Upload
engr-farrukh-rehan
View
215
Download
1
Embed Size (px)
DESCRIPTION
Cost Sheet
Citation preview
Percentage
UsedUnit Cost Wastage
COST PER
KGCOST PER TON
74 3.38 15% 3.01 3008.20
25 4.38 2% 1.18 1182.60
1 160 0% 1.60 1600.00
5Rs / Bag 0.13 125.00
5.92 5915.8
MOTIOR CAPACITY (HP) QTY Output W Output KW Eff INPUT KWTOTAL KW
LOAD
25 1 18650 18.65 0.92 20.27 20.27
5 2 3730 3.73 0.92 4.05 8.11
2 1 1492 1.492 0.92 1.62 1.62
1 2 746 0.746 0.92 0.81 1.62
31.62
252.995661.95
20.00283.10330.00
PLANT ENERGY CALCULATIONS
Labour Cost Per Ton
283
5811
TOTAL KW OF PLANT
M.A.S.C LINING PLANT COST DISTRIBUTION
TOTAL DIRECT MATERIAL COST
5198
330
SUMMARY
PRODUCT MATERIAL COST
Energy Cost per Ton on 20 Ton Production in 8 Hrs Shift
Material
Stone
Lining Powder
Boric Acid
Filling Bags
Total energy consumption in 8 Hrs ( KwH)Total Energy Cost in 8 Hrs ( Rs )
Targeted Production in 8 hrs ( Ton)
232.44
Material Cost Per Ton (Rs)
Labor Cost Per Ton (Rs)
Energy Cost Per Ton (Rs)
TOTAL COST (Rs)
Per 40 Kgs Filling =1 bag Price