Coursework PCP

Embed Size (px)

Citation preview

  • 8/21/2019 Coursework PCP

    1/12

    LOUGHBOROUGH UNIVERSITY

    MMC203: Manufacturing Planning & Control

    Coursework (Semester 2)

    Guilherme Scandolara Rubio B310755

    March 24, 2014

  • 8/21/2019 Coursework PCP

    2/12

    Introduction and Assumptions

    This report presents the analysis of an industrial scenario and the proposal of five different

    medium term capacity plans that ensure sufficient capacity to meet the projected customer

    requirements, comparing them and selecting the one that better fits the situation. In this

    section will be presented the assumptions for the performed study. These assumptions are:

    Analysing the actual orders for the first two months (in table 1) indicates that theforecast is a little conservative. Comparing these two months actual orders with their

    forecasts a correction factor was calculated and applied for the rest of the forecast.

    The new forecast is presented in the Appendix 1.

    It is assumed that there is no variation in the production process, and that the unitsproduced by the workers meet the quality standards.

    It is assumed that the hired employees will have the same production rate as the olderones.

    It is assumed that when the overtime is required the operator will perform it all theworking days of the month.

    It is assumed that when used the agency labor, the temporary worker will be hired forthe whole month.

    The appendix 2 shows the production rates and costs of each type of working force. The cost of keeping finished products in inventory is 1,00 per unit per month.

    Capacity Plans

    There are three main types of capacity plans: level capacity, chase demand and demand

    management. The level capacity plan consists in keeping the processing capacity constant

    through the planning period while the inventory levels are allowed to fluctuate to absorb thevariations in market demand. In the chase demand plan the inventory levels are kept to a

    minimum and the capacity is constantly adjusted in line with the variation of the demand.

    These are called pure strategies, however they are only suited to very specific situations,

    and usually the best approach is a mixed strategy, using elements of both of them. In this

    report are presented one pure level capacity plan, two pure chase demand plans and two

    mixed plans. The plan considered being the most suited for the scenario was the plan 5, using

    mixed strategy. The data of the plans and the table comparing them is in the appendix 3 until

    appendix 8.

    Plan 1Level Capacity

  • 8/21/2019 Coursework PCP

    3/12

    This strategy has some advantages compared to the others, like minimizing the changes to

    working force, that is kept constant, and simpler production scheduling and ordering system.

    However the inventory levels and costs are higher than in the other plans and it is unable to

    respond to sudden changes in the demand above the inventory level. In the plan tested for the

    scenario using this strategy the total cost of the plan was the higher among the five plans,

    316,710, being 51,750 just the inventory holding costs. The average inventory level was of2156 units with a maximum of 3090 in one month.

    Plan 2 and 3Chase demand

    The chase demand strategy has the advantage of keeping the inventory levels to a minimum,

    maintaining only the safety stock, and being more responsive to demand changes. This is

    particularly used in industries with high stock costs. However the utilization of the resources

    in this strategy is lower than in the level capacity one, since the maximum production is

    almost never achieved, in order to avoid creating stock. Also the effort to schedule and recruit

    are higher and the moral is lower, due to the job insecurity and stress due overtime. The Plan

    2 adopted the chase demand strategy manly by changing the production rates, while in the

    Plan 3 the tactic to chase demand was achieved by changing the workforce size.

    The Plan 2 had a considerable reduced total cost 301,206, since the inventory costs were

    only related to the 200 units in the safety stock. The direct labor costs were higher than the

    other plans, since three new employees were hired, however the costs of changing the

    workforce were not very high, since the capacity was adjusted by changing the production

    rate.

    The Plan 3 had the most changes in the workforce size, in 14 of the 24 months there was at

    least one change in the workforce, costing 42,500 for all of them. However this strategy was

    more efficient in chasing the demand and had the best cost of the pure strategies, 287,300.

    Plan 4 and 5 Mix Strategies

    These strategies used elements of both of the pure strategies. In the Plan 4 instead of

    leveling the capacity for the whole period of 24 months, this period was divided into two

    smaller periods, and the capacity was leveled for each of them independently. This resulted in

    smaller inventory costs by the end of the period than the pure level capacity strategy and a

    total cost of 298,466.

    The Plan 5 had some advantages comparing to the other plans, beginning with the total cost

    that was the lowest of the five, 280,147. This strategy was more similar to the chase demandstrategies, however while in the pure chase demand strategies the actual production was

    almost never equal the capacity of the period (to avoid stock) in this plan it was allowed to

    form stock at the end of each period. This way the utilization of the workforce was always

    kept to a maximum. And although the stock costs were higher than in the chase demand

    strategies, the extra stock produced each period could be used in the next one, requiring less

    changes in the workforce than in the Plan 3. In the end only 4 months required changes in the

    working force and still the inventory levels were not as high as in the level capacity strategy,

    with an average of 851 units per period and a total of 20,427 of inventory costs.

    Conclusion

  • 8/21/2019 Coursework PCP

    4/12

    It was observed that the best-suited plan for this scenario was the mixed strategy plan 5. It

    had the lowest cost and some advantages compared to the others like higher utilization of the

    resources, low workforce changes and not so high inventory levels to deal with sudden

    changes in the demand. It is important to notice that if the demand continues to grow in the

    way presented in this scenario in the long term it must be necessary to make changes in the

    equipment in order to have extra capacity. The machinery was already with a utilization ofmore than 60% with 2000 units a month, and with a demand of 2900 units a month it is

    getting closer to its maximum capacity. Also since the demand is clearly seasonal, lower in

    the first months and higher in the last months of the year, some marketing strategies might be

    used to try to smooth the demand.

    Appendix 1 - Forecast

    Forcasting

    Month

    Orders

    Received

    Forecast

    Requests Correction

    1 1850 1800 1850

    2 1430 1400 1430

    3 1425 1400 1435

    4 1875 1900 1947

    5 1950 1998

    6 1950 1998

    7 2000 2050

    8 2000 20509 2500 2562

    10 2500 2562

    11 2500 2562

    12 2500 2562

    13 1900 1947

    14 1500 1537

    15 1500 1537

    16 2040 2091

    17 2100 2152

    18 2100 2152

    19 2200 2255

    20 2200 2255

    21 2800 2869

    22 2800 2869

    23 2800 2869

    24 2800 2869

    Table 1: Forecast Correction

  • 8/21/2019 Coursework PCP

    5/12

    Appendix 2 - Workforce production rate and costs per month

    Full TimeN of employees Production Cost Recruitment Cost

    1 333 1600

    2 666 3200

    3 1000 4800

    4 1333 6400

    5 1666 8000

    6 2000 9600

    7 2333 11200 2500

    8 2666 12800 5000

    9 3000 14400 7500

    Overtime

    N of employees Additional Production Cost

    1 66 480

    2 133 960

    3 200 1440

    4 266 1920

    5 333 2400

    6 400 2880

    Agency Labour

    N of employees Additional Production Costs

    1 250 2000

    2 500 4000

    3 750 6000

  • 8/21/2019 Coursework PCP

    6/12

    Appendix 3 Plan 1: Level Capacity

  • 8/21/2019 Coursework PCP

    7/12

    Appendix 4 Plan 2: Chase demand changing production rate

  • 8/21/2019 Coursework PCP

    8/12

    Appendix 5

    Plan 3: Chase Demand changing workforce

  • 8/21/2019 Coursework PCP

    9/12

    Appendix 6

    Plan 4: Mix Strategy 1

  • 8/21/2019 Coursework PCP

    10/12

    Appendix 8

    Total Costs Comparasion

  • 8/21/2019 Coursework PCP

    11/12

    Appendix 7

    Plan 5: Mix Strategy 2

  • 8/21/2019 Coursework PCP

    12/12