Sakhalin Energy Investment Company, Ltd Controlled Document Sakhalin II Assets Document Number: Asset Origi n Module Discipli ne Doc Type Doc No. Sheet No. Rev No. 7000 S 90 10 P 0112 00 02 Title: PRIGORODNOYE ASSET WORK INSTRUCTION - CONTROL VALVE IPF FUNCTION TEST Custodian: Graham Harris / Haridas Bhaskaran (SEIC) Classification: Restricted P Preliminary – For Comment / Information AFU Approved For Use Issue Purpose AFD Approved for Design V Superseded / Cancelled AFC Approved for Construction ASB As-Built T TEOC Approval Document Re v Issue Purpose Description Originator: Name (Company) Signature Date Checked by: Name (Company) Signature Approved by: Name (Company) Signature Originator: Franklin Ucar (SEIC) 02 AFU Approved for Use Checked By: Graeme Bottoms (SEIC) Approved By: Haridas Bhaskaran (SEIC) Location of Change Brief Description of Change to Latest Revision This document contains proprietary information and is intended for use by Sakhalin Energy Investment Company, Ltd. (SEIC) authorised personnel or companies only. The copyright of this document is vested in SEIC. All rights reserved. The contents of this controlled document shall not be altered without formal approval of the document Custodian. It is the responsibility of each user of this document to verify the current revision prior to use. The SEIC Electronic Document Management System is the only SEIC approved source for verifying current revisions. All revision controls and note on updates are maintained electronically through LiveLink. This is governed through the following SEIC document control procedures: - Document Control Procedure 1000-S-90-01-P-0002-00

Control Valve IPF Function Test1

Embed Size (px)

DESCRIPTION

IPF control valve

Citation preview

Page 1: Control Valve IPF Function Test1

Sakhalin Energy Investment Company, LtdControlled Document

Sakhalin II Assets

Document Number:

Asset Origin Module Discipline Doc Type

Doc No. Sheet No. Rev No.

7000 S 90 10 P 0112 00 02

Title:

PRIGORODNOYE ASSET

WORK INSTRUCTION - CONTROL VALVE IPF FUNCTION TEST

Custodian: Graham Harris / Haridas Bhaskaran (SEIC) Classification: Restricted

P Preliminary – For Comment / Information AFU Approved For Use Issue Purpose AFD Approved for Design V Superseded / Cancelled

AFC Approved for Construction ASB As-BuiltT TEOC Approval Document

Rev Issue Purpose

Description

Originator: Name (Company) Signature

DateChecked by: Name (Company) Signature

Approved by: Name (Company) Signature

Originator: Franklin Ucar (SEIC)

02 AFU Approved for Use Checked By:

Graeme Bottoms (SEIC)

Approved By:

Haridas Bhaskaran (SEIC)

Location of Change Brief Description of Change to Latest Revision

This document contains proprietary information and is intended for use by Sakhalin Energy Investment Company, Ltd. (SEIC) authorised personnel or companies only. The copyright of this document is vested in SEIC. All rights reserved. The contents of this controlled document shall not be altered without formal approval of the document Custodian.

It is the responsibility of each user of this document to verify the current revision prior to use. The SEIC Electronic Document Management System is the only SEIC approved source for verifying current revisions.All revision controls and note on updates are maintained electronically through LiveLink. This is governed through the following SEIC document control procedures: - Document Control Procedure 1000-S-90-01-P-0002-00

Page 2: Control Valve IPF Function Test1

WORK INSTRUCTION - CONTROL VALVE IPF FUNCTION TEST Rev 02

TABLE OF CONTENTS

1 PURPOSE......................................................................................................................................... 3

2 SCOPE.............................................................................................................................................. 3

3 RESPONSIBILITY AND AUTHORITY..............................................................................................3

4 DEFINITIONS AND ABBREVIATIONS.............................................................................................3

5 REFERENCES.................................................................................................................................. 3

6 CONTROL VALVE IPF FUNCTION TEST........................................................................................46.1 PREPARATION FOR ALL JOBS.......................................................................................................46.2 FIELD PROOF TEST......................................................................................................................... 46.3 CERTIFICATION............................................................................................................................... 46.4 Closing The Job................................................................................................................................. 4

Appendix A - Historical Revision Change List.............................................................................................5

7000-S-90-10-P-0112-00-E Page 2 of 5

Page 3: Control Valve IPF Function Test1

WORK INSTRUCTION - CONTROL VALVE IPF FUNCTION TEST Rev 02

1 PURPOSE

The purpose of this work instruction is to describe the action to perform and the precaution to be taken in carrying out IPF proof test on control valves which form part of an IPF loop at SEIC Prigorodnoye Asset.

2 SCOPE

This work instruction describes the procedure and the necessary actions to follow by the instrument and contractor personnel in testing the control valve which is used as part of an IPF loop installed within SEIC Prigorodnoye Asset.

3 RESPONSIBILITY AND AUTHORITY

All Instrument personnel and Contractor should follow this work instruction when working on any of the control Valves in the SEIC Prigorodnoye Asset.

SEIC Supervisor or Senior technician must have prior knowledge of the test and shall witness the test as required.

The Contractor shall notify SEIC Supervisor or Senior technician 24 hours in advance for any test to be carried out on the system.

4 DEFINITIONS AND ABBREVIATIONS

FGSFire & Gas System by Yokogawa Pro-SafeIPSInstrumented Protective System (IPS) by Yokogawa ProsafeSAP-PMElectronic maintenance management systemDCSDistributed Control System by Yokogawa Centum CS3000

5 REFERENCES

N/A

7000-S-90-10-P-0112-00-E Page 3 of 5

Page 4: Control Valve IPF Function Test1

WORK INSTRUCTION - CONTROL VALVE IPF FUNCTION TEST Rev 02

6 CONTROL VALVE IPF FUNCTION TEST

6.1 PREPARATION FOR ALL JOBS

Once the SAP-PM work order is obtained, ensure that the loop diagram and PEFS are together with the PTW before starting the work. The stroke time of the Control Valve is not critical as it depends on the position of the Control Valve prior to activation. Hence the purpose here is to ensure that the solenoid is triggered and the Control Valve closes when triggered by the IPF loop.

Locate the Control Valve in the field, check the tag number against the tag number on the permit.

As per SAP order if the Control Valve that has to be tested has operator task to be followed, ensure that the panel operator has identified and taken the necessary precaution before proceeding.

Force shall be part of this working instruction.

6.2 FIELD PROOF TEST

Check all associated components such as solenoid valves, proximity sensor/switch, air regulator are in good working condition.

Ensure all required insulation if available is in good condition. Force the SOV output signal from IPS. If there are issues with the components, ensure that the problems are resolved before

pursuing with the test. Inform the relevant panel operator in the MCR of intent to commence test. Request panel operator MCR to inform valve status and confirm consistency with field. Request technician at IPS panel to initiate trip command for the valve. Watch the valve and as soon as it comes to the fail-safe closed position, request status

indication from MCR and IPS panel to confirm consistency with field. To open the valve automatically request MCR to RESET trip. Watch the valve as it opens and request status indication from MCR and IPS panel to

confirm consistency with field. Re-confirm the correct valve position with MCR panelman before removing the force. Remove the force from IPS. Inform both MCR and IPS panel of completion of tests.

6.3 CERTIFICATION

A label indicating the date of service for IPF proof test and the name of contractor/ technician, should be affixed on the on the actuator of the Control valve.

6.4 CLOSING THE JOB

If required reset the open loop signal status in the IPS/FGS system. Inform the panel operator that the job is completed. Get the panel operator to normalise as required in the operator task. Log in work permit as required by the procedure. Go into SAP to record history against the functional location with the test data. Close the work request in SAP.

7000-S-90-10-P-0112-00-E Page 4 of 5

Page 5: Control Valve IPF Function Test1

WORK INSTRUCTION - CONTROL VALVE IPF FUNCTION TEST Rev 02

Appendix A - Historical Revision Change List

Rev Location of Change Brief Description of Change

P1 Preliminary For Comment – Originator: Wong Chue Seng 7 Sep 07

01 AFU Approved for Use – Haridas Bhaskaran Oct 08

02 AFU Approved for Use – Haridas Bhaskaran May 08

7000-S-90-10-P-0112-00-E Page 5 of 5