13
Contract R-39093 I-69 Added Travel Lanes and Preventive Maintenance Delaware and Madison County

Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Contract R-39093 I-69 Added Travel Lanes and Preventive

Maintenance Delaware and Madison County

Page 2: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

ROADWAY IMPROVEMENTS:

Limits of Added Travel Lanes (8 miles) vs. Pavement Rehabilitation (6 miles)

Rehabilitation of 20 bridges

2

Contract R-39093

Page 3: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Project Scope (continued)

New Signs New Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail / Safety Features Wetland Mitigation

3

Contract R-39093

Page 4: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

I-69 MAINTENANCE OF TRAFFIC: Work Zone Speed Limit shall be 55 mph. Work Site Speed Limit shall be 45 mph. Two lanes of traffic shall be maintained in each direction

with the use of crossovers and contra-flow lanes. Night-time lane closures will be used Local detour routes will be used during closure of Columbus

Ave. and CR 400 W

4

Contract R-39093

Page 5: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

ASPHALT TEST STRIPS :

5

Contract R-39093

In the Added Travel Lanes Sections, twenty two different test strips will be constructed.

Primary objective: to explore options for more cost-effective pavement structures

Page 6: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

I-69 Design Build

Page 7: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Added Travel Lanes Phase 2 Build Inside Lanes Shoulder and Median

Southbound Northbound

Page 8: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Added Travel Lanes Phase 3 Patch and Mill Proposed Center Lanes

Southbound Northbound

Page 9: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Added Travel Lanes Phase 4 Patch and Mill Existing Right Lane

Southbound Northbound

Page 10: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Preventative Maintenance Overlay Phase 3A Construction Phasing

Southbound Northbound

Page 11: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Preventative Maintenance Overlay Phase 4A Construction Phasing

Southbound Northbound

Page 12: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Project Schedule Begin Construction: Late June / Early July 2018 Columbus Avenue Closure: Fall 2018 CR 400 W Closure: April – July 2019 SR 9 / 109 Restrictions: 2019 SR 9 / 67 Restrictions: 2019 Project Completion: - November 2019

12

Contract R-39093

Page 13: Contract R-39093 I-69 Added Travel Lanes and Preventive ... Public Info Meeting Presentation 6-11-2018.pdfNew Interchange Lighting New Traffic Signals New Pavement Markings New Guardrail

Thank you!

13