Upload
wq22030202
View
219
Download
0
Embed Size (px)
Citation preview
8/12/2019 Controller Workload
1/6
Controller Workload: What are they doing and why are they doing so
much of it?
By David A. Strobhar
Beville Engineering, Inc.
201 West Franklin St., Suite D
Dayton, Ohio 45459
Abstract
The ability to measure a phenomena is critical to being able to control and/or
modify it. The workload imposed on pipeline controllers has until recently been measured
only by subjective assessments from pipeline personnel. However, Beville Engineering has
undertaken recent studies to quantify controller workload. The studies relied ontechniques developed for measuring the workload of oil refinery operators. Use of job
sampling for steady state workload analysis will be explained. The job sampling
methodology will be described along with the type of data obtained from the pipeline
studies. The relationship between time spent on tasks and the number of tasks that need to
be performed will be discussed. The impact of type of pipeline and SCADA configuration
on steady state workload will be highlighted. Methods to lower controller workload will
be discussed relative to the objective data.
Changing anything requires some understanding of that which you are attempting
to change. This holds true for pipeline controllers, where an understanding of the position
is needed in order to change the jobs to make them more efficient, higher performing,and/or different in nature (e.g., commodity based versus geography based). Until recently,
most of the understanding came from people who had worked the job previously.
However, unless one person had worked all the positions, comparisons across positions
became difficult. Subjective assessments of the job were utilized, but they usually lacked a
common frame of reference for what was difficult or easy.
Objective measures of job characteristics are needed in order to assess how a job
can be altered and/or how it should be changed in light of new technology. Beville
Engineering has been developing such measures and applying them to oil refinery
personnel for the past ten years. Recently, the same techniques have been applied to
pipeline controllers with considerable success.
The technique applied is referred to as job sampling. It is a variation of traditional
time and motion studies. In time-and-motion study, the objective is to determine a
standard time for a repeated task. However, because of the continuous nature of process
operations, repeated activities occur only over a long period. The objective of job
sampling is to capture a snapshot of the controllers shift when the controller is most likely
8/12/2019 Controller Workload
2/6
to be heavily loaded. Taking a long sample of the controllers activity at the beginning and
ending of the shifts captures those repeated activities the controller is likely to experience
day-to-day.
Questions typically occur on the ability to use only a few samples of a controllers
activity as representative of the entire job, Isnt every day different? Certainly everydayis slightly different, but not as much as might be suspected. While the object of the activity
(a specific pipeline) may vary from day-to-day, the types of activities tend to repeat or
have a constancy (starting/stopping a line). Sample/Re-sample tests on the reliability of the
technique show an unaccounted variance of less than 6%.
Two four-hour samples were collected for each pipeline position. The sample start
times were adjusted to each particular location to capture the first four hours of the
controllers day shift. The second sample was taken in the late afternoon and/or early
evening in order to catch a quieter, yet not dead, time period. The two samples
provide indication of peak workload, the difference from peak to normal, and an
average workload.
All job related activities are recorded during the sample period. The start and stop
time for each task is logged, and notations made as to the task itself. The task data is later
categorized. In the case of the pipeline controllers, the data collected were categorized
into one of three areas: (1) communication interactions, including with whom they
interacted, (2) SCADA interactions, including instrument inspections, control moves,
alarms, CRT and display usage, and (3) administrative activities, including logging and line
balances.
One measure obtained from job samples is the actual amount of time the controller
spends on job related tasks, which Beville refers to as direct time. A higher direct timeindicates a greater portion of time being spent on job related activities. Direct time is
represented as a percentage, calculated by dividing recorded task times (in minutes) by the
sample duration (in minutes).
Figure 1 shows the average breakdown of percentage direct time for both
controllers and refinery board operators. The breakdown of the time is different due to the
different nature of the two jobs.
Figure 1. Controller & Refinery Board Operator Direct Time Averages
Controller Refinery Board Operator
Task % Time Task % Time
Communication 16.8 Administrative 17.4SCADA Interaction 21.4 Operational 21.3
Admin/Logging 23.2 Maintenance 1.9
Inspections 9.9
Laboratory 0.8
Total 61.4 Total 51.3
8/12/2019 Controller Workload
3/6
Despite the difference in the task categories, some general comparisons can be
made between pipeline controllers and refinery board operators. The controllers are
typically spending more time, about 10%, on job related tasks that are board operators.
This difference in utilization may stem from board operator jobs matching processing
units, and therefore not easily dividable for balancing workload. Pipeline controllers also
spend more time on logging, which is one sub-task of the board operators administrativetask.
While direct time is important, it captures only half the story. In addition to how
much time is spent on job related tasks, the number of tasks that must be performed
influences workload. Spending 40 minutes out of an hour on four tasks will be perceived
to be far less busy than spending 40 minutes out of an hour on ten tasks. Combining the
direct time loading with the number of tasks provides an indication of busyness.
Busyness is simply the combination of two measures of steady state loading, (1)
direct time and (2) the number of tasks, to form a third derived measure of workload,
mean time between task (MTBT). Mean time between task is calculated as follows
A chart showing the relationship between the direct time and number of tasks is
shown in Figure 2. The lines on the chart are equivalency curves, where different levels of
direct time and number of tasks have the same degree of busyness, or mean time between
tasks. Movement up or right on the chart indicates increasing busyness, decreasing mean
time between tasks.
Three equivalency curves are shown on the chart. A MTBT 2.0
(lower left of chart) is characteristic of an under-loaded job.
The controller workload samples shown in the figure represents different types of
controller workload:
Position A (Crude Pipeline) Large swing in workload is seen between the AM
and PM samples. The controller was handling predominately crude pipelines,
which are characterized by a significant increase in workload for the early morning
period. The workload for the AM sample is less than .5 minutes mean timebetween tasks, which is more typical of an upset situation. This is in contrast to
the PM sample, which was in the under-loaded range.
Position B (LPG Pipeline) The busyness for this controller stayed constant over
the two sample periods, with a shift in number of tasks to direct time from the AM
to PM period. This type of response is typical for stable positions such as product
pipeline control.
[ ]Sampl eLength Mi nutes Dir ectTime Mi nutesNumber of Task s
( ) ( )
8/12/2019 Controller Workload
4/6
8/12/2019 Controller Workload
5/6
confused with how often each CRT was looked at. Since eye movements were not
recorded, it is impossible to say precisely which CRTs were looked at. However, despite alarge number of screens, the controllers typically only actively interacted with two. This is
consistent with similar findings for refinery board operators. While the other screens may
be providing value, most the control actions will be on two.
The job sample data provided insights and information on ways to alter controller
jobs to enhance performance. Understanding the current workload allows a determination
to be made as to whether the controller can handle additional tasks or systems without any
associated job changes. If the position is under loaded, additional tasks or responsibilities
can be added without other changes to the system. If the job is overloaded, or nearly
overloaded, then changes can be made to the job to reduce the workload, either to
improve performance or enable the controller to take on additional tasks/responsibilities.
The sample data can indicate opportunities to alter controller workload. If one task
is taking up a disproportionate amount of the controllers time, as indicated by the direct
time breakdown (such as logging), then it is a candidate for automation or possible system
re-design. Busyness indicates opportunities to reduce operator workload. Reducing
frequent, short duration tasks, such as responding to alarms or communication with the
field, can dramatically reduce the controllers level of busyness. Large swings in busyness,
Figure 3 - Control Display Usage
0
50
100
150
200
250
300
350
400
450
500
STATION14
STATION13
CRUDESYSTEMTANKS
STATION12
STATION11
STATION10
STATION9
STATION8
STATION7
STATION6
STATION5
METERSDISPLAY
STATION4
STATION3
STATION2
LINE#4BALANCE
STATION1
LINE#3PROFILE
LINE#1BALANCE
LINE#2
LINE#1PROFILE
CRT DISPLAY
AMOUNTOFTIMEON
EACH
CRT(MI
NUTES)
CRT 1 CRT 2 CRT 3 CRT 4 CRT 5
8/12/2019 Controller Workload
6/6
similar to that for the crude pipeline controller, are candidates for either differential
staffing (provide AM help) or dynamic task reallocation (where another controller could
help on some of the tasks). If a large amount of display paging is occurring, display
redesign can reduce the paging demands.
Workstation design should reflect the reliance on the number of CRTs used tomake most of the control changes. The data should not be interpreted as saying that only
two CRTs should be provided, but it does say eight CRTs for one controller is overkill. In
addition, the display system structure should reflect the number of CRTs that are typically
used for most operational adjustments by the controller.
Job sampling to identify controller workload has been successfully used for oil
refinery operators and has now been successfully applied to pipeline controllers. The data
provide objective measures of current controller characteristics that provide insight into
how the job can or should be altered in the future. By establishing where the controllers
are now, it is easier to understand how to get them to where you want them to be in
the future.