Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
July 2020Delfin Midstream- North American LNG export using FLNG
Corporate Presentation
Key Take-Aways
Fully permitted project with 13 MTPA export licence from Department of Energy
Lowest cost project and smallest FID increment (<550 $/tpa (all-in) for 3.5 MTPA)
FLNG design development with SHI and Black&Veatch on a full “LSTK EPC wrap” basis
No need for new pipelines - Re-purposing of offshore pipelines connecting into existing onshore grid
Leveraging low cost Asian shipyard fabrication and Export Credit support
Developing Upstream JVs and Downstream integrations (LNG-to-power, LNG bunkering, break-bulk)
Supported by strong and committed shareholders to fund the Delfin project to FID
Key differentiators: (A) Low cost, (B) Smaller scale, (C) Commercial flexibility, (D) Expansions
2
1
2
3
4
5
6
7
8
Capitalizing on two major Industry Revolutions
Shale RevolutionFloating LNG Revolution
>35 FSRUs have opened up
new markets and many new
import countries, importing 10-
15% of global LNG supply
7 FLNGs in operation or under
construction (supplying ~5%
of global LNG)
The Combination:
3
The LNG market is stuck with traditional models that do not address the world’s demand for low cost
flexible LNG to become a preferred fuel-of-choice over coal and liquids
▪ The Traditional Model is pursuing “Economies-of-Scale” with major projects of 10+ MTPA requiring many long-term offtake
contracts to underpin the financing
▪ The world markets need low-cost, flexible LNG supply and has limited capacity to underpin major conventional projects
▪ The Solution: Standardized Floating LNG allows the costs to be 20-40% cheaper with FID thresholds of just 2-2.5 MTPA
▪ Delfin LNG will consist of:
o Terminal with moorings for 4 FLNG Vessels located 50 miles offshore of
Cameron Parish, Louisiana
o Existing 42” UTOS (owned) and HIOS (long-term leased) subsea pipeline
systems re-purposed to transport gas from shore to the terminal
o Subsea pipeline end manifold, spur flowline to single-point, disconnectable
mooring system for FLNG Vessels
o Existing pipeline interconnects with several major onshore natural gas
pipelines, including onshore natural gas compression facility (owned)
▪ Delfin owns the intellectual property: environmental permits, export licenses,
completed FEED studies, right to operate FLNG vessels, marketing organization
▪ Delfin’s FLNG Vessels are based on the “offshore proven” Black & Veatch
PRICO liquefaction technology
▪ Delfin’s FLNG Vessels offer significant advantages over onshore liquefaction
facilities:
o Lower capital costs per ton for smaller FID threshold
o Shorter construction periods, reducing financing costs
o Lower environmental / community impact
o Mobility allowing for maximized economic value
▪ Each FLNG Vessel to be financed (debt and equity) at the project level with its
own commercial/financial structure
Gulf of Mexico Project Overview
4
Anchor project: Delfin LNG
UTOS
Pipeline(42”, 30 miles)
HIOS
Pipeline(42”, 21 miles)
WC 167
FLNGV1
FLNGV3
FLNGV2
FLNGV4
Grand ChenierPipeline
(30”)
FLNGV5
FLNGV6
Station 44 Grand Chenier
Station
WC 171
GoM Projects
Expansion project: Avocet LNG
Delfin Midstream owns a second pipeline system (Grand Chenier pipeline) which may
be developed for either:
▪ A second Deepwater Port (Avocet LNG) for an additional 2 FLNGV
▪ Increased feedgas supply to the Delfin DWP to enhance gas supply flexibility and
security or expand with additional FLNG Vessels at the Delfin Deepwater Port
Delfin LNG Avocet LNG
Key differentiators: Lower Costs & Faster FIDs
5
FLNG FID with 2.0-2.5 MTPA of Offtake compared to 10+ MTPA for land-based projects
Lower Unit Costs Lower Project Viability Thresholds Faster FIDs
Note: Delfin’s total costs are around 500-550 $/tpa and includes all costs up to start of commercial operations (incl. FLNG Vessel, disconnectable mooring system, pipeline connections, owner’s
costs, transit, installation, commissioning, contingencies), excl. finance costs, on a nameplate capacity basis
450
500
550
600
650
700
750
800
850
900
950
0 3 6 9 12 15 18 21 24 27 30
Tota
l Co
sts
($/t
on
) (n
am
ep
late
ba
sis)
LNG Nameplate Capacity (MTPA)
Delfin
FLNG Vessels
Lower Costs & Smaller Scale offer opportunities
6
450
500
550
600
650
700
750
800
850
900
950
0 3 6 9 12 15 18 21 24 27 30
Tota
l Co
sts
($/t
on
) (n
am
ep
late
ba
sis)
LNG Nameplate Capacity (MTPA)
Delfin
FLNG Vessels
▪ Delfin can offer a discount on a toll of 0.20 to 0.40
$/mmbtu (depending on term, credit and other details)
▪ Delfin can offer discounted rates for shorter terms of 15,
12 or even 10 years
▪ Delfin can offer enhanced flexible pricing. For example, a
flexible tolling structure with a floor of 1.70 $/mmbtu and a
ceiling of 2.40 $/mmbtu, fluctuating based on a an agreed
index (Brent, HH, JKM, etc)
▪ Intrinsic value of a floating asset enhances the viability for
shorter term contracts
▪ Successful marketing of the Delfin vessels will enable
Delfin to provide solid returns to its shareholders while
maintaining lowest competitive rates for its customers
Benefits of cost differences
▪ Each FLNG will have full commercial flexibility (toll / SPA / integrated, etc.)
▪ With firm, creditworthy offtake of 2.0 to 2.5 MTPA, which secures debt
financing, Delfin can take FID. Large projects need to secure many offtake
deals before FID is in sight providing uncertainty to the foundation Buyers.
▪ Delfin can offer equity participation to a buyer on the FLNG (at Project Level)
▪ Delfin can offer slot flexibility to customers that wish to maintain optionality on
their FID timing, i.e. a firm offtake agreement with optionality on FLNG slots
▪ A dedicated slot in a downstream value chain can link its FID to the
downstream FID (e.g. a large power plant can decide the FLNG FID)
▪ Allocating 250 mmscfd from upstream reserves to an integrated project is a
feasible option for many upstream producers and would already take 50% of
an FLNGV capacity, enabling more easily and Upstream integrated project
Benefits of FID threshold differences
800 $/tpa
550 $/tpa
3.5 MTPA 12+ MTPA
▪ Utilizing existing pipelines (i.e. Delfin LNG is partly “brownfield”)
▪ No need for new onshore pipelines
▪ Low cost Asian labor
▪ Standardization of generic liquefier FLNG technology
▪ Manufacturing-like construction process in shipyard
▪ Construction at existing yard which eliminates investments on sites
and utilities to enable plant fabrication
▪ LNG offloading is done in a side-by-side configuration, which
eliminates the need for long cryogenic pipelines and marine
infrastructure (i.e. the LNGC berth is an integral part of the FLNG)
How to achieve material cost savings?
Commercial Structuring – Maximum Flexibility
Financing of US Export Projects
▪ Financing is a key commercial constraint for each project
▪ US projects have been financed on the back of HH+ offtake
commitments with credit worthy offtakers.
Delfin is Uniquely Different
▪ FID in smaller increments at lower unit costs
▪ Build in an Asian shipyard to support vendor and Export Credit
Agency financing
▪ Flexible asset, which can be re-deployed (facilitate shorter
contracts, asset intrinsic value)
▪ Each FLNG Vessel can make FID independently, with it’s own
financing and commercial model
A) Traditional Toll or HH Indexed FOB (10-20 years)
Toll can be flexible and be partially indexed to LNG prices, Brent, or
indices or a mix
B) Integrated Upstream-Liquefaction Joint Venture
Reserves+FLNG vessel are in a JV that produces gas, transports gas
to the FLNG vessel and sells FOB LNG (on an index basis)
C) Strategic Partnerships (e.g. Traders/Producers)
Delfin and Partner Joint Venture with some balance sheet support
from Partner supporting debt financing
D) Integrated LNG-to-Power project
Delfin contributes a dedicated FLNG slot to an integrated value chain
development, creating full value chain alignment
E) LNG FOB to bunker / small-scale buyersBunkering and small-scale volumes sold on small parcel basis
Illustration of Delfin’s commercial optionality
UTOS Avocet
HIOS
FLNGV-1 FLNGV-2
FLNGV-3 FLNGV-4
FSRU
LNGC
Gas-to-Power
Gas distribution
LNG break-bulk
Upstream hydrocarbon reserves
Upstream IntegrationJV of upstream reserves with
a dedicated FLNGV slot
selling LNG on SPA basis
Downstream IntegrationJV of liquefaction and
downstream market
Toll / LNG SPA FOB(e.g. fixed, flexible, HH, Brent,
TTF, JKM, mixed, . . .)
LNG DES SPA(e.g. fixed, flexible,
HH, Brent, TTF, JKM,
mixed, . . .)
LNGC
LNG bunkering FOB
LNGC Bunker
7
Differentiation for Chinese / Korean players
LNG Offtake Financing FLNG ConstructionUpstream gas supply &
Gas Transportation
Delfin has mature FLNG Vessel solutions for construction in Korea and China
Delfin offers lowest cost US LNG, significant commercial flexibility and significant in-country contents to local LNG Buyers, marketing to established LNG buyers, regional gas companies and power companies
Delfin and Shipyards work jointly towards ECAs and debt financiers to secure favorable export credit support and export debt financing
Complete construction of the FLNG, topside module fabrication, integration, completion and pre-commissioning/commissioning in country
Additional opportunities are possible for E&P companies or gas/commodity trading to produce/ North American shale gas as feed gas supply for liquefaction onboard Delfin FLNG Vessel and structure the project as an integrated project
L N G F L N G
Shipyard Group Leasing Arms
Chinese / Koreans lenders
Export Credit Agencies
Export-Import banks
95% of the project CAPEX can be constructed in Asia
The big three Chinese Buyers
2nd tier Chinese Gas Companies
KOGAS
Korean GenCo’s / IPPs
Import Developers
Chinese Yard(s) & module fabricators
Samsung Heavy Industries
E&P Companies
Integrated O&G
8
9
Permitting Success
Major Milestones Accomplished
▪ DOE approval to export gas to Free Trade Agreement (“FTA”) countries
▪ Pre-filing work for Maritime Administration (“MARAD”) and Federal Energy Regulatory Commission (“FERC”) permits
▪ Formal submission of MARAD and FERC permits
▪ Receipt of MARAD determination that application was “complete”
▪ Successful modification of application for change in technical design
▪ Receipt of Draft Environmental Impact Statement (“DEIS”)
▪ Receipt of Final Environmental Impact Statement (“FEIS”)
▪ Receipt of Record of Decision (“ROD”)
▪ DOE approval to export gas to Non-Free Trade Agreement (“FTA”) countries
▪ FERC Order Received for Land-based infrastructure
Notable Reports / Ancillary Permits
▪ Application to Louisiana Department of Natural Resources
▪ Application to US Army Corps of Engineers
▪ Coastal Zone Management Consistency Certification for Louisiana
▪ Coastal Zone Management Consistency Certification for Texas
▪ US Environmental Protection Agency (“EPA”) Region 6 Permit
▪ Louisiana Department of Environmental Air Permit for onshore facilities
▪ Port Operations Manual
▪ Various modeling reports – air, noise, dispersion, spill consequence
▪ 12 resource reports for FERC Certificate of Public Convenience and Necessity
Successfully permitted the first FLNG project in North America
9
Permitting of Avocet and expansion projects in GOM will be short
and cost-efficient by leveraging the Delfin permitting work
Abundant Gas Supply and Transportation
Delfin is able to make FID in 0.5 BCF/day increments allowing for FID(s) without building new pipeline
10
Source: Company Information, EIA
▪ Delfin’s offshore pipelines connect directly into the
onshore pipeline grid with access to various basins
(Haynesville, Carthage, Perryville) as well as other
shale basins (SCOOP/STACK, Marcellus, etc.)
▪ Multiple options have been structured to secure
pipeline capacity for at least the first two FLNG
Vessels
▪ Pipeline capacities can be increased by adding
compression and/or reversals
▪ Detailed discussions ongoing with several different
pipeline and gas supply service companies for
commercial terms and Precedent Agreements
▪ Given the smaller capacity needed per FLNG
Vessel FID there is ample opportunity to utilize
existing, un-used pipeline capacities
Lake Charles
Port Arthur
Delfin
Deepwater Port
UTOS Avocet
HIOS
FLNG History & Outlook
First FIDs
FLNG Growth
Key Factors:
▪ Technical concepts
▪ Business Models
▪ Contract &
Execution Models
▪ Clients / partners /
stakeholders
20162007
Pioneering work
70’ies 80’ies 90’ies
Various proposal and studies
but with limited potential
▪ Production successfully kicked-off
▪ Developed as a reliable and robust production scheme
▪ Adopted and endorsed by key stakeholders(IOCs, NOCs, Independents, Buyers, Lenders, Insurers, etc.)
11
Hilli Episeyo
Tango
PFLNG-1
Prelude
In operation
FLNG is an Established Industry Technology
FLNG advantages offer great benefits for North American applications
▪ Liquefier FLNG Vessels offer significant lower costs and are proven in operation
▪ Large cost savings by re-purposing of existing offshore (obsolete) pipelines
▪ Bundling process facilities and marine terminal infrastructure
▪ Construction of the entire facility at existing Asian yard facilities in a controlled
environment, based on proven practices for construction, lowering costs and shortening
the execution schedule
▪ Enhanced control and supervision of costs and schedule in execution
▪ Minimal use of land and shore facilities
▪ Favorable financing support / credit enhancement
▪ Repeatability and standardization for subsequent vessels
▪ Redeployable
Delfin FLNGs are “Liquefiers” providing all-in costs of 500-550 $/ton(1)
Successful execution of FLNG Hilli Episeyo
From FID to COD in less than 4 years
✓ EPC schedule 41 months
✓ Total costs (into service) << 500 $/t (on
nameplate basis)
✓ 100% commercial availability since COD in
May 2018
Note:1: includes all costs up to start of commercial operations (incl. FLNG Vessel, disconnectable mooring system, pipeline connections, owner’s costs, transit, installation,
commissioning, contingencies), excl. finance costs, on a nameplate capacity basis
12
Petronas FLNG-1Malaysia
Shell Prelude FLNGAustralia
Exmar FLNG bargeYPF Argentina
(small-scale; costs > 500 $/t)
Golar Hilli Episeyo, Cameroon
Petronas FLNG-2Malaysia
ENI Coral FLNGMozambique
BPK / Golar GimiMauritania/Senegal
Wellstream producing FLNG Vessels
>> 1000 $/ton
Liquefier FLNG Vessels
< 500 $/t
“Liquefier” versus “Wellstream Producer”
Typical additional features
▪ Reservoir, well and subsea controls
▪ Multiple risers and umbilical system
▪ Flow assurance systems
▪ Inlet separation and treatment (water,
sand, impurities, liquids, etc.)
▪ Condensate / LPG separation, handling,
storage and offloading
▪ Additional utility and support systems
Delfin Liquefier FLNGReceives pipeline quality feedgas
Wellstream Producer = LNG FPSOProduces a raw wellstream from a reservoir(s)
Lower CAPEX & OPEX – Standardization – High
availability - Redeployable
Project/Field specific – additional complex process systems -
reservoir/well operations – higher CAPEX & OPEX
13
Delfin FLNG Vessel Designs
14
Common particulars for all the Delfin FLNG Vessel designs
▪ 2-train PRICO liquefaction technology with parallel drives per train
▪ Single train pre-treatment design (AGRU, Dehydration, Hg removal)
▪ Modularized topsides with air cooling for hull and topside systems
▪ Side-by-side offloading
▪ Offshore Classed and Flag with min. 25 years design life
A. Newbuild FLNG Vessel
▪ FEED to be completed Q3 2020
▪ LSTK EPCIC Term Sheet negotiated
▪ Consortium of Samsung and Black & Veatch responsible under a single contract for ”EPC wrap”,
with completion, schedule and performance guarantees satisfying project finance
B. Conversion FLNG Vessel
▪ Conversion of a modern Moss LNG carrier
▪ Lengthening of vessel with insertion of new midship section
▪ FEED completed and EPC bids received
▪ Cooperation with Chinese (or Singaporean) shipyards and Black & Veatch
C. Electric-driven Newbuild FLNG Barge (targeting an additional NA project)
▪ Newbuild barge
▪ Electric driven (Hydro-power supply from shore)
▪ Pre-FEED completed
▪ Cooperation with Consortium of Samsung and Black & Veatch
Offshore Installation, Ship-Shaped LNG Production and Storage Unit, POSMOOR, BIS, HELIDK (optional)
FLNG NewbuildingConsortium
LSTK EPCIC
3 FLNG designs developed based on the generic 2-train design
PRICO SMR – The right technology for FLNG
15
Why PRICO SMR?
▪ Well proven on onshore and floating applications
▪ Simple in operation (starting, stopping, re-starting, turn-down)
▪ Well managed technical risks
▪ Applied over a broad range of capacities & gas compositions
▪ Heavies removal integrated in the process
▪ One train = one module concept
▪ A compact system allows a ideal layout optimized with hull sizing
▪ Low topsides weight
▪ Considers environmental impact with air cooling and eliminating
emission issues
▪ Marinized technology
▪ Excellent track record for Performance Acceptance Tests
demonstrating Guaranteed Production and reliable offshore
production
▪ Proven offshore with low costs
▪ Proven offshore with very high availability
▪ Proven offshore with competitive execution schedule
▪ Proven offshore with highly competitive efficiency
▪ Proven offshore with short commissioning period
▪ Proven offshore for small footprint applications
▪ Proven offshore for Offshore Codes & Standards
Proven for Offshore FLNG applications
Exmar FLNG bargeYPF Argentina
(in operation)
Golar Hilli Episeyo, Cameroon(in operation)
BPK / Golar GimiMauritania/Senegal
(under construction)
OPEX and Efficiency
Liquefactionsystem
Gas turbine
WHRU Turbine GGeneral vessel
consumers
Direct-driven liquefaction and waste-heat recovery
▪ Offshore proven and efficient PRICO Single-Mixed
Refrigerant liquefaction technology (SMR also selected
by major onshore projects)
▪ Lifecycle cost and efficiency optimized design
▪ Mechanical drive of the refrigerant compressors by aero-
derivative gas turbines
▪ Inlet air chilling of the gas turbines to maximise the power
output
▪ Waste-heat recovery from the gas turbine exhausts is
used to provide process heating and to produce power for
topsides and hull consumers
▪ Direct air cooling of mixed refrigerant increases
production efficiency compared to a seawater-fresh-water
cooling system
Topside heat consumers
Delfin Liquefier FLNG▪ An FLNG is an integrated and efficient design that allows OPEX to be low (abt.
0.45 $/mmbtu on nameplate basis and less for multiple FLNGVs in operation)
and competitive to land-based facilities
▪ Delfin is in full control over the Delfin Deepwater Port allowing the Port service
costs to be well controlled (at-cost, no profit centre) and lower than for land-
based facilities (e.g. no pilotage, no inherent costs like dredging, at-cost port
fees)
▪ Being offshore allows a significant saving in time for visiting LNG carriers and
no risks of navigational delays and external factors (Pilot Unions, congestion
events, one-way-traffic, fog delays, Port fees)
IAC
World-class fuel efficiency and overall retainage performance
16
Delfin Deepwater Port Operations
▪ The Delfin Deepwater Port will operate as a Port under MARAD and U.S. Coast
Guard authority, with Port operation manuals and procedures as any other coastal
port
▪ Advantages of the Delfin Deepwater Port versus an onshore LNG terminal:
o Delfin is 100% owner and operator controlling Port services and fees at-cost (no
profit centre)
o High berth availability (1 berth per 3.5 MTPA) and >100 small-scale berth p.a.
for each FLNGV
o No congestion from shipping traffic or “one-way-traffic” rules – Delfin DWP is 40
nm offshore
o Less fog and fog related navigational restrictions compared to onshore LNG
plants
o No restrictions related to traffic delays, shoals or obstructions following a
hurricane
▪ Side-by-Side LNG carrier operations is a well-established practice with several
thousands performed between LNGC/FSRU and LNGC/FLNG as well as for small-
scale and bunkering applications
▪ LNG carriers will be assisted by tugs to berth alongside with Mooring Masters
assisting the LNGC captains
▪ The location is a benign location, with predominantly low and short waves
concurrent with wind directions, offering favorable SBS conditions
▪ The FLNGV is single-point moored using a disconnectable system and with
redundant heading-control thrusters
▪ The FLNGV can disconnect from the mooring and sail away on its own propulsion
to avoid any severe hurricane passing over the site
Deepwater Ports have proven operations for decades
with well defined regulatory governance
Standard procedures for navigation and
cargo operations at FLNG terminals
▪ Visiting LNG carriers tender Notice-Of-
Readiness
▪ Mooring Master/Pilot will board LNGC
▪ Tugs will connect aft and forward
▪ LNGC approaches FLNG on SB side
▪ Mooring lines are transferred
▪ LNGC berthing and moored
▪ Connection of Loading Arms
▪ Cargo transfer
▪ Disconnect loading arms
▪ Disconnect mooring and depart
17
Delfin Deepwater Port – A small-scale LNG hub
18
LNG export to nearby markets
using small-scale LNG carriers
(3,000-30,000 cbm)
LNG distribution for LNG bunkering and
other small-scale consumptions
Mexico
▪ Delfin is the owner and operator of the Delfin Deepwater Port (DWP) and therefore in full control of the operations, allowing for
supplemental small scale distribution of LNG from the facility
▪ The Delfin DWP will consist of 4 FLNG Vessels with a total of 13 MTPA export capacity
▪ Each vessel is fully equipped with a berth and offloading facilities (~3.5 MTPA / berth)
▪ The mooring, offloading, cargo and process systems are designed or can be amended to suit small-scale LNG carriers, with dedicated
berth facilities for full small-scale compatibility
▪ Given the high berth availability, benign metocean conditions and heading control capabilities each FLNGV can provide an efficient LNG
supply hub for small scale vessels
▪ A total of 200,000 – 400,000 MTPA of small-scale supply can well be incorporated in the production planning and ADP per FLNG Vessel
NOTE: For coastal redistribution or US bunker services Jones’ Act compliant vessels are expected to load from the FLNGV
Delfin Base Case & North American Expansion
19
Delfin LNG – 13 MTPA
(Anchor Project)
▪ Fully permitted as Deepwater Port with
MARAD/USCG and 13 MTPA DoE
Export Licence
▪ Completed conversion FLNG FEED
▪ Executing Newbuild FLNG FEED and
negotiating LSTK EPCIC contract
Avocet LNG+ – 14 MTPA
▪ Avocet 100% owned by DMI
▪ Permitting scoping work ongoing
▪ Opportunity to acquire adjacent
pipeline
▪ Evaluation for expansion / integration
with Delfin LNG project ongoing
Mexico LNG
▪ Opportunities for several FLNG
Vessels utilizing existing pipeline
capacities sourcing back to the US
▪ Opportunity to leverage existing
facilities and licences to enable a short
development timeline with limited
regulatory risks
West Canada LNG
▪ Development support work
▪ Front-end work executed
▪ LNG marketing activities
DMI has identified over 40 MTPA of liquefaction opportunities that have access to
operating or post-FID pipelines. All locations can use DMI’s existing FLNG design
South Texas – 7+ MTPA
▪ Pipeline screening ongoing
▪ Evaluation of gas supply options
▪ Pricing and commercial evaluations
▪ Preparing scoping work for permitting
work
Leveraging Technology Value from Delfin LNG
Delfin Liquefier FLNGReceives pipeline quality feedgas
20
West Canada FLNG Avocet FLNG Mexico FLNG SouthTexas FLNG
Generic Liquefiers with minor adjustments to suit location specific requirements
The Delfin FLNG Technology is a generic Liquefier for use across North America
“Variations-on-a-theme”
21
Clear path to the first FID and beyond
Permits & Licenses
▪ Ample capacity in US Gulf Coast to access liquid points in Louisiana
▪ No need to build large scale pipelines for at least the first and second FLNGV
▪ Precedent agreements and commercial terms negotiated for gas transport capacity to St.44
▪ Fully permitted facility including Non-FTA export permit for up 13 MTPA
▪ Newbuild FLNGV being designed in full compliance with existing permitting
▪ Pre-FEED completed, including LSTK EPCIC term sheet development with Samsung and Black&Veatch
▪ Newbuild FLNG FEED ongoing with completion in Q3
▪ Conversion FLNG FEED completed for Chinese/Singapore shipyard cooperation
▪ Agreement with KDB as FA and structurer to secure K-Sure and KEXIM support
▪ Exploring vendor/yard financing schemes
▪ Financial structuring support from GS
▪ Detailed offtake discussions with multiple buyers (IOC, portfolio, Traders, Utilities)
▪ Increasing Asian interest from 2nd tier consumers in the power and small-scale LNG business
▪ Strong interest for the commercial flexibility from Delfin being “smaller at lower cost”
▪ Total all-in CAPEX estimated to be less than $2 billion on the basis of a full LSTK EPCIC wrap
▪ Significant interest in project level equity from Mezzanine and Preferred Equity providers
FEED & EPC
Pipeline Access
Debt Financing
Equity Financing
Offtake
Expansion▪ Development support for a West Canada project, executed front-end work
▪ Avocet development planning in progress
▪ Downstream expansion with small-scale, bunkering and gas-to-power opportunities
Success Factors Progress achieved
July 2020END
Corporate Presentation