Upload
senthil031277
View
214
Download
0
Embed Size (px)
Citation preview
7/28/2019 CPCB Guidelines for TPP
1/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.1
SECTION-14
ENVIRONMENTAL ASPECTS IN POWER SECTOR
14.1. INTRODUCTIONThe implementation of power projects requires clearance from Ministry
of Environment and Forests from the following aspects :
a) Environmental aspectsb) Forest (Conservation) Act 1980 angle
The above clearances are communicated separately and a Project
requiring both clearance is deemed to be cleared by MOEF only after the
clearance from both aspects is given.
14.2. ENVIRONMENT CLEARANCEThe Environment Impact Assessment (EIA) Notification `1994, inter-alia,
provides that expansion or modernisation or a new power project shall not
be undertaken in the country unless accorded environment clearance by
the Central Government in the Ministry of Environment and Forest
(MOEF).
This however, does not apply to projects with investment costs less than
50 crores.
The above EIA Notification, sets out procedure for clearance of projects.
For site specific projects, such as hydro electric and pit head thermal
power stations, the site clearance is to be obtained first from MOEF forinitiation of any surveys and investigations. The MOEF would convey a
decision regarding suitability of otherwise of the site within 30 days.
Thereafter, for such site specific projects are to be submitted by the
proponents to MOEF for clearance. The reports shall be evaluated and
assessed by the Impact Assessment Agency which may consult a
Committee of Experts. If required, comments of the public may be
solicited and public hearing arranged. The Notification stipulates that the
assessment shall be completed within a period of ninety days from the
receipt of the requisite documents and data hearing, where required, and
decision conveyed within thirty days thereafter. The clearance granted is
valid for a period of five years for commencement of the
construction/operation.
7/28/2019 CPCB Guidelines for TPP
2/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.2
14.3.0 ENVIRONMENTAL APPRAISAL OF THERMAL POWER
PROJECTS
The proponents of thermal power projects including coal/lignite fired
thermal, gas, combined cycle gas based and co-generation projects submit
20 copies of the application to MOEF in the specified Performa along
with the Environmental Impact Report/Environment Management Plan.
The impact Assessment Agency examines the reports and calls for
additional data, documents. on receipt of complete information, the
projects are placed before the committee of Experts for thermal powerstations. If needed, visits to recommendations of the Committee of
Experts, MOEF further process the projects for clearance/rejection of the
proposals. The cases rejected for non furnishing of complete information
may be reopened on the receipt of complete information.
The expert committee Constituted by MOEF and represented by Chief
Engineer (C&E) CEA, had considered 31 schemes with 17498.55 MW
installed capacity during 1998-99. Out of these, 24 schemes with
10786.55 MW installed capacity had been given clearance fromenvironmental angle.
14.4.0 ENVIRONMENT CONCERNS OF THERMAL POWER
STATIONS
The products of combustion in thermal power plants using coal/lignite
LDO/Naphtha are gaseous emissions containing carbon dioxide, oxides of
sulfur and Nitrogen as also solid particulate matter (ash) where
coal/lignite is used. Beside these, the waste water from the process
contains pollutants.
14.4.1 AIR POLLUTION
Initially, perceptions of objectionable effects of air pollutants were
limited to those easily detected like odour and smoke stacks. Later, it was
the concern over long term/chronic effects that led to the identification of
six criteria pollutants. These six criteria pollutants are sulfur DI-oxide
(S02), Carbon Mono-oxide (CO), Nitrogen oxide (NO2), Dzone (D#),
suspended particulate and non methane hydrocarbons (NMHC) Ozonereferred to as volatile organic compounds (VDC). There is substantial
evidence linking them to health effects at high concentrations. Three of
7/28/2019 CPCB Guidelines for TPP
3/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.3
whom namely O3,SO2 and NO2 are also known phytotoxicants (toxic tovegetation). In the later part Lead (Pb) was added to that list.
Green House Gases which are responsible for temprature enhancement
cause global warming. These Green House Gases are CO2. (Carbon
dioxide), CH4 (Methane), N20 (Nitous Oxide) & CO (Carbon Monoxide)
14.4.1.1. OXIDES OF NITROGEN (NOX )
All combustion processes are sources of NOx at the high temperature
generated in the combustion process. Formation of NOx may be due tothermal NOx which is the result of oxidation of nitrogen in the air and
due to fuel NOX which is due to nitrogen present in the fuel. In general,
higher the combustion temperature the higher NOx is produced.
14.4.1.2 OXIDES OF SULPHUR
The combustion of sulfur containing fossil fuels, especially coal is the
primary source of SOX. About 97 to 99% of SOX emitted from
combustion sources is in the form of sulfur dioxide which is a criteriapollutant, the reminder is mostly SO3, which in the presence of
atmosphere water is transformed into Sulfuric Acid at higher
concentrations, produce deleterious effects on the respiratory system.
14.4.1.3. PARTICULATE MATTER
The terms particulate matter, particulate, particles are used
interchangeably and all refer to finely divided solids and liquids dispersed
in the air.
14.4.2 WATER POLLUTION
Water pollution refers to any change in natural waters that may impair
further use of the water, caused by the introduction of organic or
inorganic substances or a change in temperature of the water.
In thermal power stations the source of water is either river, lake, pond or
sea where from water is usually taken. There is possibility of water being
contaminated from the source itself. Further contamination or pollutioncould be added by the pollutants of thermal power plant waste as
inorganic or organic compounds.
7/28/2019 CPCB Guidelines for TPP
4/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.4
14.4.3 LAND DEGRADATION
The thermal power stations are generally located on the non-forest land
and do not involve much Resettlement and Rehabilitation problems.
However it`s effects due to stack emission etc, on flora and fauna, wild
life sanctuaries and human life etc. have to be studied for any adverse
effects. One of the serious effects of thermal power stations land
requirement for ash disposal and hazardous elements percolation to
ground water through ash disposal in ash ponds. Due to enormous
quantity of ash content in Indian coal, approximately 1 Acre per MW ofinstalled thermal capacity is required for ash disposal.
14.4.4 NOISE POLLUTION
Some areas inside the plant will have noisy equipments such as crushers,
belt conveyors, fans, pumps, milling plant, compressors, boiler, turbine
etc. Various measures taken to reduce the noise generation and exposure
of workers to high noise levels in the plant area will generally include :
i) Silencers of fans, compressors, steam safety valves etc.
ii) Using noise absorbent materials.
iii) Providing noise barriers for various areas.
iv) Noise proof control rooms.
v) Provision of green belt around the plat will further reduce noise
levels.
14.5.0 REGULATORY MEASURES
14.5.1 AIR (PREVENTION & CONTROL OF POLLUTION) ACT, 1981.
In India, 1st Air (Prevention & Control of Pollution) Act was enacted in
1981 with amendments in 1987 for prevention, control and abatement of
air pollution and it came into force with effect from May 91. The act
provides for Central as well as State Boards with such powers and
functions as necessary to provide and control the quality of Air. National
ambient air quality standards by Central Pollution Control Board have
been issued vide Gazette Notification of April 94. For wider dispersal of
SO2, stack height of different capacity units have been stipulated. Forunits less than 500 MW the stack height has been stipulated as 220 meters
whereas 500 MW units it is 275 meters.
7/28/2019 CPCB Guidelines for TPP
5/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.5
14.5.2 ENVIRONMENT (PROTECTION) ACT 1986
Environment (Protection) Act 1986 came into force w.e.f. 19.11.86 and
provides for protection, improvement of environment and for matters
connected therewith. It empowers the Central Govt. to take all such
measures as deemed necessary for protecting and meeting quality of
environment and preventing, controlling and abating environmental
pollution. Standards for liquid effluents have been issued under PEA
Notification, dated 19th
November, 1986
1986 Environment Protection Act has much sharper teeth and provides
for stringent punishment for any violation of Act. As per Sec. 15 of the
Act, whosoever fails to comply or contravenes any of the provisions of
this Act, may be punished with imprisonment which may extend unto five
years or with fine extending unto Rs. one lake or both. In case the failure
continues for more than one year, the imprisonment may be extended to
seven years.
14..5.3 EMISSION/EFFLUENTS STANDARDS
The standards for emissions/effluent have been notified by the
CPCB/MOEF as under :
14.5.3.1 SUSPENDED PARTICULATE MATTER (SPUME)
The bulk of the ash produced from the combustion of coal / lights in the
thermal power station and carried by the flue gases is trapped by the
Espies or bag filters and only a small quantity escapes through stacks.
The Espies of such designs and efficiency are provided that limits the
SPUME in the stack emissions below the prescribed norms. The
standards for SPUME levels as notified by MEd are given at Annex
14.1
7/28/2019 CPCB Guidelines for TPP
6/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.6
14.5.3.2 SULPHUR DIOXIDE EMISSIONS
The non-cooking coal available in the country earmarked for power
generation generally contains low level of sulphur unto 0.50% except for
the coal available in the North Eastern region of the country. There are
no prescribed sulphur dioxide is sought to be achieved by prescribing
minimum sac k height limits for power stations which are given at Annex
14.2. The Indian Air quality Standards prescribed by CPCB stipulates
the limits of SPUME, SOx, NOx, Respriable particulate matter (RPM)
CO & Pb in the ambient air. These standards are given at Annex 14.3
Even using high sulphur coal, the sulphur dioxide emission can be
reduced in the boilers using fluidised bed combustion technology. The
sulphur dioxide produced in the combustion is mixed in the boiler with
the lime fed alongwith the coal.
14.5.3.3 NITROGEN OXIDE EMISSIONS
The formation of Nitrogen oxide depends on the temperature and
residence time of gases in the combustion chamber at that temperature.The formation of Nitrogen oxide can be reduced by providing low
nitrogen oxide burners. No norms for the nitrogen oxide emission at
stack have been notified by MOEF for coal/lignite fired thermal power
stations.
The levels of Nitrogen dioxide in the ambient air are prescribed by the
AAQ standards which would limit the concentration of nitrogen oxide
producing industries in an area.
145.3.4 EFFLUENT DISCHARGE
The process of power generation produces liquid effluents. The standards
for liquid effluents from power stations have been prescribed in the EPA
Notification dated 19th
Nov. 1986 which are reproduced at Annex 14.4.
7/28/2019 CPCB Guidelines for TPP
7/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.7
14.6.0 OTHER ISSUES
14.6.1 COAL WASHING/BENEFICIATION.
Number of studies have been conducted in the past to quantify the
economics of using beneficiated coal in Indian power stations. These
studies have indicated in quantitative terms the benefits of using washed
coal both in terms of O&M as well as capital cost of the project. Vide
MOEF Notification dated 19th
September, 1997, (Annexure vi) certain
categories of thermal plants are required to use washed coal containingash not more than 34 % by June 2001. These plants include the thermal
plants located beyond one thousand Km. from pit heads and thermal
plants located in urban areas or sensitive areas. Subsequently a
committee was formed under the chairmanship of Member (Thermal),
CEA to examine the ways and means of implementation MOEF
Notification vide MOP Office Order No. dated. The committee was
submitted its report in February 2000. Subsequently MOP has set up two
more committee for implementing the recommendations of the main
committee.
14.6.2 FLY ASH UTILISATION
The Coal/Lignite fired thermal power stations produce enormous
quantities of ash. The ash has traditionally been disposed off in the ash
ponds which has the potential of polluting the surface and ground water
unless adequate care is taken. In order to check the percolation of ash
effluents to the ground water, ash pond lining is being provided wherever
necessary. The fly ash collected in the dry form, could however, be
beneficially used for brick making and cement manufacturing. Incentives
have been issued by the ministry of Power letter of 27th
May 1996.
Which are reproduced at Annexure 14.5. Inspite of all out efforts only 5
% of ash is being utilised for gainful purpose at present. The notification
dated 14-9-99 issued by MOEF in respect of Fly ash is reproduced at
Annexure 14.6.
14.6.3 FLUE GAS DESULPHRISATION (FGD) PLANT
The MOEF insists on making space provision for FGD Plant in thedesigns of thermal power units of 500 MW and above capacity as also at
stations with capacity of 1500 to 2000 MW to facilitate their addition at a
7/28/2019 CPCB Guidelines for TPP
8/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.8
later date in case of the need for such plant is established. In case ofsensitive areas the installation of FGD is insisted upon even for stations
with smaller installation.
14.6.4 MONITORING OF ENVIRONMENTAL STATUS OF THERMAL
POWER STATIONS IN INDIA
CEA has also been actively engaged in the monitoring of environmental
status of thermal power stations in the country. Monthly environmental
status reports in respect of Stack emission, AAQ and effluent discharges
are received from the thermal power stations, analysed and remedialmeasures suggested where ever required. Some of thermal units being
operated do not have requisite infrastructure for environmental
monitoring. Where-ever the units are not meeting statutory
environmental requirements, are unable to install/replace existing ESP`s
etc. due to paucity of funds. Though provisions exist in the law for
closing down of the thermal power stations for not meeting
environmental standards, we can hardly afford to close any unit in the
power starved situation. Though, at present emphasis is laid on meeting
particulate matter from stack emission, even for that regularly data is notbeing received from some of thermal power stations.
7/28/2019 CPCB Guidelines for TPP
9/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.9
Annexure 14.1
THERMAL POWER PLANTS : EMISSION STANDARDS
NOTIFICATION
MOEF vide Notification of 19th
May 1993 issued as amendment rules to
environment (Protection) Act 1986. The particulate matter emission limits forthermal power stations are as follows :-
(i) Generation capacity 62.5 MW or more - 150 mg/Nm3
(ii) Generation capacity less than 62.5 MW and plant
Commissioned prior to 1.1.82 - 350 mg/Nm3
(iii) Units located in protected area irrespective of
generation capacity. - 150 mg/Nm3
Annexure 14.2
THERMAL POWER PLANTS : STACK HEIGHT/LIMITS
Generation Capacity Stack Height (Metres)
500 MW and above 275
200 MW/210 MW and above to
less than 500 MW
Less than 200 MW/210 MW
220
H=14 (Q) 0.3
where Q is emission rate of SO2,
in Kg/h, and H is Stack height in
metres
Source : EPA Notification
(G.S.R. 742 (E), dt. 30th Aug, 1990.
7/28/2019 CPCB Guidelines for TPP
10/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.10
Annexure-14.3ENVIROMENT & FORESTS
CENTRAL POLLUTION BOARD
NATIONAL AMBIENT AIR QUALITY STANDARDS, NOTFN. 11.4.94
S.O. 384(E) - The central pollution Control Board in exercise of its
power conferred under section 16 (2) (n) of the Air (Prevention and Control of
pollution) Act, 1981 (14 of 1981) hereby notify the National Ambient Air
Quality standards with immediate effect.
As per CPCB notification dt. 11.4.94,A.A.Q standard has been given
below in brackets.SCHEDULE I
Concentration in Ambient Air
Pollutant Time
weighted
average
Indl.
Area
(ug/m3)
Res. Rural
Other
areas
(ug/m3)
Sensitive
Area
(ug/m3)
Method of
measure
Sulphur
Dioxide(SO2)
* Annual
average
** 24 hours
80
120
60
80
15
30
1. Improve
West &Gacke
method
2. Ultraviolet
flourescence
Oxides of
Nitrogen
* Annual
Average
** 24 hour
80
120
60
80
15
30
1. Jacob and
Hochheiser
modified (Na
Arsenite
2. Gas Phase
Chemilumin
scene
Suspended
Particulate
Matter
(SPM)
* Annual
Average
** 24 hour
360
500
140
200
70
100
High Volume
sampling, (Avg.
flow rate not less
than 1.1m3/min
Respirable
particulatematter (size
less than 10
Annual
Average
** 24 hours
120
150
60
100
50
75
7/28/2019 CPCB Guidelines for TPP
11/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.11
Concentration in Ambient AirPollutant Time
weighted
average
Indl.
Area
(ug/m3)
Res. Rural
Other
areas
(ug/m3)
Sensitive
Area
(ug/m3)
Method of
measure
um)(RPM)
Lead (Pb) Annual
Average
** 24 hours
1.0
1.5
0.75
1.0
0.50
0.75
AAS method
after sampling.
Using ERM
2000 of equiv.
Filter paper.
Carbon
monooxide
(CO)
** 8 hour
mg/m3
1 hour
mg/m3
5.0
10.0
2.0
4.0
1.0
2.0
Non dispersive
infrared
spectroscopy
* Annual Arithmetic Mean of minimum 104 measurements in a year taken
twice a week 24 hours at uniform intervals.
** 24 hours/8 hours values should be met 98% of the time in a year. However,
2% of time, it may exceed but not on two consecutive days.
7/28/2019 CPCB Guidelines for TPP
12/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.12
ANNEXURE 14.4
THERMAL POWER PLANT : STANDARDS FOR LIQUID EFFLUENT
SOURCE
PARAMETERS STANDARDS MAX.
LIMITING
CONCENTRATION mg/1
(EXECPT FOR pH &
TEMP.)
Condenser Cooling Water
(once through cooling
system)
PH
Temperature
6.5 to 8.5
Not more than 7deg. C
higher than the intake
Free available
chlorine
0.5
Boiler Blowdown Suspended
Soilds
Oil & GreaseCopper (Total)
Iron (Total)
100
201.0
1.0
Cooling Tower Blowdown Free available
Chlorine
Zinc
Chromium
(Total)
Phosphate
0.5
1.0
0.2
5.0
Other corrosion Limit to be inhibiting material established on case by case basis
by Central Board in case of Union Territories and state Boards in case of states.
Ash Pond Effluent PH
Suspended
Solids
Oil & Greases
6.5 to 8.5
100
20
Source EPA Notification
(S.O., 844 (E), dt. 19.11.86)
as amended by ---------------notification no.--------------
dt.----
7/28/2019 CPCB Guidelines for TPP
13/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.13
ANNEXURE 14.5
COPY OF COMPREHENSIVE GUIDELINES FOR FLY ASH
UTILISATION AND DISPOSAL ISSUED BY SECRETARY, MOP
VIDE DO NO.11/16/93-RO(K)/E.II DATED 27.5.1996COMPREHENSIVE GUIDELINES FOR FLY ASH UTILISATION AND
DISPOSAL
(i) Dry fly ash should be supplied by the power stations, free of cost, to the
entrepreneurs for a period of 10 years from the day a unit goes into fly
ash based production. The terms of the supply of ash after the initialperiod of 10 years, should be settled annually by the Power Station
Authorities and the concerned entrepreneurs; in case of disagreement, the
matter could be decided by CEA or Building Materials and Technology
Promotion Council (BMTC) for which a suitable provision should be
incorporated in the contracts.
(ii) Where ever Power Stations do not have dry fly ash collection facilities,
they may be required to set up this facility. All new power stations
should provide arrangements for collection and supply of dry fly ash.
This would be ensured by CEA while appraising projects for techno-economic clearance. If any of the State Electricity Boards (SEBs) dry
ash collection, this would considered by the Ministry of Power as a part
of R&D Scheme.
(iii) All proposals formulated and sponsored by the concerned
Boards/Corporations and Utilities for setting up of the Thermal Power
Plants should, in future, invariably incorporate specific provisions for
promoting the maximum utilisation of fly ash generated by the plants.
Central Electricity Authority would examine such proposals for techno-
economic clearance as are found to comply with these requirements.
(iv) The transportation of fly ash from thermal Power Plant should be the
responsibility of entrepreneurs. No subsidy for transport of fly ash or its
end products would be advisable.
(v) Power utilities should be advised to make arrangements, wherever
possible, for giving land to the prospective entrepreneurs on concessional
terms contiguous to the power stations. However, supply of power
should be settled on case to case basis.
(vi) The Bureau of Indian Standards should formulate Indian Standards on
building materials produced from fly ash or incorporate suitable
amendments in the existing standards to cover these materials.(vii) Financial assistance from Governmental financial institutions at
subsidised rates of interest should be made available to prospective
7/28/2019 CPCB Guidelines for TPP
14/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.14
entrepreneurs for setting up fly ash based unit for manufacturing buildingmaterials.
(viii) Indigenous equipment required for setting up fly ash based industry
should be exempted from excise duty/sales tax. In case of imported
equipment required for manufacture of building materials utilising fly ash
should be 50 % of the normal rates.
(ix) The end products of coal ash should be exempted for the first 5 years
from excise duty, sales tax etc. where atleast 50% of coal ash is utilised as
raw materials for coal ash utilisation between 25 % to 50 % such
exemption should be 50 % of the normal rates.
(x) All incentives and according the same preferential treatment should beprovided to all coal ash using industries as are given to small scale
industries.
(xi) The technologies developed in R&D institutions should be made
available at low price to the manufacturers.
(xii) Local authorities, including States Govts. need also to liberalise their
industrial policy for establishing ash utilisation industries.
7/28/2019 CPCB Guidelines for TPP
15/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.15
ANNEXURE 14.6
Notification of MOEF dated 14.9.1999, in respect of Fly Ash.
1. Use of Fly ash bottom ash or pond ash in the manufacture of bricks
and other construction activities:
(i) No person shall within a radios of fifty kilometers from coal or lignite
based thermal power plants, manufacture clay bricks or tiles or blocks for
use in construction activities without mixing of least 25% of ash (fly ash,
bottom ash or pond ash) with soil on weight to weight basis.(ii) The authority for ensuring the use of specified quantity of ash as per para
(I) above shall be the concerned Regional Officers of the State pollution
Control Board or the Pollution Control Committee as the case may be. In
case of non-compliance, the said authority, in addition to cancellation of
consent order issued to establish the brick kiln, shall move the district
administration for cancellation of mining lease. The cancellation of
mining lease shall be decided after due hearing. To enable the said
authority to verify the actual use of ash, the thermal power plant shall
maintain month-wise records of ash made available to each brick kiln.(iii) In case of non-availability of ash from thermal power plant in sufficient
quantities as certified by the said power plant, the stipulation under para
(1) shall be suitably modified (waived/relaxed) by the concerned
State/Union Territory Government.
(iv) Each coal or lignite based thermal power plant shall constitute a dispute
settlement committee which shall include at the General Manager of the
thermal power plant and a representative of All India Brick and Tile
Manufacture`s Federation (AIBTMF). Such a committee shall ensure
unhindered loading and transport of ash without any undue loss of time.
Any unresolved dispute shall be dealt with by State/Union Territory level
committee to be set up by State/Union Territory Government comprising
Member Secretary of the State Pollution Control Board/Pollution Control
Committee, representatives of Ministry of Power in the State/Union
Territory Government and a representative AIBTMF.
2. Utilisation of ash by Thermal Power Plants :
All coal or lignite based thermal power plants shall utilise the ash
generated in he power plants as follows :
7/28/2019 CPCB Guidelines for TPP
16/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.16
Every coal or lignite based thermal power plant shall make available ash,for a least 10 years from the date of publication of this notification
without any payment or any other consideration, for the purpose of
manufacturing ash based products such as cement, concrete based, bricks,
panels or any other material or for construction of roads, embankment,
dams, dykes or for any other construction activity.
(i) Every coal or lignite based thermal power plant commissioned subject
to environmentally clearance conditions stipulating the submission of
an action plant for full utilisation of fly ash shall, within a period a of
nine years from the publication of this notification, phase out thedumping and disposal of fly ash on land in accordance with the plan.
Such an action plant shall provide for thirty percent of the fly ash
utilisation, within three years from the publication of this notification
with further increase in utilisation by at least 10% points every year
progressively for the next six years to enable utilisation of the entire
fly ash generated in the power plant at least by the end of ninth year
Progress in this regard shall be reviewed after five years.
(ii) (iii)Every coal or lignite based thermal power plant not covered bypara (ii) above shall, within a period of 15 years from the date of
publication of this notification, phase out the utilisation of fly ash in
accordance with the action plan to be drawn up by the power plants.
Such action plan shall provide for 20% of fly ash utilisation within
three years from the date of publication of this notification, with
further increase in utilisation every year progressively for next 12
years to enable utilisation of the entire ash generated in the power
plan.
(iii) All action plan prepared by coal or lignite thermal power plants in
accordance with sub para (ii) and (iii) of para 2 of this notification,
shall be submitted to the Central Control Board, concerned State
Pollution Control Boards/Committee and concerned regional office of
the Ministry of Environment and Forest within a period of six months
from the date of publication of this notification.
(iv) The Central and State Government Agencies, the State Electricity
Boards, the National Thermal Power Corporation and the
management of the thermal power plant shall facilitate in making
available land, electricity and water for manufacturing activities and
provide access to the ash lifting area for promoting and setting up ofash-based production units in the proximity of the area where ash is
generate by power plant.
7/28/2019 CPCB Guidelines for TPP
17/17
Performance Review of Thermal Power Stations 2001-02 Section 14 Page no. 14.17
(v) Annual implementation report providing information about thecompliance of provision in this notification shall be submitted by the
30th
day of April every year to the Central Pollution Control Board,
concerned State Pollution Control Boards/Committee and concerned
regional office of the Ministry of Environment and Forests by the
Coal or lignite based thermal power plants.
3. Specification for use of ash-based products :
(i) Manufacture of ash-based products such as cement, concrete blocks,bricks, panels or any other material for the use of ash in construction
activity such as in road laying, embankments or use as landfill to
reclaim low lying areas including back filling in abandoned mines or
pitheads or for any other use shall be carried out in accordance with
certification and guidelines laid-down by the Bureau of Indian
Standards, Indian Bureau of Mines, Indian Roads Congress, Central
Building Research Institute, Roorkee, Central Road Research
Institute, in New Delhi, Building Material and Technology Promotion
Council, New Delhi, Central Public Works Department, State PublicWorks Departments and other Central and State Government
Agencies.
(ii) The Central Public Works Departments, Public Works Departments in
the State/Union Territory Government, Development Authority,
Housing Boards, National Highway Authority of India and other
construction agencies including those in the private sector shall also
prescribe the use of ash and ash based products in their respective
schedules of specifications and construction applications, including
appropriate standards and codes of factors, within a period of four
months from the publication of this notification.
(iii) All local authorities shall specify in their respective building bye-laws
and regulations the use of ash and ash based products and
construction techniques in building materials, roads, embankments or
for any other use within a period of four months from the date of
publication of this notification.