Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
04/06/2020
1
COVID-19 and the energy sector
(2020)10 June 2020
Before viewing this webinar, please visit www.lexiswebinars.co.uk/test-your-system to ensure that your network and PC are configured correctly.
Tip: Press F11 on your keyboard to enlarge the webinar player.
LexisNexis® Confidential 2
The law as stated during this webinar is
up to date as of 3 June 2020
COVID-19 and the energy sector
(2020)
LexisNexis® Confidential 3
Introductions
1
2
3
04/06/2020
2
LexisNexis® Confidential 4
Partner (Italy)
Herbert Smith Freehills
Partner (UK)
Herbert Smith Freehills
Silke Goldberg
Lorenzo Parola
Partner (Germany)
Herbert Smith Freehills
Marius Boewe
LexisNexis® Confidential 5
Partner (France)
Herbert Smith Freehills
Partner (Spain)
Herbert Smith Freehills
Ignacio Paz
Mathias Dantin
LexisNexis® Confidential 6
The Impact of Covid-19 on the
Energy Sector in Italy, Spain,
France, Germany and the United
Kingdom
4
5
6
04/06/2020
3
LexisNexis® Confidential 7
Index
Introduction: general context
Consumers: main measures
Generation: impact on renewable projects
Contractors and Offtakers: hardship, force majeure and change in law clauses
Investors: new foreign investments regime
LexisNexis® Confidential 8
Introduction: general context
LexisNexis® Confidential 9
Introduction : Impact on electricity and gas sectors – France
Decrease of consumption and prices of electricity and gas
Electricity
Sources: RTEand France Stratégie
7
8
9
04/06/2020
4
LexisNexis® Confidential 10
Introduction : Impact on Electricity and gas sectors – France cont.
Decrease of consumption and prices of electricity and gas
Gas
• At the beginning of February, gas prices in Europe and the United States fellby 18%.
• North West European gas demand has fallen 40% since start of April amidstcontinued lockdown and warmer weather.
• Engie's regulated gas sales tariffs have fallen by 2.8% as of 1st June 2020 incomparison to its 1st of May tariffs, but since 1st January 2019, Engie’s tariffshave fallen by 25.3 %
• Slight decline because Engie’s regulated gas sales tariffs are no longer indexedon the oil price.
Sources: CRE ; l’Energie Tout compris and Aurora
LexisNexis® Confidential 11
Introduction: Impact on Electricity and Gas Sectors - Italy
• Stark decrease in consumptions during lock-down
o Power: minus 17% in April
o Gas: minus ca. 30% in April
• Major impact on power prices (last week of May 10€/MWh)
• In April 48.3% of the Italian power demand was covered by renewables
LexisNexis® Confidential 12
Introduction: general context - Spain
• In general terms: government support packages with new measures in severalareas (employment, financial, insolvency, competition, litigation, insurancenew FDI, etc.
• Energy: several measures and the announcement of the new Climate Changeand Energy Transition Act – Spain.
10
11
12
04/06/2020
5
LexisNexis® Confidential 13
Introduction: general context – Germany
Government support packages
• The German Federal Government has announced several measures to helpbusinesses:
o Financial help for small businesses (including freelancers and self employed)
o Further liquidity support for businesses through special loans, facilitated by the German Bank for Reconstruction (Kreditanstalt für Wiederaufbau, KfW) (for all businesses)
o Setting up of an Economic Stabilisation Fund (ESF)(Wirtschaftsstabilisierungsfond) (for larger companies)
o This fund was set up under an Act on the Establishment of an Economic Stabilisation Fund (Gesetz zur Errichtung eines
Wirtschaftsstabilisierungsfond)(WStFG), entered into force on 28 March 2020
• These measures are not sector specific and are mainly focused on providingstability to the wider economy
LexisNexis® Confidential 14
Introduction: general context – Germany cont.
Additional support packages
• The COVID-19 Insolvency Suspension Act (COVInsAG, CIS Act):
o Came into force with retrospective applicability as of 1 March 2020
o Suspends the obligation to file for insolvency (until 30 September 2020)
• Termination rights for non-payment of rent have been suspended
• Provides restructuring loans and protection from insolvency claw-back
• Simplifies the making of corporate resolutions
• Provides additional support measures for small businesses and consumers
• In addition, enforcement measures regarding tax issues have beensuspended
• There is no date for the end of small business support/further liquiditymeasures, though the ESF programme is due to end on 31 December 2021
• An agreement between the Federal Govt. and credit insurers has securedsupply chains in the German Economy, with an additional guarantee beingprovided by the Government
LexisNexis® Confidential 15
Introduction: general context – United Kingdom
Government support packages
• The Government has a business support finder tool, with wide rangingsupport measures in place:
o The Coronavirus job retention scheme (furloughment).
o Coronavirus Large Business Interruption Loan Scheme (CLBILS).
o Coronavirus Business Interruption Loan Scheme (CBILS).
o COVID Corporate Financing Facility (CCFF, alongside the Bank ofEngland)
• There are no private sectors excluded from the schemes, but support isgenerally not available for public sector organisations.
• No specific legislation aimed at the energy sector has been released as yet.
• Ofgem has prioritised the protection of vulnerable consumers and issuedguidance for energy licensees – all regulatory obligations remain in place.
13
14
15
04/06/2020
6
LexisNexis® Confidential 16
Consumers: main measures
LexisNexis® Confidential 17
Consumers: main measures adopted – France
Guaranteed supply of energy and
gas to vulnerable consumers
Through the extension of the
winter truce (extension from the
31 March 2020 to the 10 July
2020) suppliers of electricity, heat
and gas may not interrupt energy
supplies to persons or families in a
principal residence, including by
termination of contract, for non-
payment of bills
Protection of micro-businesses
• prohibition of the interruption or
suspension of the supply of
electricity, gas and water in the
premises; and
• companies may request the
staggering of the payment of the
corresponding invoices due over
the same period, without any
penalty, from energy suppliers.
LexisNexis® Confidential 18
Consumers: main measures adopted – Italy
Guaranteed supply of
energy and gas to
vulnerable consumers
Supply of power to all power
customers in low voltage and
all gas customers with an
annual consumption of
natural gas less than 200,000
cm cannot be interrupted
even if they do not comply
with their payment
obligations)
Relief for retailers
All payments already due to
DSOs as of 2 April 2020 are
extended by 15 working days.
DSOs cannot terminate the
agreement nor enforce the
guarantees posted by retailers
if at least 70% (power) or 80%
(gas) of the invoices due by 30
April is paid
Suspension of power and
gas bills
The obligation to pay power
and gas bills has been
suspended to all
end/consumers in the
so/called “red zone”
Reduction of general system
charges
� Law-Decree 19 May 2020, No. 34 specifically sets out a reduction of general system
charges in respect of the invoices relating to May, June
and July 2020 to be implemented by ARERA for
low-voltage connected users other than domestic users.
16
17
18
04/06/2020
7
LexisNexis® Confidential 19
Consumers: main measures adopted - Spain
Guaranteed supply of
energy and water to
vulnerable consumers
The supply to consumers in
their habitual residence of
energy and water, among
others, may not be suspended.
Electricity discount
(“bono social”)
The group of potential
beneficiaries has been
temporally extended.
Flexibility in electricity
and natural gas supply
contracts for the self-
employed and
businesses
Self-employed persons and
companies may request the
suspension or modification of
their supply contracts among
others.
Suspension of
electricity, natural gas
and oil product bills
for businesses and the
self-employed
The obligation to pay electricity and
gas bills, among others, has been
suspended.
LexisNexis® Confidential 20
Consumers: main measures adopted - Germany
Impact of the CIS Act
The Act allows consumers and
small businesses (balance sheet
p.a. <€2m) to defer or
temporarily suspend payments to
energy suppliers, if they
experience difficulties in making
payments.
No shut-offs
Almost all utility providers who
are members of the VKU
association have agreed that
they will not cut off defaulting
customers’ electricity if they
miss payments.
Tax deferrals
Consumers can ask for some
taxes to be deferred if the
taxpayer is directly affected by
COVID-19, and if their
collection would lead to
significant hardship – includes
VAT
LexisNexis® Confidential 21
Consumers: main measures adopted – United Kingdom
All regulatory obligations
remain in place (Ofgem)
The regulator is taking a
pragmatic approach,
particularly where
vulnerable consumers
may be harmed.
Emergency package for
consumers struggling to
pay energy bills
Consumers can review
payment plans; take
breaks or reductions; and
may access hardship
funds. No meters will be
disconnected.
Relief for retailers
Government grants are
available to support
businesses struggling to pay
bills, though these are not
specifically energy linked –
((CBILS) and other schemes
e.g. business rates holidays).
19
20
21
04/06/2020
8
LexisNexis® Confidential 22
Generation: impact on
renewable projects
LexisNexis® Confidential 23
Generation: impact on renewable projects – France
Adjusted timetables for renewables call for tenders (awarding subsidies)
• 19 March 2020 – Directorate General for Energy and Climate (DGEC)
o Extension periods will be granted to producers penalised by delays and the impossibility ofensuring deliveries of key equipment, particularly photovoltaic modules.
• 23 March 2020 – DGEC
o Adjustment of the next calls for various renewable energy tenders in France (see adjustedschedule in the next slide):
o extension by two months of the submission date for the bids;
o split of the scheduled batches of tender for the onshore wind and ground-based solarsessions.
Consideration of delays due to the Covid-19 crisis
• 3 April 2020 – Announcement of the Ministry of Ecological and Inclusive Transition
o Additional delays granted for the commissioning of the biogas production facilities that areunder construction in order not to penalize projects that have been delayed due to the healthcrisis;
o A temporary suspension of the biogas purchase contract for production plants experiencingoperational difficulties for various reasons, such as lack of inputs.
• 21 April 2020 – DGEC
o Biomass, biogas cogeneration and waste incineration units will benefit from neutralisation ofdowntime or reduced operation periods in the calculation of their availability or energyefficiency.
LexisNexis® Confidential 24
Generation: impact on renewable projects – France cont.
New schedule of the call for tenders by technology
Sectors Date of submission of bids
Old date New date
Solar PV Sol 3 July 20201/3:
3 July 2020
2/3:
3 November 2020
Solar PV Fessenheim 31 July 2020 30 September 2020
Wind 1 July 20201/3:
1 July 2020
2/3:
1 November 2020
Solar PV Building 6 July 2020 6 September 2020
Solar PV Innovative 3 April 2020 3 June 2020
Solar PV ZNI 12 June 2020 12 August 2020
Self-consumption 18 May 2020 18 July 2020
Small hydro 31 March 2020 30 May 2020
Sectors Date of submission of bids
Old date New date
Solar PV Sol 3 July 20201/3:
3 July 2020
2/3:
3 November
2020
Solar PV Fessenheim 31 July 2020 30 September 2020
Wind 1 July 20201/3:
1 July 2020
2/3:
1 November
2020
Solar PV Building 6 July 2020 6 September 2020
Solar PV Innovative 3 April 2020 3 June 2020
Solar PV ZNI 12 June 2020 12 August 2020
Self-consumption 18 May 2020 18 July 2020
Small hydro 31 March 2020 30 May 2020
22
23
24
04/06/2020
9
LexisNexis® Confidential 25
Generation: engagements towards a decarbonised economy –France
10 April 2020 – Support to the Green Deal
• French Minister for the Ecological and Inclusive Transition signed an open letterstating Green deal as a roadmap to overcome the economic crisis.
27 April 2018 - Letter from the French authorities to the other European countriesregarding decarbonised economy
• A collective reflection should be initiated at the European level to secure thefinancing of decarbonised electricity production tools (i.e. including nuclear powerplants).
• The cost of fossil energies should be proportionate to their true environmentalimpact in order to avoid burdening energy transition policies with anyunnecessary risks.
• France's call for a carbon price floor.
• The current crisis show the relevance of a transition towards a more resilientelectricity production system. This should be achieved by developing both:
o a diversified decarbonised electricity mix; and
o a strong supply chain of critical components in Europe.
LexisNexis® Confidential 26
Generation: engagements towards a decarbonised economy –France cont.
Adoption of the Multiannual Energy Program (PPE) and the Low Carbon National Strategy (SNBC)
Decree of 21 April 2020
• Adoption of the Multiannual Energy Program (PPE) and the Low Carbon National Strategy (SNBC)
• Elaboration process started in 2017: public consultation from 20 January to 20 February 2020 but no change in measures followed the public consultation.
• PPE objectives compared to the 2012 consumption:
o By 2023: final energy consumption decreased by 7,5%;
o By 2028: final energy consumption decreased by 16,5%.
Source: decree n°2020-456 of the 21 avril 2020
regarding the multiannual energy program
LexisNexis® Confidential 27
Generation: impact on renewable projects – Italy
• Suspension until 15 May 2020 of all terms relating to permitting proceedings ongoing as of 23 February 2020 and extension until 15 June of the validity of any certificate, permit, concession, authorization expiring between 31 January 2020 and 15 April 2020.
• GSE (the Italian renewables agency):
o Suspended until 30 April 2020 all terms of proceedings related to renewables and energy efficiency, in particular:
o Suspension of all terms of inspection proceedings related to renewables and energy efficiency.
o Extension of all terms relating to requests of documentary integration
o Extended a series of deadlines (originally expiring in the forthcoming days) relating to renewables and energy efficiency.
• The Ministry of Economic Development stated that power plants carry out a public
service and must implement all measures to ensure full operation of the plants.
• (i) Supply and distribution of power, gas, steam and air conditioned (ii) installation
of electrical systems (iii) private security services are excluded from the lock-down
obligation. Also those activities which are "functional" to insure the continuity of
the supply chain of essential activities and public services (e.g. O&M) are excluded.
25
26
27
04/06/2020
10
LexisNexis® Confidential 28
Generation: impact on renewable projects – Spain
• Biomass and Wind Power Plants awarded specific remuneration comply with
requirements established before 28 March 2020. The deadline is suspended
until the 4 June 2020, when the suspension is lifted.
• Extension of the term to obtain definitive start up certificate of under-
construction plants that obtained access and connection permits before Law
24/2013 will expire if the definitive start-up certificate is not obtained within
two months of the end of the state of alarm.
That is, the limitation period which was set 31 March 2020 for access and
connection permits is extended until two months after the end of the state of
alarm
LexisNexis® Confidential 29
Generation: impact on renewable projects – Germany
• Normally, renewable plants, onshore wind and solar power plants over 750kW, and biomass plants over 150kW awarded under tender procedures must be implemented within a certain time period
• If not, they are subject to fines (after 18 months).
• Contracts may also be forfeited completely (if deadlines are missed after 24 months)
• Currently, the Federal Network Agency decided to conduct the tender process as requested by law.
• However, the results will not be published, which will postpone the beginning of the deadlines mentioned above.
• Future obligations:
o Germany targets a 65% renewable energy mix by 2030, however this was
already falling behind due to other factors
o The German energy association Bundesverband der Energie und
Wasserwirtschaft (BDEW) has urged Germany not to forget its climate
change obligations during the oubreak
LexisNexis® Confidential 30
Generation: impact on renewable projects – United Kingdom
• A review of Ofgem’s overall processes is ongoing, covering how consultations canbe run over the next year.
• RIIO-2 hearings have been postponed until further notice.
• Reviewed plans are to be published in due course.
• The Crown Estate has extended the timetable for Round 4 of its offshore windprojects tender:
o Submission window increased from 7 to 10 weeks.
• The Low Carbon Contracts Company (LCCC) manages the administration of CfD
payments:
o A drop in electricity demand has led to a shortfall in supplier
contributions.
o The LCCC will receive a government loan, amount to be determined.
o The Supplier Obligation Interim Levy Rate may have to be increased to
cover June’s payments.
o BEIS may conduct a consultation on the reduction of liabilities for CfD
payments
28
29
30
04/06/2020
11
LexisNexis® Confidential 31
Contractors and Offtakers:
hardships, force majeure and
change in law clauses
LexisNexis® Confidential 32
Contractors and offtakers: force majeure - France
Force Majeure provisions
• Since 2016, force majeure is governed by Article 1218 of the French Civil Code which
specifically provides a statutory regime for force majeure in contracts governed by French
law, even where the contract does not contain a force majeure provision.
• Article 1218 provides that a party can invoke force majeure to excuse its failure to perform
its contractual obligations if: (i) the event was beyond the control of the non-performing
party; (ii) the event was not reasonably foreseeable at the time of entering into the
contract; and (iii) the non-performing party could not have avoided the effects of the alleged
force majeure event with appropriate measures and is therefore unable to perform its
contractual obligations.
• The statutory regime is not mandatory, however, and parties can opt out of it completely or
vary it by including force majeure clauses in their contracts, in which case the points
identified above with respect to contractual force majeure apply
• Successfully invoking FM is notoriously difficult under French law.
• On a side note, on February 29th, the French Minister of Finance Bruno Le Maire said that
the COVID-19 epidemic would qualify as a "force majeure” event for companies with
government. In a letter also dated 29 February to the Mayors of France, the Minister also
suggested they could be lenient in applying liquidated damages. However, the order No.
2020-319 of 25 March 2020 does not contain any presumption of force majeure and the
note of the legal service of the Minister of Economy (i.e., DAJ) on this order recalled that
force majeure can only be assessed on a case-by-case basis.
LexisNexis® Confidential 33
Contractors and offtakers: Hardship - France
Hardship provisions
• Parties to a contract governed by French law and entered into after 1 October 2016 may seek to rely on the doctrine of hardship (imprévision) codified at article 1195 of the French Civil Code to try to renegotiate their contract when an unforeseeable change of circumstances makes performance excessively burdensome for a party that had not agreed to assume such a risk. If the parties cannot reach an agreement on renegotiation of the contract, either party may apply to the courts for the contract to be amended or terminated
• However parties can also exclude article 1195 of the Civil Code, or make adjustments to the conditions under which it applies, especially as concerns renegotiation or recourse to the courts
31
32
33
04/06/2020
12
LexisNexis® Confidential 34
Contractors and offtakers – ARENH Litigations – France
Force majeure and ARENH contract
• Majority of alternative suppliers have requested volumes under the ARENH mechanism in2018-2020 as the price (fixed by legislation at 42 €/MWh) was more advantageous thanmarket prices.
o For the year 2020, CRE has received a total of 147.0 TWh of electricity requests forARENH mechanism while the quantity of electricity allocated to alternative suppliers iscapped at 100 TWh by law.
o CRE renewed its recommendation to increase the volume limit of the ARENH, which isno longer adapted to the current situation on the French electricity market.
• Due to the COVID-19 crisis, market prices dropped to 20 €/MWh.
• Exceptional measures - due to the COVID crisis, the CRE has adopted the followingmeasures:
o suppression of CP2 penalties for the year 2020;
o the CRE encourages amicable agreements in case of dispute arising between EDF andthe alternative suppliers; and
o alternative suppliers will be able to obtain payment delays on ARENH’s invoices.
• Reshape of the ARENH - The French Ministry for the Ecological and Inclusive Transition haslaunched, on 10 April 2020, a tender process to obtain assistance and legal advicealongside the Directorate General for Energy and Climate (DGEC) in order to support theState in the development and implementation of new methods of market regulationelectricity.
LexisNexis® Confidential 35
Contractors and offtakers – ARENH Litigations – France cont.
Force majeure and ARENH contract
• Alternative suppliers have requested:o the activation of the force majeure clause in the ARENH contract to suspend the contract
and to purchase electricity on the market; ando the transmission to RTE of the evolution of the ARENH volumes delivered by EDF to the
alternative suppliers concerned to activate the force majeure clause.
• EDF refused to activate the force majeure clause and the CRE rejected the alternativesuppliers’ requests by a deliberation dated 26 March 2020.
• On 17 April 2020, the Conseil d’Etat rejected an interim proceeding introduced by twoFrench associations representing alternative suppliers (ANODE and AFIEG) requesting thesuspension of the CRE’s deliberation.
• On 20 May 2020, the Paris Commercial Court issued an interim order in favour of TotalDirect Energie ruling that:o conditions of the force majeure, as defined in the contract with EDF, are met;o Total Direct Energie could invoke the force majeure clause in the contract signed with
EDF; ando the Paris Commercial Court ordered EDF to suspend the contract.
• EDF has announced its intention to appeal the Paris Commercial Court interim order. Notethat other alternative suppliers have also introduced a similar interim order request beforethe Commercial Court.
LexisNexis® Confidential 36
Contractors and offtakers: force majeure – Italy
Relevant provisions under Italian civil code: articles 1218, 1256, 1463, 1464 and 1467:
• O&M, EPC, PPA and Asset Management agreements include clauses similar to usual common
law contracts. Detailed force majeure provisions are often included.
• Case by case analysis of the project contracts, with particular reference to the exhaustive or
non-exhaustive lists of force majeure events.
• Impossibile to claim force majeure for events foreseeable and non-avoidable.
• In case of absence of detailed force majeure provisions an evaluation of certain elements must
be carried out (inter alia, facts proving the delay in the fulfilment of certain obligations, impact
of such facts on the scope of the contract, absence – or extreme hardship – of alternative
solutions).
• Subcontractors’ force majeure.
• O&M contracts, scheduled maintenance does not need to be suspended as it is aimed at
ensuring generation continuity, unscheduled maintenance may not be suspended if necessary
to allow the proper operation of the plants. It is possible to draw a distinction between (i)
activities to be carried out on site by contractor’s employees – which may not be suspended,
without prejudice to H&S – and (ii) supply of main components, which may – upon certain
conditions – trigger force majeure.
• Obligations: mitigation, communication of the event, prompt resumption of the relevant
obligations at the end of the force majeure event.
• Right to withdraw of either party for prolonged FM.
34
35
36
04/06/2020
13
LexisNexis® Confidential 37
Statutory Hardship
• Right to terminate the contract.
• Has the statutory hardship provision under the Italian Civil Code been expressly waived?
• In PPAs is volatility of energy price really unforeseeable?
MAC
• Right to request other party to provide additional assurances (eg EFET contracts
General remarks
• Specific provisions aimed at regulating the impact of the Covid-19 outbreak under project contracts which are executed or amended.
• Disputes between the parties. Possibility that a party brings a claim in order to reopen agreed commercial terms.
• Cross default provisions: termination of a single contract may have a broader impact.
Contractors and offtakers: hardship and MAC – Italy
LexisNexis® Confidential 38
Contractors: force majeure and MAC – Spain
• Force majeure: certain obligations of the contract become impossible (circumstances that could not have been foreseen or could not have been avoided).
Under the effect of this circumstance:
o the affected party will be temporarily released from the obligations affected; and,
o neither party may claim any compensation for the non-performance of the affected obligations.
• MAC (Material Adverse Change): severe change in the circumstances of the contract that may lead to a termination of the contract obligations.
o Complex clauses.
o Restricted application.
LexisNexis® Confidential 39
Contractors and offtakers: force majeure – Germany
Relevant provisions under the German civil code: Sec. 206, 275, 286 et. seq., 293 et. seq., 313, 326)
• No legal definition in German law, the precise meaning depends on the legislative context but is often regarded as an external event that has no operational connection and cannot be averted even with the utmost care that can reasonably be expected � pandemics e.g. SARS-CoV have previously classified as Force Majeure in the context of travel law
• energy contracts mostly contain force majeure clauses (incl. definition of FM) releasing both contracting parties from their contractual obligations to perform for the duration of the force majeure and indemnify each other against claims for damages
o the legal and contractual situation must be examined in each individual case
o most clauses contain certain information schemes and procedure for resumption of
performance for the contracting parties, liability risk in case of non-compliance
• In the absence of Force Majeure clauses contractual and tortious liability is based on principle of fault under German Law:
o Only limited direct reference to Force Majeure (höhere Gewalt) in the German Civil Code
(e.g. Sec. 206, 703 (3) BGB)
o provisions on impossibility (Sec. 275 & Sec. 326 BGB), default (Sec. 286 et seq. & 293 et. seq.
BGB) or loss of the basis of the transaction (Sec. 313 BGB) apply in absence of FM clauses in
the contract
o In case of an epidemic there will generally be no fault, so that there will be no liability for
damages though possible liability if contracting party has failed to take appropriate measures
to mitigate harm
37
38
39
04/06/2020
14
LexisNexis® Confidential 40
Contractors and offtakers: MAC and Change in Law – Germany
• MAC-Clauses (Material Adverse Change):
o More common in Anglo-American jurisdictions
o Requirements for a valid MAC-Clause
o MAC-Clauses and COVID19
o Preexisting official legislation comparable to MAC-Clauses = Interference with the
basis of the transaction (Section 313 BGB)
o Advantages MAC-Clauses in comparison to Preexisting official legislation (Section
313 BGB)
o Possible comeback of MAC in the light of COVID 19 on the German market?
• Change in law – Clauses
LexisNexis® Confidential 41
Contractors and offtakers: Boilerplate clauses – United Kingdom
• Force Majeure provisions in project contracts: certain obligations of the contract
become impossible (circumstances that could not have been foreseen or could
not have been avoided).
o The Infrastructure and Projects Authority (IPA) stated that the COVID-19 crisis
is not to be regarded as an event of force majeure for PFI contract purposes.
o Contractors in such projects are to consider themselves as part of the Public
Sector Response to the emergency.
o List of circumstances constituting FM may be closed or open ended.
• MAC (Material Adverse Change): a severe change in the circumstances under which the contract was entered into may trigger termination of contractual obligations.
o Complex clauses.
o Restricted application.
• Change in law: a change to the applicable law would make performing an obligation illegal
o Check all relevant alterations to the law.
LexisNexis® Confidential 42
Investors: new foreign
investment regime
40
41
42
04/06/2020
15
LexisNexis® Confidential 43
Investors: new foreign investments regime - France
Strengthening of the French foreign investment control regime
New order dated 27 April 2020 and recent announcements from the French Minister of Economy
Changes in the foreign investment control concern:
• biotechnology companies, for instance those working on research for a vaccine against COVID-19, are sustainably added to the list of sensitive sectors (R&D activities relating to critical technologies).
• France will lower as from the second semester and until the end of the year 2020, to 10% (against 25% currently) the threshold of control of the acquisition of stakes by non-European investors in the share capital of strategic French companies.
• Since the COVID-19 crisis, the French Ministry of Economy has already demonstrated its extensive use of FDI powers: the refusal by the Ministry of Economy of the acquisition project of the French tech company (Photonis) developing applications with military uses, by the US group Teledyne, is the 1st case of veto in France.
LexisNexis® Confidential 44
Duty to notify the Presidency of the Council of Ministers of:
Objective scope - transactions and corporate resolutions involving:
• strategic assets listed in the Ministerial Decree no. 85/2014 (e.g. national natural gas transmission network, related compression stations and dispatching centres, gas storage facilities, national electricity transmission grid and relevant control and dispatching facilities).
• Under the "Liquidity Decree", all energy infrastructures, real estate investments essential for the use of these infrastructures and energy supply (e.g. generation, wholesale supply, etc.). Significant extension of the notification duties:
o Including renewables? Requests for clarification will be submitted to the Government on behalf of the Italian Wind IPPs Association (ANEV).
o Risk: the government is likely to be overwhelmed with notifications.
Subjective scope - if investors are:
• Non/EU persons, or EU persons controlled by, non-EU persons, in case of acquisition of a controlling stake or (until 31 December 2020) a shareholding interest <10%, if the acquisition value exceeds Euro 1 million (as well as for acquisitions leading to a surpassing of each of15%, 20%, 25% and 50%thresholds); or
• EU persons, in case of acquisition (until 31 December 2020) of a controlling interest.
Consequences: Investments made without the required prior authorisation will be invalid and legallyvoid.
• A breach of the restrictions would lead to heavy fines (up to twice the value of the transaction and in any case not less than 1% of the cumulative turnover achieved by the companies involved).
Investors: new foreign investments regime – Italy
LexisNexis® Confidential 45
An authorisation from the Council of Ministers will be required:
Subjective Scope: if investors are:
• non resident in EU or EFTA; or,
• EU or EFTA residents whose beneficial owners are, or that are controlled by, non- residents.
Objective Scope: if as a result of the investment:
• the investor holds a shareholding interest =/< 10%; or,
• the investor takes part in the management or control.
Consequences
• investments made without the required prior authorisation will be invalid and legally void until they have been properly legalised.
• breach of the restrictions constitutes a very serious offence, which would lead to a fine (which could amount to the sum of the transaction)
Investors: new foreign investments regime – Spain
43
44
45
04/06/2020
16
LexisNexis® Confidential 46
Investors: new foreign investments regime - Germany
• Germany plans to further tighten its foreign investments regime:
• In 2017, Germany introduced a notification obligation for foreign acquisitions in a number of sectors, including critical infrastructure
• Currently, non-EU investment of at least 25% of the voting rights in Germancompanies may be reviewed on the grounds of national security and/or public order
• Certain sectors, including energy infrastructure, are subject to mandatory notificationif at least 10% of the voting rights are acquired by non-EU investors.
• After several iterations of tightening, the Government recently proposed new foreigninvestment rules. These go slightly further than the EU Regulation:
o If passed, standard of review will be whether a foreign investment will be “likely to affect” public order or security
o Previous standard was “endanger”
o Currently, military/defence foreign investments have a “stand still obligation” –i.e. they are paused whilst a ministerial review is carried out, and deals cannot be closed before clearance
o Additional amendment would expand the stand still obligation on foreign investments from defence sectors to other sectors – including critical infrastructure
LexisNexis® Confidential 47
Investors: foreign investments regime – United Kingdom
The National Security and Investment Bill (December 2019, awaiting second reading):
New notification system- businesses can flag transactions, giving rise to national security concerns:
• Likely to be on a voluntary basis.
• If a transaction may impact Government held information and nationalinfrastructure.
• Applies to acquisitions of businesses and other assets which have national security implications.
• Government will screen the transaction.
Additional risk mitigation measures- the government may, on the grounds of nationalsecurity concerns:
• Add conditions.
• Block transactions entirely (last resort); though there is a right to appeal.
Matches other jurisdictions- trend in other countries to introduce screening:
• Consistent with the EU’s new provisions.
LexisNexis® Confidential 48
Concluding remarks
46
47
48
04/06/2020
17
LexisNexis® Confidential 49
Upcoming Construction webinars
• Termination of construction contracts (2020) – 7 July 2020
• Insolvency in construction (2020) – 13 October 2020
• Insurance in construction (2020) – 23 November 2020
LexisNexis® Confidential 50
Thank you and reminders
• This webinar is designed to help solicitors meet requirements A2 (Maintain competence and legal knowledge) and A4 (Draw on detailed knowledge/understanding) of the SRA's Statement of solicitor competence. You may also use the quiz, which can be accessed via the "Take a quiz" link on the webinar details page, to reinforce your understanding of the webinar content. You should answer 7 out of 10 questions correctly and will have two attempts at the quiz.
• Please submit feedback via the survey screen.
• This webinar will be archived immediately, and will be available to view on-demand for 24months.
• A transcript of the webinar can be made available on request within 48 hours.
• You can use the training and evaluation record form which is included in the supporting materials for this webinar to log this training activity and how it relates to the continuing competences that the SRA requires from all solicitors.
If you have any queries, please contact us:
+44 (0) 330 161 2401
@LexisUKWebinars
lexisnexis-webinars
Thank you for attending.
We hope you’ve enjoyed this session.
Bespoke in-house training solutions
• Tailored for your business
• Extensive portfolio of expert presenters
• All areas of legal practice covered
• Location of your choice
Find out more - http://www.lexiswebinars.co.uk/in-house-training
49
50
51