CONTRACT MANAGEMENT GUIDE

Contract Administration

Office of the Vice President for Finance and Administration

Texas A&M Health Science Center

Page 2: CONTRACT MANAGEMENT GUIDE Contract Administration

Contract Administration's mission is to guide our campus clients through the complex contracting processes to achieve their contract needs.

CONTRACT APPROVED

Mission

Page 3: CONTRACT MANAGEMENT GUIDE Contract Administration

Contract Management

Planning Procurement Contract Formation Rate/Price

Establishment Contract Administration

Page 4: CONTRACT MANAGEMENT GUIDE Contract Administration

Contract Management

There is no single “right” way to contract.

Page 5: CONTRACT MANAGEMENT GUIDE Contract Administration

Contracting Management Framework

Planning: Identify contracting objectives and contracting strategy.

Procurement: Fairly and objectively select the most qualified contractors.

Contract Formation: Ensure the contract contains provisions that hold the contractor accountable for producing the desired results.

Rate/Price Establishment: Establish processes that are cost-effective and aligned with the cost of providing the goods and services.

Contract Administration/Oversight: Monitor and enforce the terms of the contract.

Page 6: CONTRACT MANAGEMENT GUIDE Contract Administration

Number of New ContractsProcessed in FY 2007

BCD

CBHEC

HSC

COM

IBT

PHARM

SRPH

72

85

52

88

18

59

22

Total: 396

Page 7: CONTRACT MANAGEMENT GUIDE Contract Administration

Contract Management Guide

Transactions involving furthering research projects must be processed through the Office of the Vice President for Research and Graduate Studies.

New process – Contract Administration to serve as single point of submission of all contracts.

Research

Research

Page 8: CONTRACT MANAGEMENT GUIDE Contract Administration

Applicability

This Contract Management Guide is intended to supplement A&M System policies and regulations on contracts and provide guidance in complying with:

SPRM 25.07: Contract Administration

SPRM 25.07.01: Contract Administration Procedures and Delegations

SPRM 25.99.02: Component Purchasing Authority

TAMUS Procurement Code

State of Texas Contract Management Guide

State of Texas Procurement Manual

Page 9: CONTRACT MANAGEMENT GUIDE Contract Administration

Purchase Order or Contract?

If vendor/other party accepts HSC term and conditions and does not require a signed contract, a purchase order may be used to obtain commonly available goods and services in excess of $5,000.00.

If the subject matter of the transaction involves human performance, such as rendition of services, then a contract should be used.

Page 10: CONTRACT MANAGEMENT GUIDE Contract Administration

Best Value in Contracting

The HSC member department may acquire goods or services by the procurement method that provides the best value, including competitive bidding and competitive sealed proposals.

ALL purchases of goods in excess of $5,000.00, and services in excess of $5,000.00 per year, must go through HSC Procurement Services regardless of contract document form.

The Recommendation for Award must provide information pertinent to procurement method, price tabulations outlining the acquisition process, basis of best value to the HSC member department and name of the preferred vendor.

Page 11: CONTRACT MANAGEMENT GUIDE Contract Administration

CONTRACT APPROVAL PROCEDURESFLOWCHART

Originator negotiates with one or more other parties to create contract.

Contract originals (two originals) may

be sent to Contracts Administration with Transmittal Form.

Contract entered into database. Contract

Administration reviews contract.

If contract found not sufficient.

Originator asked to make changes.

Contract found sufficient.

Originator returns contract to Contracts

Administration for further review.

Page 12: CONTRACT MANAGEMENT GUIDE Contract Administration

CONTRACT APPROVAL PROCEDURESFLOWCHART

Is contract over $50,000?Is contract

developed by other party?

If the answer to one of the questions is

yes.

Contract is forwarded to the HSC Chief Legal Officer for review.

If contract is found not sufficient.

Contract returned to Contracts

Administration. Originator asked to

make recommended changes.

Contract found sufficient

Originator returns contract to Contracts

Administration for further review.

Contract Administration

updates database.

Page 13: CONTRACT MANAGEMENT GUIDE Contract Administration

CONTRACT APPROVAL PROCEDURESFLOWCHART

Contract Administration

advises originator the contract is ready to begin routing. A

transmittal form needs to be

completed by the originator. Two

unsigned originals of the contract should be attached to the transmittal form.

Contract found sufficient

Originator obtains necessary

signatures for the transmittal form up to Dean/Director level and returns contract and transmittal form

to Contracts Administration.

After final signature is received, HSC Contracts Administration

keeps one fully executed original and if necessary sends the other fully executed original

back to the other party. One PDF copy of the fully executed

contract is forwarded to the originator for recordkeeping.

Contracts Administration routes to appropriate HSC signatories and to the other party for

signature.

Page 14: CONTRACT MANAGEMENT GUIDE Contract Administration

  Proper Contract Form

Standard Form of Agreements: Standard agreements are forms that have been approved as such by the A&M System Office of General Counsel (OGC). Review by OGC is unnecessary for a standard form of agreement for three years unless substantive changes have been made to the agreement.

Other Contracts:  Other parties prefer to use their contract for a transaction.  If a non-standard contract will be used for a transaction, the contract must be submitted for review to HSC Chief Legal Officer and/or OGC as to form and legal sufficiency.

Page 15: CONTRACT MANAGEMENT GUIDE Contract Administration

Completing the Contract

All contracts must be submitted to the HSC Office of Contract Administration for compliance review.

All contracts must be complete and all necessary information must be type written.

Attach all necessary contract addenda.

After compliance review, the signatures of persons or officials with delegated authority must be obtained.

Page 16: CONTRACT MANAGEMENT GUIDE Contract Administration

Completing the Contract

No contract shall be routed to the other party for review or signing without prior approval from HSC Contracts Administration.

All contracts must have applicable contract administrative and legal reviews and appropriate signatures prior to performance by the parties as set forth within the contract.

Page 17: CONTRACT MANAGEMENT GUIDE Contract Administration

Signatures of Authorized Representatives of the Parties

Signatures. No person has the authority to bind the HSC contractually except in accordance with A&M System policy. Else, the person could be held personally liable.

Contracts are legally binding on the HSC only upon signature by an HSC official with delegated contractual signatory authority (Delegation of Authority Matrix).

Page 18: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Contracts

The following must be submitted to the Office of Contracts Administration:

– Two originals of the contract;

– At least two originals of all other contract addenda that are required for processing the contract, as discussed in this Management Guide, if not included within the body of the contract itself; and

– Completed Contract / Agreement Transmittal Approval Form.

Page 19: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Contracts

When the Office of Contracts Administration receives contracts:

1. The contracts / agreement transmittal approval form is date stamped.

2. The contract is issued a contract number.

3. A file folder is created.

4. The formal review process commences.

5. Upon completion of legal / administrative review, the contract is then routed to the appropriate HSC official(s) for signature.

Page 20: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Contracts

After the contract has been signed by all parties:

1. Contracts Administration will keep one fully signed copy for its file - Contract Repository.

2. One fully signed original kept by or returned to the other party.

3. One PDF copy of the contract forwarded to the originating department for recordkeeping.

Document Management System Laserfiche

X

Page 21: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Time Frames

All forms of agreements less than $50,000 must be submitted to the HSC Office of Contracts Administration at least 30 business days prior to start date.

Contracts originating from other party must be submitted at least 45 business days prior to start date.

Page 22: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Time Frames

Contracts for Consulting Services(Payment of more than $15,000 will be made)

Submitted at least 60 business days prior to the start date for services. 

Why?

The additional time is to notify the Governor's Office of Budget Planning and Policy/Legislative Budget Board and to publish a request for proposal for the consulting services.

Page 23: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Time Frames

Contracts for Professional Services(As defined by state law for which the amount of the contract exceeds $14,000)

Contract must be submitted at least 60 days prior to the start date for services. 

Why?

The additional time is to notify the Legislative Budget Board and to publish a request for proposal for the professional services.

Page 24: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Time Frames

Contracts for which Vice President Recommended/Approval Must

be Obtained (Less than $100,000.00) 

Barry C. Nelson, Ph.D.

Vice President for Finance &

Administration

David S. Carlson, Ph.D.

Vice President for Research &

Graduate Studies

Alicia Dorsey, Ph.D.

Vice President for Communications

& Program Development

Roderick McCallum, Ph.D.

Vice President for Academic Affairs

David Cantrell, M.A., M.B.A., M.P.A.Vice President for

Information Technology and

Chief Information Officer

NOTE: Rayellen Milburn, CPA, Senior Associate Vice President for Finance & Administration, has delegated authority to sign contracts less than $50,000.00

Page 25: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Time Frames

Contracts for which President Approval Must Be

Obtained ($100,000.00 to $199,000.00) 

The contract will require Vice President‘s approval before processing to the President for approval.

Approval by the President may take one week minimum.

President and Vice Chancellor for Health Affairs

Nancy W. Dickey, M.D.

Page 26: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Time Frames

Contracts for which Chancellor Approval Must Be

Obtained ($200,000.00 to $299,000.00) 

The contract will require HSC President‘s approval before processing to the Chancellor for approval.

The Chancellor approval process usually takes at least two weeks minimum.

ChancellorMichael

McKinney

Page 27: CONTRACT MANAGEMENT GUIDE Contract Administration

Processing Time FramesContracts for which A&M System Board of Regents Approval Must be Obtained

($300,000.00 or greater and/or term of contract longer than five years)

HSC member business administrator should contact the Office of Contracts Administration for guidance with Agenda Items for contracts that must be approved by the Board of Regents. The Board of Regents approval process usually takes at least two months.

The Texas A&M University System Board of Regents

Page 28: CONTRACT MANAGEMENT GUIDE Contract Administration

The Elements of Contract Drafting

Offer and Acceptance Consideration Indefiniteness Enforceability Capacity Parol Evidence Interpretation Mistake Force Majeure Promise and Condition Modification and Discharge Warranties Damages Operative Language and Boilerplate Third Parties

Page 29: CONTRACT MANAGEMENT GUIDE Contract Administration

Contract Processing

Sooner than Later!