Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS ® 2019

Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Cost Risk Assessment and Value Engineering

Jose Theiler, P.E., CVS®

2019

Page 2: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Agenda• FDOT CSRA and VE Programs• CSRA Meet VE

• Information Phase

• What is Project Risk Assessment?• Base Inputs Review• Risk Identification and Quantification• Monte Carlo Analysis• Analysis Results

• CSRA Meet VE• Function Analysis Phase• Creative Phase

• Timing of CSRA and VE• Why CSRA and VE• Lessons Learned

Page 3: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

FDOT CSRA & VE Programs

Cost & Schedule Risk Analysis

• >$500M – Financial Plan + CSRA Workshop (FHWA Requirement)

• >$100M – CSRA Workshop

• >$20M – CSRA Self-Modeling Tool

Value Engineering Study

• State Requirement: Any Project >$25M

• FHWA Requirement: • >$40M – Bridge Projects

• >$50M – Roadway Projects

• Waivers may be granted by Districts for “in-between” Projects

Page 4: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

FDOT CSRA & VE Programs

Cost & Schedule Risk Analysis

• Increased Awareness of Project

• Improved Communication

• Realistic Expectations of $ and Schedule

• Increased Confidence in Project Cost and Contingencies

• Risk Management Shown to • Decrease number of project problems• Avoid unnecessary costs

Value Engineering Study

• Increased Awareness of Project

• Improved Value of Project• Improved Worth through increase in

Performance• Reduce Risks with Engineering

Solutions• Reduced Cost by Controlling Cost,

Schedule and Risks Exposure

Page 5: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

CSRA Meet VE

CRSAIdentify

Assess

Analyze Mitigate

Allocate

Monitor & Control

VEInformation

Function Analysis

EvaluationCreative

Development

Presentation

RecommendationThreat / Opportunity

Page 6: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

CSRA Meet VE

• Information Phase• Project Overview

• Risk Analysis

• Function Analysis Phase

• Creative Phase

Page 7: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

What is Project Risk Assessment?

• Risk Identification• Qualitative and Quantitative

Risk Analysis• Value Engineering &Mitigation

Strategies• Risk Monitoring & Controlling

Analysis Needs

• How much will it cost?• How long will it take?• Why does it cost that much?• Why does it take that long?

Usual Questions

Page 8: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

What is Project Risk Assessment?

Page 9: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

What is Project Risk Assessment?

Page 10: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Base Inputs Review (Cost)

The Way We’ve Always Done It

Outputs = fQty Unit $ Contin-

gency

5 ea x $12 + 20% = $72

Base Cost=

51

.75

68

.7560

Risk

9 11

10

50%Outputs = fQty Risk

5

5.54.5

11

.5

12

.512

9 11

10

Unit Cost50%

Cost Range=

57 73

69.4

The Risk Assessment Way

x +

70th Percentile Confidence

(16% Risk Reserve)

+

Page 11: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Base Inputs Review (Schedule)

Activity A

Start End

Activity C

Activity D

Activity B

Page 12: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Risk Identification and Quantification

• Describe the event properly

• How likely is it to occur?

• If the event occurs, what are the potential impacts (cost/schedule)?

• on the low end?

• on the upper end?

• most likely?

• Is the event dependent on or correlated with other events:

• “If this happens, then this other will NOT happen…”

Page 13: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Monte Carlo Simulation

Page 14: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Analysis Results

Page 15: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

CSRA Meet VE

• Information Phase• Project Overview

• Risk Analysis

• Function Analysis Phase• Basic Functions

• Secondary Functions

• All-the-time Functions• Mitigate Risks

• Creative Phase• Risk Response Strategies

MitigateRisks

Page 16: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

CSRA Meet VE

• Information Phase• Project Overview

• Risk Analysis

• Function Analysis Phase• Basic Functions

• Secondary Functions

• All-the-time Functions• Mitigate Risks

• Creative Phase• Risk Response Strategies

Temporary Structure

Existing Piles

Existing Columns

Eccentric Load Structure

To Seaport & Airport

Create Space

Page 17: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Understanding Results

Mitigation

Effective Risk Reserve$1,306.9 - $1,167.5 =

$139.4 M

FHWA Requirement

$1

,400

.4

Page 18: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Timing of a CSRA & VE

Value EngineeringStudy

Page 19: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Why CSRA & VE Together?

• Increased Efficiencies in the Information Phase

• Facilitates Delivery of CSRA Results to VE Team

• Approximately Right vs. Precisely Wrong

• Increased Project Awareness and Accountability

• Consistent, Predictable, Repeatable, Through Innovation• Process driven – Two proven processes working together

• Proactive Plan to Manage Risks

• Set of VE Recommendations Mitigating Risks

• Informed Decision Making

• Appropriate Allocation of Risks and Contingencies

Page 20: Cost Risk Assessment and Value Engineering · Cost Risk Assessment and Value Engineering Jose Theiler, P.E., CVS® 2019. Agenda •FDOT CSRA and VE Programs •CSRA Meet VE •Information

Things to Consider When CSRA & VE Together

• One Team, One Goal, One Combined Process

• Allow a week between Information and Other Phases

• Avoid Cramming CSRA & VE in one week

• Coordinate with FHWA for approval of CSRA portion to count as FHWA Cost Estimate Review process (FHWA must approve Consultant as qualified provider)

• Build a Risk Management Plan as part of the VE Implementation Phase