1
Percentage Used Unit Cost Wastage COST PER KG COST PER TON 74 3.38 15% 3.01 3008.20 25 4.38 2% 1.18 1182.60 1 160 0% 1.60 1600.00 5Rs / Bag 0.13 125.00 5.92 5915.8 MOTIOR CAPACITY (HP) QTY Output W Output KW Eff INPUT KW TOTAL KW LOAD 25 1 18650 18.65 0.92 20.27 20.27 5 2 3730 3.73 0.92 4.05 8.11 2 1 1492 1.492 0.92 1.62 1.62 1 2 746 0.746 0.92 0.81 1.62 31.62 252.99 5661.95 20.00 283.10 330.00 PLANT ENERGY CALCULATIONS Labour Cost Per Ton 283 5811 TOTAL KW OF PLANT M.A.S.C LINING PLANT COST DISTRIBUTION TOTAL DIRECT MATERIAL COST 5198 330 SUMMARY PRODUCT MATERIAL COST Energy Cost per Ton on 20 Ton Production in 8 Hrs Shift Material Stone Lining Powder Boric Acid Filling Bags Total energy consumption in 8 Hrs ( KwH) Total Energy Cost in 8 Hrs ( Rs ) Targeted Production in 8 hrs ( Ton) 232.44 Material Cost Per Ton (Rs) Labor Cost Per Ton (Rs) Energy Cost Per Ton (Rs) TOTAL COST (Rs) Per 40 Kgs Filling =1 bag Price

Cost Sheet Lining Plant

Embed Size (px)

DESCRIPTION

Cost Sheet

Citation preview

Page 1: Cost Sheet Lining Plant

Percentage

UsedUnit Cost Wastage

COST PER

KGCOST PER TON

74 3.38 15% 3.01 3008.20

25 4.38 2% 1.18 1182.60

1 160 0% 1.60 1600.00

5Rs / Bag 0.13 125.00

5.92 5915.8

MOTIOR CAPACITY (HP) QTY Output W Output KW Eff INPUT KWTOTAL KW

LOAD

25 1 18650 18.65 0.92 20.27 20.27

5 2 3730 3.73 0.92 4.05 8.11

2 1 1492 1.492 0.92 1.62 1.62

1 2 746 0.746 0.92 0.81 1.62

31.62

252.995661.95

20.00283.10330.00

PLANT ENERGY CALCULATIONS

Labour Cost Per Ton

283

5811

TOTAL KW OF PLANT

M.A.S.C LINING PLANT COST DISTRIBUTION

TOTAL DIRECT MATERIAL COST

5198

330

SUMMARY

PRODUCT MATERIAL COST

Energy Cost per Ton on 20 Ton Production in 8 Hrs Shift

Material

Stone

Lining Powder

Boric Acid

Filling Bags

Total energy consumption in 8 Hrs ( KwH)Total Energy Cost in 8 Hrs ( Rs )

Targeted Production in 8 hrs ( Ton)

232.44

Material Cost Per Ton (Rs)

Labor Cost Per Ton (Rs)

Energy Cost Per Ton (Rs)

TOTAL COST (Rs)

Per 40 Kgs Filling =1 bag Price