Upload
maida
View
55
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Cost Allocation Considerations. Herb Healy. October 5, 2009. Cost Allocation Considerations. In ISO and EnerNOC supply-side proposal, energy payment levels differ ISO Pays LMP-G, where G is the cost of generation in the customer’s retail rate EnerNOC - PowerPoint PPT Presentation
Citation preview
Cost Allocation Considerations
Herb Healy
October 5, 2009
2
Cost Allocation Considerations
In ISO and EnerNOC supply-side proposal, energy payment levels differ
• ISO – Pays LMP-G, where G is the cost of generation in the customer’s retail rate
• EnerNOC– Pays LMP at or above a threshold price
• Both ISO and EnerNOC require allocation of energy payments
EnerNOC advocates
• LMP – G allocated to the host LSE– LSE is held harmless by this payment structure (see following)
• “G” portion of LMP payment is an uplift to Real Time Load Obligation (RTLO)– Prorate across all load
Scenario: Customer X has 1 MW of price-responsive load reductionLSE A is Asset Load owner for Customer X in ISO energy wholesale market
Assume: --RT LMP = $80/MWh--Customer X retail rate for supply (G) = $60/MWh
Allocation of LMP-G Cost to Host LSE
3
ISO
Customer XLSE
A
$20(=LMP-G)
$20(=LMP-G)
($60)(=Lost revenue to LSEA
from Customer X)
LSEA: Pays market (LMP-G) $20 Loses customer revenue (G) $60 Total cost $80
If LSEA is long: Sells 1 MWh @ LMP $80 revenue
If LSEA is short: Avoids procurement of 1 MWh @ LMP ($80) avoided
expense
Host LSE held harmless by DR Participation
4
Comments on ISO’s Draft Report“Evaluation of Demand Response Payments Rates and Cost Allocation Methods”
• The paper illustrates and analyzes a valid cost allocation methodology– The methodology is applicable only to the particular, narrow example that is
outlined in the document
• ‘G’ – An ethereal concept. Difficult to determine in its simplest manifestation, widely divergent from a contractual and risk perspective for the vast majority of C&I loads
• Use of study as basis for correct payment level is faulty– Study explicitly (and fatally) ignores DR’s marginal benefit to load, which is
quite significant
– Study assumes that the participation of DR in independent of the compensation price This proves…. if you pay less (for the same benefit), you are better off than paying
more (for that same benefit)
EnerNOC Proposed Additional Analysis
• EnerNOC is not proposing a specific threshold today
• Believe current DALRP threshold using 11.37 MMBtu/ kWh is too high
• Proposes additional analysis– Potential savings to system, considering various levels of participation in the
market
– Appropriate heat rates indexed to FRFI
– Look-back correction mechanism
• Consideration of impacts of bidding parameter flexibility
From EnerNOC presentation to MC, September 21, 2009“Energy Market Construct for PRD -Payment Level, Threshold, and M&V”
Example Benefit to Load – Draft Results
Basis of analysis
• 100 MW of DR participation
Analysis shows:• DR will lower LMPs• Hourly benefits are highest in high priced, scarcity hours,But• Overall savings to load are derived for higher levels of participation