29
Bertrand RENARD April 2009 CEA / DSM / Irfu / SACM 1 Cooling down and acceptance tests Saclay cryo-magnetic test facility for W7-X coils

Cooling down and acceptance tests - CEA/CEA · 2009. 4. 30. · CEA / DSM / Irfu / SACM Bertrand RENARD April 2009 2 1. Test Facility description OUTLINE 2. Coil Test procedure 3

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 1

    Cooling down and acceptance tests

    Saclay cryo-magnetic test facility for W7-X coils

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 2

    1. Test Facility description

    OUTLINE

    2. Coil Test procedure

    3. Cooling down

    4. Improvements from the tests

    Cryostat, Valve boxes and SatelliteLiquefier / refrigeratorPower SupplyData acquisition system

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 3

    Cryostat, Valve boxes and Satellite

    Test facility: one cryostat

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 4

    Safety valves

    CalibrationLeak

    Wirings

    Currentleads

    Valves

    Test facility: valve box

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 5

    Test facility: inside the cryostat

    NitrogenShield

    Connectionsfor Coils

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 6

    6

    � Liquefier

    Liquid helium tank: 5 000 liters

    Production 70 l/h

    use:Satellite tankCurrent leads

    � Refrigerator

    Power 200 W @ 4.5 K

    Total mass flow rate46 g/s @ 300 K

    15 g/s @ 5 K, 6 bars

    Test facility: refrigerator / liquefier

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 7

    � Power supply

    cooled by water

    Max current: 25 kA

    Max voltage: +/-10 V

    Ramp: 20 to 200 A/s

    Scheme of the magnet safety system

    Test facility: power supply and safety system

    � Magnet Safety SystemNormal: slow discharge through the power supply.Quench: fast discharge through 20 mΩprotection resistor.

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 8Laurent GENINI Greifswald June 16-17, 2008CEA/DSM/IRFU/SACM

    � 80 sensors for each coil:Temperatures, pressure, mass flow, strain gauges,

    extensometers, voltage drops, current, vacuum…

    � During cool down and warm up:All sensors: 0,025 Hz.

    � During current test:� All sensors: 1 Hz.�In case of quench:

    Cryogenic sensors: 100 Hz.Voltage drops and current: 5 kHz

    Quench acquisition window: Pre trigger 2 s Post trigger 8 s

    Test facility: data acquisition system

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 9

    1. Test Facility description

    OUTLINE

    2. Coil Test procedureCoil preparationRoom temperature testsCryogenic testsRecording and documentation

    3. Cooling down

    4. Improvements from the tests

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 10

    Unloading from transport lorry and transport frame

    Visual checks

    Coil installation under the support ring

    Test procedure: coil preparation

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 11

    Conductor bending

    Junction boxes

    Reinforcement structure

    Cabling and tests• Temperature sensors, • Strain gauges, • Extensometers

    Insulation of conductor

    QD tests

    DC test

    Test procedure: coil preparation

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 12

    Cryostat open:

    QD test

    DC test

    Cryostat closed:

    Vacuum pumping

    Leak test

    Cooling down

    RRR measurement

    Test procedure: cooling down

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 13

    Nominal current

    Temperature margin test

    Fast discharge

    Nominal temperature check

    Interlayer resistance

    Pressure drop

    Test procedure: current test

    Non-planar coil: 17.6 kAStored energy: 7.7 MJDischarge time: ~ 2.5 s

    Planar coil: 16 kAStored energy: 1.2 MJDischarge time: 0.45 s

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 14

    Leak measurement

    AC test (interturn insulation)

    DC test (ground insulation)

    Impedance measurement

    Warming up (electric heating + break vacuum with nitrogen)

    Test procedure: warming up

    Impedance measurement from Ehmler et al.

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 15

    Cabling and tests• Temperature sensors, • Strain gauges, • Extensometers

    QD tests

    DC test

    Junction boxes dismantling

    Preparation for departure

    Visual checks

    Truck loading

    Test procedure: coil departure preparation

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 16

    1. Test Facility description

    OUTLINE

    Description

    2. Coil Test procedureRequirements

    3. Cooling downDescription and limitations

    4. Improvements from the testsNon-conformities and modifications

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 17

    Coil cooling down: energy extracted

    2.3 mCoil average diameter

    Total mass

    Case (ss)

    Insulation (Epoxy resin)

    Conductor total

    Conductor total length

    5300 kg

    3640 kg

    540 kg

    870 kg

    945 m

    Non-planar coil inertia

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 18

    AAB10, 11-20 July 2007, position 2A

    The inlet temperature ramp reaches the limit of 2 K/h

    Coil cooling down: ramp

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 19

    ∆T in-out reaches the limit of 40 K on the casing

    Coil cooling down: maximum gradient

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 20

    Total coil energy loss

    Coil cooling down: total power

    ),(.)(. 2/ condradNPHmdt

    dTTCpm outinHe

    coilcoil

    ++∆=

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 21

    Coil cooling down: limitations

    Helium inlet temperature limiting parameters:

    � Maximum gradient in the coil: 40 K

    � Maximum rate of inlet temperature decrease:2 K/h between 300 and 100 K

    4 K/h between 100 and 50 K

    10 K/h below 50 K

    � Refrigerator power� Mass flow rate

    � Nitrogen power

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 22

    1. Test Facility description

    OUTLINE

    2. Coil Test procedure

    3. Cooling down

    4. Improvements from the tests

    Test required values and non-conformitiesImprovements on the test facilityImprovements of the coils, retest…� a chance to learn!

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 23

    All tests are recorded for legal liability and manufacturing warranty.

    A complete paper and electronic documentationis produced.

    (one engineer full time)

    Improvements from tests: documentation

    If the “Scope and Requirements” are not fulfuilled, a

    non-conformity reportis issued

    This NCR requires a decision about possible actions to modify the coils or the test facility

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 24

    Liquefier / Refrigerator

    Little ageing problems, big delays

    � Leak on the body of a manual valve

    delay roughly 3 months

    � Deviation of a pressure sensor

    delay roughly 3 weeks

    � Actions:

    Additional safety analysis of pollution in the He cycle

    Maintenance

    Replacement of the cycle compressor (last year)

    Improvements from tests: liquefier maintenance

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 25

    Leak on the junction boxes� Problem

    After 3 years of tests, suddenly leaks appeared on the junction boxes…

    Finding and avoiding leaks is time consuming

    Improvements from tests: helium leak

    � Possibilities:

    Junction box surface

    Rectangular gasket

    � Actions:

    Realization of boxes for a leak test outside of the cryostat

    More caution and systematic testing

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 26

    High electric resistance � Problem

    High resistance between extra length busbars and the junction boxes… Impossibility to perform the current test at the nominal values.

    Improvements from tests: junction resistance

    � Actions performed:

    Re gilding of copper surfaces

    Increase in caution during connection of the bus

    � Possibilities:

    Oxidization of the gold

    Parallelism between the copper plates and the junction boxes

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 27

    DC test under vacuum to check the insulation of the coil

    � Problem: cryostat alone DC test valid

    with coils DC test hazardous

    Not valid DC test

    � For non planar coils:

    9.1 kV at room T,10.4 kV at cryogenic T.

    � Actions :

    Vacuum test for the QD feedthroughevery other current tests

    Addition of insulation rings between cryostat and QD feedthrough

    Additional Paschen test planned for the coils

    Improvements from tests: DC tests

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 28

    - Coil testing is 90% accomplished (15/03/09)

    - 84 current tests performed

    (63 different coils + 7 coils twice + 7 coils three times)

    - Yearly ratio has increased (projection)

    Assessment of the tests

    • Preparation of coils and coil sensors• Cooling and warming speed• Maintenance of cold box and Helium circuits• Helium liquefaction before cold tests

    Maximum speed of testing is limited by:

    0

    5

    10

    15

    20

    25

    30

    0 1 2 3 4 5 6

    Year (+2003)

    Cur

    rent

    test

    s

  • Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 29

    CONCLUSION

    Cryogenic and current tests are a big effort

    These tests demonstrate that coils work

    Many improvements and techings gained from the tests

    QD wires modified

    Reworked insulation of double layer connections (coil types 4&5)

    Leaks repaired on aluminium weldings and casing circuits

    Team 5 Technicians and 3 Engineers + support other CEA services