirmed for technical reasons or
because the Acquiring Authority
decided not to proceed with the
compulsory purchase and asks for
the Order to be treated as
withdrawn. The Circular couldtherefore be taken to imply such a
power but none is expressly
identified. The Inspector concluded:
The Order is to all practical intents
and purposes withdrawn and it
seems to me that to argue or
conclude otherwise serves no
purpose in the public interest. There
is however no explicit provision in
Technical deficiencies(continued)
Although there was no overall ambiguity in the
Councils intention that proposed modificationwas not consented to by the objector. TheSecretary of States position is that he maynot, without the consent of all personsinterested, modify a CPO by adding land notoriginally included in the CPO.
reasons. The Secretary of States
letter advises that the Council may
wish to note that the National
Planning Casework Unit provides
informal advice on draft Compulsory
Purchase Orders, should the
authority decide to submit a
subsequent Order.
7/26/2019 Cpo Report 2015 Main Report May2015
16/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2928
Housing CPO evidential burden
law for withdrawal of a CPO. It thus
seems to me that the Order must
still be considered to stand and that
accordingly the proper course would
be for the Order not to be
confirmed.
As regards confirming the plots inrespect of which no objections had
been made, whilst there was a
convenience factor in doing so, the
Inspector expressly rejected that
approach. The reason and
justification for acquiring those small
areas was the same as for the rest
of the Order Land. Since the Council
did not argue that some of the Order
Land is needed and some is not and
was not pursuing compulsory
acquisition of the other plots in
respect of which there were
outstanding objections then its case
for compulsory acquisition could not
be sustained for the two small areas.
Housing CPOs made by Islington
LBCand the City of Westminster
respectively9are examples of Orders
not being confirmed but where the
use of compulsory purchase
arguably incentivised landowners to
take action to address problems
with the relevant property. These
Orders illustrate a dynamic
particularly relevant to Housing
CPOs namely the response of the
landowner. Planning CPOs are
essentially prospective the
Acquiring Authority is advancing a
case for the future development,
redevelopment or improvement of a
site. It is usually problematic for an
objector to counter those benefits or
attack them head-on unless he has
an alternative viable scheme of his
own. In contrast, Housing CPOs
expressly require assessment of the
current condition and use of
property. There is often therefore
increased scope for an objector to
take steps to address an acquiring
authoritys concerns and at the same
time counter the need for
compulsory acquisition.
Islington
The Islington case featured pre-1919three storey brick buildings. The
ground floor contained shops. There
was residential accommodation
above. The Councils case was that
the nearby area had been
regenerated by New Deal for
Communities. The Order lands were
empty, an eyesore, in disrepair and
in need of complete renovation.
There was also, it was argued, a
demonstrable need in the area for
housing. Extensive evidence of
contact with the owner was
advanced, especially the Councils
frustration with the lack of progress.
The Council therefore proposed to
pass the property to a Registered
Housing Provider (RP). It also
contended that the Owners lacked
the capacity to bring the property
into use and that piecemeal
acquisition of properties over many
years together with poor stock
management and maintenance had
blighted neighbouring property. A
Notice under Section 215 of the
Town and Country Planning Act
1990 had been served to require
works to the front elevations. In
short, the Councils case was that
Owners were financially not in a
position to remedy the situation and
had taken no steps to demonstrate
an intention to renovate.
The Owners case was that they
were intending to carry out works to
bring the properties back into mixed
residential and commercial use.
Planning Permission was now in
place. The Order was therefore
premature. A detailed explanation of
personal problems, share ownership
issues and other issues was given.
Factual matters were disputed,
especially that the Council had been
wrong that certain units were empty.
Some works had been undertaken
to comply with the S215 notice. The
Council had refused to accept an
undertaking not to make a CPO if
work began within 20 weeks. There
would be delays with redevelopment
if the Order were confirmed because
the RP would need new consents. A
week before the Public Inquiry, the
objectors met with local builders and
agreed implementation of the
planning permission, albeit there
were no written terms.
The Inspector concluded that the
poor state of building and housing
need was established. Compulsorypurchase is the last resort. There
were reasons for the delay: litigation
and personal circumstances were
mitigating factors. Planning
permissions for extensions and
refurbishment now existed. The
Owners had expressed the intention
to implement the permissions and
had made moves to do so even
though these might not have
advanced to a stage that provides
the Council with the comfort as to a
prompt and satisfactory outcome.
Dialogue with the Council had been
maintained and the S215 notice
complied with in part.
Objectors commitment
The Inspector noted that despite
the Councils contention to the
contrary I consider that [the
objectors have] shown a degree
of steadfast commitment to moving
forward with project of redeveloping
the properties [and] expressed [a]
preparedness to provide an
undertaking to the Council to ensure
development is carried out to an
agreed timetable should the Order
not be confirmed. There is also
evidence that the presence or threat
of a CPO may have deterred
potential financial backing for
developers and this has itself
frustrated action.
Procedural issues/Withdrawal of Order(continued)
Where acquisition by agreement has
been reached and an Acquiring
Authority needs to withdraw an
Order, i.e. cease the compulsory
CPO process that should not be
problematical. That is an
administrative process and theSecretary of State is amenable to
Orders being withdrawn de facto,
albeit that de jure they may be noted
as being not confirmed. However,
if an Order is proposed to be
withdrawn for any other reason, then
care is required and an Acquiring
Authority must be alive to the costs
implications. It is hard to see why in
principle objectors reasonable and
legitimate costs should not be
recoverable in some circumstances
where a contested Order is sought
to be withdrawn, especially close
to the date of an Inquiry.
9. The London Borough of Islington (141-157 Whitecross Street, London EC1Y 8JL) Compulsory Purchase Order 2009. (S17(1)(b) Housing Act 1985.
Decision date 6 May 2010) and City of Westminster (39 Kensington Gardens Square W2) Compulsory Purchase Order 2010)
7/26/2019 Cpo Report 2015 Main Report May2015
17/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 3130
In contrast, the Inspector concluded
that the Council had no formal
agreements in place with any
specified RSL or developer and that
factually the Council was wrong in its
belief that properties were not
occupied.The Secretary of States conclusion
was that this was a finely balanced
case and that from the evidence
presented there is likelihood that if
the properties remain with the
owners there is a reasonable
prospect of their refurbishment/
redevelopment and the residential
elements being brought back into
active use within a relatively short
space of time. This is likely to be
speedier than if the Order was to be
confirmed and the properties passed
on by the Council to an RSL. Given
those conclusions, a compelling
case for compulsory acquisition was
not clearly demonstrated.
Westminster
The Westminster case concerned a
Listed Grade II mid terraced property
in an established residential area in
central London. It comprised six
floors of accommodation including a
half basement that had been empty
for five years. There had been some
squatting and the Owner had
obtained a possession Order. The
building was in a deteriorating
condition. Statutory notices had
been served but not complied with.
Shortly prior to the CPO being
made, dangerous structure notices
and a S215 notice were served.
The Councils case was that it was
an eyesore and a blight on the
neighbourhood. It was proposed
that, if acquired, the Council would
dispose of it to Westminster
Community Homes Ltd which would
apply for planning permission to
convert it into affordable homes.
The owner lived overseas. Evidence
was produced of that there hadpreviously been delays but a new
professional team had been
appointed and that since then more
active steps had been taken. Of
crucial importance in the case was
the contention that no party was
likely to be in a position to bring the
building into use until planning issues
had been resolved. There was
disagreement between the owners
advisers and the Council as to
whether permission was required for
uses including self-contained flats.
A Certificate of Lawfulness of
existing use or development had
been applied for but refused. The
Owner applied for listed building
consent which was granted.
However, planning permission was
refused on grounds that 9 residential
units failed to provide an appropriate
mix of unit sizes including family
units. A revised scheme was
however acknowledged to be likelyto have officer support. The Owner
had already spent 60,000 on the
proposals and was not prepared to
give an undertaking sought by the
Council wherein the Council would
not implement a confirmed CPO if
certain conditions were met.
Intention and timescale
The Secretary of States conclusions
were that there was no issue
between parties as to the physical
state of the building. The Owners
actions constituted evidence of
intention to carry out works, the
delays were explicable and the
monies spent demonstrated
commitment. There was therefore a
strong financial incentive for the
Owner to pursue refurbishment andconversion. Moreover, it was not
clear that the Councils preferred
social housing developer was in any
better financial position to develop
than the Owner. Works undertaken
meant that the property was no
longer a blight or eyesore.
The Secretary of State concluded
that the Owners recent actions
provide strong evidence that the
property will be brought back into
residential use within a reasonable
timeframe. A CPO was t herefore
not required to achieve that aim, nor
was there an overriding public
interest having regard to Art 1 First
Protocol ECHR rights.
This was a finely balanced case in
which the Secretary of State was
faced with the need to determine
what weight should be given to the
presently stated and evidenced
intentions of a landowner as against
previously an undeniably indifferent
delivery performance. In such
circumstances it is to be anticipated
and is appropriate that the benefit
of the doubt should be given to an
owner where it can be demonstrated
that there is a reasonable prospect
of a satisfactory outcome without
resort to compulsion.
Bradford
A Housing CPO made by Bradford
City Council10sought compulsory
acquisition of a three storey semi-
detached dwelling within a
Conservation Area. The Order Lands
contained trees subject to a Tree
Preservation Order.
The Councils case was that the
property was in a dilapidatedcondition and had been substantially
unoccupied for ten years. Various
complaints about anti-social
behaviour and nuisance were
associated with the property. It was
a blight on the Conservation Area.
Notwithstanding contact between
the Council and the Owner, steps
had not been taken by the Owner to
engage professional assistance to
renovate the property.
The Owner explained her personal
circumstances including family, work
and health issues that had adversely
affected the upkeep of the property.
Details of work that had been
undertaken were set out. Evidence
was also submitted querying why
the Councils use of compulsory
purchase powers was directed at
the Order property rather than many
other properties. It was argued thatthe Council had paid little heed to
the personal circumstances and had
thereby compromised the owners
human rights.
The Inspector accepted that the
dwelling was in poor condition and
had an adverse effect on its
environs. It was not unreasonable for
the Owner to put renovation on hold
given her particular health and
personal circumstances. Given those
circumstances, the Inspector
considered that the timing of the
Councils compulsory acquisition
was insensitive and premature. On
balance, the case was less than
compelling, especially given that the
Council was not pursuing the
compulsory acquisition of many
other vacant properties in the area.
The Inspector concluded that
bringing one dwelling back into use,quicker than the Owner might be
able to manage, was unlikely to
significantly improve the housing
stock of the District and would
interfere unnecessarily with the
Owners human rights.
Housing CPO evidential burden (continued)
The Secretary of State concluded that the
Owners recent actions provide strongevidence that the property will be broughtback into residential use within a reasonabletimeframe. A CPO was therefore notrequired to achieve that aim, nor was therean overriding public interest having regard toArt 1 First Protocol ECHR rights.
10. City of Bradford Metropolitan District Council (7 Parkfield Road, Manningham, Bradford, West Yorkshire, BD8 7AB) Compulsory Purchase Order 2013 (S17 Housing
Act 1985. Decision date 4 January 2013)
7/26/2019 Cpo Report 2015 Main Report May2015
18/25
Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 3332
Deliverability/Financial Viability/Alternative Scheme
Banbury
A further Housing CPO case in
which the balance between the
aspirations of the Acquiring Authority
and developer was in issue was the
Cherwell District Council CPO
under S17 of the Housing Act1985 in respect of The Crown
House site, Banbury11. The
purpose of the CPO was to provide
affordable housing and to regenerate
a long term vacant site in the centre
of Banbury. The landowner objected
on the basis that delays in bringing
the site back into use had not been
of the objectors making and that
planning permission had now been
granted and that the proposals for
bringing the site into beneficial use
were now viable.
Competing proposals
Initially an issue was raised as to
whether the CPO had been made
under appropriate powers but that
was not pursued further.
The Acquiring Authority promoted a
scheme for conversion of the
buildings on the site to 20 one bed
and 20 two bed residential units and
a 90 m2
ground floor retail space.The objector was Slighte Limited.
It proposed two potential schemes.
(i) 73 bedroom hotel, a restaurant
and 5 duplex apartments, together
with a change of use of part of the
existing office building to residential
use, making a total of 15 affordable
units; and (ii) conversion of Crown
House to 33 apartments.
The purpose of a Planning CPO
made by Manchester City Council
(City of Manchester (Former
London Road Fire Station)
Compulsory Purchase Order
2010)12was to safeguard and
enhance the regeneration of the
Piccadilly area and safeguarding the
fabric of a Grade II listed building,
namely the former London Road Fire
Station (LRFS). The Site also
included the Coroners Court, Police
Station and Bank.
The Inspector noted that the CPO
[was] unusual in that a scheme for
the redevelopment of the LRFS as a
regeneration driven, conservation-
conscious, 4* hotel, as favoured by
the Council, has been put forward
by the Objector (Britannia Centre
Ltd). In that sense, there were two
competing schemes, one supported
by the acquiring authority and that
promoted by the objector, Britannia.
The Council contended that
Britannia had failed to take
reasonable and adequate steps for
properly preserving the property, had
failed to bring forward proposals for
redevelopment in an acceptable
manner, and had not implementedplanning permission previously
granted.
Britannia countered that its
proposals would secure
development in a manner consistent
with the Councils regeneration
objectives for the Piccadilly area and
that the Council had disregarded
extant grants of planning permission
and LBC for its redevelopment as a
4* hotel, English Heritage support for
proposals, Britannias intention to
implement, and the timescales
required for redevelopment by a 3rd
party if the Council acquired the site.
Two key issues were identified:
Was there certainty, or at leastnear certainty, that Britannia
would complete the conversion
by 2014?
If not, was there a compelling
case in the public interest for the
Council to be in a position,
through a confirmed CPO, to
acquire the LRFS?
Britannias actions were subject to
some criticism. There was a lengthy
back-story of alleged delays. An
Implementation Agreement had not
been signed and there was tardiness
in implementing planning permission.
The Inspector was critical of the
basis upon which Britannias expert
witnesses were appointed and
instructed together with those
witnesses unquestioning
acceptance of what they had been
told by Britannia. Britannias
company witness also apparently
had little personal experience of the
matter and no knowledge ofcompany resolutions or financial
requirements as to acceptable rates
of return. The Inspector concluded
that unsurprisingly, against this
background, the Council has
concluded that Britannia cannot be
relied upon. At the same time, the
Inspector acknowledged the
possibility needs to be considered
that, whatever has gone before,
Britannia is now committed to
12. City of Manchester (former London Road Fire Station) Compulsory Purchase Order 2010. (S226(1)(a) TCPA 1990. Decision 28 November 2011)
redevelop in accordance with the
programme....
As regards the second issue, it was
argued by Britannia that a lack of
certainty around its proposal was
insufficient on its own to justify the
CPO. It was necessary for theCouncil to show that redevelopment,
in the near future, was necessary
and that there were demonstrable
regeneration and conservation/
building fabric benefits.
Timescale
The Secretary of State concluded
that although the purposes of the
CPO would accord with the adopted
planning framework for the area and
contribute to achievement of the
promotion or improvement of the
economic, social and environmental
wellbeing of the area, the financial
viability of the scheme the CPO was
intended to bring forward had not
been demonstrated and that, in
addition, the case for urgency had
not been made out. Moreover, and
crucially, redevelopment of the LRFS
with attendant regeneration benefits,
would be more likely to come
forward under Britannias auspices
than the Councils.
In addition, the Secretary of State
agreed with the Inspectors
conclusion that the fabric of the
building could be safeguarded by
measures that stopped short of
expropriation and, on that basis, the
purposes for which the acquiring
authority is proposing to acquire the
land could clearly be achieved by
other means.
Housing CPO evidential burden (continued)
The Inspector concluded that
although the Acquiring Authoritys
proposals accorded with the Local
Development Framework,
particularly in terms of meeting the
affordable housing needs of the
area, Slightes hotel led scheme
would accord marginally more
closely with development plan policy
by providing both housing and Town
Centre suitable development of a
restaurant and hotel.
Notwithstanding that 40 affordable
units would be a meaningful number
it comprised less than 1% of the
affordable units anticipated to be
delivered through the Plan system.
The Inspector therefore concluded
that the need for affordable housing,
whilst important, would not be
overwhelming.
In terms of funding and viability of
the Acquiring Authoritys scheme
there was little agreement between
the parties as to the costs involved
but the Inspector concluded that the
Acquiring Authority had a budget in
excess of 7 million and at a site
cost of 950,000 the combined
costs of site purchase and
construction would be comfortablywithin the Acquiring Authoritys
budget.
Track record v presentintentions
The Inspectors analysis of the
competing interests also included
assessment in detail of what
situation would prevail if the CPO
were n