CPCB Guidelines for TPP

Embed Size (px)

Citation preview

  • 7/28/2019 CPCB Guidelines for TPP

    1/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.1

    SECTION-14

    ENVIRONMENTAL ASPECTS IN POWER SECTOR

    14.1. INTRODUCTIONThe implementation of power projects requires clearance from Ministry

    of Environment and Forests from the following aspects :

    a) Environmental aspectsb) Forest (Conservation) Act 1980 angle

    The above clearances are communicated separately and a Project

    requiring both clearance is deemed to be cleared by MOEF only after the

    clearance from both aspects is given.

    14.2. ENVIRONMENT CLEARANCEThe Environment Impact Assessment (EIA) Notification `1994, inter-alia,

    provides that expansion or modernisation or a new power project shall not

    be undertaken in the country unless accorded environment clearance by

    the Central Government in the Ministry of Environment and Forest

    (MOEF).

    This however, does not apply to projects with investment costs less than

    50 crores.

    The above EIA Notification, sets out procedure for clearance of projects.

    For site specific projects, such as hydro electric and pit head thermal

    power stations, the site clearance is to be obtained first from MOEF forinitiation of any surveys and investigations. The MOEF would convey a

    decision regarding suitability of otherwise of the site within 30 days.

    Thereafter, for such site specific projects are to be submitted by the

    proponents to MOEF for clearance. The reports shall be evaluated and

    assessed by the Impact Assessment Agency which may consult a

    Committee of Experts. If required, comments of the public may be

    solicited and public hearing arranged. The Notification stipulates that the

    assessment shall be completed within a period of ninety days from the

    receipt of the requisite documents and data hearing, where required, and

    decision conveyed within thirty days thereafter. The clearance granted is

    valid for a period of five years for commencement of the

    construction/operation.

  • 7/28/2019 CPCB Guidelines for TPP

    2/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.2

    14.3.0 ENVIRONMENTAL APPRAISAL OF THERMAL POWER

    PROJECTS

    The proponents of thermal power projects including coal/lignite fired

    thermal, gas, combined cycle gas based and co-generation projects submit

    20 copies of the application to MOEF in the specified Performa along

    with the Environmental Impact Report/Environment Management Plan.

    The impact Assessment Agency examines the reports and calls for

    additional data, documents. on receipt of complete information, the

    projects are placed before the committee of Experts for thermal powerstations. If needed, visits to recommendations of the Committee of

    Experts, MOEF further process the projects for clearance/rejection of the

    proposals. The cases rejected for non furnishing of complete information

    may be reopened on the receipt of complete information.

    The expert committee Constituted by MOEF and represented by Chief

    Engineer (C&E) CEA, had considered 31 schemes with 17498.55 MW

    installed capacity during 1998-99. Out of these, 24 schemes with

    10786.55 MW installed capacity had been given clearance fromenvironmental angle.

    14.4.0 ENVIRONMENT CONCERNS OF THERMAL POWER

    STATIONS

    The products of combustion in thermal power plants using coal/lignite

    LDO/Naphtha are gaseous emissions containing carbon dioxide, oxides of

    sulfur and Nitrogen as also solid particulate matter (ash) where

    coal/lignite is used. Beside these, the waste water from the process

    contains pollutants.

    14.4.1 AIR POLLUTION

    Initially, perceptions of objectionable effects of air pollutants were

    limited to those easily detected like odour and smoke stacks. Later, it was

    the concern over long term/chronic effects that led to the identification of

    six criteria pollutants. These six criteria pollutants are sulfur DI-oxide

    (S02), Carbon Mono-oxide (CO), Nitrogen oxide (NO2), Dzone (D#),

    suspended particulate and non methane hydrocarbons (NMHC) Ozonereferred to as volatile organic compounds (VDC). There is substantial

    evidence linking them to health effects at high concentrations. Three of

  • 7/28/2019 CPCB Guidelines for TPP

    3/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.3

    whom namely O3,SO2 and NO2 are also known phytotoxicants (toxic tovegetation). In the later part Lead (Pb) was added to that list.

    Green House Gases which are responsible for temprature enhancement

    cause global warming. These Green House Gases are CO2. (Carbon

    dioxide), CH4 (Methane), N20 (Nitous Oxide) & CO (Carbon Monoxide)

    14.4.1.1. OXIDES OF NITROGEN (NOX )

    All combustion processes are sources of NOx at the high temperature

    generated in the combustion process. Formation of NOx may be due tothermal NOx which is the result of oxidation of nitrogen in the air and

    due to fuel NOX which is due to nitrogen present in the fuel. In general,

    higher the combustion temperature the higher NOx is produced.

    14.4.1.2 OXIDES OF SULPHUR

    The combustion of sulfur containing fossil fuels, especially coal is the

    primary source of SOX. About 97 to 99% of SOX emitted from

    combustion sources is in the form of sulfur dioxide which is a criteriapollutant, the reminder is mostly SO3, which in the presence of

    atmosphere water is transformed into Sulfuric Acid at higher

    concentrations, produce deleterious effects on the respiratory system.

    14.4.1.3. PARTICULATE MATTER

    The terms particulate matter, particulate, particles are used

    interchangeably and all refer to finely divided solids and liquids dispersed

    in the air.

    14.4.2 WATER POLLUTION

    Water pollution refers to any change in natural waters that may impair

    further use of the water, caused by the introduction of organic or

    inorganic substances or a change in temperature of the water.

    In thermal power stations the source of water is either river, lake, pond or

    sea where from water is usually taken. There is possibility of water being

    contaminated from the source itself. Further contamination or pollutioncould be added by the pollutants of thermal power plant waste as

    inorganic or organic compounds.

  • 7/28/2019 CPCB Guidelines for TPP

    4/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.4

    14.4.3 LAND DEGRADATION

    The thermal power stations are generally located on the non-forest land

    and do not involve much Resettlement and Rehabilitation problems.

    However it`s effects due to stack emission etc, on flora and fauna, wild

    life sanctuaries and human life etc. have to be studied for any adverse

    effects. One of the serious effects of thermal power stations land

    requirement for ash disposal and hazardous elements percolation to

    ground water through ash disposal in ash ponds. Due to enormous

    quantity of ash content in Indian coal, approximately 1 Acre per MW ofinstalled thermal capacity is required for ash disposal.

    14.4.4 NOISE POLLUTION

    Some areas inside the plant will have noisy equipments such as crushers,

    belt conveyors, fans, pumps, milling plant, compressors, boiler, turbine

    etc. Various measures taken to reduce the noise generation and exposure

    of workers to high noise levels in the plant area will generally include :

    i) Silencers of fans, compressors, steam safety valves etc.

    ii) Using noise absorbent materials.

    iii) Providing noise barriers for various areas.

    iv) Noise proof control rooms.

    v) Provision of green belt around the plat will further reduce noise

    levels.

    14.5.0 REGULATORY MEASURES

    14.5.1 AIR (PREVENTION & CONTROL OF POLLUTION) ACT, 1981.

    In India, 1st Air (Prevention & Control of Pollution) Act was enacted in

    1981 with amendments in 1987 for prevention, control and abatement of

    air pollution and it came into force with effect from May 91. The act

    provides for Central as well as State Boards with such powers and

    functions as necessary to provide and control the quality of Air. National

    ambient air quality standards by Central Pollution Control Board have

    been issued vide Gazette Notification of April 94. For wider dispersal of

    SO2, stack height of different capacity units have been stipulated. Forunits less than 500 MW the stack height has been stipulated as 220 meters

    whereas 500 MW units it is 275 meters.

  • 7/28/2019 CPCB Guidelines for TPP

    5/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.5

    14.5.2 ENVIRONMENT (PROTECTION) ACT 1986

    Environment (Protection) Act 1986 came into force w.e.f. 19.11.86 and

    provides for protection, improvement of environment and for matters

    connected therewith. It empowers the Central Govt. to take all such

    measures as deemed necessary for protecting and meeting quality of

    environment and preventing, controlling and abating environmental

    pollution. Standards for liquid effluents have been issued under PEA

    Notification, dated 19th

    November, 1986

    1986 Environment Protection Act has much sharper teeth and provides

    for stringent punishment for any violation of Act. As per Sec. 15 of the

    Act, whosoever fails to comply or contravenes any of the provisions of

    this Act, may be punished with imprisonment which may extend unto five

    years or with fine extending unto Rs. one lake or both. In case the failure

    continues for more than one year, the imprisonment may be extended to

    seven years.

    14..5.3 EMISSION/EFFLUENTS STANDARDS

    The standards for emissions/effluent have been notified by the

    CPCB/MOEF as under :

    14.5.3.1 SUSPENDED PARTICULATE MATTER (SPUME)

    The bulk of the ash produced from the combustion of coal / lights in the

    thermal power station and carried by the flue gases is trapped by the

    Espies or bag filters and only a small quantity escapes through stacks.

    The Espies of such designs and efficiency are provided that limits the

    SPUME in the stack emissions below the prescribed norms. The

    standards for SPUME levels as notified by MEd are given at Annex

    14.1

  • 7/28/2019 CPCB Guidelines for TPP

    6/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.6

    14.5.3.2 SULPHUR DIOXIDE EMISSIONS

    The non-cooking coal available in the country earmarked for power

    generation generally contains low level of sulphur unto 0.50% except for

    the coal available in the North Eastern region of the country. There are

    no prescribed sulphur dioxide is sought to be achieved by prescribing

    minimum sac k height limits for power stations which are given at Annex

    14.2. The Indian Air quality Standards prescribed by CPCB stipulates

    the limits of SPUME, SOx, NOx, Respriable particulate matter (RPM)

    CO & Pb in the ambient air. These standards are given at Annex 14.3

    Even using high sulphur coal, the sulphur dioxide emission can be

    reduced in the boilers using fluidised bed combustion technology. The

    sulphur dioxide produced in the combustion is mixed in the boiler with

    the lime fed alongwith the coal.

    14.5.3.3 NITROGEN OXIDE EMISSIONS

    The formation of Nitrogen oxide depends on the temperature and

    residence time of gases in the combustion chamber at that temperature.The formation of Nitrogen oxide can be reduced by providing low

    nitrogen oxide burners. No norms for the nitrogen oxide emission at

    stack have been notified by MOEF for coal/lignite fired thermal power

    stations.

    The levels of Nitrogen dioxide in the ambient air are prescribed by the

    AAQ standards which would limit the concentration of nitrogen oxide

    producing industries in an area.

    145.3.4 EFFLUENT DISCHARGE

    The process of power generation produces liquid effluents. The standards

    for liquid effluents from power stations have been prescribed in the EPA

    Notification dated 19th

    Nov. 1986 which are reproduced at Annex 14.4.

  • 7/28/2019 CPCB Guidelines for TPP

    7/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.7

    14.6.0 OTHER ISSUES

    14.6.1 COAL WASHING/BENEFICIATION.

    Number of studies have been conducted in the past to quantify the

    economics of using beneficiated coal in Indian power stations. These

    studies have indicated in quantitative terms the benefits of using washed

    coal both in terms of O&M as well as capital cost of the project. Vide

    MOEF Notification dated 19th

    September, 1997, (Annexure vi) certain

    categories of thermal plants are required to use washed coal containingash not more than 34 % by June 2001. These plants include the thermal

    plants located beyond one thousand Km. from pit heads and thermal

    plants located in urban areas or sensitive areas. Subsequently a

    committee was formed under the chairmanship of Member (Thermal),

    CEA to examine the ways and means of implementation MOEF

    Notification vide MOP Office Order No. dated. The committee was

    submitted its report in February 2000. Subsequently MOP has set up two

    more committee for implementing the recommendations of the main

    committee.

    14.6.2 FLY ASH UTILISATION

    The Coal/Lignite fired thermal power stations produce enormous

    quantities of ash. The ash has traditionally been disposed off in the ash

    ponds which has the potential of polluting the surface and ground water

    unless adequate care is taken. In order to check the percolation of ash

    effluents to the ground water, ash pond lining is being provided wherever

    necessary. The fly ash collected in the dry form, could however, be

    beneficially used for brick making and cement manufacturing. Incentives

    have been issued by the ministry of Power letter of 27th

    May 1996.

    Which are reproduced at Annexure 14.5. Inspite of all out efforts only 5

    % of ash is being utilised for gainful purpose at present. The notification

    dated 14-9-99 issued by MOEF in respect of Fly ash is reproduced at

    Annexure 14.6.

    14.6.3 FLUE GAS DESULPHRISATION (FGD) PLANT

    The MOEF insists on making space provision for FGD Plant in thedesigns of thermal power units of 500 MW and above capacity as also at

    stations with capacity of 1500 to 2000 MW to facilitate their addition at a

  • 7/28/2019 CPCB Guidelines for TPP

    8/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.8

    later date in case of the need for such plant is established. In case ofsensitive areas the installation of FGD is insisted upon even for stations

    with smaller installation.

    14.6.4 MONITORING OF ENVIRONMENTAL STATUS OF THERMAL

    POWER STATIONS IN INDIA

    CEA has also been actively engaged in the monitoring of environmental

    status of thermal power stations in the country. Monthly environmental

    status reports in respect of Stack emission, AAQ and effluent discharges

    are received from the thermal power stations, analysed and remedialmeasures suggested where ever required. Some of thermal units being

    operated do not have requisite infrastructure for environmental

    monitoring. Where-ever the units are not meeting statutory

    environmental requirements, are unable to install/replace existing ESP`s

    etc. due to paucity of funds. Though provisions exist in the law for

    closing down of the thermal power stations for not meeting

    environmental standards, we can hardly afford to close any unit in the

    power starved situation. Though, at present emphasis is laid on meeting

    particulate matter from stack emission, even for that regularly data is notbeing received from some of thermal power stations.

  • 7/28/2019 CPCB Guidelines for TPP

    9/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.9

    Annexure 14.1

    THERMAL POWER PLANTS : EMISSION STANDARDS

    NOTIFICATION

    MOEF vide Notification of 19th

    May 1993 issued as amendment rules to

    environment (Protection) Act 1986. The particulate matter emission limits forthermal power stations are as follows :-

    (i) Generation capacity 62.5 MW or more - 150 mg/Nm3

    (ii) Generation capacity less than 62.5 MW and plant

    Commissioned prior to 1.1.82 - 350 mg/Nm3

    (iii) Units located in protected area irrespective of

    generation capacity. - 150 mg/Nm3

    Annexure 14.2

    THERMAL POWER PLANTS : STACK HEIGHT/LIMITS

    Generation Capacity Stack Height (Metres)

    500 MW and above 275

    200 MW/210 MW and above to

    less than 500 MW

    Less than 200 MW/210 MW

    220

    H=14 (Q) 0.3

    where Q is emission rate of SO2,

    in Kg/h, and H is Stack height in

    metres

    Source : EPA Notification

    (G.S.R. 742 (E), dt. 30th Aug, 1990.

  • 7/28/2019 CPCB Guidelines for TPP

    10/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.10

    Annexure-14.3ENVIROMENT & FORESTS

    CENTRAL POLLUTION BOARD

    NATIONAL AMBIENT AIR QUALITY STANDARDS, NOTFN. 11.4.94

    S.O. 384(E) - The central pollution Control Board in exercise of its

    power conferred under section 16 (2) (n) of the Air (Prevention and Control of

    pollution) Act, 1981 (14 of 1981) hereby notify the National Ambient Air

    Quality standards with immediate effect.

    As per CPCB notification dt. 11.4.94,A.A.Q standard has been given

    below in brackets.SCHEDULE I

    Concentration in Ambient Air

    Pollutant Time

    weighted

    average

    Indl.

    Area

    (ug/m3)

    Res. Rural

    Other

    areas

    (ug/m3)

    Sensitive

    Area

    (ug/m3)

    Method of

    measure

    Sulphur

    Dioxide(SO2)

    * Annual

    average

    ** 24 hours

    80

    120

    60

    80

    15

    30

    1. Improve

    West &Gacke

    method

    2. Ultraviolet

    flourescence

    Oxides of

    Nitrogen

    * Annual

    Average

    ** 24 hour

    80

    120

    60

    80

    15

    30

    1. Jacob and

    Hochheiser

    modified (Na

    Arsenite

    2. Gas Phase

    Chemilumin

    scene

    Suspended

    Particulate

    Matter

    (SPM)

    * Annual

    Average

    ** 24 hour

    360

    500

    140

    200

    70

    100

    High Volume

    sampling, (Avg.

    flow rate not less

    than 1.1m3/min

    Respirable

    particulatematter (size

    less than 10

    Annual

    Average

    ** 24 hours

    120

    150

    60

    100

    50

    75

  • 7/28/2019 CPCB Guidelines for TPP

    11/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.11

    Concentration in Ambient AirPollutant Time

    weighted

    average

    Indl.

    Area

    (ug/m3)

    Res. Rural

    Other

    areas

    (ug/m3)

    Sensitive

    Area

    (ug/m3)

    Method of

    measure

    um)(RPM)

    Lead (Pb) Annual

    Average

    ** 24 hours

    1.0

    1.5

    0.75

    1.0

    0.50

    0.75

    AAS method

    after sampling.

    Using ERM

    2000 of equiv.

    Filter paper.

    Carbon

    monooxide

    (CO)

    ** 8 hour

    mg/m3

    1 hour

    mg/m3

    5.0

    10.0

    2.0

    4.0

    1.0

    2.0

    Non dispersive

    infrared

    spectroscopy

    * Annual Arithmetic Mean of minimum 104 measurements in a year taken

    twice a week 24 hours at uniform intervals.

    ** 24 hours/8 hours values should be met 98% of the time in a year. However,

    2% of time, it may exceed but not on two consecutive days.

  • 7/28/2019 CPCB Guidelines for TPP

    12/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.12

    ANNEXURE 14.4

    THERMAL POWER PLANT : STANDARDS FOR LIQUID EFFLUENT

    SOURCE

    PARAMETERS STANDARDS MAX.

    LIMITING

    CONCENTRATION mg/1

    (EXECPT FOR pH &

    TEMP.)

    Condenser Cooling Water

    (once through cooling

    system)

    PH

    Temperature

    6.5 to 8.5

    Not more than 7deg. C

    higher than the intake

    Free available

    chlorine

    0.5

    Boiler Blowdown Suspended

    Soilds

    Oil & GreaseCopper (Total)

    Iron (Total)

    100

    201.0

    1.0

    Cooling Tower Blowdown Free available

    Chlorine

    Zinc

    Chromium

    (Total)

    Phosphate

    0.5

    1.0

    0.2

    5.0

    Other corrosion Limit to be inhibiting material established on case by case basis

    by Central Board in case of Union Territories and state Boards in case of states.

    Ash Pond Effluent PH

    Suspended

    Solids

    Oil & Greases

    6.5 to 8.5

    100

    20

    Source EPA Notification

    (S.O., 844 (E), dt. 19.11.86)

    as amended by ---------------notification no.--------------

    dt.----

  • 7/28/2019 CPCB Guidelines for TPP

    13/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.13

    ANNEXURE 14.5

    COPY OF COMPREHENSIVE GUIDELINES FOR FLY ASH

    UTILISATION AND DISPOSAL ISSUED BY SECRETARY, MOP

    VIDE DO NO.11/16/93-RO(K)/E.II DATED 27.5.1996COMPREHENSIVE GUIDELINES FOR FLY ASH UTILISATION AND

    DISPOSAL

    (i) Dry fly ash should be supplied by the power stations, free of cost, to the

    entrepreneurs for a period of 10 years from the day a unit goes into fly

    ash based production. The terms of the supply of ash after the initialperiod of 10 years, should be settled annually by the Power Station

    Authorities and the concerned entrepreneurs; in case of disagreement, the

    matter could be decided by CEA or Building Materials and Technology

    Promotion Council (BMTC) for which a suitable provision should be

    incorporated in the contracts.

    (ii) Where ever Power Stations do not have dry fly ash collection facilities,

    they may be required to set up this facility. All new power stations

    should provide arrangements for collection and supply of dry fly ash.

    This would be ensured by CEA while appraising projects for techno-economic clearance. If any of the State Electricity Boards (SEBs) dry

    ash collection, this would considered by the Ministry of Power as a part

    of R&D Scheme.

    (iii) All proposals formulated and sponsored by the concerned

    Boards/Corporations and Utilities for setting up of the Thermal Power

    Plants should, in future, invariably incorporate specific provisions for

    promoting the maximum utilisation of fly ash generated by the plants.

    Central Electricity Authority would examine such proposals for techno-

    economic clearance as are found to comply with these requirements.

    (iv) The transportation of fly ash from thermal Power Plant should be the

    responsibility of entrepreneurs. No subsidy for transport of fly ash or its

    end products would be advisable.

    (v) Power utilities should be advised to make arrangements, wherever

    possible, for giving land to the prospective entrepreneurs on concessional

    terms contiguous to the power stations. However, supply of power

    should be settled on case to case basis.

    (vi) The Bureau of Indian Standards should formulate Indian Standards on

    building materials produced from fly ash or incorporate suitable

    amendments in the existing standards to cover these materials.(vii) Financial assistance from Governmental financial institutions at

    subsidised rates of interest should be made available to prospective

  • 7/28/2019 CPCB Guidelines for TPP

    14/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.14

    entrepreneurs for setting up fly ash based unit for manufacturing buildingmaterials.

    (viii) Indigenous equipment required for setting up fly ash based industry

    should be exempted from excise duty/sales tax. In case of imported

    equipment required for manufacture of building materials utilising fly ash

    should be 50 % of the normal rates.

    (ix) The end products of coal ash should be exempted for the first 5 years

    from excise duty, sales tax etc. where atleast 50% of coal ash is utilised as

    raw materials for coal ash utilisation between 25 % to 50 % such

    exemption should be 50 % of the normal rates.

    (x) All incentives and according the same preferential treatment should beprovided to all coal ash using industries as are given to small scale

    industries.

    (xi) The technologies developed in R&D institutions should be made

    available at low price to the manufacturers.

    (xii) Local authorities, including States Govts. need also to liberalise their

    industrial policy for establishing ash utilisation industries.

  • 7/28/2019 CPCB Guidelines for TPP

    15/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.15

    ANNEXURE 14.6

    Notification of MOEF dated 14.9.1999, in respect of Fly Ash.

    1. Use of Fly ash bottom ash or pond ash in the manufacture of bricks

    and other construction activities:

    (i) No person shall within a radios of fifty kilometers from coal or lignite

    based thermal power plants, manufacture clay bricks or tiles or blocks for

    use in construction activities without mixing of least 25% of ash (fly ash,

    bottom ash or pond ash) with soil on weight to weight basis.(ii) The authority for ensuring the use of specified quantity of ash as per para

    (I) above shall be the concerned Regional Officers of the State pollution

    Control Board or the Pollution Control Committee as the case may be. In

    case of non-compliance, the said authority, in addition to cancellation of

    consent order issued to establish the brick kiln, shall move the district

    administration for cancellation of mining lease. The cancellation of

    mining lease shall be decided after due hearing. To enable the said

    authority to verify the actual use of ash, the thermal power plant shall

    maintain month-wise records of ash made available to each brick kiln.(iii) In case of non-availability of ash from thermal power plant in sufficient

    quantities as certified by the said power plant, the stipulation under para

    (1) shall be suitably modified (waived/relaxed) by the concerned

    State/Union Territory Government.

    (iv) Each coal or lignite based thermal power plant shall constitute a dispute

    settlement committee which shall include at the General Manager of the

    thermal power plant and a representative of All India Brick and Tile

    Manufacture`s Federation (AIBTMF). Such a committee shall ensure

    unhindered loading and transport of ash without any undue loss of time.

    Any unresolved dispute shall be dealt with by State/Union Territory level

    committee to be set up by State/Union Territory Government comprising

    Member Secretary of the State Pollution Control Board/Pollution Control

    Committee, representatives of Ministry of Power in the State/Union

    Territory Government and a representative AIBTMF.

    2. Utilisation of ash by Thermal Power Plants :

    All coal or lignite based thermal power plants shall utilise the ash

    generated in he power plants as follows :

  • 7/28/2019 CPCB Guidelines for TPP

    16/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.16

    Every coal or lignite based thermal power plant shall make available ash,for a least 10 years from the date of publication of this notification

    without any payment or any other consideration, for the purpose of

    manufacturing ash based products such as cement, concrete based, bricks,

    panels or any other material or for construction of roads, embankment,

    dams, dykes or for any other construction activity.

    (i) Every coal or lignite based thermal power plant commissioned subject

    to environmentally clearance conditions stipulating the submission of

    an action plant for full utilisation of fly ash shall, within a period a of

    nine years from the publication of this notification, phase out thedumping and disposal of fly ash on land in accordance with the plan.

    Such an action plant shall provide for thirty percent of the fly ash

    utilisation, within three years from the publication of this notification

    with further increase in utilisation by at least 10% points every year

    progressively for the next six years to enable utilisation of the entire

    fly ash generated in the power plant at least by the end of ninth year

    Progress in this regard shall be reviewed after five years.

    (ii) (iii)Every coal or lignite based thermal power plant not covered bypara (ii) above shall, within a period of 15 years from the date of

    publication of this notification, phase out the utilisation of fly ash in

    accordance with the action plan to be drawn up by the power plants.

    Such action plan shall provide for 20% of fly ash utilisation within

    three years from the date of publication of this notification, with

    further increase in utilisation every year progressively for next 12

    years to enable utilisation of the entire ash generated in the power

    plan.

    (iii) All action plan prepared by coal or lignite thermal power plants in

    accordance with sub para (ii) and (iii) of para 2 of this notification,

    shall be submitted to the Central Control Board, concerned State

    Pollution Control Boards/Committee and concerned regional office of

    the Ministry of Environment and Forest within a period of six months

    from the date of publication of this notification.

    (iv) The Central and State Government Agencies, the State Electricity

    Boards, the National Thermal Power Corporation and the

    management of the thermal power plant shall facilitate in making

    available land, electricity and water for manufacturing activities and

    provide access to the ash lifting area for promoting and setting up ofash-based production units in the proximity of the area where ash is

    generate by power plant.

  • 7/28/2019 CPCB Guidelines for TPP

    17/17

    Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.17

    (v) Annual implementation report providing information about thecompliance of provision in this notification shall be submitted by the

    30th

    day of April every year to the Central Pollution Control Board,

    concerned State Pollution Control Boards/Committee and concerned

    regional office of the Ministry of Environment and Forests by the

    Coal or lignite based thermal power plants.

    3. Specification for use of ash-based products :

    (i) Manufacture of ash-based products such as cement, concrete blocks,bricks, panels or any other material for the use of ash in construction

    activity such as in road laying, embankments or use as landfill to

    reclaim low lying areas including back filling in abandoned mines or

    pitheads or for any other use shall be carried out in accordance with

    certification and guidelines laid-down by the Bureau of Indian

    Standards, Indian Bureau of Mines, Indian Roads Congress, Central

    Building Research Institute, Roorkee, Central Road Research

    Institute, in New Delhi, Building Material and Technology Promotion

    Council, New Delhi, Central Public Works Department, State PublicWorks Departments and other Central and State Government

    Agencies.

    (ii) The Central Public Works Departments, Public Works Departments in

    the State/Union Territory Government, Development Authority,

    Housing Boards, National Highway Authority of India and other

    construction agencies including those in the private sector shall also

    prescribe the use of ash and ash based products in their respective

    schedules of specifications and construction applications, including

    appropriate standards and codes of factors, within a period of four

    months from the publication of this notification.

    (iii) All local authorities shall specify in their respective building bye-laws

    and regulations the use of ash and ash based products and

    construction techniques in building materials, roads, embankments or

    for any other use within a period of four months from the date of

    publication of this notification.