Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Introduction Existing Conditions Structural Redesign Wall System Redesign Analysis Delivery Method
Analysis Recommendations
Agenda
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
IntroductionBuilding Overview
Building Architecture• 360, 000 SF Total Area• Two stories of classrooms• Large Auditorium and Gymnasium AreasSite Development• Full outdoor Tennis and Basketball Facilities• ¼ mile Track• Football, softball and baseball fields throughout site• Two road relocations
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionConstruction Overview
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Construction Started – July 2000Scheduled Completion – September 2002
Total Cost: $74 millionBuilding Only: $40 million
Design-> Bid-> Build
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionSite Overview
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
•Northampton Township, PA
•Suburb of Philadelphia
•Surrounding Neighborhoods
•Formerly Farmland
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionOwner Overview
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
- 95% of students pursue higher education- Mean SAT score of 531.7V, 573.1M- 28 National Merit commendations
Current High School – Designed for 2000 students
Current Enrollment - 3000
One of the most affluent school districts in PA
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Existing ConditionsContract Overview
IntroductionExisting
ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
•Public Job
•Lump Sum
•Lowest Bidder
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Existing ConditionsOriginal Estimate
IntroductionExisting
ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Existing ConditionsOriginal Schedule
IntroductionExisting
ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
July 2000 – September 2002
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Existing ConditionsOriginal Cash Flow Chart
IntroductionExisting
ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Structural RedesignOverview of Original Design
IntroductionExisting ConditionsStructural
RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Structural RedesignOverview of Original Design
IntroductionExisting ConditionsStructural
RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Load-bearing CMU Block Walls
8” Hollow Core Plank
Concrete Slab
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Structural RedesignOverview of Original Design
IntroductionExisting ConditionsStructural
RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Why use this system?•Durability
•Acoustics
•Cost
•Ease Of Construction
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Structural RedesignSteel Design
IntroductionExisting ConditionsStructural
RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
•Concrete Spread Footings
•Steel Columns
•Steel Beams
•Lightweight Concrete Slab on Metal Deck
•Metal Non-Loadbearing Studs
Steel System Elements
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Structural RedesignSteel Design
IntroductionExisting ConditionsStructural
RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Assumptions•Live Load = 50 psf
•Dead Load = 30 psf
•Steel Strength = 50 ksi
•Concrete Strength = 3 ksi
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Structural RedesignSteel Beam Layout
IntroductionExisting ConditionsStructural
RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Structural RedesignSteel Design
IntroductionExisting ConditionsStructural
RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Wall SystemOverview
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Option 1 : Non-loadbearing concrete block
Option 2 : Gypsum Wall Board
Time ??
Cost ??
Durability ??
Acoustics ??
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Wall SystemFiberock
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
•Easy to Install•Ample Fire Rating
Very High Impact Abuse Resistant Gypsum Wallboard
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Wall SystemAcoustics
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
TL = 10 log (1/ τ)
TL = Transmission Lossτ = Transmission
Coefficient.
•Good Acoustics Necessary to Provide an Appropriate Environment for Learning
•Sound Transmission Between Classrooms is Vital
Transmission Loss Equation
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Wall SystemAcoustics
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
TL = 10 log (1/ τ)
TL = Transmission Lossτ = Transmission Coefficient.
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Redesign AnalysisSchedule
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Original Design – CMU/Plank Construction
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Redesign AnalysisSchedule
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Redesigned Steel Schedule
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Redesign AnalysisSchedule
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Start DateDec. 1Dec. 1
SystemOriginal
Proposed
Completion DateNov. 12May 21
•Proposed System Saves 6 months
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Redesign AnalysisCost
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Original Design Estimate
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Redesign AnalysisCost
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Steel Redesign Estimate
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Redesign AnalysisCost
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Original Design - $2,053,378Steel Redesign - $1,696,437
Savings = $356,941
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
Redesign AnalysisConstructability
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Cranes?•Already 2 On Site•Needed for Plank Installation
Sequencing?•Divide by section•Divide by floor
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Delivery Method AnalysisCouncil Rock Contract Structure
Pennsylvania State Law Requires CM
19 Prime Contractors
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Delivery Method AnalysisContract Structure in Other States
General Contractor Runs Construction Process
Electrical, Plumbing, HVAC Contractors
Subcontractors
Owner Manages the Project Without Assistance
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Delivery Method AnalysisAdvantages of CR’s Structure
•Construction Knowledge Brought to
the Owner
•Value Engineering During Design
•CM Doesn’t Hold Contracts
•Planning and Public Relations by the
CM
•Managing Change Orders, Submittals,
RFI’s
•Fulltime On-site Supervision
•Smaller Bid Packages Promote
Lower/Local Bids
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Delivery Method AnalysisDisadvantages of CR’s CM Structure
•Contractor Bickering/ Finger-
pointing
•Lowest Bidder = Bad
Estimator
•Inability to Select Based on
Factors Other than Price
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
RecommendationsConclusion
Steel Redesign• Saves Time• Saves MoneyWall Redesign• Saves Time• Similar PerformanceConstruction Manager• Saves Money• Improved Management• It’s the Law
Seth GlinskiConstruction Management Option
Spring 2003 Thesis
IntroductionExisting ConditionsStructural RedesignWall SystemRedesign AnalysisDelivery Method
AnalysisRecommendations
Acknowledgements
The Architectural Engineering Faculty of Penn State
The Architectural Engineering Class of 2003
Donald Alderfer
Ted Kryven
Michael Holland
My Family and Friends