48

Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM
Page 2: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Introductions

2

Page 3: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Project Updates

3

So Where Are We? • 1,000-Car Garage • Courthouse Tower • 500-Car Garage • Midrise Building • East Wing Remodeling • HMGP Roofing @ East Wing

Page 4: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Where we started…….

4

The Courthouse Campus and Surroundings

The Courthouse Tower Site On the Former West Garage

1,000-Car Garage Site on the Former Comcast Property

Page 5: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

1,000-Car Garage

5

Scope of Work New 1,000-space parking

garage and approximately 12,000 square feet of office space in support of the new Civil/Family Courthouse

Project Cost: $29.5 million

CBE Participation: 25%

Completion: Late Spring 2014

Page 6: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

What we’re building……

6

Page 7: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

December, 2012: Work begins on site.

7

The cleared 1,000-Car Garage site with the historic Coca-Cola building in the upper right corner

Page 8: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Progress through August 9, 2013

8

1,000-Car Garage construction progress with the historic Coca-Cola building in the upper right corner

Page 9: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Progress through December 11, 2013

9

1,000-Car Garage construction progress with the historic Coca-Cola building in the upper right corner

Page 10: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

1,000 Car Garage

10

It’s built….. So what happens now? Open the garage!! Resolve use of garage

by the public during evening and weekend hours.

Page 11: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

1,000 Car Garage---The Big Questions

11

When will the new 1,000-car garage open for use? Late May or Early June Who gets to park in the new garage? Employees will be assigned to a garage—either the East Garage or the new one. Assignments have not been made yet. Can I still park in the East Garage? When garage assignments are made, your AVI card will only work in your assigned garage.

Page 12: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

1,000 Car Garage---The Big Questions

12

How do I get into the Courthouse from the new garage? You’ll need to walk to the Courthouse entrance on SE 6th Street. Is there going to be covered walkway from the new garage? No. What about cars/traffic, the weather, security entrances? Be prepared. Use caution.

Construction Site

Page 13: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

13

1,000 Car Garage: 1st Floor Functional Overview

And

rew

s

Aven

ue

S.E. 7th Street

Historic Coca-Cola Building

Shelled Space

Elevators & Stairs

Guardian ad-Litem Offices

Parking Entrance/Exit

Elevators & Stairs

Parking Entrance/Exit

Page 14: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Scope of Work

14

Courthouse Tower 714,000 square foot,

20-story Courthouse

Project Cost: $219 M

CBE Participation: 29%

Includes New Courthouse Tower, connecting bridge, East Wing façade & elevator, and demolition of West and Central Wings

Phased Completion

Tower: Mid-2015

Page 15: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

What we’re building……

15

Page 16: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Site in December, 2012.

16

The cleared former Judge’s garage has been cleared and the site is prepared for underground work.

Page 17: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Site in Early August, 2013.

17

.

Page 18: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Site in Early January, 2014.

18

.

Page 19: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Race Upwards….

19

.

Page 20: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Race Upwards….

20

.

Page 21: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Challenges…

21

.

Pedestrian Safety along SE 6th Street

Courthouse Drive Connecting Bridge

Construction

Logistics for Occupancy

Demolition of the Existing Central and West Wings

Page 22: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Sustainability

22

.

• The building will use 21% less energy than that required by code saving over $300,000 per year.

• The ventilation air rate will

equal or exceed the ASHRAE standard 62.1-2004 for air quality.

• CO2 concentrations will be

measured and increased ventilation rates provided when needed.

• Higher than average HVAC

filters (MERVE 13) will be used to provide clean indoor air.

• New materials are specified to

contain low or no volatile organic compounds (VOCs) in adhesive, paints, sealants, flooring, and furniture.

Going for Gold!!

Page 23: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Sustainable Green Building Features

23

.

• High performance glazing • High performance insulation • White roof with high performance insulation • Energy efficient lighting design • Daylighting, occupancy sensor controls and EMS

sweep controls for lighting • Water saving landscape design • Low flow water saving plumbing fixtures • Rainwater harvesting • Efficient HVAC design • High efficiency chillers • High efficiency motors • CO2 demand control of outside air • Reduced stormwater outflow and enhanced

treatment of stormwater • Public transportation access • Construction waste recycling • Materials with recycled content and regional

origin • Low mercury lamps • Green pest management and cleaning program

and sustainable education program

Page 24: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

24

Building Organization

Court Administration & Executive Offices

Clerk of Courts

State Attorney

Clerk Offices & Executive Offices

State Attorney & Building IT

Page 25: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Scope of Work

25

500-Car Garage & Plaza New public plaza, secure 500-

car garage and public art project.

Project Cost: $14.9 Million Separate construction

solicitation may be required

Completion: 2017

Page 26: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

What We’re Going to Build…..

26

The Secure 500-Car Garage and Public Plaza along SE 6th Street Courthouse Tower in the Background

Page 27: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

What We’re Going to Build…..

27

The Secure 500-Car Garage and Public Plaza along Courthouse Drive

Page 28: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Functionally Integrated Public Art

28

FLOW by Margi Nothard

Page 29: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Challenges….

29

.

Construction Award of the Garage and Plaza

Safe Pedestrian and

Vehicular Movements on SE 6th Street

East Wing and New Tower Disruption

Page 30: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Scope of Work

30

Midrise Renovations Internal reconfiguration of all

four floors to consolidate Public Defender, State Attorney, BSO and Clerk of Courts occupancies and provide a fire sprinkler system for life-safety

Project Cost: $10.9 million CBE Participation: 25% Reduction in rental space Scheduled Completion: Late

2015

Page 31: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Midrise

31

Aftermath of Hurricane Wilma

Page 32: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Midrise

32

Exterior Completely Rebuilt in Aftermath of Hurricane Wilma

Page 33: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Challenges….

33

.

Logistical Planning to Minimize Impacts on Occupants

Page 34: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Scope of Work

34

East Wing Renovations • Proposed complete renovation

of floors 2, 4, 5 and 6. • Renovation of existing

restrooms, mechanical rooms, and retrofit of building systems with the exception of replacement chillers.

• New systems furniture for all

agencies.

• Preliminary Cost Estimate: $12-14 Million

• Scheduled Completion: 2018

Page 35: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

HMGP Wind Mitigation Project – East Wing Roof

35

• 100% Design Doc’s being finalized.

• Project Cost: $2,066,000 • Out to Bid • Construction Start:

Summer 2014

• Scheduled Completion: Early 2015

Page 36: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

The Scope of Work

36

North Wing Renovations • Preliminary scope includes

traffic and small claims court modifications and 1st floor renovations.

• Preliminary scope, cost

estimates and schedules are being developed.

Page 37: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Courthouse Complex Project Schedules

37

2013 2015 2014 2017 2016 2018

New Courthouse

1,000-Car Garage

Midrise Renovation

East Wing Renovation

HMGP Roofing

Facilities Projects

North Wing

Tower Construction

Accept/Move-In Demo Central & West Wings

Construct 500-Car Garage & Plaza

Construction Accept

Transition and Operation

Design Construct 3rd & 4th Floors Construct

1st & 2nd Floors

Construct Design

Procurement

Design Procurement

Construct

Replace N & E Wing Generator/Switchgear Design Construct

East Garage Enhance North Wing ADA

Design Procurement

Construct

Page 38: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Pending Activities…..

38

Page 39: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Issues to Resolve In The Next Few Months…..

39

Occupancy Planning • Finalize funding and purchase of furniture. • Develop detailed planning for stakeholder groups to

occupy the new Courthouse Tower. • Develop detailed security planning and operational

transition plans.

Page 40: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Moving into the new building……

40

2013 2015 2014 2017 2016 2018

New Courthouse

Tower Construction

Accept/Move-In Demo Central & West Wings

Construct 500-Car Garage & Plaza

Page 41: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Moving into the new building……

41

2013 2015 2014 2017 2016 2018

New Courthouse

Tower Construction

Accept/Move-In Demo Central & West Wings

Construct 500-Car Garage & Plaza

• Establish Move Coordination Team

• Match existing locations to new destinations

• Establish Move Sequence

• Coordinate schedules and budgets

• Develop communications plan

Preparation

Page 42: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Moving into the new building……

Involves Everyone

42

You May Not Be Moving…. But You Will Be Impacted Relocation Project Team

Relocation Project Manager Relocation Area Coordinators Agency Contacts Relocation Project Team Directory

Page 43: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Moving into the new building……

Requires Team Work

43

Employee Team Security Team Computer Team Data Team Printer Team AV Team Network Team Testing Team Training Team Vendor Liaisons CMD/FMD/ BSO “Tiger Team”

Page 44: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Moving into the new building……

Big Questions Remain

44

Current locations vs destinations. Floor plan analysis Departmental interviews Associated agency planning

Relocation sequence and restrictions

Sequence of moves and operational startups Prioritization of relocations Limitations/dependencies and other restrictions

Continuity of operations plan

Scheduled downtimes for select court/agency activities Contingency measures

Page 45: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

45

Initiate housecleaning!!! Trash Shred Store Move

Establish and implement relocation communications plan

Stakeholders (Senior management) Employees Associated agencies Public FAQ and rumor control

Moving into the new building……

Take Care of Small Details

Page 46: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Issues for Consideration • The future of SE 6th Street

• Impact of The Wave

46

Page 47: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Questions?

Stay updated on the Courthouse Projects via the Broward County’s Website and Twitter

47

Website link: www.broward.org/newcourthouse WATCH FOR NEW EMPLOYEE AREA FEATURING UPDATES AND NEWS!!! Twitter: @courtnewsflash

Page 48: Courthouse project Sneak Peek, February 28, 2014Courthouse project Sneak Peek, February 28, 2014 Created Date: 3/4/2014 8:51:25 AM

Questions?

E-Mail questions to:

48

[email protected]