Upload
cleopatra-malone
View
214
Download
0
Embed Size (px)
Citation preview
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 1
Five Ways to Builda
Microsoft Project Schedule
Lynn Frock, PMP513-321-3187 Phone
www.lynnfrock.com
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 2
Table of Contents
1. Presentation Assumptions.
2. The Five Ways to Build a Schedule.
3. Comparison Criteria.
4. Constraint Based
5. Project Network Diagram Only
6. Project Network Diagram with Contacts
7. Project Network Diagram with Leveled Resources
8. Portfolio / Program with a Resource Pool
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 3
Presentation Assumptions
• Schedule variance requires timely analysis & response. – Minimize negative variance.
– Maximize positive variance.
• Stakeholders need fact based status.
• Requested change requires accurate analysis.– Impacts on time, cost and quality compared to baseline.
• Efficient and current resource forecasting & deployment.
• The team is accountable to the current agreed baseline.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 4
The Five Ways to Build a Schedule
1. Constraint Based <<== (not recommended).
2. Project Network Diagram Only.
3. Project Network Diagram with contact information.
4. Project Network Diagram with leveled resources.
5. Portfolio / Program with a Resource Pool.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 5
Comparison Criteria
• Management needs.
• When appropriate.
• Advantages.
• Disadvantages.
• Construction and update techniques.
• Skills required.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 6
1. Constraint Based **not recommended**
• Management needs:– A sufficiently detailed, accurate project schedule.
– May or may not need resource assignment detail.
• Appropriate when:– Almost never.
• Advantages:– Little understanding of Microsoft Project modeling required.
– No understanding of the Precedence Diagramming Method (activity sequencing) required.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 7
1. Constraint Based **not recommended**
(Continued)
• Disadvantages– No Project Network Diagram.
– No Critical Path – all tasks marked as on the Critical Path.
– Difficult to predict impacts of task slippage.
– Changes can require manual recalculation.
– Microsoft Project leveling feature much less useful.
– Very difficult to model different scenarios for evaluation.
– Very time consuming.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 8
1. Constraint Based **not recommended**
(Continued)
• Construction and update techniques:– Set the Project start date and working time definitions.– Enter task, duration and milestone data.– Manually calculate and set each task & milestone date.– Manually adjust impacted dates after entering actuals and
approved changes.– Manually adjust dates, as needed, to resolve resource
overloads.
• Skills required:– Entering basic project, working time and task data.– Setting task constraints.– Workflow analysis modeling.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 9
2. Project Network Diagram Only.
• Management needs:– A sufficiently detailed, accurate project schedule.– Do not need resource assignment details.
• Appropriate when:– Resource schedules are managed in some other way.– Perhaps each task represents a sub-project.
• Advantages:– Microsoft Project re-calculates start/finish dates and duration
when a modification potentially affects any of those values.– Impacts of variance are quickly available.– Easier to create alternative schedule scenarios.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 10
2. Project Network Diagram Only
(Continued)
• Disadvantages– No resource assignment schedule.
– No ability to understand resource capacity or find over-assignments and overloads.
• Construction and update techniques:– Set the Project start date & define the project working time.
– Enter task, duration and milestone data.
– Define the Project Network Diagram (internal & external links).
– Enter actuals (could include cost data).
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 11
2. Project Network Diagram Only (Continued)
• Skills required:– Workflow analysis & modeling.
– Activity sequencing (Precedence Diagramming method).
– Entering basic project, working time, task data and actuals.
– Using Microsoft Project to entering the Precedence Diagramming Method’s internal & external links.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 12
3. Project Network Diagram with Contact Information
• Management needs:– A sufficiently detailed, accurate project schedule.– The name of the person, department or organization
responsible for the task (or deliverable).
• Appropriate when:– Resource schedules are managed in some other way.– Perhaps each task represents a sub-project.
• Advantages– Same as the Project Network Diagram based approach.– Plus: A contact is listed for task information.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 13
3. Project Network Diagram with Contact Information (Continued)
• Disadvantages– Same as the Project Network Diagram based approach.
• Construction techniques:– Same as the Project Network Diagram based approach.
– Plus: A contact name is added to the Contact field or a user defined field.
• Skills required:– Same as the Project Network Diagram based approach.
– Plus: Adding the contact name without causing work to be calculated.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 14
4. Project Network Diagram with Leveled Resources
• Management needs:– A sufficiently detailed, accurate, realistic project schedule
(no over-assigned resources.)
– The name (or type) and quantity of each assigned resources.
• Appropriate when:– Resource shortages might not be discovered in time.
– Resource overloads could harm the project.
– Costs will be forecast and tracked using Microsoft Project.
– Earned Value is used.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 15
4. Project Network Diagram with Leveled Resources (Continued)
• Advantages– Same as the Project Network Diagram based approach.– Plus: Understand which and how many resources are needed
when.
• Disadvantages– More modeling time is required.– Balancing resources can be tedious.
• Construction techniques:– Same as the Project Network Diagram based approach.– Plus: Assign resources to tasks with accurate work (hours)
and duration estimates.– Plus: Enter actual work (hours) or actual duration.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 16
4. Project Network Diagram with Leveled Resources (Continued)
• Skills required:– Same as the Project Network Diagram based approach.
– Plus: Ability to define and assign resources.
– Plus: Ability to model resource work - understand & use the duration / units / work relationship.
– Plus: Use Microsoft Project features to balance resources as per management decisions.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 17
5. Portfolio / Program with a Resource Pool
• Management needs:– How much capacity is available for additional projects?
– What happens to delivery if project priorities are changed?
– Same as the Project Network Diagram Method with Resources, but across a portfolio of projects.
• Appropriate when:– Resources are shared across projects.
– Resource skill shortages and overloads are difficult to discover in a timely way.
– Resources must be efficiently utilized.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 18
5. Portfolio / Program with a Resource Pool (Continued)
• Advantages:– Resources are not over assigned.
– Resource capacity and load is known to some future time.
– The impact of adding projects or changing priorities can be analyzed.
• Disadvantages– Requires a defined, disciplined administrative process to
maintain an updated and resource leveled portfolio.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 19
5. Portfolio / Program with a Resource Pool (Continued)
• Construction Techniques:– Establish a resource pool.– Add chartered projects to the portfolio (connect to the pool).– Define relative project priorities.– Balance resources across the portfolio.– Remove completed projects from the portfolio.
• Skills required:– Resource pool definitions.– Connecting to the pool.– Resource leveling procedures.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 20
The Five Ways to Build a Schedule
1. Constraint Based <<== (not recommended).
2. Project Network Diagram Only.
3. Project Network Diagram with contact information.
4. Project Network Diagram with leveled resources.
5. Portfolio / Program with a Resource Pool.