Shared Services Group

Site Services

BOEING is a trademark of Boeing Management Company.Copyright © 2012 Boeing. All rights reserved. File location:

Pre-Bid Meeting forBSC Land Development Project:

Paint Utilities & Firewater Pump House Boeing South Carolina Facility

Welcome

Boeing SSG Project Manager/Engineer Wes WilsonSupplier Management Matt Daly (Monica Rubinstein)Global Performance PM Glenn Ellzey

Please make sure you sign the list of attendees being passed around.

Page 3: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved.

Introductions Wes Wilson

Safety

SM /Contract overview Matt Daly

Bidding process

Price Exhibit Review

Security Wes Wilson

Project SOW Wes Wilson

3BOEING PROPRIETARY

Agenda

Page 4: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 4BOEING PROPRIETARY

Boeing Land Development Project

Safety / Construction Requirements

• Safety is a component of our Guiding Principles at The Boeing Company. We recognize that safety is everyone's responsibility and the successful construction team will keep safety in the forefront of all activities.

• GC shall provide safety orientation to all employees, subcontractor personnel, Boeing employees, Boeing representatives and Agencies.

• GC shall provide FOD training to all employees and subcontractor employees.

• All local and federal regulations shall be followed including the Boeing Service Provider Manual and all OSHA requirements.

• Personal Protective Equipment (PPE) as outlined below shall be mandatory minimum for access to the construction site:

• Hard Hats• Sturdy, closed toe shoe• Latest ANSI Standard approved safety glasses & side shields• Long pants• Shirts with 4 inch minimum sleeve length• Class II reflective vest (outer garment)

Page 5: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 5BOEING PROPRIETARY

Bid Highlights:

• Format: Firm Fixed Price Lump Sum

• Bid Walk: Tuesday, 7/8/14 9:30am EST

• Final Submittal of Bid Questions: Tuesday, 7/15/14 by 5pm EST

• Proposal Due date: Friday, 7/18/14 by 2pm EST

• Method of delivery: Email proposal to Purchasing Agent & deliver 6 printed copies of proposals to address provided.

• Purchasing Agent: Matt Daly

Contract:

• Boeing Terms and Conditions – Construction General Provisions

• Payment Terms: Net 30

• Payment schedule - Progress payments based on construction completion %’s.

Price Exhibit - instructions have been sent to all bidders

Boeing Land Development Project

Page 6: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved.

Security Badge Requirements – Boeing Badges Required for all of GCs management

team and any employees required to enter Boeing Site. GC shall provide badges to all other employees

No Smoking

Building access, flight line access etc…

Traffic, speed limits, parking– Parking passes will be issued by Boeing PM Team

Flagman (At site entrances and movement of any construction vehicle in the existing parking area)

6BOEING PROPRIETARY

Boeing Land Development Project

Page 7: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 7BOEING PROPRIETARY

BSC Proposed Paint Facility (Conceptual)

Page 8: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 8BOEING PROPRIETARY

BSC Proposed Paint Facility

Clear, Muck, Fill & Grade of All Areas

Page 9: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 9BOEING PROPRIETARY

Areas of Work

Paint Facility

New Pump House

Existing Pump House

Boeing Substation

Utility Cooridor

Page 10: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 10BOEING PROPRIETARY

Firewater Pump House

Approximate Location of Proposed Firewater Pump House

Existing Firewater Pump House

Page 11: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 11

Paint Utilities

Page 12: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 12

Quality Control

Quality is a paramount concern at Boeing

Boeing expects a quality product that provides a long serviceable life

Plans, specifications, and standards should be strictly adhered to

Testing and inspection must be given time to perform work

Contractor shall provide testing for all systems (electrical and mechanical)

– Owner shall be notified 48 hours in advance of testing

Soil testing done by Boeing’s third party testing service shall be binding unless there is evidence of an improper test procedure. Notification must be given immediately if the contractor wished to protest a test result.

Project should be bid accordingly

Page 13: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 13

Construction Logistic Plan

Construction Fence

Construction Zone

Construction Traffic Flow

Construction Trailer

Page 14: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 14

Site Coordination

Work closely with Gulf Stream on daily work coordination

Develop joint safety and security plan

Page 15: Copyright © 2012 Boeing. All rights reserved. SSG Presentation Template – REV 1/2012 Welcome

Shared Services Group | Site Services

Copyright © 2012 Boeing. All rights reserved. 15BOEING PROPRIETARY

Key Dates:

• Timing /Schedule• Paint Utilities Bid Walk: 7/8/14; 9:30am EST

• Final Submittal of Bid Questions: 7/15/14 by 5pm EST

• Proposal Due date: 7/18/14 by 2pm EST

• Contract Award: 7/30/14

• Construction Phasing:

• Paint Utilities International Blvd. North: 8/1/14 – 10/1/14

• Paint Utilities International Blvd. South: 8/28/14 – 3/20/15

• Firewater Pump House: 10/15/14 – 3/20/15

Boeing Land Development Project