Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 1
Cooling down and acceptance tests
Saclay cryo-magnetic test facility for W7-X coils
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 2
1. Test Facility description
OUTLINE
2. Coil Test procedure
3. Cooling down
4. Improvements from the tests
Cryostat, Valve boxes and SatelliteLiquefier / refrigeratorPower SupplyData acquisition system
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 3
Cryostat, Valve boxes and Satellite
Test facility: one cryostat
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 4
Safety valves
CalibrationLeak
Wirings
Currentleads
Valves
Test facility: valve box
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 5
Test facility: inside the cryostat
NitrogenShield
Connectionsfor Coils
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 6
6
� Liquefier
Liquid helium tank: 5 000 liters
Production 70 l/h
use:Satellite tankCurrent leads
� Refrigerator
Power 200 W @ 4.5 K
Total mass flow rate46 g/s @ 300 K
15 g/s @ 5 K, 6 bars
Test facility: refrigerator / liquefier
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 7
� Power supply
cooled by water
Max current: 25 kA
Max voltage: +/-10 V
Ramp: 20 to 200 A/s
Scheme of the magnet safety system
Test facility: power supply and safety system
� Magnet Safety SystemNormal: slow discharge through the power supply.Quench: fast discharge through 20 mΩprotection resistor.
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 8Laurent GENINI Greifswald June 16-17, 2008CEA/DSM/IRFU/SACM
� 80 sensors for each coil:Temperatures, pressure, mass flow, strain gauges,
extensometers, voltage drops, current, vacuum…
� During cool down and warm up:All sensors: 0,025 Hz.
� During current test:� All sensors: 1 Hz.�In case of quench:
Cryogenic sensors: 100 Hz.Voltage drops and current: 5 kHz
Quench acquisition window: Pre trigger 2 s Post trigger 8 s
Test facility: data acquisition system
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 9
1. Test Facility description
OUTLINE
2. Coil Test procedureCoil preparationRoom temperature testsCryogenic testsRecording and documentation
3. Cooling down
4. Improvements from the tests
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 10
Unloading from transport lorry and transport frame
Visual checks
Coil installation under the support ring
Test procedure: coil preparation
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 11
Conductor bending
Junction boxes
Reinforcement structure
Cabling and tests• Temperature sensors, • Strain gauges, • Extensometers
Insulation of conductor
QD tests
DC test
Test procedure: coil preparation
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 12
Cryostat open:
QD test
DC test
Cryostat closed:
Vacuum pumping
Leak test
Cooling down
RRR measurement
Test procedure: cooling down
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 13
Nominal current
Temperature margin test
Fast discharge
Nominal temperature check
Interlayer resistance
Pressure drop
Test procedure: current test
Non-planar coil: 17.6 kAStored energy: 7.7 MJDischarge time: ~ 2.5 s
Planar coil: 16 kAStored energy: 1.2 MJDischarge time: 0.45 s
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 14
Leak measurement
AC test (interturn insulation)
DC test (ground insulation)
Impedance measurement
Warming up (electric heating + break vacuum with nitrogen)
Test procedure: warming up
Impedance measurement from Ehmler et al.
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 15
Cabling and tests• Temperature sensors, • Strain gauges, • Extensometers
QD tests
DC test
Junction boxes dismantling
Preparation for departure
Visual checks
Truck loading
Test procedure: coil departure preparation
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 16
1. Test Facility description
OUTLINE
Description
2. Coil Test procedureRequirements
3. Cooling downDescription and limitations
4. Improvements from the testsNon-conformities and modifications
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 17
Coil cooling down: energy extracted
2.3 mCoil average diameter
Total mass
Case (ss)
Insulation (Epoxy resin)
Conductor total
Conductor total length
5300 kg
3640 kg
540 kg
870 kg
945 m
Non-planar coil inertia
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 18
AAB10, 11-20 July 2007, position 2A
The inlet temperature ramp reaches the limit of 2 K/h
Coil cooling down: ramp
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 19
∆T in-out reaches the limit of 40 K on the casing
Coil cooling down: maximum gradient
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 20
Total coil energy loss
Coil cooling down: total power
),(.)(. 2/ condradNPHmdt
dTTCpm outinHe
coilcoil
++∆=
∑
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 21
Coil cooling down: limitations
Helium inlet temperature limiting parameters:
� Maximum gradient in the coil: 40 K
� Maximum rate of inlet temperature decrease:2 K/h between 300 and 100 K
4 K/h between 100 and 50 K
10 K/h below 50 K
� Refrigerator power� Mass flow rate
� Nitrogen power
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 22
1. Test Facility description
OUTLINE
2. Coil Test procedure
3. Cooling down
4. Improvements from the tests
Test required values and non-conformitiesImprovements on the test facilityImprovements of the coils, retest…� a chance to learn!
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 23
All tests are recorded for legal liability and manufacturing warranty.
A complete paper and electronic documentationis produced.
(one engineer full time)
Improvements from tests: documentation
If the “Scope and Requirements” are not fulfuilled, a
non-conformity reportis issued
This NCR requires a decision about possible actions to modify the coils or the test facility
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 24
Liquefier / Refrigerator
Little ageing problems, big delays
� Leak on the body of a manual valve
delay roughly 3 months
� Deviation of a pressure sensor
delay roughly 3 weeks
� Actions:
Additional safety analysis of pollution in the He cycle
Maintenance
Replacement of the cycle compressor (last year)
Improvements from tests: liquefier maintenance
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 25
Leak on the junction boxes� Problem
After 3 years of tests, suddenly leaks appeared on the junction boxes…
Finding and avoiding leaks is time consuming
Improvements from tests: helium leak
� Possibilities:
Junction box surface
Rectangular gasket
� Actions:
Realization of boxes for a leak test outside of the cryostat
More caution and systematic testing
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 26
High electric resistance � Problem
High resistance between extra length busbars and the junction boxes… Impossibility to perform the current test at the nominal values.
Improvements from tests: junction resistance
� Actions performed:
Re gilding of copper surfaces
Increase in caution during connection of the bus
� Possibilities:
Oxidization of the gold
Parallelism between the copper plates and the junction boxes
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 27
DC test under vacuum to check the insulation of the coil
� Problem: cryostat alone DC test valid
with coils DC test hazardous
Not valid DC test
� For non planar coils:
9.1 kV at room T,10.4 kV at cryogenic T.
� Actions :
Vacuum test for the QD feedthroughevery other current tests
Addition of insulation rings between cryostat and QD feedthrough
Additional Paschen test planned for the coils
Improvements from tests: DC tests
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 28
- Coil testing is 90% accomplished (15/03/09)
- 84 current tests performed
(63 different coils + 7 coils twice + 7 coils three times)
- Yearly ratio has increased (projection)
Assessment of the tests
• Preparation of coils and coil sensors• Cooling and warming speed• Maintenance of cold box and Helium circuits• Helium liquefaction before cold tests
Maximum speed of testing is limited by:
0
5
10
15
20
25
30
0 1 2 3 4 5 6
Year (+2003)
Cur
rent
test
s
Bertrand RENARD April 2009CEA / DSM / Irfu / SACM 29
CONCLUSION
Cryogenic and current tests are a big effort
These tests demonstrate that coils work
Many improvements and techings gained from the tests
QD wires modified
Reworked insulation of double layer connections (coil types 4&5)
Leaks repaired on aluminium weldings and casing circuits
Team 5 Technicians and 3 Engineers + support other CEA services