56
COSME Webinar 10 January 2019 Financial management and reporting

COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

COSME Webinar10 January 2019

Financial management and reporting

Page 2: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

AIMS OF THE WEBINAR

To provide beneficiaries with a set of guidelines and best

practices on:

- Appropriate financial management

- Correct reporting

To avoid recurrent errors identified during ex-post audits

For questions: [email protected]

2

Page 3: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

TARGET AUDIENCE

• COS-CLUSTER-2015-3-02

• COS-DESIGN-2015-3-03-1

• COS-DESIGN-2015-3-06

• COS-EarlyWarningEU-2016-4-01

3

Page 4: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

WHY IS REPORTING IMPORTANT?

4

In final implementation phase, reporting is near!

Report should cover entire project duration

Do not repeat project proposal Focus on results!

Tell a true story – What went well, and what wrong

What changed?

Any staff changes?

Did you have issues with subcontracting?

Did you shift the budget from one heading to another?

Any other major changes during implementation?

Which deliverables performed well, and which faced difficulties?

Were your amendments effective?

INTELLECTUAL PROPERTY RIGHTS (GDPR)

Which deliverables are private, and which ones are public?

Page 5: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

WHY IS REPORTING IMPORTANT?

5

Focus on achievements

What performance indicators were measured?

How did you manage the risks / unforeseen circumstances?

What is in plan for the future?

Focus on continuation and sustainability

Talk about lessons learnt

Highlight how the results fit into the general EU policy

Page 6: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

WHY IS REPORTING IMPORTANT?

6

Last but not least!

Work on publishable summary

Think about style, include a photo or two, and highlight results

Spellcheck!

Prepare one Technical Final Report, but remember

ALL partners contribute to the final report (Financial Report):

encode actual costs

Page 7: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

DOs (1)

1st February: All partners to check access to the periodic reporting

Inform EASME/project coordinator immediately should you not receive a notification

+ contact [email protected] in case of problems

Page 8: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

DOs (2) Finalise the Continuous Reporting (Deliverables, Milestones before sending report) coordinator (Work Package leader)

Relationship data:

• In the Financial Statements: total amount for each beneficiary

• EASME provides the state of relationship data as encoded in the EYE IT tool on 1 February 2019. Please send the file back as Annex to your Technical Report and explain discrepancies between it and your financial statement (if any)

Conflicts/disagreements between partners and LIO: to be solved before report submission ( consortium agreement)

Page 9: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

DOs (3)

Make sure that both LEAR and PFSIGN are validated and appointed (e.g. after change in your organisation)

otherwise submission of report without that partner (or

delayed)

Respect both EYE funding ceilings:

75% of programme management costs

(direct personal costs, other direct costs, subcontracting, indirect costs)

+

up to 100% NE budget

Page 10: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

DOs (4)

• Unit costs for SME owners/natural beneficiaries without salary

• Possible Helpdesk interventions in case this category is not available (contact your PO)

• Declare the number of actual hours worked by the SME owner at the unit rate

Page 11: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

DONTs (1)

• Don't wait until the end of the submission deadline to gather data from partners

• Don't submit any supporting document unless explicitly asked to do so

• Don’t modify the templates provided

• Don't mix cost-categories

• Don't contact the EYE Support Office regarding Final Reporting

Page 12: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

FINAL REPORTING

12

• Technical Report

• Financial Report

Page 13: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

REPORTING – FINANCIAL DOCUMENTS

13

Final report

• Final technical report

• Final financial report, including:

• Individual financial statement (see annex 4)

• Explanation of the use of resources

• Final summary financial statement

• CFS (see annex 5), if applicable

Page 14: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

SOME DEFINITIONS TO BEGIN WITH

• Eligible costs

• What are not eligible costs

• Direct and indirect costs

• VAT

14

Page 15: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

• Costs actually incurred, identifiable and verifiable,

recorded in the accounts, etc.

• non-deductible VAT paid is also eligible Actual costs

• Not Applicable to your grant agreement Unit costs

• A percentage to be calculated on the direct costsFlat rate

• Not Applicable to your grant agreement

Lump sum

Forms of cost

15

Page 16: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

BUDGET CATEGORIES AND FORMS OF COSTS

Personnel Subcontracting

Financial

support to 3rd

parties

Other

Actual costs NA

Unit costs NA NA

Flat-rate

costs

Lump sum

costs NA

INDIRECT

COSTS

DIRECT COSTS SPECIFIC

CATETORIES

OF COSTS

FORMS OF

COSTS

BUDGET CATEGORIES

16

Page 17: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

EXAMPLES OF GENERAL ERRORS DETECTED IN EX-POST AUDITS

• Amounts claimed in financial statements do not reconcile with the costs incurred and booked in the accounting system

• Declaration of costs based on budget estimates instead of amounts spent

• Lack of supporting documents to substantiate costs(lack/incomplete timesheets, miscalculation of

hourly/daily/monthly rates, lack of supporting documents related to procurement procedures…)

• Costs incurred outside of eligibility period

• Miscalculations of costs

• Durable equipment not depreciated / purchase costs not reasonable / no link to project

17

Page 18: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

PERSONNEL COSTS

Page 19: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

PERSONNEL COSTS Errors identified during the ex-post audits

Lack of supporting documents

Lack of reconciliationbetween the

FS and accounting

records

Clericalerrors

Indirect costs

claimedas direct

costs

Unreliable time records

Differences in time units between

timesheets and FS

Ineligibleelements

included in the rate

Eligible elements

not included in the rate

Incorrect methodology

for calculating the rates

Incorrect calculation of

the annual productive

hours

Wrong classification

of costs

19

Page 20: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

ERRORS RELATED TO PERSONNEL COSTS

• Wrong calculation of annual productive hours

• Lack of timesheets (or other evidence) to record the time worked on the project

• Timesheets do not comply with the minimum requirements as set in Grant Agreement

• Hours claimed cannot be supported / impossible number of hours claimed

• Salary costs include ineligible elements or they do not include eligible elements

20

Page 21: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

ERRORS RELATED TO PERSONNEL COSTS

• Consultants or external staff costs are incorrectly declared as personnel costs

• Beneficiaries without personnel wrongly declare personnel costs

• Charging of 'billable hours' (commercial rate) instead of actual costs

• Criteria for in-house consultants not met

21

Page 22: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

1.Categories of personnel eligible under staff costs:

• Employees: Staff working for the beneficiary under a

written employment contract (or equivalent appointing act)

• Natural persons working under a direct contract with

the beneficiary other than an employment contract (in-

house consultants)

• Seconded by a third party against payment

22

Page 23: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

2. Categories of personnel to be considered assubcontracting:

• A person employed under a contract with a third intermediaryparty (e.g. interim action employment, consultancy company).

• Natural persons working under a direct contract with thebeneficiary other than an employment contract, if:

the contract fixes only a global remuneration (withoutspecifying time to be worked), the remuneration is based ondeliverables;

or when the eligibility criteria for being considered as in-houseconsultant under staff costs are not met

23

Page 24: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

3.Category of personnel to be considered as other

direct costs:

• Trainees, including the costs of their recruitment and

remuneration

Prior approval of EASME is necessary for being

claimed in the financial statement!

24

Page 25: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Components of the annual personnel costs for the

person

Must be limited to:

The gross salary stated on payroll

2. Social security contributions

3. Taxes included in the remuneration

Other costs included in the remuneration

(e.g. fee paid by the beneficiary for a complementary healthinsurance scheme for the employee, 13th month, complementfor hazardous work or night shifts, transportation allowance,lunch vouchers etc.)

25

Page 26: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Annual personnel costs

Annual productive hours

Actual Personnel Cost =

Hours worked for the project x Hourly rate

Hourly rate =

The hourly rate is to be calculated per financial year

If the financial year is not closed at the time of reporting,

the beneficiary must use the last closed financial year available.

Actual personnel costs: calculation

26

Page 27: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Three options for the annual productive days / hours

calculation

1. 1720 fixed hours: for persons working full time (pro rata forpersons working part time or working only part of the year forthe beneficiary)

2. Individual annual productive hours: total number of days/hoursworked by the persons in the year for the beneficiary

3. Standard number of annual hours generally applied by thebeneficiary for its personnel in accordance with its usual costaccounting practices.

The beneficiary has the possibility to change from one option to theother. Within the same financial year, the same option shouldapply.

27

Page 28: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Reporting period (example)

2017 2018 2019

01/10/2017 31/03/2019

Hourly rates of 2018 will also be used for these

months

ADVANTAGES FOR THE BENEFICIARIES

NO ADJUSTMENTS TO BE DECLARED IN THE NEXT PERIOD

LEGAL CERTAINTY: NO DOUBTS ABOUT WHAT PERIOD AND WHAT DATA MUST BE USED FOR THE CALCULATION

REMOVES ERRORS DUE TO INCORRECT CALCULATIONS FOR FRACTIONS OF A YEAR

Use of the last closed financial year

Actual personnel costs: Calculation

28

Page 29: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Example of calculation of individual annual productive hours:Dr Rossi -full-time project manager (working 8 hrs/day, from Mon-Fri). Hiscontract includes 22 working days of annual leave, plus 8 days of publicholidays. In the financial year covered by the reporting period, Dr Rossiworked 29 hrs of overtime and was on sick leave for 5 days.

• The individual annual workable hours are:

365 days- 104 days (Saturdays and Sundays)- 22 days (annual leave)- 8 days (public holidays) =

231 days

231 days x 8 hours per day = 1 848 hours• Individual annual productive hours for Dr. Rossi:

1 848 Annual workable hours+ 29 overtime (hours)- 40 annual sick leave (5 days x 8 hours)=

1837

• Individual annual productive hours for Dr Rossi = 1 837

29

Page 30: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Example for calculation of standard annual productive hours:According to employment contract Dr. Bianchi – full time project manager –works 8 hours/day, from Mon-Fri. National legislation provides for 22 workingdays annual leave+8 days of public holidays. The collective labour agreementadds 3 days of annual leave.Standard annual workable hours:365 days — 104 days (Saturdays and Sundays) — 22 days (annual leave) —8 days (public holidays) — 3 days (collective agreement) = 228 days x 8hours per day = 1824 hoursStandard annual productive hours :The Company uses its usual cost accounting to calculate hourly rates for EUactions.Annual workable days = 228 days minus- average annual sick leave (days) = 3- days of general training (days) = 4- other unproductive activities (days) = 9productive days = 212 days x 8 working hours per day = standard annualproductive hours = 1 696This number must be compared with 90 % of standard annual workable hours(1 824).90 % of 1824 = 1 6421 696 hours (usual cost accounting practice) > 1 642 hours (90 % annualworkable hours). The Beneficiary may apply its number of standard annualproductive hours (i.e. 1 696)30

Page 31: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Calculations of staff costs to be charged in the financial statements

• Hourly/daily/monthlyrate

Time unit charged to the action

(hourly/daily/monthly)x

31

Page 32: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Be careful!

• The rate must be calculated by financial year (i.e. for 12-month period reported in the annual accounts of theBeneficiary)

• The rate has to be based on full closed financial year.

• At the end of the reporting if the financial year is notclosed, data from the last full closed financial yearneeds to be used.

• The beneficiary has the possibility to change methodologyused for calculating the rates from one option to the other.Within the same financial year, they should apply thesame option.

32

Page 33: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Declaration on exclusive work for the action

OR

In most cases you will need to record hours spent on the project.Please do it at least on a monthly basis, and have your timesheetscountersigned by supervisor!

Time recording

Time sheets

33

Page 34: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Timesheets should include the following minimum information

1. Title and number of the action, as specified in the GA;

2. Beneficiary’s full name, as specified in the GA;

3. Full name, date and signature of the person working for

the action;

4. Counter-signature from supervisor’s or other

relevant person - Every timesheet needs to be

countersigned !

5. Number of hours worked for the action in the period

covered by the time record, with at least month level

granularity.34

Page 35: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Natural persons working under a direct contract

35

Page 36: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Most frequent errors in relation to natural persons working under a

direct contract as staff costs identified during the ex-post audits:

Lack of consultancy agreement

Lack of invoices

Natural persons

costs do not meet the 4 cumulative

criteria

Costs not recorded

in the accounting

system

Consultancycontract witha legal entity

36

Page 37: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Natural persons working under a direct contract

Cumulative conditions to be met for being considered eligible under staff costs:

1. There must be a direct contract between the natural person (individual) and thebeneficiary.

2. The person must work under the beneficiary's instructions and, unlessotherwise agreed with the beneficiary through a teleworking agreement, on thebeneficiary's premises.

3. The result of the work carried out must belong to the beneficiary.

4. The costs are not significantly different from those for personnel performingsimilar tasks under an employment contract with the beneficiary.

37

Page 38: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Natural persons working under a direct contract

For the monthly/daily/hourly rate, the beneficiary must use one of the following

options:

• if the contract specifies a monthly/daily/hourly rate: this rate must be used;

• if the contract states a fixed amount for the services of the natural person and

the number of hours to be worked: this global amount must be divided by the

number of months/days/hours to be worked for the beneficiary under that contract.

38

Page 39: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Natural persons working under a direct contract

• If the contract fixes only a global amount and does not specify thetime to be worked, the costs can NOT be declared as personnelcosts, but may be eligible as purchase of a service (see Article 9 ofthe GA) or a subcontract (see Article 10 of the GA), provided that thespecific eligibility conditions set out in Article 9 or 10 are met.

• Beneficiaries who are using this type of contract should notify EASMEand should request a budget transfer from personnel tosubcontracting cost categories, at the latest at the time of submission ofthe final report.

39

Page 40: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

PROCUREMENT

Page 41: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Errors related to procurement: purchase of goods, works and services,

subcontracting

• Lack of evidence that procurement procedure was sound (best valuefor money, transparency and equal treatment)

• Where competitive tendering was not used, this was not sufficientlydocumented and justified

• Participant's own normal practice not applied

• Sub/contracting to a related party (conflict of interest)

41

Page 42: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Subcontracting

Article 10.1 MGA

“The beneficiaries must award the subcontractsensuring the best value for money or, ifappropriate, the lowest price. In doing so, theymust avoid any conflict of interests”

42

Page 43: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Basic principles of procurement

• The beneficiary must provide evidence that theprinciple of best value for money, transparency andequal treatment has been respected when selecting thesuppliers.

• The beneficiary must avoid any conflict of interest whenawarding contracts.

• Public authorities need to follow national rules onprocurement, private entities their own rules andprocedures

• Compliance with the principles of procurement should beapplied in following costs categories:

Subcontracting

Equipment

Other goods and services43

Page 44: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Other direct costs

• Travel and subsistence

• Equipment

• Costs of other goods and services

44

Page 45: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Travel and subsistence

In the travel category, action related travels of staff assigned to the action should be claimed only.

Certain travel costs cannot be claimed under travel and subsistence costs category, but can be declared under other categories:

• Travel costs of subcontractors should be claimed under subcontracting;

• Travel costs of trainees should be claimed under other direct costs;

45

Page 46: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Equipment

• The depreciation cost of equipment, infrastructure or otherassets are eligible if:• they are purchased in compliance with the basic principle of

procurements• the assets are included in the asset register of the beneficiary• the depreciation is recorded in the beneficiary’s accounts and is

calculated in accordance with international accounting standardsand beneficiary’s usual accounting practices.

• The basis for depreciation = acquisition value (excluding VAT,eventually discounts received).

• Only portion of costs which corresponds to the duration of theaction and the rate of actual use for the purpose of the actioncan be charged to the project

46

Page 47: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Example of depreciation calculation

(A/B) x C x D

• A = period the asset was used by the Beneficiary

• B = estimated useful life (total period of depreciation)

• C = actual cost of equipment

• D = percentage of use for the purposes of the action

Example: Purchase of a computer at a cost of €6,000. Estimated useful life of 3 years. Installed on 01/01/2014.

Action runs from 01/01/2013 to 31/12/2015.

50% used for the purposes of the action.

Which depreciation cost should be charged to the action

47

Page 48: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Equipment

= (24/36) * 6000* 50%= (0.6667) * 3000= €2000 = eligible depreciation cost for the project

48

Page 49: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Equipment

The cost of renting or leasing equipment, infrastructureor other assets are also eligible, if:

• If they do not exceed the depreciation costs of similarequipment

• And do not include any financing fees

49

Page 50: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

BUDGET RE-ALLOCATION OR AMENDMENTS

Page 51: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Budget re-allocation or Amendment

Budget transfers and re-allocation

Amendment needed?

From one beneficiary to another NO

From one budget category to another NO

Transfer of budget with substantial change of Annex I – Description of the Action

YES

Transfers between forms of costs (actual costs, unit costs, etc.)

YES if no budget was foreseen for the "form" receiving the transfer

New subcontractsYES (strongly advised. Please check

with your PA)

51

Page 52: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Example of Budget transfer for a co-beneficiary

52

Total budget at Consortium level must remain as initially foreseen

Page 53: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

CALCULATION OF THE FINAL GRANT AMOUNT – 4 STEPS

53

This amount is calculated by the Agency in the following steps:

• Step 1 – Application of the reimbursement rate to the eligible costs

• Step 2 – Limit to the maximum grant amount

• Step 3 – Reduction due to the no-profit rule

• Step 4 – Reduction due to improper implementation or breach of other obligations

Requested EU Contribution = declared costs X Reimbursement rate %

Page 54: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

Useful links:

Cosme Funding Opportunities:

https://ec.europa.eu/easme/en/cosme-0

Reference documents

• Guidelines to financial reporting for Coordinators and Beneficiaries of the COSME Grant Agreements (2014-2020), February 2016.

54

Page 55: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

SPEAKERS

55

EASME Unit C.1 Finance

Sector C.1.5 COSME

Head of Sector – Cedric De Ridder

Senior Financial Officer – Paolo Roz

Financial Adviser – Simona Da Corta Fumei

EASME Unit A.1 COSME

Sector A.1.5 Competitiveness

Project Adviser – Alan Vella

Page 56: COSME Webinarec.europa.eu/easme/sites/easme-site/files/financial... · 2019-02-15 · According to employment contract Dr. Bianchi –full time project manager – works 8 hours/day,

QUESTIONS?

[email protected]

56

THANK YOU FOR YOUR ATTENTION