25
Civil Engineering and Development Department Contract No. NE/2015/02 Tseung Kwan O Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report January 2017

Contract No. NE/2015/02 Tseung Kwan O Lam Tin …...Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road-P2 and Associated Works Water Gate System and Temporary Steel Cofferdam

  • Upload
    others

  • View
    10

  • Download
    1

Embed Size (px)

Citation preview

Civil Engineering and

Development Department

Contract No. NE/2015/02 – Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report January 2017

Contract No. NE/2015/02

Tseung Kwan O – Lam Tin Tunnel Road-P2 and Associated Works

Water Gate System and Temporary Steel Cofferdam Design Report

Rev. Date Prepared by Checked by Approved by

A 11-Oct-2016 Trevor Chung Kelvin Tse Clifford Phung

B 2-Nov-2016 Trevor Chung Kelvin Tse Clifford Phung

C 17-Nov-2016 Trevor Chung Kelvin Tse Clifford Phung

D 9-Dec-2016 Trevor Chung Kelvin Tse Clifford Phung

E 19-Jan-2017 Trevor Chung Kelvin Tse Clifford Phung

Prepared by

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

CONTENTS

1 INTRODUCTION ................................................................................................................... 1

1.1 Background ....................................................................................................................................1

1.2 Scope of the Report .......................................................................................................................1

2 DESIGN OF WATER GATE SYSTEM ................................................................................... 2

2.1 Description of Water Gate System .................................................................................................2

2.2 Methodologies ................................................................................................................................2

2.2.1 Double Water Gate Operation ....................................................................................................... 3

2.3 Components of Water Gate ...........................................................................................................4

2.3.1 Water Gate Steel Frame ................................................................................................................ 4

2.3.2 Pin Connection .............................................................................................................................. 5

2.4 Demonstration of Calculation .........................................................................................................6

2.4.1 Structural Analysis of Water Gate Steel Frame ............................................................................. 6

3 DESIGN OF TEMPORARY STEEL COFFERDAM ................................................................ 7

3.1 Available Geotechnical Information ...............................................................................................7

3.1.1 Site Geology .................................................................................................................................. 7

3.2 Geotechnical Design Parameters ..................................................................................................8

3.2.1 Adopted Soil Parameters ............................................................................................................... 8

3.2.2 Design Seawater Level .................................................................................................................. 8

3.3 Proposed Temporary Steel Cofferdam ..........................................................................................9

3.3.1 General .......................................................................................................................................... 9

3.3.2 Type 1 Cofferdam – Composite Steel Sheet Pile Wall ................................................................... 9

3.3.3 Type 2 Cofferdam – Pre-fabricated Steel Water Tanks ............................................................... 10

3.3.4 Type 3 Cofferdam – Concrete Block Wall and Geotextile ............................................................ 11

3.4 Construction Sequence ............................................................................................................... 11

4 CONCLUSION ..................................................................................................................... 12

LIST OF APPENDICES

Appendix A Drawings

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 1

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

1 INTRODUCTION

1.1 Background

Civil Engineering and Development Department (CEDD) has awarded the Works Contract

No. NE/2015/02 – Tseung Kwan O - Lam Tin Tunnel – Road P2 and Associated Works to

the Joint Venture of China Road and Bridge Corporation and Build King Civil Engineering

Ltd. (CRBC - Build King JV) in July 2016. The works include approximately 3 hectares of

reclamation works at Junk Bay (Tseung Kwan O), construction of the 800m long P2 Road

(with approximate 200m being an underpass structure) and associated building, civil,

structural, marine, electrical and mechanical, landscaping and environmental works.

This submission serves as the submission under Environmental Permit Condition 3.3D with

layout plans and explanatory statement to show the design and operation arrangement of

the double water gate system and temporary steel cofferdam.

Figure 1.1 – Location Plan of Contract No. NE/2015/02

1.2 Scope of the Report

This report presents the detailed design of water gate system and temporary steel

cofferdam for enclosing the marine works area.

Contract No.

NE/2015/02

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 2

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

2 DESIGN OF WATER GATE SYSTEM

2.1 Description of Water Gate System

Water gate system is the only marine access to the marine works area and is considered to

be part of the steel cofferdam. Vessels will navigate through our double water gate system

for transporting dredging mud and construction materials. The system aims to avoid any

leakage of polluted water from the site so as to comply with water quality objectives. Our

proposed size of water gate system is designed to accommodate the size of marine

construction vessel including derrick barge, split hopper barge and motor tug. The internal

dimension of the water gate system is suggested to be 55m(L) x 24m(B). Considering the

tight construction programme with the gate installation on the critical path, design of this

system allows easy and speedy installation and yet ensures its functional requirements.

Here a modified semi-submersible barge with watertight gates to be installed at both sides

of the barge is introduced.

Figure 2.1 - Double Water Gate System with a Vessel inside the Basin

2.2 Methodologies

The modified barge will be towed and sunk in place by filling its water ballast. Cofferdam

will be installed at its corners enclosing the marine works area. The gate is proposed to be

located at the eastern tip of the site. With due consideration of site constraints such as

works boundary, works programme, water depth, wave loads, marine construction traffic,

extent of dredged slope, size of the gate system and interface with adjacent projects,

potentially, it is proposed to locate the gate at the eastern side of the site shown in Figure

2.2. Therefore, it will not clash with the adjacent works and minimize the impacts to all

works nearby.

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 3

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

Figure 2.2 – General Layout Plan of Double Water Gate System

2.2.1 Double Water Gate Operation

Water gates are operated as if the gates of roll-on-roll-off barge equipped with hydraulic

cylinders and buoyancy ballasts. The water gates are fitted with rubber or other

waterproofing seals at the bottom and two vertical sides.

The water gate is operated in steps as follows:

1. Pump ballast water out of the water gate tip to float up the gate to water level;

2. Use the electrical winches to pull water gate into the closed position ensuring the

water-tightness;

3. To open the gate, the above steps are followed in reverse order.

For the operation of double water gates system, whenever the vessels move out of the

enclosed works area, the sequences of operation shall be as follows:

1. Open the inner gate and the vessel moves into the basin;

2. Close the inner water gate;

3. Exchange the water in the basin by pumping sea water into the basin and pumping

muddy water into enclosed area;

N

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 4

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

11

22

33

44

55

66

VV

22

VV

11

VV

22

VV

22

VV

22

VV

22

4. When all the water in the basin has exchanged by one cycle, i.e. the volume of

water in the vessel basin (with the vessel) has been replaced by sea water, open

the outer water gate and the vessel move out of the basin;

5. When the vessels move into the enclosed works area, the above sequences shall

be reversed except the water exchange in Step 3 above is not required. (In the case

where the water in the basin is polluted, the outer gate will keep closed and water

exchange will be carried out before letting the vessels move in.)

6. The gates will be kept closed at all time during marine construction period except

that when the vessels need to move in/out the enclosed work area.

The details of double water gate system and its operation are shown in Figure 2.3.

Figure 2.3 - Operation of Double Water Gate System

2.3 Components of Water Gate

2.3.1 Water Gate Steel Frame

The water gate steel frame structure is a combination of a vertical frame and a plan truss. A

3-D view of the steel frame structure is shown in Figure 2.4. The dimension of the vertical

steel frame is 24.6m(B) x 10.5m(H) and it is formed by horizontal and vertical UB/UC

sections. The horizontal steel members are continuous and act as the main structural

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 5

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

members spanning over the width of the water gate while the vertical steel members with

typical 2.4m spacing act as secondary beams. The plan steel truss is 24.6m in length and

1.5m in depth. It is in a form of warren pattern with verticals, consisting 10 bays with typical

bay length of 2.4m. The structural framing and steel member size of the water gate is

shown on drawing no. 91447/K/CFD/GA/0008 in Appendix A.

Figure 2.4 – Water Gate Steel Frame

2.3.2 Pin Connection

The water gate is connected to the barge with pin connection. The pin connection consists

of 3 pieces of steel plate with 50mm thickness and a Grade 8.8 M60 steel pin. The steel

plates of the pin connections are connected to the bottom member of the steel frame and

the barge through welding. 8 nos. of stiffener plates with 20mm thickness are added to

each pin connection to enhance its structural performance. There are 11 nos. of pin

connections in total. A 3-D view of the pin connection is shown in Figure 2.5. Details of the

pin connection are shown on drawing no. 91447/K/CFD/TD/0006 in Appendix A.

Figure 2.5 – Pin Connection

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 6

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

2.4 Demonstration of Calculation

2.4.1 Structural Analysis of Water Gate Steel Frame

Structural analysis of the water gate steel frame will be undertaken using three-dimensional

space-frames. The computer model will be used to determine the load effects due to all the

applied loads.

The structural analysis of the water gate steel frame is performed by SAP2000(V15) as

frame and truss structure.

The following list of structural analysis software will be used:

SAP2000 version 15.1.0 – General elastic static linear analysis.

In-House Spreadsheet – From the analysis model, loading effects of steel members and

support reactions under different design cases are obtained and used for steel member and

connection design. In-house spreadsheet is used for the design of the water gate steel

frame.

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 7

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

3 DESIGN OF TEMPORARY STEEL COFFERDAM

3.1 Available Geotechnical Information

3.1.1 Site Geology

According to 1:20000 Hong Kong Geological Survey Map Sheet No. 11, the site (Road P2

and associated works) are underlain by Mesozoic intermediate to silicic volcanic and

granitic rocks of the Early Cretaceous Repulse Bay Volcanic Group. The volcanic rock

mass along the site is predominately comprised of Mount Davis.

Figure 3.1 – Part-Print of Geological Survey Map

Road P2 and

Associated Works

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 8

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

3.2 Geotechnical Design Parameters

3.2.1 Adopted Soil Parameters

The adopted soil parameters for the steel cofferdam design with reference to the plots for

new reclamation land in the Design Memorandum for Road P2 Structures are summarized

in Table 3.1.

Soil Type Unit

Weight, ɣ (kN/m3)

Cohesion, c’ (kPa)

Friction Angle,

’ (o)

Design Soil Stiffness, E’ (kPa)

Undrained Shear

Strength, Su (kPa)

Undrained Young’s Modulus, Eu (kPa)

Marine Deposit (Sand)

19 4 34 10,500 - -

Marine Deposit

(Silt/Clay) 19 0 28 90.4σv’ 0.26σv’ 104σv’

ALL (Silt/Clay)

19 5 33 13,900 40 16000

CDT 19 4 37 121,000 - -

Table 3.1 – Summary of Design Parameters

3.2.2 Design Seawater Level

In accordance with the Port Works Design Manual: Part 1 – General Design Considerations

for Marine Works (2002), the extreme sea level at Quarry Bay / North Point for a returned

period of 2 years is +2.65mPD, and this is adopted as the highest design seawater level for

the design of the temporary steel cofferdam.

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 9

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

3.3 Proposed Temporary Steel Cofferdam

3.3.1 General

The actual dredging level and area will depend on the cone penetration test results and the

design of dredging slope. In addition, sufficient working space has to be provided. By

considering the above, the area enclosed by the steel cofferdam has been reviewed and

updated as shown in the latest steel cofferdam design drawings. Notwithstanding this, the

total maximum dredged volume (400,000m3) will be strictly followed.

3 types of temporary steel cofferdam, namely Type 1, Type 2 and Type 3, are proposed

with consideration of the site conditions. Type 1 steel cofferdam is composed of composite

interlocked steel sheet pile wall (FSP IV) locally strengthened with universal beams

(610x229x113kg/m UB) at 800mm c/c. Type 2 cofferdam is in the form of pre-fabricated

steel tanks. Type 3 is formed of concrete block wall and geotextile.

3.3.2 Type 1 Cofferdam – Composite Steel Sheet Pile Wall

Figure 3.2 – Type 1 Cofferdam

Type 1 Cofferdam is proposed at the east and south of marine works area where the hard

geological stratum is relatively deep. The interlocked sheet pile wall FSP IV will be from

+2.75mPD at the top down to -20mPD. 610x229x113kg/m UB will be used to strengthen

the sheet pile wall at 800mm c/c from -4.5mPD to -16.5mPD.

The wave and static water loads on the Type 1 Cofferdam has been determined in

accordance with the Port Works Design Manual: Part 1 – General Design Considerations

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 10

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

for Marine Works. Stability checking, as well as detailed analysis of the Type 1 Cofferdam

using the Geotechnical Programme “PLAXIS”, is performed.

The structural checking of the Type 1 Cofferdam is based on the maximum bending

moment and shear force obtained from the PLAXIS analysis. The structural checking is

carried out in accordance with the Code of Practice for Structural Use of Steel 2011.

The detailed design drawings are enclosed in Appendix A.

3.3.3 Type 2 Cofferdam – Pre-fabricated Steel Water Tanks

Figure 3.3 – Type 2 Cofferdam

The Type 2 Cofferdam in the form of steel water tanks is proposed at the west of marine

works area and locally at the east of the marine works area adjacent to the existing DSD

de-silting compound. Type 2 Cofferdam will be with a top level at +2.85mPD, and with 1m

embedment into the existing seabed level. Type 2 Cofferdam is further divided into 2 sub-

types, namely Type 2A and Type 2B. Type 2A and Type 2B Cofferdam is designed to be

8.75m (H) x ~9m (W) x ~4m (B) and 8.75m (H) x ~9m (W) x ~6m (B) respectively. To

ensure its stability during its service, concrete blocks (or alternatively sand) will be placed

into the tanks to increase its self-weight. A tight connection with the use of steel plate will

be provided between individual units of steel water tank to prevent spread of sediments to

the open sea.

With considering the proposed location of the Type 2A cofferdam, it is expected that the

wave load on the Type 2 Cofferdam will be minimal. Therefore, the Type 2 Cofferdam is

designed against static water pressure, considering that there is 1m water level difference

between the marine works area and the open sea. For Type 2B Cofferdam, both wave and

static water loads are considered in the design in accordance with the Port Works Design

Manual: Part 1 – General Design Considerations for Marine Works.

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 11

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

Stability checking, as well as detailed analysis of the Type 2 Cofferdam using the Structural

Programme “SAP2000”, is performed. The structural checking is also carried out in

accordance with the Code of Practice for Structural Use of Steel 2011.

The detailed design drawings are enclosed in Appendix A.

3.3.4 Type 3 Cofferdam – Concrete Block Wall and Geotextile

Figure 3.4 – Type 3 Cofferdam

The Type 3 cofferdam is in composed of concrete blocks with geotextile layer behind. It will

only be constructed very locally near the existing seawall where the existing seabed is not

flat and Type 2 cofferdam cannot be constructed. Before the Type 3 cofferdam

construction, bag concrete will be placed on the existing seabed to prepare a level ground.

The detailed design drawings are enclosed in Appendix A.

3.4 Construction Sequence

The construction sequence for the proposed temporary steel cofferdam is summarized as

follow:

(i) Install silt curtain (According to EP Condition 3.3E, silt curtains surrounding the

dredging and reclamation areas shall be deployed during installation/removal works

of the cofferdam and dredging and filling works in accordance with the Silt Curtain

Deployment Plan submitted under Condition 2.8).

(ii) Install temporary cofferdam and double water gate system.

(iii) Carry out marine works (dredging of marine sediments and filling works).

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report 12

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

4 CONCLUSION

Based on the detailed analysis and design of the water gate system and temporary steel

cofferdam, it is considered that the proposed scheme is feasible and safe with adequate

factor of safety, and the impacts of the proposed works on the adjacent ground,

underground utilities and existing structures are considered negligible.

This report has also demonstrated that the marine water quality outside the cofferdam will

not be adversely affected by the dredging/filling works, and the design is fully compliant to

EP Condition 3.3D.

CEDD Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel Road P2 and Associated Works Water Gate System and Temporary Steel Cofferdam Design Report

Water Gate System and Temporary Steel Cofferdam Design Report

January 2017 S:\UPLOAD_TEMP\Design from Meinhardt\TW1 Design of Temporary Steel Cofferdam\ET IEC Submissions\20170114\Rev. E\Water Gate System and Temporary Steel Cofferdam Design Report.doc

APPENDIX A

DRAWINGS

Temporary Works Design Drawings in compliance with Contract No. NE/2015/02

___________________ ________________ Chengrui Hu Date Independent Checking Engineer on behalf of: Hewson Consulting Limited, Unit 1101, 11/F, 9 Chong Yip Street, Kwun Tong, Kowloon, Hong Kong

30/11/2016

MSc, CEng, MICE, MHKIE, RPE

Temporary Works Design Drawings in compliance with Contract No. NE/2015/02

___________________ ________________ Chengrui Hu Date Independent Checking Engineer on behalf of: Hewson Consulting Limited, Unit 1101, 11/F, 9 Chong Yip Street, Kwun Tong, Kowloon, Hong Kong

30/11/2016

MSc, CEng, MICE, MHKIE, RPE

Temporary Works Design Drawings in compliance with Contract No. NE/2015/02

___________________ ________________ Chengrui Hu Date Independent Checking Engineer on behalf of: Hewson Consulting Limited, Unit 1101, 11/F, 9 Chong Yip Street, Kwun Tong, Kowloon, Hong Kong

30/11/2016

MSc, CEng, MICE, MHKIE, RPE

Temporary Works Design Drawings in compliance with Contract No. NE/2015/02

___________________ ________________ Chengrui Hu Date Independent Checking Engineer on behalf of: Hewson Consulting Limited, Unit 1101, 11/F, 9 Chong Yip Street, Kwun Tong, Kowloon, Hong Kong

30/11/2016

MSc, CEng, MICE, MHKIE, RPE

Temporary Works Design Drawings in compliance with Contract No. NE/2015/02

___________________ ________________ Chengrui Hu Date Independent Checking Engineer on behalf of: Hewson Consulting Limited, Unit 1101, 11/F, 9 Chong Yip Street, Kwun Tong, Kowloon, Hong Kong

30/11/2016

MSc, CEng, MICE, MHKIE, RPE

Temporary Works Design Drawings in compliance with Contract No. NE/2015/02

___________________ ________________ Chengrui Hu Date Independent Checking Engineer on behalf of: Hewson Consulting Limited, Unit 1101, 11/F, 9 Chong Yip Street, Kwun Tong, Kowloon, Hong Kong

30/11/2016

MSc, CEng, MICE, MHKIE, RPE