BSc (Hons) in Quantity Surveying & Construction Management
i Cost Studies University of Sheffield Hallam.
Acknowledgement
It is my great pleasure to thank Almighty God who gave me courage and confident to
complete this assignment successfully. I am very grateful to the University of Sheffield
Hallam for giving opportunity to follow the BSc (Hons) in Quantity Surveying andConstruction Management course.
I would like to thank my Lecturers, Mr. N.T.K Lokuliyana and Mrs. Tharusa Randiwera
for guiding by giving necessary instruction and advice for completing the project
successfully. They have taken pains to go through the project and make necessary
corrections as and when required. I express my thanks to the International College
ofBusiness and technology and its Staff for extending support, and guidance as well.
Last but not the least I would thank my class members without whom this project would
have been a distant reality.
8/13/2019 Cost Studies Roman Number
2/7
8/13/2019 Cost Studies Roman Number
3/7
BSc (Hons) in Quantity Surveying & Construction Management
iii Cost Studies University of Sheffield Hallam.
Introduction
Construction industry totally depended on the money from the ancient times. Without
money the construction cannot move a single step. So, cost and the construction have
very tight relationship. Day by day the construction cost is increasing rapidly and valueof construction shown high in local markets. Because of this clients are keep an eye on
cost estimation methods.
Nowadays, Cost estimation one of the main procedures in many sectors. Especially in
construction execution this process has been considered one the basic work. The
profession of Quantity surveyor developed to control the cost from initial stage to
completion stage. Cost estimations are carried out in several methods using different
types of techniques.
Cost estimating is one of the most important steps in project management. A cost
estimate establishes the base line of the project cost at different stages of development
of the project. A cost estimate at a given stage of project development represents a
prediction provided by the cost engineer or estimator on the basis of available data.
According to the American Association of Cost Engineers, cost engineering is defined
as that area of engineering practice where engineering judgment and experience are
utilized in the application of scientific principles and techniques to the problem of cost
estimation, cost control and profitability (C. Hendrickson 1998)
Eventually, cost estimation gives high value for the construction process and
construction industry obviously keep rely on cost estimating techniques in near future.
8/13/2019 Cost Studies Roman Number
4/7
BSc (Hons) in Quantity Surveying & Construction Management
iv Cost Studies University of Sheffield Hallam.
Executive Summary
Major aim of this assignment is to analyze the cost estimating techniques in the pre
contract stage of construction process. All estimating technique methods are bounded
to RIBA work plane 2007.RIBA has divide its eight pre contract stages in three maingroups, those are
Preparation Stage
Design Stage
Pre- Construction Stage
According to above three stages all cost control and cost planning process are well
explained with examples. Moreover this assignment includes method of preparingestimate for cost controlling process with the respect of above RIBA stages. This
assignment briefly analyzing about the value engineering and Life cycle costing in
construction projects. These two sections are very important in pre contract stage in
terms of cost estimation.
8/13/2019 Cost Studies Roman Number
5/7
BSc (Hons) in Quantity Surveying & Construction Management
v Cost Studies University of Sheffield Hallam.
Conclusion
Human being needs oxygen for exists in the world, like wise construction process need
money for successful completion. That much relationship has wide in modern world
between money and construction. Cost controlling method has initiated to control theunwanted cost in construction industry. These techniques are widely used in the world
since the cost of construction has been lifting up forward.
The term cost controlling includes several techniques which are used by different
professional in pre contract stage. As we following British standards our estimating
thingies are based on RIBA work plane. Broadly this assignment is also written
according to RIBA work plan 2007 edition.
Hopefully this assignment is a good creation about cost controlling process to develop
and improve a construction process. Every success story has painful start and end,
according to that I have gone through many references such as EBooks and journals
and even I had an opportunity discuss about the company with some senior estimators.
Almost everything has done under the assignment criteria and is really satisfied with my
job.
8/13/2019 Cost Studies Roman Number
6/7
8/13/2019 Cost Studies Roman Number
7/7
BSc (Hons) in Quantity Surveying & Construction Management
vii Cost Studies University of Sheffield Hallam.
Nuzul Azam Haron, (Unknown), Scribd, [Online], Last Accessed 10 th of January 2014,
http://s3.amazonaws.com/zanran_storage/www.fab.utm.my/ContentPages/981725817.p
df
Methods of Estimating for Cost Planning, (Unknown), [Online]. Last accessed 9th
ofJanuary 2014, http://www.ukessays.com/essays/construction/the-methods-of-preparing-
estimates-for-cost-planning-construction-essay.php
Cube method estimating, (2010),[Online], Last accessed 10 th of January 2014 ,
http://constructionfield.net/cube-method-estimating/
Value management in building design and construction, (2013), [Online], Last accessed
10 th of January 2014,
http://www.designingbuildings.co.uk/wiki/Value_management_in_building_design_and_
construction
RIBA outline plan of work, (2013), [Online], Last accessed 10 th of January 2014 ,
http://www.architecture.com/Files/RIBAProfessionalServices/ClientServices/RIBAOutlin
ePlanOfWork2008Amend.pdf
The harvard green building resource,(unknown), [Online], Last Accessed 10 th of
January 2014 ,http://www.green.harvard.edu/theresource/new-construction/life-cycle-costing
http://s3.amazonaws.com/zanran_storage/www.fab.utm.my/ContentPages/981725817.pdfhttp://s3.amazonaws.com/zanran_storage/www.fab.utm.my/ContentPages/981725817.pdfhttp://s3.amazonaws.com/zanran_storage/www.fab.utm.my/ContentPages/981725817.pdfhttp://www.ukessays.com/essays/construction/the-methods-of-preparing-estimates-for-cost-planning-construction-essay.phphttp://www.ukessays.com/essays/construction/the-methods-of-preparing-estimates-for-cost-planning-construction-essay.phphttp://www.ukessays.com/essays/construction/the-methods-of-preparing-estimates-for-cost-planning-construction-essay.phphttp://www.ukessays.com/essays/construction/the-methods-of-preparing-estimates-for-cost-planning-construction-essay.phphttp://constructionfield.net/cube-method-estimating/http://constructionfield.net/cube-method-estimating/http://www.designingbuildings.co.uk/wiki/Value_management_in_building_design_and_constructionhttp://www.designingbuildings.co.uk/wiki/Value_management_in_building_design_and_constructionhttp://www.designingbuildings.co.uk/wiki/Value_management_in_building_design_and_constructionhttp://www.architecture.com/Files/RIBAProfessionalServices/ClientServices/RIBAOutlinePlanOfWork2008Amend.pdfhttp://www.architecture.com/Files/RIBAProfessionalServices/ClientServices/RIBAOutlinePlanOfWork2008Amend.pdfhttp://www.architecture.com/Files/RIBAProfessionalServices/ClientServices/RIBAOutlinePlanOfWork2008Amend.pdfhttp://www.green.harvard.edu/theresource/new-construction/life-cycle-costinghttp://www.green.harvard.edu/theresource/new-construction/life-cycle-costinghttp://www.green.harvard.edu/theresource/new-construction/life-cycle-costinghttp://www.green.harvard.edu/theresource/new-construction/life-cycle-costinghttp://www.green.harvard.edu/theresource/new-construction/life-cycle-costinghttp://www.green.harvard.edu/theresource/new-construction/life-cycle-costinghttp://www.architecture.com/Files/RIBAProfessionalServices/ClientServices/RIBAOutlinePlanOfWork2008Amend.pdfhttp://www.architecture.com/Files/RIBAProfessionalServices/ClientServices/RIBAOutlinePlanOfWork2008Amend.pdfhttp://www.designingbuildings.co.uk/wiki/Value_management_in_building_design_and_constructionhttp://www.designingbuildings.co.uk/wiki/Value_management_in_building_design_and_constructionhttp://constructionfield.net/cube-method-estimating/http://www.ukessays.com/essays/construction/the-methods-of-preparing-estimates-for-cost-planning-construction-essay.phphttp://www.ukessays.com/essays/construction/the-methods-of-preparing-estimates-for-cost-planning-construction-essay.phphttp://s3.amazonaws.com/zanran_storage/www.fab.utm.my/ContentPages/981725817.pdfhttp://s3.amazonaws.com/zanran_storage/www.fab.utm.my/ContentPages/981725817.pdf