Bi l. Element % RM 1 Substructures 5.60 533,132.58 2 Superstructure 35.09 3,337,568.67 3 Finishes 8.27 785,844.20 4 Fitting and furnishing N/A 5 Services 26.70 2,540,296.10 6 External works 7.40 703,254.23 Total Building Cost 8,022,491.08 7 Preliminaries 1.28 122,395.30 8 Contingencies (less) 2.32 220,000.00 9 Provisional Sum N/A 10 Prime cost sum 13.34 1,269,408.00 TOTAL CONTRACT SUM 100 9,511,899.08 Location : Terengganu Year : 2004 Gross Floor Area: 4,522 m² Cost/m² : 9,511,899.08 4,522 =RM 2,103.47 Cost index Nov 2004 : 118.4 1.1. Cost of Proposed Building Location : Taman Universiti Year : 2015 Gross Floor Area: 1500 m² Cost Index Jan 2015: 98.6

COST INFORMATION ESTIMATION

Embed Size (px)

DESCRIPTION

GENERAL LABORATORY AND ADMIN BUILDING

Citation preview

Bil.Element%RM

1Substructures

5.60533,132.58

2Superstructure

35.093,337,568.67

3Finishes

8.27785,844.20

4Fitting and furnishing

N/A

5Services

26.702,540,296.10

6External works

7.40703,254.23

Total Building Cost8,022,491.08

7Preliminaries

1.28122,395.30

8Contingencies (less)

2.32220,000.00

9Provisional Sum

N/A

10

Prime cost sum13.341,269,408.00

TOTAL CONTRACT SUM1009,511,899.08

Location : TerengganuYear: 2004Gross Floor Area: 4,522 mCost/m:Cost index Nov 2004 : 118.4

1.1. Cost of Proposed Building

Location : Taman Universiti Year: 2015Gross Floor Area: 1500 mCost Index Jan 2015: 98.6i. Cost index: x cost/m2(analysis) x RM 2,103.47 = RM1,751.70

ii. Total Cost: Cost /m2(analysis) x Gross Floor Area RM 1,751.7x 1500m2 = RM2,627,560.92,

iii. Add 5% Preliminaries: x RM 2,627,560.92 = RM 131,378.05 =RM131,378.05+ RM 2,627,560.92, =RM 2,758,938.97

iv. Add 3% Contingency: x RM 2,758,938.97= RM 82,768.17 = RM 82,768.17 + RM 2,758,938.97 = RM 2,841,752.14

v. Add 5% External Work: x RM 2,841,752.14= RM 142,087.61 = RM 142,087.61+ RM 2,841,752.14 = RM 2,983,839.75

vi. Total Construction Cost: RM 2,983,839.75

vii. Cost/m2:

= RM 1,989.23