52
SEABRIDGE GOLD Corporate Presentation April 2018

Corporate Presentation January 2018 - Seabridge Goldseabridgegold.net/pdf/corp_pres.pdf · SEABRIDGE GOLD. Forward Looking Statements. All reserve and resource estimates reported

Embed Size (px)

Citation preview

  • SEABRIDGE GOLD

    Corporate PresentationApril 2018

  • SEABRIDGE GOLD

    Forward Looking Statements

    All reserve and resource estimates reported by the Company were calculated in accordance with the Canadian National Instrument 43-101 and the Canadian Institute of Mining and Metallurgy Classification system. These standards differ significantly from the requirements of the U.S. Securities and Exchange Commission. Mineral resources which are not mineral reserves do not have demonstrated economic viability.

    Statements relating to the estimated or expected future production and operating results and costs and financial condition ofSeabridge, planned work at the Companys projects and the expected results of such work are forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by words such as the following: expects, plans, anticipates, believes, intends, estimates, projects, assumes, potential and similar expressions. Forward-looking statements also include reference to events or conditions that will, would, may, could or should occur. Information concerning exploration results and mineral reserve and resource estimates may also be deemed to be forward-looking statements, as it constitutes a prediction of what might be found to be present when and if a project is actually developed. These forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable at the time they are made, are inherently subject to a variety of risks and uncertainties which could cause actual events or results to differ materially from those reflected in the forward-looking statements, including, without limitation: uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from logistical, technical or other factors; the possibility that results of work will not fulfill projections/expectations and realize the perceived potential of the Companys projects; uncertainties involved in the interpretation of drilling results and other tests and the estimation of gold reserves and resources; risk of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of environmental issues at the Companys projects; the possibility of cost overruns or unanticipated expenses in work programs; theneed to obtain permits and comply with environmental laws and regulations and other government requirements; fluctuations in the price of gold and other risks and uncertainties, including those described in the Companys Annual Information Form filed with SEDAR in Canada (available at www.sedar.com) for the year ended December 31, 2017 and in the Companys Annual Report Form 40-F filed with the U.S. Securities and Exchange Commission on EDGAR (available at www.sec.gov/edgar.shtml).

    Forward-looking statements are based on the beliefs, estimates and opinions of the Companys management or its independent professional consultants on the date the statements are made.

    2

  • SEABRIDGE GOLD

    The Case for Seabridge

    KSM: 38.8M oz gold plus 10.2B lbs copper (2.2B tonnes at 0.55 gpt Au and 0.21% Cu)

    Courageous Lake: 6.5M oz gold (91M tonnes at 2.2 gpt Au)Proven and Probable

    Reserves

    58.3M shares outstanding Low Share Dilution

    $14 Enterprise Value per oz of gold reservesLow Valuation

    All reserves are located in Canada KSM is shovel ready; Environmental Assessment completedLow Political Risk

    Recent resource additions and new discoveries could add significant higher grade reserves to improve project economicsExploration Upside

    Iskut B.C.: District scale with high-grade epithermal gold potential Snowstorm Nevada: On the intersection of 3 major gold trendsNew Acquisitions

    3

  • SEABRIDGE GOLD

    Gold ReservesReserves rank Seabridge among worlds top ten gold companies

    4

    Source: Company data. Data as of March 31, 2018. Note: Companies shown include North Americas largest gold companies and selected gold project development companies.

    -

    15

    30

    45

    60

    75

    New

    mon

    t

    Poly

    us

    Barr

    ick

    New

    cres

    t

    Gol

    dcor

    p

    Angl

    ogol

    d

    Seab

    ridge

    Kinr

    oss

    Agni

    co-E

    agle

    Nov

    aGol

    d

    Poly

    met

    al

    Det

    our

    New

    Gol

    d

    Yam

    ana

    Alam

    os

    Pret

    ium

    Buen

    aven

    tura

    45M oz

    Gol

    d R

    eser

    ves

    (m o

    z)

  • SEABRIDGE GOLD

    Seabridge Designed to Provide Leverage to Gold

    5

    Seabridge ranks 1st in reserves/share among leading gold companies

    Source: Company data. Data as of March 31, 2018.Note: Companies shown include North Americas largest gold companies and selected gold project development companies.

    -

    0.20

    0.40

    0.60

    0.80

    Seab

    ridge

    Poly

    us

    New

    mon

    t

    Angl

    ogol

    d

    Det

    our

    Agni

    co-E

    agle

    New

    cres

    t

    Gol

    dcor

    p

    Nov

    aGol

    d

    Barr

    ick

    Pret

    ium

    Poly

    met

    al

    New

    Gol

    d

    Alam

    os

    Kinr

    oss

    Yam

    ana

    Buen

    aven

    tura

    0.78 Reserve oz/share

    Gol

    d R

    eser

    ves

    per C

    omm

    on S

    hare

  • SEABRIDGE GOLD

    Seabridge Designed to Provide Leverage to Gold (cont.)

    6

    Source: Company data. Data as of March 31, 2018.Note: Companies shown include North Americas largest gold companies and selected gold project development companies. Averages exclude Seabridge.

    Gold reserves/share equates to value/share that competitors cannot match

    -

    10x

    20x

    30x

    40x

    50x

    60x

    -

    $200

    $400

    $600

    $800

    $1,000

    $1,200

    Seab

    ridge

    Poly

    us

    New

    mon

    t

    Angl

    ogol

    d

    Det

    our

    Agni

    co-E

    agle

    New

    cres

    t

    Gol

    dcor

    p

    Nov

    aGol

    d

    Barr

    ick

    Pret

    ium

    Poly

    met

    al

    New

    Gol

    d

    Alam

    os

    Kinr

    oss

    Yam

    ana

    Buen

    aven

    tura

    Spot

    Gol

    d Va

    lue

    per C

    omm

    on S

    hare

    Ratio to Seabridge

    $1,028

    Spot Gold Value per Common Share Average: $114

    Ratio to Seabridge Average: 20x

  • SEABRIDGE GOLD

    Seabridge Designed to Provide Leverage to Gold (cont.)

    7

    Source: Company data. Data as of March 31, 2018.Note: Companies shown include North Americas largest gold companies and selected gold project development companies. Averages exclude Seabridge. Ratio of In-Situ Value per Share is calculated as: (Share Price) / [((Spot Gold Price) * (Gold 2P Ounces)) / (Basic Shares Outstanding)]

    Significant Upside Potential From In-Situ Value of Reserves

    -

    10x

    20x

    30x

    40x

    50x

    60x

    70x

    80x

    90x

    -

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    Seab

    ridge

    Nov

    aGol

    d

    Angl

    ogol

    d

    Det

    our

    New

    Gol

    d

    Pret

    ium

    Poly

    us

    Kinr

    oss

    New

    cres

    t

    Yam

    ana

    Alam

    os

    Gol

    dcor

    p

    Barr

    ick

    Poly

    met

    al

    New

    mon

    t

    Agni

    co-E

    agle

    Buen

    aven

    tura

    Shar

    e Pr

    ice

    / In-

    Situ

    Val

    ue p

    er S

    hare

    Ratio to Seabridge

    1.05%

    Spot Gold Value per Common Share Average: 18%

    Ratio to Seabridge Average: 17x

  • SEABRIDGE GOLD

    Share Dilution Matters!

    8

    Source: Company data. Data as of March 31, 2018. Note: For a breakdown of Seabridges mineral reserves and resources by project, tonnes and grade, please visit http://seabridgegold.net/resources.php

    Reserves and Resources continue to grow faster than shares outstanding

    -

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    -

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

    Shares Outstanding (M

    illions)O

    unce

    s of

    Gol

    d (M

    illion

    s)

    Proven & Probable Gold Reserves Measured & Indicated Gold Resources Inferred Gold Resources Shares Outstanding

  • SEABRIDGE GOLD

    Historical Performance

    9

    Source: Company and index dataNote: Price Performance represents performance over time from January 2000 through March 2018.

    (100%)

    400%

    900%

    1,400%

    1,900%

    2,400%

    2,900%

    3,400%

    3,900%

    4,400%

    4,900%

    5,400%

    5,900%

    6,400%

    00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 1718Seabridge Newmont Barrick Goldcorp HUI Gold

    In a rising gold market, Seabridge is a stock to own

    Price Performance: +1,897% +367%+481% +166%(24%)+92%

  • SEABRIDGE GOLD

    Attractive Valuation

    10

    Source: Company data. Data as of March 31, 2018.(1) Enterprise Value calculated as market capitalization (basic) plus net debt and minority interestNote: Companies shown include North Americas largest gold companies and selected gold project development companies

    Seabridge has a very low enterprise value per oz of gold reserves

    -

    $50

    $100

    $150

    $200

    $250

    $300

    $350Po

    lym

    etal

    New

    mon

    t

    Barr

    ick

    Yam

    ana

    Gol

    dcor

    p

    Pret

    ium

    Kinr

    oss

    New

    cres

    t

    Poly

    us

    Alam

    os

    New

    Gol

    d

    Det

    our

    Angl

    ogol

    d

    Nov

    aGol

    d

    Seab

    ridge

    Ente

    rpris

    e Va

    lue

    per R

    eser

    ve o

    z

    $14/oz

  • SEABRIDGE GOLD

    Low Political Risk

    Illegal strikes and local opposition delay approved projects (Conga, Santa Anna, Tintaya)Peru

    Open pit mining and use of cyanide banned in certain areas 100% tax on export earnings for some resource projects (Famatina, San Jose)Argentina

    Increased taxes and royalties (Fruta del Norte)Ecuador

    Creeping expropriation through imposed local and government ownership(Batu Hijau, Grasberg, Tujuh Bukit)Indonesia

    Increased royalty structure and challenging power supply issues (all projects) Local opposition delays approved projects (El Morro, Pascua-Lama)Chile Stable regulatory and tax regime Established, reliable procedures for obtaining permits include deadlines for

    government agenciesCanada

    11

    Where would you rather be?

  • SEABRIDGE GOLD

    KSM Project, British Columbia, Canada KSM is the worlds largest undeveloped

    gold/copper project (by reserves) Located in mining friendly British

    Columbia near past producers Highly favorable logistics Estimated cash costs and total costs

    well below current industry averages Base Case exhibits outstanding

    capital efficiency BC Environmental Assessment

    approved July 30, 2014. Federal approval received December 2014

    Signed Benefit Agreement with key Treaty Nation

    Newly added Deep Kerr and Lower Iron Cap deposits add significant upside potential

    12

  • SEABRIDGE GOLD

    KSM Approved by BC and Canada

    13

  • SEABRIDGE GOLD

    KSM Favorable Logistics

    14

  • SEABRIDGE GOLD

    KSM Mitchell Zone

    15

  • SEABRIDGE GOLD

    KSM Proven and Probable Reserves

    16

    Note: Reserves were calculated using $1200 gold, $2.70 copper and $17.50 silver

    Zone Mining MethodReserve Category

    Millions Tonnes

    Average Grades Contained Metal

    Gold (gpT)

    Copper (%)

    Silver (gpT)

    Gold (million ounces)

    Copper (million pounds)

    Silver (million ounces)

    MitchellOpen Pit

    Proven 460 0.68 0.17 3.1 10.1 1,767 45

    Probable 481 0.63 0.16 2.9 9.7 1,677 44

    Block Cave Probable 453 0.53 0.17 3.5 7.7 1,648 51

    Iron Cap Block Cave Probable 224 0.49 0.20 3.6 3.5 983 26

    Sulphurets Open Pit Probable 304 0.59 0.22 0.8 5.8 1,495 8

    Kerr Open Pit Probable 276 0.22 0.43 1.0 2.0 2,586 9

    Totals

    Proven 460 0.68 0.17 3.1 10.1 1,767 45

    Probable 1,738 0.51 0.22 2.5 28.7 8,388 138

    Total 2,198 0.55 0.21 2.6 38.8 10,155 183

  • SEABRIDGE GOLD

    KSM 2016 Preliminary Feasibility Study

    17

    The PFS projects a large, long-life mine

    Unit Years 1-7 LOM 53-Year Plan Average Grades:Gold gpt 0.82 0.55Copper % 0.24 0.21Silver gpt 2.8 2.6Molybdenum ppm 48 43

    Average Annual Production:Gold oz 933,000 540,000Copper M lbs 205 156Silver M oz 2.6 2.2Molybdenum M lbs 1.6 1.2

    Note: Numbers above have been rounded.

  • SEABRIDGE GOLD

    2016 PFS: Before Tax Economic Analysis

    18

    Note: For Operating and Total Costs, copper, silver and molybdenum revenues are taken as a by-product credits. Total Costs include all Initial Capital, Sustaining Capital and Closure Costs. Numbers above have been rounded.

    Case Unit Base Alternate Q3 2016 Spot

    Initial Capital Cost $M $5,000 $5,000 $4,800

    Net Cash Flow $M $15,900 $26,300 $16,100

    NPV @ 5% $M $3,300 $6,500 $3,500

    Internal Rate of Return % 10.4% 14.6% 11.1%

    Payback Period years 6.0 4.1 5.6

    Operating Costs (LOM) $/oz Au $277 $183 $404

    Total Costs (includes all capital) $/oz Au $673 $580 $787

    Metal Prices:

    Gold $/oz $1,230 $1,500 $1,350

    Copper $/lb $2.75 $3.00 $2.20

    Silver $/oz $17.75 $25.00 $20.00

    Molybdenum $/oz $8.49 $10.00 $7.00

    US$/Cdn$ Exchange Rate - 0.80 0.80 0.77

  • SEABRIDGE GOLD

    2016 PFS: After Tax Economic Analysis

    19

    Note: Taxes include B.C. Mineral Tax plus Canadian Federal and B.C. Corporate Income Taxes. Numbers above have been rounded.

    Case Unit Base Alternate Q3 2016 Spot

    Initial Capital Cost $M $5,000 $5,000 $4,800

    Net Cash Flow $M $10,000 $16,700 $10,100

    NPV @ 5% $M $1,500 $3,700 $1,700

    Internal Rate of Return % 8.0% 11.4% 8.5%

    Payback Period years 6.8 4.9 6.4

    Metal Prices:

    Gold $/oz $1,230 $1,500 $1,350Copper $/lb $2.75 $3.00 $2.20Silver $/oz $17.75 $25.00 $20.00Molybdenum $/lb $8.49 $10.00 $7.00

    US$/Cdn$ Exchange Rate 0.80 0.80 0.77

  • SEABRIDGE GOLD

    Deep Kerr core zone found in 2013 now contains 2.0 billion tonne inferred resource grading 0.41% copper and 0.31 g/T gold

    New inferred resource at Iron Cap zone estimated at 1.3 billion tonnes at 0.48 g/T gold and 0.30% copper

    Additions to KSM resources since 2013 total 36.5 million ounces of gold and 25.2 billion pounds of copper at grades significantly higher than existing reserves

    Deep Kerrs grades and size compare favorably with some of the worlds largest, most profitable, operating copper/gold mines

    New PEA demonstrates significant economic improvements to KSM from Deep Kerr higher-grade resources

    Economic improvements from Iron Cap additions still to come

    New Discoveries at Grades Higher Than Reserves

    20

  • 2000m Elev.

    -2000m Elev.

    4000m Elev.

    CAVE MODELS

    2000m

    KSM PROJECTLONG SECTION

    2016 NSR BLOCK MODEL

    S N

    > $ 48

    24-48

    16-24

    NSR $/T

    PIT MODELS

    Proposed Exploration Aditprojected to section000m Elev.

    Proposed Access Tunnelprojected to section

    IRON CAP

    MITCHELLSULPHURETSKERR

    21

  • SEABRIDGE GOLD

    PEA Mine Plan Reduces Waste by 2.4 Billion Tonnes

    22

    Note: Mine plans were constructed using $1200 gold, $2.70 copper and $17.50 silver

    Zone Mining MethodResource Category

    Millions Tonnes

    Average Grades Contained Metal

    Gold (gpT)

    Copper (%)

    Silver (gpT)

    Gold (million ounces)

    Copper (million pounds)

    Silver (million ounces)

    MitchellOpen Pit

    M&I 418 0.78 0.20 2.9 10.4 1,783 40Inferred 12 0.47 0.20 5.2 0.2 50 2

    Block CaveM&I 606 0.66 0.20 4.1 12.9 2,726 81

    Inferred 87 0.40 0.13 3.1 1.1 259 9

    Iron Cap Block CaveIndicated 122 0.64 0.24 4.1 2.5 643 16Inferred 77 0.46 0.22 3.5 1.1 384 9

    Sulphurets Open PitIndicated 92 0.70 0.29 0.6 2.1 584 2Inferred 11 0.59 0.25 0.8 0.2 60 0

    Kerr Block CaveIndicated 24 0.26 0.54 1.1 0.2 290 1Inferred 932 0.31 0.49 1.7 9.3 9,962 52

    TotalsM&I 1,262 0.69 0.22 3.4 28.0 6,026 139

    Inferred 1,119 0.33 0.43 2.0 12.0 10,716 72

  • SEABRIDGE GOLD

    KSM 2016 Preliminary Economic Assessment

    23

    The PEA incorporates Deep Kerr and Lower Iron Cap with170k tpd throughput capacity

    Unit Years 1-7 LOM 51-Year Plan Average Grades:Gold gpt 0.78 0.52Copper % 0.26 0.32Silver gpt 2.7 2.7

    Average Annual Production:Gold oz 1,150,000 592,000Copper M lbs 307 286Silver M oz 3.3 2.8

    Note: As the PEA is preliminary in nature, it includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Numbers above have been rounded.

  • SEABRIDGE GOLD

    2016 PEA: Before Tax Economic Analysis

    24

    Note: For Operating and Total Costs, copper and silver revenues are taken as a by-product credits. Total Costs include all Initial Capital, Sustaining Capital and Closure Costs. As the PEA is preliminary in nature, it includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Numbers above have been rounded.

    Case Unit Base Alternate Q3 2016 Spot

    Initial Capital Cost $M $5,500 $5,500 $5,300

    Net Cash Flow $M $26,300 $38,700 $24,100

    NPV @ 5% $M $6,100 $10,200 $5,700

    Internal Rate of Return % 12.7% 16.9% 12.9%

    Payback Period years 5.6 3.9 5.3

    Operating Costs (LOM) $/oz Au -$179 -$319 $32

    Total Costs (includes all capital) $/oz Au $358 $218 $553

    Metal Prices:

    Gold $/oz $1,230 $1,500 $1,350

    Copper $/lb $2.75 $3.00 $2.20

    Silver $/oz $17.75 $25.00 $20.00

    US$/Cdn$ Exchange Rate 0.80 0.80 0.77

  • SEABRIDGE GOLD

    2016 PEA: After Tax Economic Analysis

    25

    Note: Taxes include B.C. Mineral Tax plus Canadian Federal and B.C. Corporate Income Taxes. As the PEA is preliminary in nature, it includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Numbers above have been rounded.

    Case Unit Base Alternate Q3 2016 Spot

    Initial Capital Cost $M $5,500 $5,500 $5,300

    Net Cash Flow $M $16,700 $24,700 $15,300

    NPV @ 5% $M $3,400 $6,000 $3,200

    Internal Rate of Return % 10.0% 13.4% 10.1%

    Payback Period years 6.4 4.7 6.1

    Metal Prices:

    Gold $/oz $1,230 $1,500 $1,350Copper $/lb $2.75 $3.00 $2.20Silver $/oz $17.75 $25.00 $20.00

    US$/Cdn$ Exchange Rate 0.80 0.80 0.77

  • SEABRIDGE GOLD 27

  • IRON CAP PERSPECTIVE VIEW TO SW2018 NSR BLOCK MODEL ON SECTIONS

    North Area2017 Drilling

    NSR $/T> 75

    50 7525 5016 - 25

    555m El. ConceptualCave Footprint

    1200m El. ConceptualCave Footprint

    870m El. ConceptualCave Footprint

    ProposedAccess

    Tunnels

    IndicatedResource

  • SEABRIDGE GOLD 29

    New Iron Cap Resources to Further Improve Economics

    NSR Cutoff

    (C$)

    Resource Category

    Tonnes (millions)

    Average Grades Contained Metal

    Gold (gpt)

    Copper (%)

    Silver (gpt)

    Moly (ppm)

    Gold (000

    ounces)

    Copper (million pounds)

    Silver (000

    ounces)

    Moly (million pounds)

    16 Indicated 370 0.43 0.23 4.2 48 5,112 1,874 49,931 48 Inferred 1,297 0.48 0.30 2.9 34 20,023 8,579 120,970 34

    20 Indicated 298 0.49 0.24 4.4 50 4,688 1,574 42,095 50 Inferred 1,098 0.52 0.32 3.0 33 18,364 7,747 105,948 33

    24 Indicated 227 0.55 0.26 4.5 46 4,007 1,299 32,785 46 Inferred 875 0.58 0.35 3.0 32 16,318 6,751 84,405 32

    28 Indicated 166 0.62 0.27 4.7 35 3,302 986 25,029 35 Inferred 670 0.65 0.39 3.0 29 13,999 5,758 64,608 29

    32 Indicated 118 0.70 0.29 4.6 26 2,666 757 17,519 26 Inferred 517 0.73 0.42 3.0 27 12,131 4,784 49,851 31

    NSR Cutoff (C$)

    Resource Category

    Tonnes (millions)

    Average Grades

    Contained Metal

    Gold (gpt)

    Copper

    (%)

    Silver

    (gpt)

    Moly

    (ppm)

    Gold

    (000

    ounces)

    Copper

    (million

    pounds)

    Silver

    (000

    ounces)

    Moly

    (million

    pounds)

    16

    Indicated

    370

    0.43

    0.23

    4.2

    48

    5,112

    1,874

    49,931

    48

    Inferred

    1,297

    0.48

    0.30

    2.9

    34

    20,023

    8,579

    120,970

    34

    20

    Indicated

    298

    0.49

    0.24

    4.4

    50

    4,688

    1,574

    42,095

    50

    Inferred

    1,098

    0.52

    0.32

    3.0

    33

    18,364

    7,747

    105,948

    33

    24

    Indicated

    227

    0.55

    0.26

    4.5

    46

    4,007

    1,299

    32,785

    46

    Inferred

    875

    0.58

    0.35

    3.0

    32

    16,318

    6,751

    84,405

    32

    28

    Indicated

    166

    0.62

    0.27

    4.7

    35

    3,302

    986

    25,029

    35

    Inferred

    670

    0.65

    0.39

    3.0

    29

    13,999

    5,758

    64,608

    29

    32

    Indicated

    118

    0.70

    0.29

    4.6

    26

    2,666

    757

    17,519

    26

    Inferred

    517

    0.73

    0.42

    3.0

    27

    12,131

    4,784

    49,851

    31

  • IRON CAP SECTION VIEW TO NE2018 NSR BLOCK MODEL

    500m

    North Area2017 Drilling

    555m El. Conceptual Cave

    1200m El. Conceptual Cave

    870m El. Conceptual CaveProposedAccess

    Tunnels

    Mineralizationis open downplunge to NW

    NSR $/T> 75

    50 7525 5016 2512 168 124 80 - 4

    Limits of Inferred Resource

  • SEABRIDGE GOLD

    Courageous Lake

    At 6.5M oz, (91 million tonnes at 2.2 gpT Au) Courageous Lake (CL) is Canadas 2nd largest undeveloped gold reserve (KSM is 1st)

    Excellent open pit grade of 2.2 gpt Au

    2012 Preliminary Feasibility Study shows viable project with exceptional leverage to higher gold prices

    Wholly owned 53 km greenstone belt provides excellent exploration potential

    Located in Northwest Territories within 100 km of Diavik and Ekati, two large operating open pit diamond mines

    31

  • SEABRIDGE GOLD

    Courageous Lake Project Location

    Project located on winter ice road, in close proximity to the Diavik and Ekati mines Demonstrating that year round

    open pit bulk tonnage operations are feasible

    Nearby mines provide real-time estimates for capital and operating costs Additionally, with mines scheduled

    to close over the next several years, a local and trained workforce will be readily available

    32

  • SEABRIDGE GOLD

    Courageous Lake PFS Pre-Tax Summary

    33

    Exceptional leverage to gold price

    Case Unit Base Alternate

    Gold Price $/oz $1,384 $1,925

    Initial Capital Cost $M $1,520 $1,520

    Mine Life years 15.0 15.0

    Average Annual Gold Production ounces 385,000 385,000

    Net Cash Flow $M $1,507 $4,519

    NPV @ 5% $M $303 $2,080

    Internal Rate of Return % 7.3% 18.7%

    Payback Period years 11.2 4.0

    Operating Costs (years 1-5) $/oz Au $674 $689

    Operating Costs (LOM) $/oz Au $780 $796

    Total Costs (includes all capital) $/oz Au $1,123 $1,141

    US$/Cdn$ Exchange Rate - 0.98x 0.99x

  • SEABRIDGE GOLD

    Courageous Lake PFS After Tax Summary

    34

    Exceptional leverage to gold price

    Note: Taxes include all Provincial taxes plus Federal Corporate Income Tax.

  • SEABRIDGE GOLD

    CL Value Enhancing Opportunities

    Access to hydro-electric generated power Examine year round road access

    opportunities

    Improve Capital and Operating

    Costs

    Exploring for higher grade material that could be exploited in the early years of production

    History of high grade production along belt

    Higher Grades

    Exploring for additional bulk mineable deposits that could extend project life beyond the current 15 year estimate

    Additional Deposits

    35

  • SEABRIDGE GOLD

    Courageous Lake Exploration Potential

    Existing 6.5M oz reserve (91 million tonnes at 2.2 gpT Au) covers only2 km of an under explored green-stone belt that stretches 53 km Owned 100% by Seabridge

    Two former producing mines on belt (Salmita and Tundra) had average grades of ~1 opt Au (30 gpt)

    Seabridge now exploring for additional deposits that could extend the estimated 15 year mine life With potentially higher grades

    mined in early years

    36

  • SEABRIDGE GOLD

    Walsh Lake Resources (March 2014)

    37

    Approximately twice the grade of Courageous Lakes reserves

    Note: Mineral resources which are not mineral reserves do not have demonstrated economic viability. Inferred mineral resources have a high degree of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred resource will ever be upgraded to a higher category.

    Walsh Lake Inferred Resource

    Cut-Off Gold

    Grade Tonnes Grade Inferred (g/T) (K) g/t (K oz)

    0.20 6,647 2.37 506

    0.30 5,987 2.60 500

    0.40 5,477 2.81 495

    0.40 5,022 3.03 489

    0.60 4,624 3.24 482 0.70 4,278 3.45 475

    0.80 3,986 3.65 468

    0.90 3,727 3.84 460

    1.00 3,512 4.02 454

  • SEABRIDGE GOLD

    Courageous Lake 2018 Drilling Targets

    38

  • SEABRIDGE GOLD

    In June 2016 Seabridge issued 695,000 shares to acquire 100% of SnipGold to obtain 100% of very large Iskut Project

    Iskut Project reports 2.2 million ounces of NI 43-101 measured and indicated gold resources at the Bronson Slope prospect

    Iskut historically produced high-grade gold and hosts many unexplored targets for high-grade material

    Iskut is located 30 kilometers from KSM, offering optimal synergies for Seabridge knowledge and infrastructure.

    2017 exploration program now underway to test Quartz Rise high-grade target

    SnipGold Acquisition

    39

  • SEABRIDGE GOLD

    Iskut Location and Access

    40

  • 41

  • SEABRIDGE GOLD

    In June, 2017 Seabridge acquired 100% of the Snowstorm gold project in Nevada from Paulson & Co. for 700,000 common shares plus 500,000 common share purchase warrants

    Snowstorm sits on the intersection of three major Nevada gold belts; Getchell, Carlin and the Northern Nevada Rift Zone

    Geologic, geochem and geophysical data documents hydrothermal alteration zones and structural settings consistent with large Nevada gold deposits

    Snowstorm is contiguous and on strike with several large producing gold projects including Getchell/Turquoise Ridge, Twin Creeks and Midas

    Annual holding costs less than US$300,000

    Snowstorm Acquisition

    42

  • SEABRIDGE GOLD

    Snowstorm Location

    43

  • SEABRIDGE GOLD

    Seabridges Newest Shareholder

    44

    Seabridge Acquires Snowstorm Project June 2017

    "We chose Seabridge as the best home for the Snowstorm project because they share our vision of the projects geologic potential and their exploration team has done an outstanding job of growing the resources and reserves on their existing projects. Moreover, Seabridges projects, particularly KSM, will provide us with significant leverage to a higher gold price

    - John Paulson, President of Paulson & Co.

  • SEABRIDGE GOLD

    -

    20

    40

    60

    80

    100

    120

    140

    160

    180

    1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017-

    $1,000

    $2,000

    $3,000

    $4,000

    $5,000

    $6,000

    $7,000

    Gol

    d Di

    scov

    erie

    s (m

    oz)

    Discovery-Oriented G

    old Budgets (US$ m)

    Gold Discoveries vs. Exploration Spending

    Gold Discoveries (m oz) Discovery-Oriented Gold Budgets (US$ m)

    Industry Not Making New Gold Discoveries

    45

    Majors have limited options for new projects

    (1) Source: SNL, GFMS and Paradigm Capital Inc.

  • SEABRIDGE GOLD

    From 1990 to 1999, the industry on average found 1.4 ounces of gold reserves and resources for every ounce produced

    For 2000 to 2009, only 0.7 ounces of gold reserves and resources were found for every ounce produced

    For 2010 to 2016, the industry estimates that at best 0.3 ounces of gold may have been found per ounce produced

    The majors need new deposits with scale and capital efficiency that can be permitted in safe jurisdictionsKSM

    New Discoveries are Lagging Production

    46

  • SEABRIDGE GOLD

    Exploration spending in 2010-2015 was running at roughly twice the level of 2000-2009 and three times the level of 1990-1999

    Nonetheless, discoveries are down dramatically

    Consequently, average finding costs have risen from $11 per resource ounce in the 1990-1999 period to $147 per ounce in 2010-2016, a 1300% increase

    Conclusion: Existing non-producing gold resources are significantly underpriced in the market but for how long?

    Cost of Finding New Ounces is Soaring

    47

  • SEABRIDGE GOLD

    Gold Industry Production in Major Decline

    48

    Majors require new projects to replace depleting production

    (2) Source: Consensus estimate. Includes CPM Group, GFMS and Metals Focus

  • SEABRIDGE GOLD

    Four Catalysts for a Higher Valuation

    Enhanced De-Risking Premium Fewer safe jurisdictions More difficulty permitting KSM has permits and

    social license in Canada

    Outstanding Exploration Record Over 36 Mn oz Au and

    25 Bn lbs Cu added over past 4 years at superior grades

    Industry exploration not replacing production: in-ground resources will soon be re-valued

    KSM, CL, Iskut and Snowstorm have best-of-class potential for adding resources

    Joint Ventures KSM is a top candidate

    for a production JV on friendly terms

    Major companies now more deal-capable

    Worlds largest mining companies under CA

    Project continues to improve

    Acceptable terms may need improved market conditions

    49

    Leverage to theGold Price Seabridge outperforms

    in a gold bull market

  • SEABRIDGE GOLD

    Corporate Information

    NYSE: SA TSX: SEA Included in GDXJ, S&P/TSX Global Mining and Global Gold Indices

    Listings

    58.3 M shares outstanding 61.9 M fully dilutedShare Structure

    No debt Approximately $20 M in working capitalBalance Sheet

    Interests are aligned with shareholders Insiders own over 30% of common sharesManagement and Board

    Own ~25% of common shares Investors include National Bank, Century Management, Van Eck,

    Weiss, TD Bank, Sprott, Fidelity, Paulson & Co.Financial Institutions

    Royal Gold (holds option to acquire 2% gold/silver NSR at KSM for $160 million in cash)Strategic Investors

    50

  • SEABRIDGE GOLD

    Experienced Management

    51

    Over 30 years of experience in the gold business, primarily as a senior officer and director of publicly traded companies including Greenstone Resources, Columbia Resources, Behre Dolbear & Company, Riverside Associates, Phibro-Salomon, Amax, and DRX

    Rudi FronkCo-Founder, Chairman & CEO

    Over 30 years of experience in the mining sector and responsible for designing and managing the technical programs required to advance Seabridge's two main assets towards feasibility

    Former Vice President of Solutions and Innovation for Newmont Mining CompanyJay Layman

    Director, President & COO

    Over 30 years of exploration experience and is responsible for the design and execution of Seabridges exploration and resource delineation programs

    Previously served as Exploration Manager and Vice President with Placer DomeBill Threlkeld

    Senior VP, Exploration

    Over 30 years of experience in mine engineering, design, strategic analysis and start-up Formerly a Group Executive, Mine Engineering at Newmont Mining Corporation

    Peter WilliamsSenior VP, Technical Services

    Has 25 years of mining industry and public accounting experience and is a CPA, CGA Currently a director of Paramount Gold Nevada Corp.

    Christopher ReynoldsVP, CFO

    Over 25 years of experience, responsible for developing and managing Seabridge's environmental programs and community engagement strategies

    Brent MurphyVP, Environmental Affairs

    Has practiced law in the areas of corporate finance and securities, corporate and mining since 1993 and has been counsel to Seabridge Gold since 1999

    Bruce ScottVP, Corporate Affairs

  • SEABRIDGE GOLD

    Board of Directors

    Founder and Chairman of Mintec, Inc. and one of the original developers of MineSight, recognized as the pre-eminent reserves modeling and mine design software system with more than 300 installations worldwide

    Frederick Banfield

    Over 30 years of experience, Mr. Gonzalez-Urien is one of the most highly regarded exploration geologists in the mining industry. Ran global exploration for Placer Dome from 1989 through 2001

    Eliseo Gonzalez-UrienChair, Compensation

    Committee

    Currently serves as the Executive Chairman of The RMH Group, Inc. Former CEO (and previously COO and CFO) of Echo Bay Mines

    Richard KrausChair, Audit Committee

    Over 40 years of legal expertise in mining, securities, financing, and mergers and acquisitions

    Former CEO of Anvil Mining and current director of Algold Resources Inc. and Uranium One

    John SabineChair, Governance and Nominating Committee

    32 years of investment banking experience Former director of Osisko Mining and Romarco Minerals. Director of

    Stillwater MiningGary Sugar

    52

    Slide Number 1Forward Looking StatementsThe Case for SeabridgeGold ReservesSeabridge Designed to Provide Leverage to GoldSeabridge Designed to Provide Leverage to Gold (cont.)Seabridge Designed to Provide Leverage to Gold (cont.)Share Dilution Matters!Historical PerformanceAttractive ValuationLow Political RiskKSM Project, British Columbia, CanadaKSM Approved by BC and CanadaKSM Favorable LogisticsKSM Mitchell ZoneKSM Proven and Probable ReservesKSM 2016 Preliminary Feasibility Study2016 PFS: Before Tax Economic Analysis2016 PFS: After Tax Economic AnalysisNew Discoveries at Grades Higher Than ReservesSlide Number 21PEA Mine Plan Reduces Waste by 2.4 Billion TonnesKSM 2016 Preliminary Economic Assessment2016 PEA: Before Tax Economic Analysis2016 PEA: After Tax Economic AnalysisSlide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30Courageous LakeCourageous Lake Project Location Courageous Lake PFS Pre-Tax SummaryCourageous Lake PFS After Tax SummaryCL Value Enhancing OpportunitiesCourageous Lake Exploration PotentialWalsh Lake Resources (March 2014)Courageous Lake 2018 Drilling TargetsSnipGold AcquisitionIskut Location and AccessSlide Number 41Snowstorm AcquisitionSnowstorm LocationSeabridges Newest ShareholderIndustry Not Making New Gold DiscoveriesNew Discoveries are Lagging ProductionCost of Finding New Ounces is SoaringGold Industry Production in Major DeclineFour Catalysts for a Higher ValuationCorporate InformationExperienced ManagementBoard of Directors