21
8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 1/21 Project : BARRY CALLEBAU Project : BARRY CALLEBAUT GENERAL RECAPITULATION MECHCANICAL ELECTRICAL WORKS NO. T O T A L I. WORK PREPARATION 142,835,000.00 Rp II. ELECTRICAL WORK 5,232,769,334.95 Rp III. MECHANICAL WORK S 3,279,355,211.59 Rp - Rp 865,495,954.65 Rp 9,520,455,501.20 Rp URAIAN PEKERJAAN TOTAL ELECTRICAL AND MECHANICAL WORKS VAT 10 % TOTAL

Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

Embed Size (px)

Citation preview

Page 1: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 1/21

Project : BARRY CALLEBAU Project : BARRY CALLEBAUT

GENERAL RECAPITULATION MECHCANICAL ELECTRICAL WORKS

NO. T O T A L

I. WORK PREPARATION 142,835,000.00Rp

II. ELECTRICAL WORK 5,232,769,334.95Rp

III. MECHANICAL WORKS 3,279,355,211.59Rp

-Rp

865,495,954.65Rp

9,520,455,501.20Rp

URAIAN PEKERJAAN

TOTAL ELECTRICAL AND MECHANICAL WORKS

VAT 10 %

TOTAL

Page 2: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 2/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5) (7)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

 

1  Cleaning area 1.00  lot 12100000 12,100,000 

2  Electrical and genset support 1.00  ls 36300000 36,300,000 

3  Water supply for operasional 1.00  ls 4356000 4,356,000 

4  Warehouse and site office facility 30.00  m2 1512500 45,375,000 

5  Mobilization and demobilization 1.00  lot 18150000 18,150,000 

6  Safety gear and safety officer 5.00  bln 907500 4,537,500 

7  Constructon All Risk (CAR) 1.00  Lot 36300000 36,300,000 

157,118,500.00 

(1)

Total

DESCRIPTION  QTY

PREPARATION WORKS

NO.  UNITUNIT RATE

(Rp.)AMOUNT (Rp.)

REMARK

S

 

Page 3: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 3/21

Project : BARRY CALLEBAUT

ELECTRICAL WORKS

I GENERAL SITE PLAN 3,488,658,122.40

2 MAIN BUILDING 893,924,758.29

3 CANTEEN 64,229,091.87

4 LOCKERS 62,770,154.48

5 MEDICAL AND PRAY ROOM 53,833,473.95

6 TRAFO BUILDING 35,632,203.67

7 POTASH AND CHEMICAL BUI 28,367,947.32

8 BOILER BUILDING 28,742,357.89

9 OFFICE BUILDING 358,986,377.29

10 STORAGE AND MAINTENAN 124,527,805.20

11 PUMP ROOM 6,344,334.92

12 GUARD HOUSE 26,665,847.12

13 WEIGHT BRIDGE 47,546,312.25

14 WWTP 12,540,548.30

 

5,232,769,334.95 T O T A L

GENERAL RECAPITULATION ELECTRICAL WORKS

NO. L O C A T I O N S TOTAL (IDR) REMARKS

Page 4: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 4/21

Project : BARRY CALLEBAUT

I. PANEL

  Me dium Voltage Panel  (By Owner)

Supply and Install Medium Voltage Cable Distribution complete with

metering, relay, grounding , copper bar, breaker & others accessories

in according to the specification and drawing.

1  MVMDP, 20 kV, including of :

- Incoming cubicle : Incoming Cubicle, Type IM - IMC (1 set)

- Outgoing cubicle : Outgoing Cubicle, type SM6 - QM (1 set)

2  Grounding

3  Accessories and support material

4  Testing & commissioning

Low Voltage Panel

Supply and install low voltage panel equipment complete with

breaker MCCB, MCB, Relays, metering, lightning surge arrester

copper bar grounding and other accessories according to

specification and drawings.

1  LVMDP 1 ( include Automatic Transfer Switch ) (TGBT 1.1)

2  PP Domestic Water Pump

3  PP Hydrant / Fire Pump

4  PP Boiler (Process)

5  PP Chiller Distribution Pumps and Air Cooler

6  PP Capacitor Bank

7  PP Chiller

8  PP office

9  PP Diesel Tank

10 PP Gas Tank

11 LVMDP 1.1 (TGBT 1.1)

PP Utility Lighting 2

1  PPLS Cantine

2  PPLS Lockers

3  PPLS Medical Pray room

4  PPLS Tranformer Building

5  PPLS Potash Building

6  PPLS Boiler Room

ELECTRICAL WORKS GENERA

NO. DESCRIPTION

(1) (2)

 

Page 5: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 5/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle

installation works

 complete with pipe conduit PVC high impact dia.

20 mm, clamp

 t-dos and accessories as shown on drawing and all

as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 2 x 36 W, Recessed type (RM) M5 51  pcs 834,900   

2 TL 1 x 18 W, LED Commercial Batten Type (Balk) 7  pcs 586,850   

3 TL 1 x 36 W, Recessed type (TKI) 2  pcs 642,510   

4 GMS 1 X 20 W (Lavatory lamp) 5  pcs 701,800   

5 Down light, PLC 20 W 58  pcs 303,468   

6 Emergency Lamp TL 20 W c/w battery back up 12  pcs 986,700   

7 Exit Lamp 10 W c/w Battery back up 5  pcs 883,300   

8 Single switch, 10A 17  pcs 25,630   

9 Double switch, 10A 11  pcs 37,400   

10 Receptacle, 1ph,16A 39  pcs 50,050   

11 Receptacle, 1ph,16A, UPS 42  pcs 50,050   

12 Receptacle, 1ph, 16 A, for IP Camera 1  pcs 50,050   

13 Receptacle, 1ph, 16 A for Hub Switch 2  pcs 50,050   

14 Receptacle, 1ph, 16 A for MCFA (Fire Alarm) 1  pcs 50,050   

15 Receptacle, 1ph, 16 A for Telephone IP PABX 1  pcs 50,050   

-   

Installastion cost -   

1 Lighting installation, NYM 3x 2,5 mm2 140  points 358,916   

2 Receptacle 1 Ph, installation, NYM 3x2,5 mm2 86  points 534,508   

3 Axial exhaust Fan, Power Installation Installation, NYY 4x6 mm2 1  points 801,762   

4 A/C, Power Installation (7000 bTUH up to 23000 Pk) 15  points 534,508   

5 A/C, Power Installation ( 27000 bTUH up to 32000 bTUH) 6  points 534,508   

6 Electrical Grounding Installation, with copper rod dia. 5/8" 1  lot 2,475,000   

7 and result impedance less than 1 Ohm, -   

8 c/w : Control box 300x300, copper bared cable to Electrical -   

9 switch board (Panel Listrik) -   

10 Accessories and Support Material 1  lot 6,089,451   

Sub Total I 207 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

(1)

ELECTRICAL WORKS OFFICE BUILDING

NO. DESCRIPTION  QTY UNITUNIT RATE

(Rp.)AMOU

Page 6: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 6/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesifiedtechnical specification.

 

Lamp Armature & Miscellanuos

1 HPK - SON 250 W, c/w Cover fibre, Industrial Lamp 80  pcs 1,705,0 

2 Light Aquahot Aqualine RTP/Rxx 1N1L With Pyrek Sleeves, equal with 3  pcs 550,0 

Philips TKO TL 1x36 W  

3 Light Aquahot Aqualine RTP/Rxx 1N 2L With Pyrek Sleeves, equal with 25  pcs 902,0 

Philips TKO TL 2x36 W  

4 TL 1 x 36 W, Recessed type (TKI), c/w : Plastic fibre cover 8  pcs 642,5 

5 TL 1 x 18 W, Recessed type (TKO), c/w cover fibre 19  pcs 477,9 

6 TL 1 x 36 W, Recessed type (TKO), c/w cover fibre 13  pcs 605,0 7 TL 2 x 36 W, Recessed type (TKO), c/w cover fibre 56  pcs 992,2 

8 TL 1 x 36 W, Recessed type (TKO), c/w ; Battery Nicad 11  pcs 1,265,0 

9 Emergency Lamp TL 20 W c/w battery back up 38  pcs 986,7 

10 HPIT 1 x 50 W, spot light 4  pcs 968,0 

11 Exit Lamp TL 10 W 27  pcs 883,3 

12 Single switch, 16A 21  pcs 25,6 

13 Double switch, 10A 3  pcs 37,4 

14 Receptacle, 1Ph, 16A, type plug - in, w/ box, for insect killer 20  pcs 50,0 

15 Receptacle UPS, 1Ph, 16A 8  pcs 50,0 

16 Receptacle, 3Ph, 16A, type plug - in, w/ box, switch and breaker protection 39  pcs 1,925,0 

17 Receptacle, 1Ph, 32A, type plug - in, w/ box, switch and breaker protection 16  pcs 2,365,0  

Installation Cost  

1 Lighting installationHPK - SON 250 W, Nym cable 3 x 2,5 mm² 80  points 358,9 

2 Lighting installation, Nym cable 3 x 2,5 mm² 200  points 358,9 

3 Lighting installation HPIT 1 x 80 W, Nym cable 3 x 2,5 mm² 4  points 358,9 

4 Receptacle installation, 1 ph, 16 A , Nym cable 3 x 2,5 mm² 28  points 534,5 

5  Receptacle installation, 1 ph, 16 A - 32 A , Nym cable 3 x 4 mm² 16  points 694,8 

6 Receptacle installation, 3 ph, 16 A , Nym cable 5 x 4 mm² 39  points 1,069,0 

7 AC Power Installation for 1 PK - 2 PK, NYM 3x2,5 mm2 7  points 534,5 

8 AC Power Installation for 3 PK, NYM 4x4 mm2 2  points 641,4 

9 AC Power Installation for Exhaust wall fan, NYM 4x4 mm2 1  points 534,5 

10 Electrical Grounding Installation, with copper rod dia. 5/8" 1  lot 2,475,0 

and result impedance less than 1 Ohm,  

c/w : Control box 300x300, copper bared cable to Electrical  

switch board (Panel Listrik)  

11 Accessories & others material 1  Lot 9,775,7 

Sub Tot

(1)

ELECTRICAL WORKS - MAIN BUILDING

NO. DESCRIPTION  QTY UNITUNIT RA

(Rp.)

 

Page 7: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 7/21

  TOTAL I - II - III - IV - V

Page 8: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 8/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 1 x 36 W, Commercial Batten Type (TKO) 8  pcs 605,000  4,840,000 

2 TL 1 x 36 W, Recessed type (TKI) 4  pcs 642,510  2,570,040 

3 TL 1 x 18 W, LED Commercial Batten Type (Balk) 7  pcs 586,850  4,107,950 

4 Down light, PLC 20 W, out bow type 10  pcs 303,468  3,034,680 

5 Down light, PLC 20 W, in bow type 2  pcs 332,750  665,500 

6 Emergency Lamp TL 20 W c/w battery back up 3  pcs 986,700  2,960,100 

7 Single switch, 10A 6  pcs 25,630  153,780 

8 Double switches, 10A 2  pcs 37,400  74,800 

9 Triple Switches, 10A 2  pcs 60,500  121,000 

10 Receptacle, 1ph,16A 26  pcs 50,050  1,301,300 

11 Receptacle, 3ph, 400V/10 A, for Extraction hood 1  pcs 181,500  181,500 

12 Receptacle, 3ph, 400V20 A for Cooking table 1  pcs 181,500  181,500 

-  - 

Installastion cost -  - 

1 Lighting installation, NYM 3x 2,5 mm2 29  points 358,916  10,408,555 

2 Receptacle 1 Ph, 16 A installation, nym 3X2,5 mm2 26  points 534,508  13,897,203 

3 Receptacle 3 Ph, 10 A, installation, nym 4X2,5 mm2 1  points 534,508  534,508 

4 Receptacle 3 Ph, 16 A, installation, nym 4X4 mm2 1  points 534,508  534,508 

5 Propeler Fan (Ceiling Fan), Power Installation 4  points 534,508  2,138,031 

6 Exhaust fan Wall , power installation 2  points 534,508  1,069,016 

7 A/C, Power Installation ( kap 9000 bTUH) 3  points 534,508  1,603,523 

8 Accessories and Support Material 1  lot 1,660,194  1,660,194 

Sub Total I 52,037,688.60 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Terminal box Fire Alarm 1  ea 2,365,000  2,365,000 

2 Smoke detector 10  pcs 385,000  3,850,000 

3 Local Control box (push button, Bell alarm, Break glass switch 1  set 660,000  660,000 

and lamp indicator  -  - 

4 End of line 1  pcs 137,500  137,500 

-  - 

Installation cost -  - 

1 Detector installation 10  points 189,530  1,895,300 

2 Installation Local Control Box, (LCB) 1  points 189,530  189,530 

3 Accessories and Support Material 1  lot 495,000  495,000 

S b T t l II 9 592 330 00

(1)

ELECTRICAL WORKS CANTEEN

NO. DESCRIPTION 

QTYUNIT UNIT RATE (Rp.)

AMOUNT

(Rp.)

Page 9: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 9/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 2 x 36 W, Recessed type (RM) M5 7  pcs 834,900  5,844,300 

2 GMS 1 X 20 W 2  pcs 701,800  1,403,600 

3 Down light, PLC 20 W 10  pcs 303,468  3,034,680 

4 Single switch, 10A 8  pcs 25,630  205,040 

5 Double switch, 10A 2  pcs 37,400  74,800 

6 Receptacle, 1ph,16A 8  pcs 50,050  400,400 

-   

Installastion cost -   

1 Lighting installation, NYM 3x 2,5 mm2 19  points 358,916  6,819,398 

2 Receptacle 1 Ph, installation 8  points 534,508  4,276,063 

3 Propeler Fan (Ceiling Fan), Power Installation Installation 1  points 534,508  534,508 

4 A/C, Power Installation (3/4 Pk) 4  points 534,508  2,138,031 

5 A/C, Power Equipment Such as : Hub Switch 1  points 534,508  534,508 

6 Accessories and Support Material 1  lot 2,359,914  2,359,914 

Sub Total I , , . 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Terminal box Fire Alarm 1  ea 2,365,000  2,365,000 

2 Smoke detector 7  pcs 385,000  2,695,000 

3 Local Control box (push button, Bell alarm, Break glass switch 1  set 660,000  660,000 

and lamp indicator  -   

4 End of line 1  pcs 137,500  137,500 

-   

Installation cost -   

1 Detector installation 8  points 189,530  1,516,240 

2 Local control Box (LCB) Installation 1  points 189,530  189,530 

3 Accessories and Support Material 1  lot 495,000  495,000 

Sub Total II 8,058,270.00 

III LAN SYSTEM

Supply, Install & testing all LAN Cabling installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

(1)

ELECTRICAL WORKS MEDICAL PRAY ROOM

NO. DESCRIPTION  QTY UNITUNIT RATE

(Rp.)AMOUNT (Rp.)

 

Page 10: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 10/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 1 x 18 W, type Water proof 2  pcs 1,210,000  2,420,000 

2 Rotary Lamp 10 W 1  pcs 1,375,000  1,375,000 

3 Single switch, 10A 1  pcs25,630 

25,630 4 Double switch, 10A 1  pcs 37,400  37,400 

5 Receptacle, 1ph,16A 1  pcs 50,050  50,050 

-  - 

Installastion cost -  - 

1 Lighting installation, NYM 3x 2,5 mm2 2  points 358,916  717,831 

2 Lighting installation, NYY 3x 2,5 mm2 for Rotary lamp c/w WLC 1  set 358,916  358,916 

3 Receptacle 1 Ph, installation 1  points 534,508  534,508 

4  Accessories and Support Material 1  lot 275,000  275,000 

Sub Total I 5,794,334.92 

II Testing & commissioning All Electrical & Electronic System 1  lot 550,000  550,000 

Sub Total II 550,000.00 

TOTAL I - II 6,344,334.92 

(1)

ELECTRICAL WORKS PUMP ROOM

NO. DESCRIPTION  QTY UNITUNIT RATE

(Rp.)AMOUNT (Rp.)

Page 11: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 11/21

 (7)

REMARKS

Page 12: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 12/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5) (

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 Industrial Lamp HPLN 250 W 6  pcs 1,705,000  10,230,000 

2 Emergency Lamp TL 20 W c/w battery back up 1  pcs 986,700  986,700 

3 Single switch, 10A 1  pcs 25,630  25,630 

4 Double switch, 10A 1  pcs 37,400  37,400 

5 Receptacle, 1ph,16A 1  pcs 50,050  50,050 

6 Receptacle, 3ph,32A 1  pcs 181,500  181,500 

-  - 

Installastion cost -  - 

1 Lighting installation, NYM 3x 2,5 mm2 1  points 358,916  358,916 

2 Lighting installation, NYM 3x 2,5 mm2 for Industrial Lamp 6  points 358,916  2,153,494 

3 Receptacle 1 Ph, installation 1  points 534,508  534,508 

4 Receptacle, 3ph,32A, NYM 4x4 mm2 1  points 694,860  694,860 

5 Accessories and Support Material 1  lot 550,000  550,000 

Sub Total I 15,803,057.89 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Terminal box Fire Alarm 1  ea 2,365,000  2,365,000 

2 Smoke detector 9  pcs 385,000  3,465,000 

3 Local Control box (push button, Bell alarm, Break glass switch 1  set 660,000  660,000 

and lamp indicator  -  - 

4 End of line 1  pcs 137,500  137,500 

-  - 

Installation cost -  - 

1 Detector installation 9  points 189,530  1,705,770 

2 LOCAL CONTROL BOX installation 1  points 189,530  189,530 

# Accessories and Support Material 1  lot 495,000  495,000 

Sub Total II 9,017,800.00 

III LAN SYSTEM

Supply, Install & testing all LAN Cabling installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Outlet LAN RJ 45 1  pcs 126,500  126,500 

Installation cost - 

1 LAN Installation, UTP Cable Cat 6 c/w: conduit 20 mm 1  pcs 2,145,000  2,145,000 

Incuding Use for : IP Camera - 

2 Accessories and Support Material 1  lot 550,000  550,000 

(1)

ELECTRICAL WORKS BOILER ROOM

NO. DESCRIPTION  QTY UNITUNIT RATE

(Rp.)AMOUNT (Rp.) REMA

Page 13: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 13/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 1 x 36 W, Recessed type (TKI) 2  pcs 642,510  1,285,020 

2 TL 1 x 18 W, Commercial batten type (TKO) 2  pcs 468,875  937,750 

3 Down light, PLC 20 W 2  pcs 303,468  606,936 

4 Single switch, 10A 2  pcs 25,630  51,260 

5 Double switch, 10A 1  pcs 37,400  37,400 

6 Receptacle, 1ph,16A 5  pcs 50,050  250,250 

7 Receptacle, 1ph, 16 A, for IP Camera 2  pcs 50,050  100,100 

-  - 

Installastion cost -  - 

1 Lighting installation, NYM 3x 2,5 mm2 6  points 358,916  2,153,494 

2 Receptacle 1 Ph, installation 2  points 534,508  1,069,016 

3 A/C, Power Installation (1 Pk) 1  points 534,508  534,508 

4 A/C, Power Equipment IP Camera 2  points 534,508  1,069,016 

5 Propeler Fan (Ceiling Fan), Power Installation Installation 1  points 534,508  534,508 

6 Accessories and Support Material 1  lot 550,000  550,000 

Sub Total I 9,179,257.12 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Smoke detector 2  pcs 385,000  770,000 

2 Local Control box (push button, Bell alarm, Break glass switch 1  set 660,000  660,000 

and lamp indicator  -  - 

3 End of line 2  pcs 137,500  275,000 

-  - 

Installation cost -  - 

1 Detector installation 2  points 189,530  379,060 

2 LOCAL CONTROL BOX installation 1  points 189,530  189,530 

3 Accessories and Support Material 1  lot 495,000  495,000 

Sub Total II 2,768,590.00 

III IP CAMERA / CCTV

Supply, Install & testing all IP Camera installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 IP Camera, fixed dome type 2  set 5,280,000  10,560,000 

2 Outlet LAN RJ 45 2  pcs 126,500  253,000 

-  - 

Installation Cost -  - 

495 000

(1)

ELECTRICAL WORKS SECURITY GUARD

NO. DESCRIPTION  QTY UNITUNIT RATE

(Rp.)AMOUNT (Rp.) REM

Page 14: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 14/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 1 x 18 W, LED Commercial Batten Type (Balk) 4  pcs 586,850  2,347,4 

2 Emergency Lamp TL 20 W c/w battery back up 2  pcs 986,700  1,973,4 

3 Single switch, 10A 1  pcs 25,630  25,6 

4 Double switch, 10A 1  pcs 37,400  37,4 

5 Receptacle, 1ph,16A 4  pcs 50,050  200,2 

6 Receptacle, 1ph, 16 A, for IP Camera 2  pcs 50,050  100,1 

7 Receptacle, 1ph, 16 A for Hub Switch 1  pcs 50,050  50,0 

-   

Installastion cost -   

1 Lighting installation, NYM 3x 2,5 mm2 6  points 358,916  2,153,4 

2 Receptacle 1 Ph, installation 7  points 534,508  3,741,5 

3 A/C, Power Installation (9000 bTUH) 2  points 534,508  1,069,0 

4 A/C, Power Equipment Hub Switch 2  points 534,508  1,069,0 

5 Accessories and Support Material 1  lot 1,325,458  1,325,4 

Sub Total I 14,092,718 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Terminal box Fire Alarm 1  ea 2,365,000  2,365,0 2 Smoke detector 2  pcs 385,000  770,0 

3 Local Control box (push button, Bell alarm, Break glass switch 1  set 660,000  660,0 

and lamp indicator  -   

4 End of line 1  pcs 137,500  137,5 

-   

Installation cost -   

1 Detector installation 2  points 189,530  379,0 

2 LOCAL CONTROL BOX installation 1  points 189,530  189,5 

3 Accessories and Support Material 1  lot 495,000  495,0 

Sub Total II 4,996,090. 

III IP CAMERA / CCTV

Supply, Install & testing all IP Camera installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 IP Camera, fixed dome type 1  set 5,280,000  5,280,0 

-   

(1)

ELECTRICAL WORKS WEIGHT BRIDGE BUILDING

NO. DESCRIPTION  QTY UNIT UNIT RATE(Rp.)

AMOUNT (R

Page 15: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 15/21

Page 16: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 16/21

Page 17: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 17/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 1 x 18 W, LED type, Commercial Batten Type (Type Balk) 2  pcs 586,850  1,17 

2 TL 1 x 36 W, Commercial Batten Type (Type TKO) 8  pcs 605,000  4,84 3 Emergency Lamp TL 20 W c/w battery back up 3  pcs 986,700  2,96 

4 Single switch, 10A 3  pcs 25,630  7 

5 Receptacle, 1ph,16A 1  pcs 50,050  5 

-   

Installastion cost -   

1 Lighting installation, NYM 3x 2,5 mm2 13  points 358,916  4,66 

2 Receptacle 1 Ph, installation 1  points 534,508  53 

3 Exhaust Wall Fan, Power Installation Installation 5  points 534,508  2,67 

4 Accessories and Support Material 1  lot 1,299,037  1,29 

Sub Total I18,272,7 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Smoke detector 4  pcs 385,000  1,54 

2 End of line 1  pcs 137,500  13 

-   

Installation cost -   

1 Detector installation 4  points 189,530  75 

2 Accessories and Support Material 1  lot 302,500  30 

Sub Total II 2,738,1 

III Kabel Tray for Electrical

 Hot dip plating type

1 Kabel Ladder 600 x 100mm 13  M' 550,000  7,26 

2 Elbow 600 x 100mm 1  ea 935,000  93 

3 Tee 300x100mm 1  ea 498,850  49 

4 In/Out rider 300x100 2  ea 324,500  64 

5 In/Out rider 200x100 2  ea 250,800  50 

6 Support & Material bantu 2  lot 1,897,500  3,79 

Sub Total III 13,639,4 

IV Testing & commissioning All Electrical & Electronic System 1  lot 1,100,000  1,10 

(1)

ELECTRICAL WORKS TRAFO ROOM

NO. DESCRIPTION  QTY UNIT UNIT RATE (Rp.) AMOUNT (

Page 18: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 18/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos1 TL 2 x 36 W, Commercial Batten Type (Type TKO) 16  pcs 938,718   

2 GMS 1 X 20 W (Lavatory lamp) 1  pcs 701,800   

3 Industrial Lamp HDK Sodium 250 W 11  pcs 1,705,000   

4 Single switch, 10A 7  pcs 25,630   

5 Double switch, 10A 4  pcs 37,400   

6 Receptacle, 1ph,16A 31  pcs 50,050   

7 Receptacle, 3ph,32A 3  pcs 181,500   

8 Receptacle, 1ph,16A for Camera CCTV 2  pcs 50,050   

9 Receptacle, 1ph,16A for Hub Switch 1  pcs 50,050   

-   

Installastion cost-   

1 Lighting installation, NYM 3x 2,5 mm2 17  points 358,916   

2 Lighting installation, NYM 3x 2,5 mm2 for Industrial Lamp 11  points 358,916   

3 Receptacle 1 Ph, installation NYM 3x2,5 mm2 34  points 534,508   

4 Receptacle, 3ph,32A, NYM 4x4 mm2 3  pcs 534,508   

5 A/C, Power Installation (3/4 Pk ) 4  points 534,508   

6 A/C, Power Equipment Hub Switch 1  points 534,508   

7 A/C, Power Equipment IP Camera 2  points 534,508   

8 A/C, Power Installation ( 6700 bTUH) 4  points 534,508   

9 Accessories and Support Material 1  lot 5,891,492   

Sub Total I 78 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

  1 Terminal box Fire Alarm 1  ea 2,365,000   

2 Smoke detector 10  pcs 385,000   

3 UV/IR - Laser Detector 1  pcs 1,430,000   

4 Local Control box (push button, Bell alarm, Break glass switch 2  set 385,000   

and lamp indicator (for Storage Maintenance & gas Tank) -   

5 End of line 1  pcs 137,500   

-   

Installation cost -   

1 Detector installation 11  points 189,530   

2 LOCAL CONTROL BOX installation 2  points 189,530   

3 Accessories and Support Material 1  lot 522,500   

(1)

ELECTRICAL WORKS STORAGE & MAINTENANCE

NO. DESCRIPTION  QTY UNIT UNIT RATE (Rp.) AMOU

Page 19: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 19/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 TL 1 x 18 W, Recessed type (TKO) 4  pcs 468,875  1,875,500 

2 TL 1 x 36 W, Recessed type (TKO) 15  pcs 642,510  9,637,650 

3 TL 1 x 36 W, Commercial Batten Type (Type Balk) 6  pcs 494,043  2,964,258 

4 GMS 1 X 20 W 2  pcs 701,800  1,403,600 

5 Emergency Lamp TL 20 W c/w battery back up 3  pcs 986,700  2,960,100 

6 Single switch, 10A 6  pcs 25,630  153,780 

7 Receptacle, 1ph,16A 13  pcs 50,050  650,650 

8 Receptacle, 3ph, 10 A (2.200 W) 1  pcs 181,500  181,500 

9 Receptacle, 3ph, 32 A (9.000 W) 2  pcs 825,000  1,650,000 

10 Receptacle, 3ph, 63 A (30.000 W) 1  pcs 1,925,000  1,925,000 

-  - 

Installastion cost -  - 

1 Installation cost for Lighting installation, NYM 3x 2,5 mm2 30  points 358,916  10,767,471 

2 Installation cost for Receptacle 1 Ph, NYM 3x 2,5 mm2 13  points 534,508  6,948,602 

3 Installation cost for Receptacle, 3ph, NYM 4x2,5 mm2 1  points 534,508  534,508 

4 Installation cost for Receptacle, 3ph, NYM 4x 6 mm2 2  points 1,041,249  2,082,498 

5 Installation cost for Receptacle, 3ph, NYM 4x 16 mm2 1  points 2,082,498  2,082,498 

6 Propeler Fan (Ceiling Fan), Power Installation Installation 5  points 694,166  3,470,830 

7 Accessories and Support Material 1  lot 1,485,000  1,485,000 

Sub Total I 50,773,444.48 

II. FIRE ALARM SYSTEM

Supply, Install & testing all Fire Alarm installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Equipment Components

1 Terminal box Fire Alarm 1  ea 2,365,000  2,365,000 

2 Smoke detector 6  pcs 385,000  2,310,000 

3 Local Control box (push button, Bell alarm, Break glass switch 1  set 385,000  385,000 

and lamp indicator  -  - 

4 End of line 1  pcs 137,500  137,500 

-  - 

Installation cost -  - 

1 Detector installation 6  points 189,530  1,137,180 

2 LOCAL CONTROL BOX installation 1  points 189,530  189,530 

3 Accessories and Support Material 1  lot 522,500  522,500 

Sub Total II 7,046,710.00 

III Testing & commissioning All Electrical & Electronic System 1  lot 4,950,000  4,950,000 

(1)

ELECTRICAL WORKS LOCKERS ROOM

NO. DESCRIPTION  QTY UNITUNIT RATE

(Rp.)

AMOUNT (Rp.)

Page 20: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 20/21

Project : BARRY CALLEBAUT

(2) (3) (4) (5) (6)=(3x5)

I. LIGHTING AND RECEPTACLE INSTALLATION WORKS

Supply, Install & testing all lighting & receptacle installation works

 complete with pipe conduit PVC high impact dia. 20 mm, clamp

 t-dos and accessories as shown on drawing and all as spesified

technical specification.

Lamp Armature & Miscellanuos

1 Spot light lamp 20 W 3  pcs 412,500  1,237,500 

2 TL 1 x 36 W, Commercial Batten Type (Type TKO) 3  pcs 642,510  1,927,530 

3 Single switch, 10A 1  pcs 25,630  25,630 

4 Double switch, 10A 2  pcs 37,400  74,800 

5 Receptacle, 1ph,16A 3  pcs 50,050  150,150 

-  - 

Installastion cost -  - 

1 Lighting installation, NYM 3x 2,5 mm2 6  points 358,916  2,153,494 

2 Receptacle 1 Ph, installation 3  points 534,508  1,603,523 

3 Exhaust Ceiling Fan, Power Installation Installation 2  points 534,508  1,069,016 

4  Accessories and Support Material 1  lot 796,295  796,295 

Sub Total I 9,037,938.79 

II Testing & commissioning All Electrical 1  lot 3,575,000  3,575,000 

Sub Total II 3,575,000.00 

TOTAL I - II 12,612,938.79 

(1)

ELECTRICAL WORKS WWTP

NO. DESCRIPTION  QTY UNITUNIT RATE

(Rp.)AMOUNT (Rp.)

Page 21: Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

8/13/2019 Cost Plan Bcci Electrical Rev 1-16102012(Final) Sn - Copy

http://slidepdf.com/reader/full/cost-plan-bcci-electrical-rev-1-16102012final-sn-copy 21/21

 (7)

REMARKS