Page 1: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

COPC/JAG-CCMStatus Updates and Recommendations

16 November 2010

Chris FinnigsmierActing JAG/CCM Chair

Page 2: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

Outline

CCM Team Membership Status Updates and Recommendations

COPC Enterprise Network Requirements Development of the Next Generation COPC

Enterprise Network (aka DISA WENet Design)

2

Page 3: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

CCM TeamMember Organization

Charles Abel* (Retires 05 Jan 2011) Air Force/AFWA/A6

Chris Finnigsmier***Air Force/AFWA/A6 (Temp CCM-Chair until 1 Apr 11)

Ken Barnett OFCM

Vacant** NOAA/NWS/NCEP/NCO (CCM-Chair)

Russell Dyson*** NOAA/NESDIS/OSDPD

Tracy LePire Navy/NAVO

Jackie Lord NOAA/NWS/OPS/TOC

Derek Eddington*** (vice Sherryl Panek) Navy/FNMOC

Charleston Simms Navy/CNMOC/N6

Technical Advisor/SME/Alternate Organization

Jami Casamento NOAA/NWS/OST

Peter Behnke Navy/FNMOC

Patrick Gregory NOAA/NESDIS/OCIO

Tom Harrison Air Force/AFWA/A6

Bruce Kenison DISA Field Office USSTRATCOM

Frank Palazzo Navy/FNMOC

* Upcoming Vacancy ** Vacant role/representative *** New to the role or group 3

Page 4: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

COPC Enterprise Network Requirements COPC Action Item 2010-1.1

COPC Action Item 2010-1.1: Exercise established processes to coordinate and capture telecommunication requirements across COPC partners, including NUOPC and JPSS related requirements. These requirements will identify current and future data flows including source, destinations, volume, latency requirement, schedule of when new data will be or needs to be enabled, encryption requirements, other data restrictions, and related COPC business functions. This information will be used to validate technical designs and resource estimates for new network infrastructure initiatives.

4

Page 5: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

COPC Enterprise Network Requirements COPC Action Item 2010-1.1

May/June - CCM developed a revised template TDs/JAGs reviewed template’s design Identified correct individuals (modelers, data assimilations

experts, etc.) to articulate requirements

July – Data Call sent by Deputy Federal Coordinator (Suspense: 31 Aug 10) To CNMOC (John Meyer), AFWA (Michael Howland), TOC (Craig

Hegemann), NCEP (Ben Kyger), and NESDIS (CDR Mark Moran)

Sept – All data requirements submitted

Sept/Oct – Analyzed the responses, reconciled differences between DOD and NOAA, asked for further fidelity

5

Page 6: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

COPC Enterprise Network Requirements COPC Action Item 2010-1.1

Recommendation: Keep action item open until the requirements have been reconciled and reported

6

Page 7: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

Development of Next Generation COPC Enterprise Network

COPC Action Item 2008-2.11

COPC Action Item 2008-2.11: JAG CCM shall coordinate the development of the next generation COPC shared network infrastructure with DoD and NOAA IT leadership. The JAG CCM shall leverage projects currently underway that are planning a NOAANet-DoD enterprise network capability.

7

Page 8: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

July/Aug 2010: Meetings with DISA to assist in the design of the COPC Weather Enterprise Network (WENet) AFWA has funded the design effort at DISA

Sept 2010: Use the COPC Data Requirements as baseline for bandwidth, ports, and protocols

8

Development of Next Generation COPC Enterprise Network

COPC Action Item 2008-2.11

Page 9: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

DISA Draft Concept of Design: Future proof on throughput by standardizing on 10 Gig

hardware through the WENet gateways Geographic redundancy with some local redundancy

(dual power supplies) Four routers, two at each gateway Two firewall/IDP, one at each gateway

9

Development of Next Generation COPC Enterprise Network

COPC Action Item 2008-2.11

Page 10: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

Network TopologyA Combat Support Agency

UNCLASSIFIED // FOR OFFICIAL USE ONLY 10

Page 11: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

DISA – Tasks completed: Validated design by performing lab testing Determined secondary WENet node location and finalize

circuit costs

DISA - Tasks to be completed: Provide detailed design document to include NOAA and

NAVO (Stennis) portion Propose a complete cost breakdown to include circuit and

equipment costs, and who pays for what

11

Development of Next Generation COPC Enterprise Network

COPC Action Item 2008-2.11

Page 12: COPC/JAG-CCM Status Updates and Recommendations 16 November 2010 Chris Finnigsmier Acting JAG/CCM Chair

Development of the Next Generation COPC Enterprise Network

COPC Action Item 2008-2.11

Recommendation: Close this action item

DISA has provided design and has performed preliminary testing

Open new action item Each center develop detailed implementation plan to how to

achieve the final design JAG/CCM proposes the cost sharing mechanism (Annex to

DAPE)

12