Cpo Report 2015 Main Report May2015

Embed Size (px)

Citation preview

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    1/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014I

    IntroductionPlanning and Housing CPOs 2003-2014

    Compulsory Purchase Orders: 2015 update

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    2/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014II 1

    Foreword 2

    Introduction 4

    Planning and Housing CPO Statistics 2012-2014 7

    Effectiveness of CPOs

    Implementation by Acquiring Authorities 19

    Reasons why some CPOs fail

    Secretary of State decisions 2009 2014 22

    Enabling power and clarity of objectives 23

    Technical deficiencies 25

    Procedural issues/Withdrawal of Order 27

    Housing CPO evidential burden 29

    Deliverability/Financial Viability/Alternative Scheme 33

    Acquisition by agreement 37

    Failure to demonstrate need 38

    Not confirmed/Withdrawal by consent 40

    Comments on reasons for CPO failure 42

    Appendix: Schedule of CPOs 43

    Contents

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    3/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 32

    Foreword

    Continued high success rates with both

    Planning and Housing Compulsory PurchaseOrders (CPOs) and a recovery in the use ofPlanning CPOs demonstrates howcompulsory purchase assists in drivingurban regeneration and housing renewal.

    CPOs are demonstrably an effective

    tool in the armoury of local

    authorities. As can be seen from our

    latest research, Planning CPOs

    continue to drive regeneration, and

    facilitate development and

    redevelopment, particularly in urban

    areas. Although levels of usage

    remain lower than pre-recession

    figures, 2014 saw a significant

    recovery in the use of PlanningCPOs, hopefully presaging the

    returning economic confidence and

    increasing viability of major schemes.

    Both Planning and Housing CPOs

    have very high success rates. In

    broad, headline terms we consider

    that it is reasonable to conclude that

    95% or more CPOs are actively

    confirmed or result in acquisition

    by agreement being achieved.

    Moreover such rates have been

    achieved consistently, year

    upon year.

    To the extent that the making of

    Planning CPOs operates as a proxy

    for economic confidence given that

    the making of a CPO is often

    representative of a key step incommitment by both the public and

    private sectors towards a major

    development scheme the signs of

    renewed development activity are

    encouraging. In 2014 58 Planning

    CPOs were submitted compared

    with 36 in 2013 representing a 61%

    increase. Moreover although the hot

    spots for use of CPOs remain

    London, the Midlands and the North

    West, there is evidence that CPOs

    are being used nationwide. In

    addition, CPOs are used to

    assemble site for smaller schemes of

    considerable local significance.

    For example, 2014 has seen

    Planning CPOs made promoting

    major schemes such as the retail-led

    Whitgift Centre in Croydon, theWatford Health Campus, and

    housing-led schemes such as

    Barnet LBCs West Hendon

    Regeneration Area and Phase 3

    of the Edge Hill project made by

    Liverpool City Council.

    Frank Orr

    Legal Director

    T: +44 191 279 9086E:frank.orr

    @bonddickinson.com

    Key contact

    Housing CPOs are more likely to

    involve acquisition of individual

    properties or small groups or

    clusters. That they can be aneffective, coordinated tool for

    housing regeneration and

    improvement is well evidenced by

    their use by Burnley Borough

    Council, which has utilised Housing

    CPOs extensively as part of its

    Vacant Property Initiative (VPI),

    addressing long-term vacant

    property as part of a targeted

    approach to housing improvement.

    CPOs must of course be used

    carefully and proportionately, having

    proper regard to the rights of

    affected third parties. Acquiring

    Authorities must demostrate that

    there is a compelling case in the

    public interest for a CPO to be

    confirmed.

    Generally local authorities

    possessing compulsory purchase

    powers (ie Acquiring Authorities)

    use their powers sparingly and most

    make only one CPO in any givenyear. There is a small, but not

    insignificant, body of Acquiring

    Authorities that use their powers

    more frequently. This we consider

    reflects their positive experience

    gained from repeated success with

    CPOs and the allocation of

    resources such as dedicated

    CPO staff.

    Our Freedom of Information

    enquiries to Acquiring Authorities (for

    which we are grateful for the

    responses received) suggestshowever that in many cases there is

    an absence of an active corporate

    memory of how CPOs were used

    and what lessons have been

    learned. We would fight shy of

    suggesting that a statutory register

    of CPOs and their outcomes is

    required, but it is best practice for an

    acquiring authority to review how its

    CPOs have been promoted and

    whether identified objectives have

    been achieved.

    As this report goes to press the

    Department for Communities and

    Local Government and HM Treasury

    have jointly instigated consultation

    on proposed reform to compulsory

    purchase processes. The

    consultation reiterates Governments

    view that compulsory purchase

    powers are an important tool for

    assembling land needed to help

    deliver social, environmental and

    economic change and that usedproperly, compulsory purchase can

    contribute towards effective

    regeneration.

    The consultation also recognises the

    need for the compulsory purchase

    system to balance interference with

    third party rights whilst improving

    efficiency and delivery. The

    proposals therefore seek to

    streamline processes in a number

    of ways, including the introductionof timescales for key stages and

    decision-making, whist maintaining

    fairness to third parties. As this

    report identifies compulsory

    purchase is an effective tool for

    delivering change and regeneration

    but there is scope for improving

    delivery of properly made CPOs

    and that aim of the consultation is

    very much to be welcomed.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    4/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 54

    Introduction

    Among the key messages of the

    earlier reports were:

    CPOs are a vital tool for

    regeneration.

    Usage in 2009 was at its lowest

    for several years.

    Success rates for both Planning

    and Housing CPOs were generally

    high.

    There was a range of reasons,

    from technical to evidential, why

    some CPOs were not confirmed.

    This report updates the statistics

    further to the end of 2014 and alsolooks at Secretary of State decisions

    between 2009-2014 not to confirm

    CPOs, i.e. it seeks to identify the

    reasons why CPOs sometimes fail.

    In addition, based on information

    obtained from Acquiring Authorities,

    the report includes initial conclusions

    about levels of implementation of

    CPOs and commencement of

    schemes where sites have been

    assembled by CPO.

    In 2010, Dickinson Dees LLP (now Bond Dickinson LLP) publisheda detailed review of the use and success of Compulsory PurchaseOrders (CPOs), particularly Planning1and Housing2CPOs. The reportcontained a statistical analysis of the outcomes of CPOs, analysing

    how many were confirmed (with or without modification), how manywere not confirmed and how many were treated as withdrawn.It also contained case reviews of the reasons why CPOs were notconfirmed. An update of the statistics was published in 2012.

    The statistical report focuses on

    Planning and Housing CPOs since

    these are by far the most numerous

    CPOs made. However, the decision

    reviews also include reference to

    CPOs made under other powers

    where there are notable reasons for

    non-confirmation. The key findings of

    this report include:

    Many local authorities make use of

    compulsory purchase powers but

    do so sparingly.

    Success rates for both Planning

    and Housing CPOs remain

    consistently high.

    In 2013 the use of Planning CPOs

    fell to the lowest level since 2003

    (the first year covered by this

    study), but recovered significantly

    in 2014.

    Use of Planning Act powers still

    remains lower than levels achieved

    pre-recession.

    There is consistently more

    frequent use of Housing Act

    powers than Planning Act powers,

    with spikes in Housing CPO usage

    reflecting targeted programmes of

    use by one or two Acquiring

    Authorities.

    For example, 2013 saw an

    increase in the use of Housing Act

    powers principally because of

    extensive use by a small number

    of Acquiring Authorities.

    Planning CPOs are more likely to

    comprise more complicated

    schemes and attract objections

    than Housing CPOs;consequently, Planning CPOs on

    average take longer than Housing

    CPOs to be determined.

    Most confirmed CPOs are

    implemented by means of General

    Vesting Declaration (GVD) as

    opposed to using a Notice to

    Treat. This vests title in the

    Acquiring Authority when

    possession occurs.

    1. Made under s.226 Town and Country Planning Act 1990

    2. Made under s.17 Housing Act 1985

    Data derived from Acquiring

    Authorities in respect of

    implementation is incomplete but

    provisionally indicates:

    up to 88% of Planning CPOs and

    90% of Housing CPOs being

    implemented by one or other ofthe statutory methods, or by

    agreement in the light of a

    confirmed CPO.

    at least 56% of Planning CPOs

    and 61% of Housing CPOS have

    resulted in completed schemes or

    schemes that are in progress.

    Acquiring Authority derived data

    of the timescales involved in the

    CPO process is consistent with

    DCLG/NPCU data.

    The reasons why some CPOs are

    not confirmed range from the

    technical to evidential and include:

    for CPOs generally: technical

    drafting errors; the availability of

    alternative solutions falling short of

    the need for compulsory

    acquisition; and failure to

    demonstrate that all Order land

    was needed

    for Housing CPOs: the weight tobe given to an owners ability to

    deliver a comparable scheme; the

    personal circumstances of an

    owner; and the Acquiring

    Authoritys failure to put in place

    delivery mechanisms for its

    preferred scheme

    for Planning CPOs: a successful

    challenge to the assumptions

    underlying the viability of a

    proposed scheme; failure to

    demonstrate that a CPO was

    timely; evidence of planning

    impediments; failure to meet the

    tests in Circular 06/04; non-

    conformity with Local

    Development Framework; and

    absence of updated evidence

    base establishing quantitative

    need.

    It should also be noted that the

    levels of CPOs not confirmed does

    not necessarily mean that the CPO

    has failed. CPOs are often treated

    as not confirmed at the request of

    an acquiring authority when

    acquisition has occurred by

    agreement against the background

    of a CPO.

    Given that that success rate of

    Planning and Housing CPOs

    remains high it can be concluded

    that they continue to represent a

    significant tool available to local

    authorities to promote site assembly

    and regeneration. We have also

    drawn some initial conclusions

    based on Acquiring Authority dataas to the extent to which confirmed

    CPOs are implemented and the

    objectives of the acquiring authority

    have been achieved. That field of

    study would benefit from further

    detailed research.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    5/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 20146 7

    Planning and Housing CPO Statistics 2012-2014

    Figure 1 shows that:

    In 2012:

    46 Planning CPOs were submitted

    by Local Authorities. That is

    almost identical to the 47 Planning

    CPOs submitted the previous

    year, 2011.

    37 Housing CPOs were

    submitted, representing a 25%

    decrease from the 50 submitted

    in 2011.

    In 2013:

    36 Planning CPOs were

    submitted. This is the lowest figure

    in all the years covered by this

    report, i.e. since 2003. Indeed it is

    lower than the 40 submitted in

    2009, during the depths of the

    recession.

    In contrast, 92 Housing CPOs

    were submitted the highest level

    for ten years. During the years

    covered by the survey, only 2004

    demonstrates higher levels of

    usage.

    2012 2013 2014

    Planning CPOs

    submitted (including

    those not determined)

    46

    (27 opposed)

    36

    (14 opposed)

    58

    (31 opposed)

    Housing CPOs

    submitted (including

    those not determined)

    37

    (13 opposed)

    92

    (23 opposed)

    66

    (22 opposed)

    Figure 1:

    Planning and Housing CPOs submitted 2012-2014 totals

    In 2014:

    58 Planning CPOs were

    submitted. This is a return to 2010

    levels and reflects a recovery from

    the 36 submitted in 2013.

    66 Housing CPOs were

    submitted. This is a drop of 29%

    from the 92 Orders submitted in

    2013 but is in line with the general

    levels of usage from 2009-2011.

    Moreover, in terms of the longer term

    trend, the number of Planning CPOs

    submitted post-recession andeconomic downturn continue to be

    of a different order to the levels of

    usage witnessed 2004-2008.

    To the extent that the use of Planning

    CPOs can be viewed as a proxy for

    economic/redevelopment activity

    and in particular as a barometer of

    economic confidence, then the

    confirmed lower levels of usage are

    perhaps unsurprising. What is

    unclear is whether there is any

    specific underlying reason for the

    drop in 2013 to 36 CPOs.

    Given the lead-times involved in

    preparation of Planning CPOs it

    may reasonably be assumed that

    the 2013 figures reflect prevailing

    economic conditions in 2011-2013

    in the UK. Moreover, given the

    increase in Planning CPOs in 2014

    to a level consistent with all other

    years from 2009, it is suggested

    that the 2013 should not

    necessarily be viewed as indicative

    of any longer term trend.

    Levels of usage of Housing CPOs

    are perhaps less representative ofgeneral economic activity and

    more closely tied to access to

    public sector funding. As Figure 2

    demonstrates, they are more

    volatile than Planning CPOs. An

    increase in the use of Housing

    CPOs can be attributed to a small

    number of Councils undertaking

    targeted programmes of

    improvement. The significant

    increase in 2013 to 92 Housing

    CPOs would appear to reflect

    more extensive use of CPOs by a

    number of authorities, notably

    Burnley as shown on pages 14

    and 15.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    6/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 98

    Figure 2:

    Planning and Housing CPOs submitted from 01/01/03 to 31/12/14

    Figure 3:

    Planning and Housing CPOs determined from 01/01/03 to 31/12/14

    The change in the numbers of

    Planning and Housing CPOs

    submitted each year for the period

    2003-2014 is illustrated in Figure 2.

    In broad terms, the level of usage of

    Planning CPOs from 2009-2014

    remains down from previous levels

    at around three quarters of 2004-

    2008 levels. However the

    submission in 2014 of 58 planning

    CPOs represents a significant

    recovery in usage from the previous

    years figure of 36 which was the

    lowest annual figure in the years

    covered by the study.

    Whilst the above figures for

    submission of CPOs are robust there

    have been some difficulties with the

    data available in respect of

    determination of CPOs. In March

    2011, the National Planning

    Casework Unit (NPCU) within the

    Department for Communities and

    Local Government (DCLG) was

    established and from May 2012 it

    began to have responsibility for

    compulsory purchase matters that

    had previously been overseen by the

    National Unit for Land Acquisition

    and Disposal (NULAD). Prior to

    that formal handover, it appears that

    to a limited degree NPCU operated

    in tandem with NULAD. For example,

    between 14 March and 31

    December 2011, NPCU received

    three Housing CPOs for

    determination. It is understood that

    during that period all other Planning

    and Housing CPOs continued to be

    handled by NULAD.

    The handover from NULAD to NPCU

    was completed around 30 April

    2012. From that date onwards it is

    understood that all Planning and

    Housing CPOs have been dealt with

    by NPCU.

    Planning and Housing CPO Statistics 2012-14(continued)

    2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

    Housing

    Planning

    20

    40

    60

    80

    100

    In 2012 to the end of April of that

    year, NULAD determined 14 Housing

    CPOs, whereas NPCU determined

    15 Housing CPOs in the rest of the

    year. In the same time periods,

    NULAD determined 26 Planning

    CPOs whereas NPCU determined

    18. We would suggest that this data

    reflects both NULAD completing the

    determination of outstanding CPOs

    before it ceased to have such

    responsibility and also NPCU taking

    a little time to get up to speed with

    its new responsibilities.

    The level of usage of Housing CPOs,

    having been more or less constant

    over the past four years, took a

    significant upturn in 2013. The profile

    of use is shown on pages 14 and 15

    in Figure 6. In broad terms it reflects

    the making of Housing Act CPOs

    once or twice per annum by most of

    the authorities using the power and

    one authority making extensive use

    of it.

    20

    40

    60

    80

    100

    120

    2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

    Housing

    Planning

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    7/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1110

    66%64%

    67%

    14%

    4%

    4%

    7%

    9%

    7%

    9%

    3%

    2%

    26%

    18%

    Confirmed without modification

    (including referred to Acquiring

    Authority for confirmation)

    Confirmed with modification

    Not confirmed

    Withdrawn

    Other

    2012

    2014

    2013

    Figure 4:

    How Planning CPOs were determined 2012 2014

    Figures 4 and 5 show how Planning

    and Housing CPOs, respectively,

    were determined from 2012-2014.

    For Planning CPOs these figures

    denote continuing high rates of

    success and indeed an increase in

    CPOs recorded positively as havingbeen confirmed. The key points to

    note include:

    The percentage confirmed without

    modification (including those

    referred back to Acquiring

    Authorities for determination)3was

    remarkably consistent: 66% in

    2012; 64% in 2013 and 67% in

    2014.

    This represents a general increase

    in the percentage of CPOs

    confirmed without modification as

    compared with 46% between

    2003 and 2009 and 60% in

    2010-2011.

    Confirmation with modification is

    more variable: 9% in 2012; 26%

    in 2013 and 18% in 2014.

    Whilst confirmation without

    modification remains more or less

    consistent, as regards the balance

    of CPOs, ie CPOs eitherconfirmed with modifications or

    not confirmed or withdrawn

    respectively, these outcomes

    often reflect the submisson of

    objections to a CPO.

    That where there is an objection

    to a CPO, potential outcomes

    may include:

    modification of an Order as a

    result of more active scrutiny and/

    or negotiation

    not confirmed decisions where a

    CPO actively fails in the light of an

    objection

    acquisition by agreement (with the

    CPO subsequently being either

    recorded as not confirmed or

    withdrawn).

    The confirmation with modification

    figures in earlier years are: 31%

    from 2003-2009; 23% in 2010;

    and 12% in 2011.

    7% of CPOs in 2013 were

    recorded as not confirmed. This

    is consistent with 6% (2003-2009)

    and 8% (2010).

    4% not confirmed in 2014 is

    slightly below average. 14% in

    2012 is above average. The figure

    of 18% for 2011 would appear to

    be out of step with t he broad

    pattern.

    The annual totals of actively

    confirmed Planning CPOs were:75% (2012); 90% (2013) (ie both

    with and without moderation) and

    85% (2014).

    3. As per the powers contained in s.14A Acquisition of Land Act 1981

    As has been emphasised in

    previous reports, the fact that a

    CPO is listed as not confirmed

    does not necessarily mean that a

    CPO should be considered to

    have failed. In many cases, it

    reflects an acquisition byagreement and request for an

    Order to be treated as not

    confirmed.

    There appears to be greater

    consistency and accuracy in the

    recording of Planning CPO data

    compared with the earlier years

    covered by our reports.

    Planning and Housing CPO Statistics 2012-14(continued)

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    8/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1312

    76%

    14%

    3%3%

    3%

    9%

    6.5%

    3%

    80%

    1.5%

    10%

    7%

    11%

    1%1%

    69%

    Confirmed without modification

    (including referred to Acquiring Authority)

    Confirmed with modification

    Not confirmed

    Withdrawn

    Inverted

    Other

    2012

    2014

    2013

    Figure 5:

    How Housing CPOs were determined 2012 2014

    Figure 5 indicates how Housing

    CPOs were determined in 2012,

    2013 and 2014. The results for 2013

    show a significant increase in usage

    of Housing CPOs from the

    immediately preceding years and an

    increase in the percentage of CPOsconfirmed. In addition, of the CPOs

    confirmed there is an increase in the

    percentage of CPOs confirmed

    without modification. The key points

    to note include:

    Success rates for Housing CPOs

    are consistently high.

    Total confirmations (confirmations

    both with and without

    modification) were 90% (2012);

    89% (2013); and 80% (2014).

    Confirmations without modification

    (76%, 80% and 69% 2012-14)

    (including those referred to the

    Acquiring Authorities for

    determination) are all higher than

    averages for previous years for

    which data is available: 62%

    (2003-2009), 61% (2010) and

    68% (2011).

    Confirmations with modification.

    (14%, 9% and 11% 2012-14)

    were all lower than previous yearsdata with one exception: 19%

    (2003-2009), 15% (2010) and

    12% (2011).

    The increase in confirmation

    without the need for modification

    and the concomitant fall in the

    percentage of CPOs confirmed

    with modification may indicate

    improvements in the technical

    standard of Orders and increasedfamiliarity with the statutory and

    policy requirements.

    The annual totals of CPOs not

    confirmed were 3% (2012); 6.5%

    (2013) and 7% (2014). The latter

    two years were slightly higher than

    both the 5% average from 2003-

    2009 and 4% and 2% in 2010 and

    2011, respectively.

    The 3% of Housing CPOs

    withdrawn in 2012 and 2013

    respectively contrasts with 10%

    (2003-2009), 18% (2010) and

    16% (2011). In that respect, 10%

    of withdrawals in 2014 is more in

    line with the historic pattern.

    The differentiation between not

    confirmed and withdrawn in

    respect of Housing CPOs needs

    to be treated with caution. We

    consider that previously there was

    a degree of inconsistency in

    recording Orders as either not

    confirmed or withdrawn.

    Present practice would usually

    appear to treat CPOs as not

    confirmed where requested to be

    treated as withdrawn. It is perhaps

    safer to compare the combined

    totals of Orders both not

    confirmed and withdrawn. For

    example, that exercise shows a

    reduction from 15% (average2003-2009), 22% (2010) and 18%

    (2011) to 6% (2012), 9.5% (2013)

    and 17% (2014).

    Planning and Housing CPO Statistics 2012-14(continued)

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    9/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1514

    Figures 6 (a) and (b) indicate how CPO usage is spread across local authorities.

    Figure 6a:

    Number of local authorities submitting Planning CPOs 2013 2014

    Figure 6b:

    Number of local authorities submitting Housing CPOs 2013 2014

    1 2 3 4 5 6 14 21

    NumberofLocalAuthorities

    2013

    Number of Housing CPOs submitted

    2014

    0

    5

    10

    15

    20

    25

    30

    0

    2013

    1

    Number of Planning CPOs submitted

    NumberofLocalAuthorities

    2 3 4

    5

    10

    15

    20

    25

    30

    2014

    In 2013, 31 separate Acquiring

    Authorities submitted Planning

    CPOs. Of these, 26 made a single

    CPO in that year. Three authorities

    (Burnley, Birmingham and

    Wolverhampton) made two CPOs

    and two (Hackney and Rochdale)

    made three.

    In 2014, 40 separate Acquiring

    Authorities submitted Planning

    CPOs. Of these, 28 made a single

    CPO in that year. Seven authorities

    (Barnet, Burnley, Daventry, Hastings,

    Birmingham, Lincoln and Watford)

    made two CPOs. Four authorities

    (Hackney, Ealing, Enfield and

    Liverpool) made three CPOs. One

    authority (Brent) made four CPOs.

    In 2013, 36 separate authorities

    submitted Housing CPOs. Nineteen

    authorities each made a solitary

    CPO. Five authorities (Birmingham,

    Doncaster, Leeds, Newham,

    Redditch) made two CPOs. Four

    authorities (Bradford, Great

    Yarmouth, Hounslow,

    Wellingborough) made three CPOs.

    Bristol made four CPOs. Four

    authorities (Derby, Sutton, Wigan,

    Wolverhampton) made five CPOs.

    Stoke-on-Trent made six CPOs. By

    far the most prolific user of Housing

    CPO powers was Burnley which in

    2013 made 21 separate CPOs.

    In 2014, a similar pattern emerges.

    Thirty eight separate authorities

    submitted Housing CPOs. Twenty

    five authorities each made a solitary

    CPO. Nine authorities ( Barnet,

    Bristol, Broadland, Barking and

    Dagenham, East Riding of Yorkshire,

    Ipswich, Tendring, Stevenage and

    Wolverhampton) made two CPOs.

    Three authorities (Derby, Blackburn

    with Darwen and Wigan) made three

    CPOs. Burnley made 14 CPOs.

    Burnley has used Housing CPO

    powers extensively as part of its

    Vacant Property Initiative (VPI).

    This initiative was particularly active

    in 2006-2009 and latterly in

    2013 -2014 and has been used to

    address long-term vacant property

    as part of a targeted, cluster

    approach to housing market renewal.

    It is understood that around 70

    properties have been subject to

    compulsory purchase in this way.

    Planning and Housing CPO Statistics 2012-14(continued)

    Those acquired have been

    refurbished and sold thereby

    bringing the properties back into

    use. Proceeds of sales were

    recycled back into the VPI.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    10/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1716

    Region No. ofCPOssubmittedin 2014

    Total number ofCPOs opposed ofthose submitted

    No. of CPOsdeterminedin 2014

    Confirmedwithmodification

    Confirmed withoutmodification(including referred toacquiring authority)

    Notconfirmed

    GO-East 4 2 3 1 4 -

    GO-EastMidlands

    2 - 4 - 4 -

    GO-London 22 13 16 2 11 2

    GO-North East 4 3 2 1 1 -

    GO-North West 13 6 6 2 4 -

    GO-South East 5 1 3 - 1 -

    GO-South West 1 1 2 - 2 -

    GO-WestMidlands

    4 4 2 1 1 -

    GO-YorkshireHumber

    3 1 3 1 2 -

    Figure 7:

    Planning CPOs by region 2014

    Region No. ofCPOssubmittedin 2014

    Total number ofCPOs opposed ofthose submitted

    No. of CPOsdeterminedin 2014

    Confirmedwithmodification

    Confirmed withoutmodification(including referred toacquiring authority)

    Notconfirmed

    GO-East 13 4 8 1 5 -

    GO-EastMidlands

    4 1 4 - 3 -

    GO-London 10 3 22 2 14 3

    GO-North East 1 1 1 - 1 -

    GO-North West 25 5 23 - 20 1

    GO-South East 1 1 1 - - 1

    GO-South West 5 2 3 - 2 -

    GO-WestMidlands

    3 2 8 1 6 -

    GO-YorkshireHumber

    4 3 3 1 2 -

    Figure 8:

    Housing CPOs by region 2014

    Planning and Housing CPO Statistics 2012-14(continued)

    The results for 2014 are consistent

    with previous findings:

    CPO usage continues to be

    spread widely but thinly. Many

    authorities use CPO powers, but

    do so sparingly. In particular it is

    unusual for an authority to make

    more than one Planning CPO

    annually.

    Of course, the number of

    individual CPOs does not of itself

    reflect the scale or nature of the

    intervention by an Acquiring

    Authority.

    In line with previous reports

    regionally London and the North

    West consistently have the

    highest totals of both Planning

    and Housing CPOs made.

    For Planning CPOs, in London 22

    were submitted in 2014

    compared with 10 the previous

    year. In the North West 13 were

    submitted in 2014 compared with

    nine in 2013.

    For Housing CPOs, in the North

    west 25 were submitted in 2014

    as against 28 the previous year. In

    London 2014 saw 10 submitted

    compared with 18 in 2013.

    There is otherwise fluctuation

    between regions. The 2014

    figures show an increase in the

    use of Housing CPO powers in

    the East region to 13 from four in

    2013. The opposite has occurred

    in the West Midlands: a fall to

    three from 14 in 2013.

    A relatively small number of

    Councils as noted above in figure

    6b account for a significant

    proportion of Housing CPOs. With

    Planning CPOs the distribution is

    more even.

    Our earlier findings established

    that Planning CPOs are more

    likely to generate objections than

    Housing Orders. That still remains

    the case but there has been an

    increase in objections to Housing

    CPOs rising to 33% as compared

    with 26% in 2013.

    Figures7 and 8 provide a breakdown of usage by former Government Office regions for 2014.

    In addition to the above data we

    have analysed those Orders

    submitted in 2012 and 2013 and

    determined by the Secretary of State

    in terms of how long it takes from

    the receipt of the Order and the

    Secretary of States decision date.

    These are set out overleaf in

    Figure 9.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    11/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 1918

    Effectiveness of CPOs Implementation by Acquiring Authorities

    2012 2013

    Opposed Unopposed Opposed Unopposed

    Planning 323 123 281 97

    Housing 296 112 119 63

    Figure 9:

    Average time (in days) from receipt of CPOs to Secretary of State decision, 2012-2013

    Our previous research has focused

    on the CPO process up to the

    Confirming Authoritys decision.

    It is acknowledged however that the

    mere fact of whether or not a CPO

    has been confirmed has some

    limitation as a measure ofeffectiveness of compulsory

    purchase as it does not address if

    and how implementation occurs.

    We have already noted above that

    withdrawal or non-confirmation of a

    CPO is not necessarily an indication

    of failure; more often than not we

    would suggest it reflects acquisition

    by agreement having been achieved

    against the background of a CPO

    such that a confirmed Order is no

    longer required. Conversely, the

    confirmation of a CPO does not

    necessarily mean that it will

    subsequently be implemented and

    all interests acquired. Indeed

    following confirmation there are a

    number of potential scenarios that

    may apply including:

    Immediate acquisition by

    implementation of the CPO of all

    or some land comprised within

    the CPO; or

    Acquisition by agreement

    notwithstanding that the CPO has

    been confirmed; or

    Delay in acquisition

    postponement of implementation

    by GVD and/or Notices to Treat;

    or

    The CPO is never implemented.

    Are confirmed CPOs alwaysimplemented?

    As regards Planning CPOs in

    particular there is a myriad of factors

    affecting viability and deliverability,

    and therefore, in turn, the speed and

    manner in which a CPO may beimplemented by the Acquiring

    Authority. We would suggest that

    anecdotally there is evidence that

    where schemes were conceived

    pre-recession but site assembly was

    facilitated and concluded by means

    of CPO in a wholly different

    economic climate then there have

    been significant delays in the

    implementation of the relevant Order.

    Indeed such situations have required

    considerable resourcefulness by

    CPO practitioners to keep the

    implementation window open,

    including reliance upon Notices to

    Treat rather than GVDs and thereby

    effectively extending the window for

    taking possession from three years

    to six years from the date of

    confirmation of CPO powers.

    In respect of Housing CPOs,

    especially those of single, problem

    properties, the situation is often

    more straightforward andimplementation frequently proceeds

    in good time by disposal of the

    property to the market forthwith.

    At the Compulsory Purchase

    Association conference in 2014, a

    question was asked from the floor as

    to whether there were any statistical

    data about whether CPOs were

    successful in the sense of both

    being implemented and thereafter

    the intended scheme coming to

    fruition. Of course it is recognised

    that the CPO process of itself cannot

    ensure delivery of a scheme per se,

    but as a mechanism it uniquely

    may facilitate a scheme which

    would not otherwise be possible.

    We therefore made Freedom ofInformation requests to all Acquiring

    Authorities that DCLG data indicated

    had made CPOs since 2003,

    enquiring as to what steps were

    taken post-confirmation and whether

    confirmed CPOs were implemented

    and the underlying scheme was

    delivered. We also sought

    information as to how long both the

    pre-confirmation process took and

    how long it took in total, from

    making a CPO to commencement of

    the underlying scheme.

    The responses were varied but we

    have obtained data in respect of

    over 800 CPOs upon which we have

    based the following observations.

    Responses ranged from fully

    completed answers to all questions

    together with additional details and

    analysis on the one hand, to refusal

    either to acknowledge that the

    authority had made any CPOs or todecline to supply any data on the

    grounds of confidentiality on the

    other hand. Moreover, the

    incomplete nature of many

    responses reflects the somewhat

    varied nature of Acquiring

    Authorities corporate memory

    of the reasons why CPOs were

    undertaken and the outcomes of

    the process. There is presently no

    statutory or other obligation on

    Acquiring Authorities to keep a

    Planning and Housing CPO Statistics 2012-14(continued)

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    12/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2120

    register of CPOs made and/or

    confirmed, or indeed to record the

    outputs of the process. We consider

    that whilst there would be benefits

    from a statutory obligation to keep

    a register of CPOs made and their

    respective outcomes, these would

    not necessarily be proportionate to

    the costs involved. However, as a

    matter of best practice, Acquiring

    Authorities may wish to keep such

    a record or register and may wish to

    complete a brief lessons learned

    report at the conclusion of the CPOprocess reflecting on how the CPO

    proceeded and identifying any best

    practice issues relevant to future use

    of CPO.

    On the basis of the data collected

    we would make the comments

    below.

    Figure 10 indicates that, as

    practitioners may expect, GVD is the

    most common way of implementing

    a CPO. There is clear evidence that

    the majority of CPOs have been

    implemented by means of GVD,

    Notice to Treat or a combination of

    (i)

    GVD

    (ii)

    NoticestoTreat/

    of Entry

    (iii)

    Combinationof (i) and (ii)

    (iv)

    Agreement

    (v)

    Nopossession

    taken

    (vi)

    Unknown

    Planning 51.8% 2.6% 11.7% 8.8% 11.4% 13.6%

    Housing 69.1% 1.5% 6.2% 6.6% 8.8% 7.6%

    Figure 10:

    Method of implementation of Planning and Housing CPOs 2003-2014

    Figure 11:

    Schemes undertaken pursuant to Planning and Housing CPOs 2003-2014

    the two. The responses received

    indicate that 70% of Planning CPOs

    and 77% of Housing CPOs have

    been confirmed by means of the

    formal, statutory process.

    In addition, it is interesting to note

    that responses indicated that in

    8.8% and 6.6% of Planning and

    Housing CPOs, respectively,

    possession was obtained by

    agreement notwithstanding that a

    confirmed CPO was in place. These

    figures perhaps need to be treatedwith some caution, however, and are

    deserving of further analysis.

    Taking the combined totals for

    columns (i) (iv) in the above table

    represents a positive answer to

    whether implementation took place

    in respect of 75% of Planning CPOs

    and 83% of Housing CPOs.

    In addition, upon closer inspection

    and enquiry it appears that some

    responses stating that no

    possession was taken have been in

    circumstances where, in fact,

    acquisition by agreement had

    occurred. Those figures t herefore

    also require further examination. The

    unknown responses reflect gaps in

    the database. If the unknowns are

    discounted the figures are 88% of

    Planning CPOs and 90% of Housing

    CPOs being implemented by the

    statutory method or by agreement in

    the light of a confirmed CPO.

    Figure 11 reflects an attempt to get

    to the heart of the question as to the

    extent to which Planning and

    Housing CPOs result in the deliveryof the intended underlying scheme.

    On a positive note, 31% of Planning

    CPOs have resulted in completed

    schemes together with 25% of

    schemes being described as in

    progress. In comparison, 50% of

    Housing CPO schemes have been

    completed, with 11% being in

    progress.

    Where schemes are described as

    not yet commenced that indicates

    that it is still envisaged that there is a

    likelihood or intention to carry out

    the scheme. In contrast, the not

    Not yet

    commenced

    In progress Completed Not

    undertaken

    Unknown

    Planning 14.9% 25.4% 31.1% 15.7% 12.9%

    Housing 8.1% 11.1% 49.7% 19.6% 11.5%

    Average time (in months) between

    CPO made andCPO confirmed

    CPO confirmedand possession

    Possession andSchemecommencement

    Planning 10.82 10.79 9.47

    Housing 8.18 9.45 6.18

    Figure 12:

    Average timescales for implementation of Planning and Housing CPOs 2003-2014

    undertaken column reflects those

    schemes that will no longer happen

    or are unlikely to happen. Around

    16% of Planning CPOs and 20% of

    Housing CPOs are not undertaken.

    From the responses received, it

    appears likely that, in terms of

    Housing CPOs, some Orders where

    the scheme has not occurred have

    however resulted in outcomes that

    were not anticipated at the outset,

    for example by way of sales to third

    parties or otherwise, and have

    thereby delivered an alternative

    scheme.

    Figure 11 reflects initial analysis of

    the responses received. It is

    intended in due course that more

    detailed analysis will be undertaken.

    In addition, we have calculated the

    average timescales for

    implementation of Planning and

    Housing CPOs from the data

    submitted by Acquiring Authorities

    as set out at Figure 12 above. These

    data are not as fine-grained as the

    DCLG/NPCU records of time taken

    to process CPOs; the data reflects

    the passage of months rather than

    days. In broad terms, Figure 12 acts

    as a check against the data derived

    from the NPCU figures. However, the

    correlation between the two sets of

    data is striking.

    Effectiveness of CPOs Implementation by Acquiring Authorities(continued)

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    13/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2322

    Enabling power and clarity of objectivesReasons why some CPOs fail Secretary of State decisions 2009 2014

    By definition, CPOs are site specific.

    Moreover, each CPO stands or falls

    on its own merits. An Acquiring

    Authority commencing the

    compulsory purchase process is well

    advised to remind itself of the

    Secretary of States requirements in

    Circular 06/04 (currently being

    revised).

    In particular, it should be

    emphasised that the onus is

    squarely on an Acquiring Authority

    to demonstrate that there is a

    compelling case in the public interest

    for compulsory acquisition. The

    decision letters reviewed

    demonstrate how the Secretary of

    State can be expected to weigh

    carefully and balance the competing

    public and private interests and to

    assess whether the interference

    proposed is both proportionate and

    necessary.

    An Acquiring Authority should bear

    in mind that the Secretary of State

    will look at each CPO on its own

    merits this is not a tick box

    exercise. It will therefore need to

    apply its mind to particular

    circumstances of each case. The

    onus is firmly on it to demonstratethat there is a compelling interest in

    the public interest and consequently,

    notwithstanding the generally high

    success rates, there is no room for

    complacency. An Acquiring Authority

    must therefore clearly identify the

    objectives and benefits of its

    proposed scheme, demonstrate that

    efforts have been made to acquire

    by agreement (or reach other

    acceptable arrangements for access

    to or use of land) and establish a

    robust evidential base in order to

    establish the need for compulsory

    purchase.

    Acquisition by agreement

    For developers seeking to take

    possession of, and develop a site

    assembled by means of compulsory

    purchase, engagement with the

    process is a pre-requisite. For

    example, the CPO process requires

    efforts to be made to acquire by

    agreement. There is some evidence

    in decision letters that CPOs have

    on occasion been perceived as a

    short cut to site assembly, obviating

    the need to try to acquire by

    agreement. That is an approval

    taken at ones peril. A developer will

    also be called upon to demonstrate

    the likely viability of its s cheme. That

    requirement should come as no

    surprise and evidence of both

    deliverability and, where appropriate,

    viability should be advanced.

    Objectors opposing schemes should

    note that an objection has a

    proportionately greater prospect of

    success where a Public Inquiry is

    held and evidence is forensically

    tested. In Housing CPOs, objections

    putting forward evidence of

    deliverability of renovation or

    redevelopment by the existing owner

    have proved successful. In Planning

    CPOs, as cases below demonstrate,

    an Inquiry provides an opportunity to

    test an Acquiring Authoritys

    assumptions about viability.

    The reasons why CPOs can fail as

    evidenced by recent Secretary of

    State decisions are set out below

    under the following headings:

    Enabling power and/clarity of

    objectives

    Technical deficiencies

    Procedural issues/withdrawal of

    Order

    Housing CPOs evidential burden

    Planning CPO viability,

    deliverability and alternative

    schemes

    Acquisition by agreement

    statutory and policy requirements

    Orders not confirmed/withdrawn.

    4. Great Yarmouth Borough Council (Land at Hall Road, Hopton-on-Sea, Great Yarmouth, Norfolk) Compulsory Purchase Order 2009 (S125 Local Govt Act 1972 and

    S164 Public Health Act 1875. Decision 30 March 2010)

    It is essential at the outset to

    establish clearly the particular

    objectives of a case and therefore

    identify the most appropriate power

    under which to make a CPO. The

    approach of Great Yarmouth

    Borough Council and Hopton-on-

    Sea Parish Council ultimately was

    fatally unclear in respect of both

    (Great Yarmouth Borough Council

    (Land at Hall Road, Hopton-on-

    Sea, Great Yarmouth, Norfolk)

    Compulsory Purchase Order

    2009)4.

    The Order Land in Hopton-on-Sea

    on the Norfolk coast comprised 0.4

    hectares of woodland covered by a

    Tree Preservation Order. It was

    adjacent to the local church, bowling

    green, a single residence and post

    office. Planning applications for

    residential development of the site

    had previously been refused by the

    LPA and on appeal.

    The impetus for compulsory

    acquisition came from the Parish

    Councils desire to manage the site

    as a woodland walk/nature reserve.

    The Parish Council was also

    concerned about the areas untidy

    and ill-maintained appearance.

    There was an extensive history of

    negotiations between the Parish

    Council and landowner. Ultimately,

    no substantive progress was made

    so the Parish Council requested that

    the Borough Council make a CPO.

    Negotiations recommenced and an

    undertaking was given by the

    landowner to make reasonable

    endeavours to clear, tidy and make

    the land safe to the Parish Councils

    reasonable satisfaction within a

    specified period of a few months

    and thereafter maintain it to the

    Parish Councils satisfaction. The

    CPO was thereupon withdrawn. The

    deadline for works was subsequently

    extended by six months but by that

    time there was little evidence of

    progress so a second CPO was

    made. In the meantime the area was

    fenced off and some works

    undertaken by the landowner.

    Statutory power

    The Order was made pursuant to

    S125 of the Local Government Act

    1972 (LGA) and S164 of t he Public

    Health Act 1875 (PHA). S125 LGA

    provides that a District Council may

    in certain circumstances

    compulsorily acquire land on behalf

    of a Parish Council provided the land

    is for a purpose for which the Parish

    Council is authorised to acquire land.

    However, that does not include

    matters specified in S124(1)(b) LGA,

    namely the benefit, improvement or

    development of their area. S164

    provides that a local authority may

    purchase or take on lease lay outplant improve and maintain lands for

    the purpose of being used as public

    walks or pleasure grounds

    The Secretary of State accepted that

    the acquisition of the lands for use

    as a woodland walk/nature reserve

    fell within the ambit of S164 PHA

    and therefore S125 LGA applied but

    commented that the Councils desire

    to tidy up the site and improve its

    scruffy and neglected appearance

    and its use by undesirables fell

    within the exclusions in S124(1)(b)

    LGA and therefore were not matters

    which alone would form a proper

    basis for a CPO. Likewise, the value

    of the woodland in providing a

    setting for the church was not a

    matter of itself for which the Parish

    Council was entitled to seek a CPO.

    These may be additional benefits,

    as the Council put it, but since t hey

    fell outside the powers the Secretary

    of State gave them little weight.

    The Inspector also noted that the

    undertaking that had been accepted

    by the Parish Council did not provide

    for public access to the land but only

    for the land to be cleared, tidied and

    made safe. The Inspector

    accordingly concluded that

    improving the appearance and

    maintenance of the land might in fact

    be the overriding objective for the

    Parish Council. Laudable as that

    may be it was not a proper basis for

    a CPO under S124(1)(b). The

    Inspector therefore concluded that

    in considering whether the Order

    should be confirmed I have therefore

    had regard to the creation of a

    woodland walk/nature reserve and

    have given little weight to any allied

    benefits.

    There were additional planning and

    evidential objections to the CPO.

    Local Plan policy provided support

    for the creation of wildlife habitats.

    However, the supporting t ext to the

    policy stated that the Council would

    seek access arrangements to sites.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    14/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2524

    Technical deficiencies

    The landowner pointed out that no

    such access agreement had been

    sought. The Inspector noted that the

    landowner had not ruled out the

    potential for granting a lease and

    during the Inquiry a draft lease was

    offered albeit one that wasunacceptable to the Council.

    Also, the Council argued that there

    was a shortfall of 0.84 ha of informal

    recreation space/childrens play

    space and that the Order Lands

    would meet half of that shortfall.

    However, the Secretary of State was

    sceptical that the woodland would

    be suitable for a range of recreational

    uses and in any event such uses

    would conflict with the proposal as a

    nature reserve. Although there was

    relatively little accessible woodland

    on the coastal fringe, the Order land

    had no particular scientific or nature

    conservation interest and was in any

    event protected by policy from

    development and was unlikely to be

    lost as a wildlife area.

    The Secretary of State thereforeconcluded that a compelling case

    had not been made out and the

    purposes werent sufficient to justify

    interference with the landowners

    human rights and that despite there

    being no obvious impediments to

    the project, the use of compulsory

    purchase powers would not be

    proportionate.

    In this instance, the Borough

    Councils case suffered from lack of

    clarity as to precisely what it was

    that the Parish Council wished to

    achieve. Indeed there was arguably

    some confusion about the precise

    intended use and its benefits. Clearly

    there was a tension between nature

    reserve and childrens play space

    use, for example. This wassignificant because of the Secretary

    of States approach to give weight to

    the benefits that fall within S164

    PHA and not the ancillary or allied

    benefits.

    The land was suitable as a woodland

    walk/nature reserve, but was not of

    particular nature conservation

    interest. The Secretary of State was

    not convinced that land was of the

    right type to address the shortage of

    recreational space. Moreover a lease

    may well have been long enough to

    secure a significant proportion of any

    benefits and could be available. In

    addition no attempt had been made

    to secure an access agreement.

    It is hard not to have some sympathy

    in this instance for the Parish Council

    given that it had spent five years

    from negotiations first commencing

    to progressing the second CPO.

    However, if there is an alternative

    means of achieving the identified

    objectives short of the need for

    compulsory acquisition, then careful

    consideration should be given to that

    alternative. In this instance could a

    suitably framed access agreement

    have sufficed. In other cases, one

    may wish to consider whether

    outright acquisition is needed or

    whether an easement would be

    sufficient.

    The Secretary of State will refuse to

    confirm a CPO that is demonstrably

    technically flawed and not capable

    of modification or remedy. Guidance

    in Appendix V to Part I of the

    Memorandum to Circular 06/04 sets

    out the technical requirements. Inaddition the procedural

    requirements, for example, as set

    out in The Compulsory Purchase

    (Inquiries Procedure) Rules 2007 or

    The Compulsory Purchase of Land

    (Written Representations Procedure)

    (Ministers) Regulations 2004, must

    be followed. A combination of

    technical and procedural errors can

    be fatal to a CPO as demonstrated

    by two Planning CPOs made by

    Mansfield DC (Mansfield District

    Council (Brownhill Road) CPO

    2010andMansfield District

    Council (Bould Street) CPO 2010)5.

    The procedural error was that

    newspaper notices did not appear in

    two successive weeks. The second

    notice appeared two weeks after the

    first, thereby effectively shortening

    the objection period for those who

    saw the second notice.

    In addition, the Order Maps were

    contrary to the Circular in that: they

    were undated; they did not contain

    street names or house numbers or

    local landmarks; and boundaries

    were not clearly delineated and

    numbering hard to pick out.

    Furthermore, the Order Schedule did

    not include Table 2 and no signed

    certificates had been provided.

    There can be no surprise that the

    CPOs were rejected on technical

    grounds. Although the Secretary of

    State may permit some

    modifications to a CPO where it is

    possible to do so without causing

    prejudice to an objector, it isimportant to take care at the outset

    to follow both the statutory

    requirements and the Secretary of

    States requirements as to the form

    of an Order.

    Checking the draft Order

    The NPCU in Birmingham provides a

    valuable informal checking service

    for draft CPOs. This can be

    especially useful not just for complex

    Orders, but in allowing fresh eyes to

    scrutinise the CPO schedule and

    map. Acquiring Authorities are

    recommended to make use of the

    NPCU.

    The limitation on the scope for

    modifying an Order is well

    demonstrated by a Housing Act

    CPO made by the East Riding of

    Yorkshire Council (The East Riding

    of Yorkshire Council (11

    Lansdowne Road, Bridlington)

    Compulsory Purchase Order

    2009)6.

    The Councils Housing CPO case

    was well made out. The property

    was in disrepair and had partially

    collapsed. The Council had

    negotiated with the landowner over

    a prolonged period of time, had clear

    5. Mansfield District Council (Brownhill Road) CPO 2010 (S226(1)(a) TCPA 1990. Decision 17 February 2011)

    6. The East Riding of Yorkshire Council (11 Lansdowne Road, Bridlington) Compulsory Purchase Order 2009 (S17 Housing Act 1985. Decision date 22 September2010)

    proposals to bring it back into use

    and the owner had shown no

    commitment to renovation. It is clear

    from the decision letter that the

    Secretary of State would in all

    probability have confirmed the Order

    had it not been for a fatal flaw in theCPO.

    There were two notable errors:

    The CPO Map included part of an

    adjoining property in error.

    The CPO Map failed to include a

    rear single storey extension that

    was an integral part of the

    dwellinghouse to which the CPO

    related. It also omitted the rear

    yard to the property.

    Consequently, the description of

    the area of land in the Schedule

    was materially inaccurate.

    Modification of the CPO to remove

    the land included in error was

    possible and caused no prejudice.

    However, it was not possible to bring

    into the CPO land excluded in error.

    Although there was no overall

    ambiguity in the Councils intention

    that proposed modification was not

    consented to by t he objector. The

    Secretary of States position is that

    he may not, without the consent of

    all persons interested, modify a CPO

    by adding land not originally included

    in the CPO. That is, with the

    agreement of the Secretary of State

    one may modify a CPO to remove

    Enabling power and objectives(continued)

    It is hard not to have some sympathyin this instance for the Parish Council

    given that it had spent five years fromnegotiations first commencing toprogressing the second CPO. However,if there is an alternative means ofachieving the identified objectives shortof the need for compulsory acquisition,then careful consideration should begiven to that alternative.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    15/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2726

    Procedural issues/Withdrawal of Order

    land, but one cannot insert land not

    originally included in the CPO

    without the consent of all affected

    parties and acquiescence of the

    Secretary of State.

    The East Lindsey District Council

    (The Gatherums, Louth)

    Compulsory Purchase Order

    20127would also appear to have not

    been confirmed following a request

    for withdrawal because of technical

    7. East Lindsey District Council (The Gatherums, Louth) Compulsory Purchase Order 2012 (S226(1)(a) TCPA 1990. Decision date 16 October 2012)

    In cases where an Acquiring

    Authority wishes to withdraw a CPO

    because acquisition has been

    achieved by agreement, an

    application is made to the

    determining Secretary of State who

    determines that the CPO is notconfirmed. Details of those CPOs

    not confirmed/withdrawn in this

    way are set out later in this report.

    But what happens when an

    Acquiring Authority wishes to

    withdraw a CPO but there is an

    outstanding objector who opposes

    the withdrawal? This issue was

    addressed in a Planning CPO Order

    made by Kings Lynn and West

    Norfolk BC (Borough Council of

    Kings Lynn and West Norfolk

    (Waterfront Regeneration Area,

    Land at the Friars) Compulsory

    Purchase Order 2009).8The

    underlying scheme fell within a

    strategic transport route forming part

    of mixed-use development within a

    wider regeneration area. Kings Lynn

    BC sought deferral of a Public

    inquiry for six months on grounds

    that the economic downturn meant

    a review of its regeneration project

    was necessary. A statutory objectoropposed the deferral on a number of

    grounds; most particularly that his

    own development proposals would

    be prejudiced by delay. The

    Secretary of State refused to

    sanction deferral. The Council wrote

    to PINS stating that it wished to

    withdraw the CPO.

    8. Borough Council of Kings Lynn and West Norfolk (Waterfront Regeneration Area, Land at the Friars) Compulsory Purchase Order 2009 (S215 (1)(b) TCPA 1990.

    Decision 14 May 2010)

    Its stated reasons were: to enable a

    review of its Waterfront Regeneration

    Area; that an alternative route not

    involving the remaining objectors

    land had been found for the strategic

    transport link (and planning

    permission for this alternative routehaving been granted four days

    earlier); and to enable funding to be

    utilised by a deadline. It was stated

    that this request was without

    prejudice to making a second Order

    because the Councils underlying

    purpose had not changed. The

    Government Office for London (GOL)

    was minded to cancel the Inquiry

    and wrote to the Council stating that

    in the interests of fairness and

    natural justice where an Acquiring

    Authority indicated close to an

    Inquiry that it no longer wished to

    pursue the CPO then remaining

    objectors who have reasonably

    incurred costs in preparation for the

    inquiry should be able to seek an

    award of costs against the Acquiring

    Authority. GOL also stated that as

    you are aware however compulsory

    purchase order costs can only be

    awarded where an inquiry has taken

    place.

    Jurisdiction

    The Inquiry therefore proceeded.

    The Council called no evidence and

    instead relied upon its Statement of

    Case. There was extensive debate

    as to whether an Acquiring Authority

    could withdraw a CPO. There was

    broad agreement that there is no

    express power to do so. However, is

    there an implied power? The

    objector argued that the Council was

    functus officio i.e. it no longer had

    the power to act in respect of the

    CPO, the CPO baton having been

    passed to the Secretary of State to

    decide whether it could beconfirmed. It was also contended

    that, in this case, the Council had

    not in fact passed an appropriate

    resolution to withdraw the Order.

    The Council relied on the decision in

    Persimmon v North Hertfordshire

    (2001 1WLR 2393) in respect of the

    withdrawal of a Local Plan. It also

    argued that if the CPO was not

    considered to be withdrawn it would

    ask the Secretary of State to confirm

    the Order in respect of those plots t o

    which there were no objections.

    The Inspector noted that, although

    the Order fell not under the ambit of

    Circular 8/93, but Circular 03/2009,

    at Annex E paragraph E6 states:

    exceptionally, an Order is not

    confirmed for technical reasons or

    because the Acquiring Authority

    decided not to proceed with the

    compulsory purchase and asks for

    the Order to be treated as

    withdrawn. The Circular couldtherefore be taken to imply such a

    power but none is expressly

    identified. The Inspector concluded:

    The Order is to all practical intents

    and purposes withdrawn and it

    seems to me that to argue or

    conclude otherwise serves no

    purpose in the public interest. There

    is however no explicit provision in

    Technical deficiencies(continued)

    Although there was no overall ambiguity in the

    Councils intention that proposed modificationwas not consented to by the objector. TheSecretary of States position is that he maynot, without the consent of all personsinterested, modify a CPO by adding land notoriginally included in the CPO.

    reasons. The Secretary of States

    letter advises that the Council may

    wish to note that the National

    Planning Casework Unit provides

    informal advice on draft Compulsory

    Purchase Orders, should the

    authority decide to submit a

    subsequent Order.

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    16/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 2928

    Housing CPO evidential burden

    law for withdrawal of a CPO. It thus

    seems to me that the Order must

    still be considered to stand and that

    accordingly the proper course would

    be for the Order not to be

    confirmed.

    As regards confirming the plots inrespect of which no objections had

    been made, whilst there was a

    convenience factor in doing so, the

    Inspector expressly rejected that

    approach. The reason and

    justification for acquiring those small

    areas was the same as for the rest

    of the Order Land. Since the Council

    did not argue that some of the Order

    Land is needed and some is not and

    was not pursuing compulsory

    acquisition of the other plots in

    respect of which there were

    outstanding objections then its case

    for compulsory acquisition could not

    be sustained for the two small areas.

    Housing CPOs made by Islington

    LBCand the City of Westminster

    respectively9are examples of Orders

    not being confirmed but where the

    use of compulsory purchase

    arguably incentivised landowners to

    take action to address problems

    with the relevant property. These

    Orders illustrate a dynamic

    particularly relevant to Housing

    CPOs namely the response of the

    landowner. Planning CPOs are

    essentially prospective the

    Acquiring Authority is advancing a

    case for the future development,

    redevelopment or improvement of a

    site. It is usually problematic for an

    objector to counter those benefits or

    attack them head-on unless he has

    an alternative viable scheme of his

    own. In contrast, Housing CPOs

    expressly require assessment of the

    current condition and use of

    property. There is often therefore

    increased scope for an objector to

    take steps to address an acquiring

    authoritys concerns and at the same

    time counter the need for

    compulsory acquisition.

    Islington

    The Islington case featured pre-1919three storey brick buildings. The

    ground floor contained shops. There

    was residential accommodation

    above. The Councils case was that

    the nearby area had been

    regenerated by New Deal for

    Communities. The Order lands were

    empty, an eyesore, in disrepair and

    in need of complete renovation.

    There was also, it was argued, a

    demonstrable need in the area for

    housing. Extensive evidence of

    contact with the owner was

    advanced, especially the Councils

    frustration with the lack of progress.

    The Council therefore proposed to

    pass the property to a Registered

    Housing Provider (RP). It also

    contended that the Owners lacked

    the capacity to bring the property

    into use and that piecemeal

    acquisition of properties over many

    years together with poor stock

    management and maintenance had

    blighted neighbouring property. A

    Notice under Section 215 of the

    Town and Country Planning Act

    1990 had been served to require

    works to the front elevations. In

    short, the Councils case was that

    Owners were financially not in a

    position to remedy the situation and

    had taken no steps to demonstrate

    an intention to renovate.

    The Owners case was that they

    were intending to carry out works to

    bring the properties back into mixed

    residential and commercial use.

    Planning Permission was now in

    place. The Order was therefore

    premature. A detailed explanation of

    personal problems, share ownership

    issues and other issues was given.

    Factual matters were disputed,

    especially that the Council had been

    wrong that certain units were empty.

    Some works had been undertaken

    to comply with the S215 notice. The

    Council had refused to accept an

    undertaking not to make a CPO if

    work began within 20 weeks. There

    would be delays with redevelopment

    if the Order were confirmed because

    the RP would need new consents. A

    week before the Public Inquiry, the

    objectors met with local builders and

    agreed implementation of the

    planning permission, albeit there

    were no written terms.

    The Inspector concluded that the

    poor state of building and housing

    need was established. Compulsorypurchase is the last resort. There

    were reasons for the delay: litigation

    and personal circumstances were

    mitigating factors. Planning

    permissions for extensions and

    refurbishment now existed. The

    Owners had expressed the intention

    to implement the permissions and

    had made moves to do so even

    though these might not have

    advanced to a stage that provides

    the Council with the comfort as to a

    prompt and satisfactory outcome.

    Dialogue with the Council had been

    maintained and the S215 notice

    complied with in part.

    Objectors commitment

    The Inspector noted that despite

    the Councils contention to the

    contrary I consider that [the

    objectors have] shown a degree

    of steadfast commitment to moving

    forward with project of redeveloping

    the properties [and] expressed [a]

    preparedness to provide an

    undertaking to the Council to ensure

    development is carried out to an

    agreed timetable should the Order

    not be confirmed. There is also

    evidence that the presence or threat

    of a CPO may have deterred

    potential financial backing for

    developers and this has itself

    frustrated action.

    Procedural issues/Withdrawal of Order(continued)

    Where acquisition by agreement has

    been reached and an Acquiring

    Authority needs to withdraw an

    Order, i.e. cease the compulsory

    CPO process that should not be

    problematical. That is an

    administrative process and theSecretary of State is amenable to

    Orders being withdrawn de facto,

    albeit that de jure they may be noted

    as being not confirmed. However,

    if an Order is proposed to be

    withdrawn for any other reason, then

    care is required and an Acquiring

    Authority must be alive to the costs

    implications. It is hard to see why in

    principle objectors reasonable and

    legitimate costs should not be

    recoverable in some circumstances

    where a contested Order is sought

    to be withdrawn, especially close

    to the date of an Inquiry.

    9. The London Borough of Islington (141-157 Whitecross Street, London EC1Y 8JL) Compulsory Purchase Order 2009. (S17(1)(b) Housing Act 1985.

    Decision date 6 May 2010) and City of Westminster (39 Kensington Gardens Square W2) Compulsory Purchase Order 2010)

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    17/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 3130

    In contrast, the Inspector concluded

    that the Council had no formal

    agreements in place with any

    specified RSL or developer and that

    factually the Council was wrong in its

    belief that properties were not

    occupied.The Secretary of States conclusion

    was that this was a finely balanced

    case and that from the evidence

    presented there is likelihood that if

    the properties remain with the

    owners there is a reasonable

    prospect of their refurbishment/

    redevelopment and the residential

    elements being brought back into

    active use within a relatively short

    space of time. This is likely to be

    speedier than if the Order was to be

    confirmed and the properties passed

    on by the Council to an RSL. Given

    those conclusions, a compelling

    case for compulsory acquisition was

    not clearly demonstrated.

    Westminster

    The Westminster case concerned a

    Listed Grade II mid terraced property

    in an established residential area in

    central London. It comprised six

    floors of accommodation including a

    half basement that had been empty

    for five years. There had been some

    squatting and the Owner had

    obtained a possession Order. The

    building was in a deteriorating

    condition. Statutory notices had

    been served but not complied with.

    Shortly prior to the CPO being

    made, dangerous structure notices

    and a S215 notice were served.

    The Councils case was that it was

    an eyesore and a blight on the

    neighbourhood. It was proposed

    that, if acquired, the Council would

    dispose of it to Westminster

    Community Homes Ltd which would

    apply for planning permission to

    convert it into affordable homes.

    The owner lived overseas. Evidence

    was produced of that there hadpreviously been delays but a new

    professional team had been

    appointed and that since then more

    active steps had been taken. Of

    crucial importance in the case was

    the contention that no party was

    likely to be in a position to bring the

    building into use until planning issues

    had been resolved. There was

    disagreement between the owners

    advisers and the Council as to

    whether permission was required for

    uses including self-contained flats.

    A Certificate of Lawfulness of

    existing use or development had

    been applied for but refused. The

    Owner applied for listed building

    consent which was granted.

    However, planning permission was

    refused on grounds that 9 residential

    units failed to provide an appropriate

    mix of unit sizes including family

    units. A revised scheme was

    however acknowledged to be likelyto have officer support. The Owner

    had already spent 60,000 on the

    proposals and was not prepared to

    give an undertaking sought by the

    Council wherein the Council would

    not implement a confirmed CPO if

    certain conditions were met.

    Intention and timescale

    The Secretary of States conclusions

    were that there was no issue

    between parties as to the physical

    state of the building. The Owners

    actions constituted evidence of

    intention to carry out works, the

    delays were explicable and the

    monies spent demonstrated

    commitment. There was therefore a

    strong financial incentive for the

    Owner to pursue refurbishment andconversion. Moreover, it was not

    clear that the Councils preferred

    social housing developer was in any

    better financial position to develop

    than the Owner. Works undertaken

    meant that the property was no

    longer a blight or eyesore.

    The Secretary of State concluded

    that the Owners recent actions

    provide strong evidence that the

    property will be brought back into

    residential use within a reasonable

    timeframe. A CPO was t herefore

    not required to achieve that aim, nor

    was there an overriding public

    interest having regard to Art 1 First

    Protocol ECHR rights.

    This was a finely balanced case in

    which the Secretary of State was

    faced with the need to determine

    what weight should be given to the

    presently stated and evidenced

    intentions of a landowner as against

    previously an undeniably indifferent

    delivery performance. In such

    circumstances it is to be anticipated

    and is appropriate that the benefit

    of the doubt should be given to an

    owner where it can be demonstrated

    that there is a reasonable prospect

    of a satisfactory outcome without

    resort to compulsion.

    Bradford

    A Housing CPO made by Bradford

    City Council10sought compulsory

    acquisition of a three storey semi-

    detached dwelling within a

    Conservation Area. The Order Lands

    contained trees subject to a Tree

    Preservation Order.

    The Councils case was that the

    property was in a dilapidatedcondition and had been substantially

    unoccupied for ten years. Various

    complaints about anti-social

    behaviour and nuisance were

    associated with the property. It was

    a blight on the Conservation Area.

    Notwithstanding contact between

    the Council and the Owner, steps

    had not been taken by the Owner to

    engage professional assistance to

    renovate the property.

    The Owner explained her personal

    circumstances including family, work

    and health issues that had adversely

    affected the upkeep of the property.

    Details of work that had been

    undertaken were set out. Evidence

    was also submitted querying why

    the Councils use of compulsory

    purchase powers was directed at

    the Order property rather than many

    other properties. It was argued thatthe Council had paid little heed to

    the personal circumstances and had

    thereby compromised the owners

    human rights.

    The Inspector accepted that the

    dwelling was in poor condition and

    had an adverse effect on its

    environs. It was not unreasonable for

    the Owner to put renovation on hold

    given her particular health and

    personal circumstances. Given those

    circumstances, the Inspector

    considered that the timing of the

    Councils compulsory acquisition

    was insensitive and premature. On

    balance, the case was less than

    compelling, especially given that the

    Council was not pursuing the

    compulsory acquisition of many

    other vacant properties in the area.

    The Inspector concluded that

    bringing one dwelling back into use,quicker than the Owner might be

    able to manage, was unlikely to

    significantly improve the housing

    stock of the District and would

    interfere unnecessarily with the

    Owners human rights.

    Housing CPO evidential burden (continued)

    The Secretary of State concluded that the

    Owners recent actions provide strongevidence that the property will be broughtback into residential use within a reasonabletimeframe. A CPO was therefore notrequired to achieve that aim, nor was therean overriding public interest having regard toArt 1 First Protocol ECHR rights.

    10. City of Bradford Metropolitan District Council (7 Parkfield Road, Manningham, Bradford, West Yorkshire, BD8 7AB) Compulsory Purchase Order 2013 (S17 Housing

    Act 1985. Decision date 4 January 2013)

  • 7/26/2019 Cpo Report 2015 Main Report May2015

    18/25

    Bond Dickinson LLP Compulsory Purchase Orders 2003 2014 3332

    Deliverability/Financial Viability/Alternative Scheme

    Banbury

    A further Housing CPO case in

    which the balance between the

    aspirations of the Acquiring Authority

    and developer was in issue was the

    Cherwell District Council CPO

    under S17 of the Housing Act1985 in respect of The Crown

    House site, Banbury11. The

    purpose of the CPO was to provide

    affordable housing and to regenerate

    a long term vacant site in the centre

    of Banbury. The landowner objected

    on the basis that delays in bringing

    the site back into use had not been

    of the objectors making and that

    planning permission had now been

    granted and that the proposals for

    bringing the site into beneficial use

    were now viable.

    Competing proposals

    Initially an issue was raised as to

    whether the CPO had been made

    under appropriate powers but that

    was not pursued further.

    The Acquiring Authority promoted a

    scheme for conversion of the

    buildings on the site to 20 one bed

    and 20 two bed residential units and

    a 90 m2

    ground floor retail space.The objector was Slighte Limited.

    It proposed two potential schemes.

    (i) 73 bedroom hotel, a restaurant

    and 5 duplex apartments, together

    with a change of use of part of the

    existing office building to residential

    use, making a total of 15 affordable

    units; and (ii) conversion of Crown

    House to 33 apartments.

    The purpose of a Planning CPO

    made by Manchester City Council

    (City of Manchester (Former

    London Road Fire Station)

    Compulsory Purchase Order

    2010)12was to safeguard and

    enhance the regeneration of the

    Piccadilly area and safeguarding the

    fabric of a Grade II listed building,

    namely the former London Road Fire

    Station (LRFS). The Site also

    included the Coroners Court, Police

    Station and Bank.

    The Inspector noted that the CPO

    [was] unusual in that a scheme for

    the redevelopment of the LRFS as a

    regeneration driven, conservation-

    conscious, 4* hotel, as favoured by

    the Council, has been put forward

    by the Objector (Britannia Centre

    Ltd). In that sense, there were two

    competing schemes, one supported

    by the acquiring authority and that

    promoted by the objector, Britannia.

    The Council contended that

    Britannia had failed to take

    reasonable and adequate steps for

    properly preserving the property, had

    failed to bring forward proposals for

    redevelopment in an acceptable

    manner, and had not implementedplanning permission previously

    granted.

    Britannia countered that its

    proposals would secure

    development in a manner consistent

    with the Councils regeneration

    objectives for the Piccadilly area and

    that the Council had disregarded

    extant grants of planning permission

    and LBC for its redevelopment as a

    4* hotel, English Heritage support for

    proposals, Britannias intention to

    implement, and the timescales

    required for redevelopment by a 3rd

    party if the Council acquired the site.

    Two key issues were identified:

    Was there certainty, or at leastnear certainty, that Britannia

    would complete the conversion

    by 2014?

    If not, was there a compelling

    case in the public interest for the

    Council to be in a position,

    through a confirmed CPO, to

    acquire the LRFS?

    Britannias actions were subject to

    some criticism. There was a lengthy

    back-story of alleged delays. An

    Implementation Agreement had not

    been signed and there was tardiness

    in implementing planning permission.

    The Inspector was critical of the

    basis upon which Britannias expert

    witnesses were appointed and

    instructed together with those

    witnesses unquestioning

    acceptance of what they had been

    told by Britannia. Britannias

    company witness also apparently

    had little personal experience of the

    matter and no knowledge ofcompany resolutions or financial

    requirements as to acceptable rates

    of return. The Inspector concluded

    that unsurprisingly, against this

    background, the Council has

    concluded that Britannia cannot be

    relied upon. At the same time, the

    Inspector acknowledged the

    possibility needs to be considered

    that, whatever has gone before,

    Britannia is now committed to

    12. City of Manchester (former London Road Fire Station) Compulsory Purchase Order 2010. (S226(1)(a) TCPA 1990. Decision 28 November 2011)

    redevelop in accordance with the

    programme....

    As regards the second issue, it was

    argued by Britannia that a lack of

    certainty around its proposal was

    insufficient on its own to justify the

    CPO. It was necessary for theCouncil to show that redevelopment,

    in the near future, was necessary

    and that there were demonstrable

    regeneration and conservation/

    building fabric benefits.

    Timescale

    The Secretary of State concluded

    that although the purposes of the

    CPO would accord with the adopted

    planning framework for the area and

    contribute to achievement of the

    promotion or improvement of the

    economic, social and environmental

    wellbeing of the area, the financial

    viability of the scheme the CPO was

    intended to bring forward had not

    been demonstrated and that, in

    addition, the case for urgency had

    not been made out. Moreover, and

    crucially, redevelopment of the LRFS

    with attendant regeneration benefits,

    would be more likely to come

    forward under Britannias auspices

    than the Councils.

    In addition, the Secretary of State

    agreed with the Inspectors

    conclusion that the fabric of the

    building could be safeguarded by

    measures that stopped short of

    expropriation and, on that basis, the

    purposes for which the acquiring

    authority is proposing to acquire the

    land could clearly be achieved by

    other means.

    Housing CPO evidential burden (continued)

    The Inspector concluded that

    although the Acquiring Authoritys

    proposals accorded with the Local

    Development Framework,

    particularly in terms of meeting the

    affordable housing needs of the

    area, Slightes hotel led scheme

    would accord marginally more

    closely with development plan policy

    by providing both housing and Town

    Centre suitable development of a

    restaurant and hotel.

    Notwithstanding that 40 affordable

    units would be a meaningful number

    it comprised less than 1% of the

    affordable units anticipated to be

    delivered through the Plan system.

    The Inspector therefore concluded

    that the need for affordable housing,

    whilst important, would not be

    overwhelming.

    In terms of funding and viability of

    the Acquiring Authoritys scheme

    there was little agreement between

    the parties as to the costs involved

    but the Inspector concluded that the

    Acquiring Authority had a budget in

    excess of 7 million and at a site

    cost of 950,000 the combined

    costs of site purchase and

    construction would be comfortablywithin the Acquiring Authoritys

    budget.

    Track record v presentintentions

    The Inspectors analysis of the

    competing interests also included

    assessment in detail of what

    situation would prevail if the CPO

    were n