TANGGUH GPF PROJECT CONTRACT CHANGE CONTROL 0 04 Jul 01 JP ISSUED FOR IMPLEMENTATION - - NY REL B 25 Jun 01 JP ISSUED FOR PMT APPROVAL - - NY REL A 20 Jun 01 JP ISSUED FOR PMT INTERNAL REVIEW - - REV DATE BY DESCRIPTION CHECK APPR. SPEC. REP. ENGINEER APROVAL COMPANY APPROVAL STATUS CODE : A = Issued for COMPANY Review - B = Issued for COMPANY review \ approval - C = Approved TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE OWNER BP BERAU LTD TANGGUH GAS PRODUCTION FACILITIES PROJECT 9000-PRC-EM-0006 REVISION 0 STATUS C Page 1 of 12 Tangguh Development

Contract Change Control9000 PRC EM 0006_BP

Embed Size (px)

DESCRIPTION

Contoh change order

Citation preview

Page 1: Contract Change Control9000 PRC EM 0006_BP

TANGGUH GPF PROJECT

CONTRACT CHANGE CONTROL

0 04 Jul 01 JP ISSUED FOR IMPLEMENTATION - - NY REL

B 25 Jun 01 JP ISSUED FOR PMT APPROVAL - - NY REL

A 20 Jun 01 JP ISSUED FOR PMT INTERNAL REVIEW - -

REV DATE BY DESCRIPTION CHECK APPR. SPEC. REP.

ENGINEER APROVAL

COMPANY APPROVAL

STATUS CODE : A = Issued for COMPANY Review - B = Issued for COMPANY review \ approval - C = Approved

TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE OWNER

BP BERAU LTD

TANGGUH GAS PRODUCTION FACILITIES PROJECT

9000-PRC-EM-0006

REVISION

0 STATUS

C

Page 1 of 12

Tangguh Development

Page 2: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 2 of 12

Revision: 0C

TABULATION OF REVISED PAGES

SHEET REVISIONS SHEET REVISIONS A B 0 A B 0 1 X 51 2 X 52 3 X X 53 4 X X 54 5 X X 55 6 X X 56 7 X X 57 8 X X 58 9 X X 59 10 X X 60 11 X X 61 12 X 62 13 63 14 64 15 65 16 66 17 67 18 68 19 69 20 70 21 71 22 72 23 73 24 74 25 75 26 76 27 77 28 78 29 79 30 80 31 81 32 82 33 83 34 84 35 85 36 86 37 87 38 88 39 89 40 90 41 ATTACHMENTS \ APPENDIX 42 1 X X A 43 2 X X B 44 3 X X C 45 4 X X D 46 5 X E 47 6 F 48 7 G 49 8 H 50 9 I

Page 3: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 3 of 12

Revision: 0C

DESCRIPTON OF CHANGES

Section Affected

Description of Change Rev

All

First Issue

A

CONTENTS TABLE

Update to reflect changes in body text B

1.0 Purpose and Scope included into one section and expanded to detail applicability

B

2.0 Section 2.0 on Terms, Definitions and Abbreviations added for clarity

B

4.0 Titles of responsible personnel update and corrected B

5.0 All titles affected changed in the body of the text B

Attachments Reference to Project Change Notice changed to Contract Change Notice in attachments 1 through 4. Contract Change Order added as Attachment 5

B

None

Issued for implementation

0

Page 4: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 4 of 12

Revision: 0C

CONTENTS

Front Page 1 Tabulation of Revised Pages 2 Description of Changes 3 Contents 4 1.0 PURPOSE AND SCOPE 5 1.1 PURPOSE 5 1.2 SCOPE 5 2.0 TERMS, DEFINITIONS AND ABBREVIATIONS 6 2.1 ABBREVIATIONS 6 2.2 TERMS AND DEFINITIONS 3.0 REFERENCES 7 4.0 RESPONSIBILITIES 8 4.1 COMPANY SENIOR PMT MANAGER 8 4.2 COMPANY CHIEF OF FACILITIES ENGINEERING 8 4.3 COMPANY COST CONTROL REPRESENTATIVE 8 4.4 CONTRACTOR PROJECT MANAGER 8 4.5 CONTRACTOR ENGINEERING MANAGER 8 5.0 PROCEDURE

10 5.1 GENERAL CHANGE CONTROL PROCESS 10 5.2 CHANGE CONTROL NOTICE 10 5.3 CONTRACTOR CHANGE CONTROL REVIEW 10 5.4 CONTRACTOR CHANGE CONTROL REGISTER 10 5.5 CONTRACTOR CHANGE APPROVAL 11 5.6 CONTRACTOR CHANGE ESTIMATES 11 5.7 CHANGE APPROVAL BY COMPANY 11 5.8 CONTRACT CHANGE PROPOSAL 12 5.9 DISPUTED CONTRACT CHANGE PROPOSAL 12 ATTACHMENT 1 CHANGE CONTROL FLOWCHART ATTACHMENT 2 CONTRACT CHANGE NOTICE ATTACHMENT 3 CONTRACT CHANGE PROPOSAL ATTACHMENT 4 CONTRACT CHANGE NOTICE REGISTER

Page 5: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 5 of 12

Revision: 0C

ATTACHMENT 5 CONTRACT CHANGE ORDER

Page 6: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 6 of 12

Revision: 0C

1.0 PURPOSE AND SCOPE 1.1 PURPOSE

The purpose of this document is to define the system to be followed for the management of any changes for the Tangguh Gas Production Facilities (GPF) Project.

1.2 SCOPE

This procedure covers change to the agreed scope of work, irrespective of the source of the change requirement, and all technical changes which change the intent of the agreed design basis criteria (i.e. COMPANY Statement of Requirements (SOR), Basis of Design documents / Design Philosophies, Safety Case, Criticality Assessment, Material Changes and any Regulatory requirements). The procedure shall also apply where there are any changes estimated to have an impact to Cost or Schedule. Examples of the source of change include (but are not limited to): ?? Change to design deliverables which change the design basis intent ?? Instructions from COMPANY to CONTRACTOR ?? Changes arising from Technical Queries / Technical Notes, Site Queries or Field

Design Changes. ?? Supplier or CONTRACTOR deviations or concessions (Concession Request) ?? Fabrication changes ?? Construction and Construction Methodology Note: In addition to this change control process, CONTRACTOR(s) shall be expected to operate suitable change control procedures for their documents. This requires the maintenance of 'Master documents' upon which changes are noted (in between the document update and re-issue) and communicated to other disciplines / parties that may be impacted by the change. Any site changes shall be recorded by either the Technical Query / Technical Notes Procedure, document number 9000-PRC-EM-0004 and / or Field Design Change Procedure, document number 9000-PRC-EM-0007 and any concessions shall be handled in accordance with Concession Request Specification, document number 9000-PRC-EM-0005.

Page 7: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 7 of 12

Revision: 0C

2.0 TERMS, DEFINITIONS AND ABBREVIATIONS

2.1 ABBREVIATIONS CCP Contract Change Proposal CTR Cost, Time and Resources Data Sheet CCN Contract Change Notification SOR Statement of Requirements

2.2 TERMS AND DEFINITIONS

2.2.1 Statement of Requirements A Statement of Requirements is any statement within the Contract that places a contractual responsibility on CONTRACTOR to perform Work, whether stated or implied in the Scope of Work, in any Exhibit, or in Cost, Time and Resources Data Sheet or any other document.

2.2.2 Concession COMPANY defines a concession as any departure from any requirements stated in the Contract.

2.2.3 CONTRACTOR Project Manager CONTRACTOR Project Manager may also be referred to as CONTRACTOR Representative as stated in the Contract Terms and Conditions and in Exhibit A.

2.2.4 CONTRACTOR Engineering Manager The CONTRACTOR Engineering Manager may also be referred to as the Engineering Representative

Page 8: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 8 of 12

Revision: 0C

3.0 REFERENCES

The following procedures are referenced within this documents and shall, where applicable and approved, be used in conjunction with any identified changes: 9000-PRC-EM-0001 Document and Drawing Numbering Procedure 9000-PRC-EM-0004 Site Technical Query / Technical Notes Procedure 9000-PRC-EM-0005 Concession Request Procedure 9000-PRC-EM-0007 Field Design Change Procedure

Page 9: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 9 of 12

Revision: 0C

4.0 RESPONSIBILITIES

4.1 COMPANY SENIOR PMT MANAGER

COMPANY Senior PMT Manager has overall responsibility for Contract Change process and shall be the authority for allowing work considered a change to proceed.

4.2 COMPANY CHIEF OF FACILITIES ENGINEERING COMPANY Chief of Facilities Engineering has overall responsibility for technical endorsement of design changes.

4.3 COMPANY COST CONTROL REPRESENTATIVE

COMPANY Cost Control Representative is responsible for reviewing the estimated cost / schedule impact of the change.

4.4 COMPANY SENIOR ASSURANCE ENGINEER COMPANY Senior Assurance Engineer has overall responsibility for ensuring that this procedure is effective, applied correctly, and is updated in accordance with any change in Project requirements. The COMPANY Senior Assurance Engineer shall also be responsible for ensuring that any changes are subject to review by the applicable engineering disciplines in order to identify the need for risk assessment.

4.5 CONTRACTOR PROJECT MANAGER CONTRACTOR Project Manager is responsible for the review and approval of all changes and Contract Change Proposals prior to submission to COMPANY for review and resolution.

4.6 CONTRACTOR ENGINEERING MANAGER CONTRACTOR’s Engineering Manager shall review and approve all changes to design drawings, design basis and any other technical changes prior to implementation. The Engineering Manager shall ensure any changes that are considered an impact to cost or schedule shall be notified to the CONTRACTOR Project Manager for notification to COMPANY.

Page 10: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 10 of 12

Revision: 0C

The Engineering Manager / Project Manager from the CONTRACTOR's organisations are responsible for ensuring technical acceptability of changes and to ensure that change does not have any adverse affect on HSE or Technical Integrity requirements. They are also responsible for the effective use and timely completion of the Change Notice component of this Contract Change Control procedure as identified in the flowchart illustration in Attachment 1. They are also responsible for the effective operation, timely notification, and overall execution of the Contract Change Proposal (CCP) component of this process and as identified in the contract (CCP- See Attachment 3).

Page 11: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 11 of 12

Revision: 0C

5.0 PROCEDURE 5.1 GENERAL CHANGE CONTROL PROCESS

All identified changes shall be reviewed by the CONTRACTOR Engineering Manager and Project Manager to ensure that the proposed changes are technically acceptable prior to preliminary approval for CONTRACTOR to proceed. The Engineering Manager and Project Manager shall review all completed Contract Change Notices (CCN) prior to submitting to COMPANY for review and agreement. The process covered by this procedure is illustrated in the flowchart in Attachment 1.

5.2 CHANGE CONTROL NOTICE All COMPANY and CONTRACTOR Personnel are responsible for notifying their respective managers of any potential change. Any person who identifies a need to change, or foresees a benefit to the Project, can raise a Contract Change Notice (CCN) - Attachment 3. The overall description, detailed description, documents affected, including criticality assessment and Safety Critical Elements Performance Standards shall be indicated in Part 1 – Change Description.

5.3 CHANGE CONTROL REVIEW

The CONTRACTOR's Engineering Manager shall review the technical need for the proposed change on a “fit for purpose” basis, and shall complete Part 2 of the CCN. He shall ensure that all the disciplines affected by the change are indicated and allocate a CCN number from the CCN register (which he shall maintain). CCN shall be assigned with numbers in accordance with the Document and Drawing Numbering Procedure, document no.: 9000-PRC-EM-0001. CONTRACTOR’s Project Manager shall also approve the preliminary decision to proceed with the change.

5.4 CHANGE CONTROL REGISTER CONTRACTOR shall maintain a register of all Contract Change Notifications to COMPANY. The CCN Register shall be updated daily, or as required and published weekly, with a copy to COMPANY by close of business every Monday. Where there is a probable cost / schedule impact, an advance copy of the CCN shall be forwarded to the COMPANY Cost Control Representative for trending purposes. The CCN register shall be reviewed for status and trending at the Weekly Meeting between COMPANY and CONTRACTOR.

Page 12: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 12 of 12

Revision: 0C

5.5 CONTRACTOR CHANGE APPROVAL

The CONTRACTOR's Engineering Manager shall solicit the approval and a confirmation of further action to be taken from his Project Manager. Should the Project Manager consider that the change is required prior to obtaining COMPANY approval, he may order such change(s) providing that all consequences due to such changes shall be borne solely by CONTRACTOR.

The CONTRACTOR's Engineering Manager shall arrange for the distribution of the completed CCN to affected parties / disciplines for any further costing and impact quantification.

5.6 CONTRACTOR CHANGE ESTIMATES The CONTRACTOR's Engineering Manager will consolidate all estimate information provided onto the master CCN and will solicit agreement to the estimate from his Project Manager

The relevant engineering discipline leads shall be responsible for supplying information regarding labour, plant, material, subcontract, schedule impact or any other necessary data to the CONTRACTOR Engineering Manager as requested. This shall be completed on Part 3 of the CCN and supported by all relevant calculations, assumptions, and technical documentation. The Project Manager and Engineering Manager will indicate agreement by signing Part 4 of the CCN and indicate whether the CCN is approved, rejected or a Contract Change Proposal (CCP) is required. The CCN shall be presented to COMPANY for approval of Part 5 of the form.

5.7 CHANGE APPROVAL BY COMPANY

COMPANY shall review the CCN and either accept or reject the CCN by completing Part 5 of the CCN and returning it to CONTRACTOR for any further action required. Subject to COMPANY approval of the CCN, the CONTRACTOR’s Engineering Manager shall ensure that the CCN is fully implemented in terms of: ?? All affected documents are reviewed and updated as required ?? All affected disciplines / contractors are notified of the approved change Implementation of the CCN shall be verified by the CONTRACTOR Engineering Manager completing the CCN Register (final column) as ‘CCN Implemented’. (See Attachment 4)

Page 13: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Page 13 of 12

Revision: 0C

5.8 CONTRACT CHANGE PROPOSAL (CCP) CONTRACTOR unconditionally accepts that any and all submittals of CONTRACTOR’s requests for changes or claims shall utilise the Contract Change Notice, provided in Attachment 2 and the Contract Change Proposal (CCP) form, provided in Attachment 3. COMPANY will not accept nor acknowledge receipt of CONTRACTOR’s requests for changes or claim unless they are submitted in such form. CONTRACTOR unconditionally acknowledges that unless a claim is submitted in the timeframe required by this Contract, on the CCP form referenced herein, then all rights to both reimbursement and extension of time related to such claims are unconditionally waived. When a CCP is indicated, the CONTRACTOR's Project Manager shall arrange for the raising of the CCP (Attachment 3) on the standard COMPANY pro forma. The CCP, and estimate and any supporting documentation shall be submitted to COMPANY for approval. The CONTRACTOR's Project Manager shall lead any clarifications / negotiations. Following receipt of Contract Change Approval (CCA) from COMPANY, and issue of a Contract Change Order (CCO) the Work shall be ordered, scheduled and executed by the respective CONTRACTOR(s). The change shall be added to the Project Schedule and tracked in accordance with the COMPANY approved reporting procedure. The Contract Change Order is provided in Attachment 5.

5.9 DISPUTED CONTRACT CHANGE PROPOSAL

If COMPANY disagrees that there is a change; a Disputed Contract Change Proposal shall be issued by COMPANY, which will instruct the CONTRACTOR on how to proceed.

Page 14: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Attachment 1 Page 1 of 3

Revision: 0C

ATTACHMENT 1

CONTRACT CHANGE CONTROL FLOWCHART

Page 15: Contract Change Control9000 PRC EM 0006_BP

COMPLETEPART 1 OF

CCN

IDENTIFYCHANGE

REVIEWPROPOSED

CHANGE

VALID CHANGE.PART 2 OF CCN SIGNED

OFF BY ENG. & RESPONSIBLE MANAGER

PROCEED WITH CHANGE

CHANGEREJECTED

VALID CHANGE.PROCESS CCN

PROGRESS TO STAGE 2

ACTIVITY

CONTRACT CHANGE CONTROL FLOWCHART

STAGE 1 - PRELIMINARY IDENTIFICATION & APPROVAL (TARGET DURATION : 72 HOURS)

RESPONSIBLE

ORIGINATINGDISCIPLINE

ORIGINATORLEAD ENGINEER(TECHNICAL AUTHORITY)

CONTRACTOR’S ENGINEERING MANAGER

CONTRACTOR’SENGINEERINGMANAGER &

PROJECT MANAGER

CONTRACTOR’SENGINEERING MANAGER

CRITERIA FOR CCN

Examples of the source of a change include but not limited to the following:

1)Deviation from contracted scope of work.

2) Change to design deliverables which change the design basis intent.

3) Instructions from COMPANY.

4) Changes arising from TQ/TN/SQ or Field Design Changes.

5) Supplier or CONTRACTOR Deviations or Concessions.

GUIDANCE / COMMENTS

DOES CHANGEFALL WITHIN

CRITERIA?

YES

REVISE ASNECESSARY

NO

Design Control Procedure

ISSUE PRELIMINARYAPPROVED CCN TO

AFFECTED DISCIPLINES FOR COST ESTIMATES

9000-PRC-EM-0006 Rev 0C Attachment 1 Page 2 of 3

Allocate Change Number

Update Change Register

Notify affected disciplines

CCN Register updated

CCN Register reviewed at Weekly Meeting

Add CCN No to Master Document Register for Cross Reference

Page 16: Contract Change Control9000 PRC EM 0006_BP

DEVELOP IMPACTS & COSTS etc.

COMPLETE PART 3 OF CCN

CONSOLIDATE IMPACTSTATEMENTS

COMPLETE PART 4 OF CCN

SIGN OFF PART 5 OF CCNISSUE TO ALL AFFECTED

DISCIPLINES AND RETURN TOCONTRACTOR FORIMPLEMENTATION

CCNAPPROVED?

YES

NO

RAISE CCP IN ACCORDANCE WITHCONTRACT REQUIREMENTS

ACTIVITYRESPONSIBLE

• AFFECTED DISCIPLINES

• CONTRACTOR’S ENGINEERING MANAGER

• CONTRACTOR’S PROJECT MANAGER• ENGINEERING MANAGER

• COMPANY COST CONTROL• COMPANY CHIEF OF FACILITIES

ENGINEERING• COMPANY GPF PMT MANAGER• COMPANY SENIOR PMT MANAGER

Mark ‘Rejected’ BoxNotify DisciplinesNotify COMPANYUpdate Register

STAGE 2: IMPACT QUANTIFICATION & FINAL APPROVAL

REVIEW CCN DATASIGN OFF PART 4 AND SUBMIT TO

COMPANY FOR APPROVAL

CONTRACT CHANGEPROPOSAL (CCP)

REQUIRED?

NO

CONTRACTOR to:• Distribute to affected disciplines• Complete update to affected documents & reissue• Update Master Doc. Register• Update CCN Register

GUIDANCE/COMMENTS

YES

TRENDINGREQUIRED?

NO

YES

END

RAISE TREND NOTICE?

9000-PRC-EM-0006 Rev 0C Attachment 1 Page 3 of 3

Page 17: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Attachment 2 Page 1 of 4

Revision: 0C

ATTACHMENT 2

CONTACT CHANGE NOTICE PRO FORMA

Page 18: Contract Change Control9000 PRC EM 0006_BP

9000-PRC-EM-0006 Attachment 2 Page 2 of 4 Rev 0C

TANGGUH GAS PRODUCTION FACILITIES

CONTRACT CHANGE NOTICE (CCN)

CCN No: Rev: Date:

Part 1 - Change Description - to be completed by Originator and Lead Engineer (Technical Authority) Originator (Print): Discipline: Lead Engineer / Technical Authority (Print):

Affected Disciplines (circle)

Process Piping Structural Instruments Mechanical Materials Eng Telecoms Electrical Construction Operations HSE Environmental Planning QA Cost Procurement Safety Eng. Pipeline

Subsea Drilling Civil Management Doc. Contl. Onshore LNG ORF LNG Plant Others Overall Description of Change:

Detailed Description of Change: (Use attachments as necessary) Reason for Change: Documents Affected by this CCN: Reference Attachments to this CCN: Does this change affect any items that are categorised as level 1 or level 2 in the Criticality Evaluation? Doest this change affect the performance standards of any items that are categorised as Safety-Critical? Does this change affect the following? (give details) Constructability Reliability HSE Technical Integrity Additional Information

Page 19: Contract Change Control9000 PRC EM 0006_BP

9000-PRC-EM-0006 Attachment 2 Page 3 of 4 Rev 0C

TANGGUH GAS PRODUCTION FACILITIES

CONTRACT CHANGE NOTICE (CCN)

CCN No:

Rev:

Date:

Part 2-Preliminary Approval to Proceed (to be completed by Contractor's Engineering Mgr & Project Mgr) Proceed with change Yes

Complete CCN Part 3 and 4

No

Engineering Manager

Project Manager

Name:

Name:

Signature: Date: Signature: Date:

Part 3 - Detailed Cost Analysis - To be completed by Affected Disciplines (return to Engineering Manger.) Estimated Cost of Change (US Dollars) $5000-10,000 $10,000-50,000 $50,000-100,000 $100,000-500,000 $500,000-1000,000 > $1000,000 + or -ve cost (specify) Estimated Cost of Preparation (Hours), i.e. hours required to assess the change. (Tick) < 40 40 - 100 100 - 200 200 - 300 300 - 400 400 + Effect of Change (Tick) Engineering Man-hours / Cost Material Cost Construction Man-hours / Cost Engineering Schedule Material Delivery Construction Schedule Further HAZID/HAZOP required? Environmental Review Required Risk Assessment Register

Discipline Man-hours Cost Impact US $

Schedule Impact Weeks

Materials Cost US $

Construction Cost US $

Indirect Costs US $

Others Costs US $

Management Civil Doc. Control. Process Piping Structural Instruments Mechanical Materials Eng. Telecoms. Electrical HVAC HSE Architectural Planning QA Cost Safety Eng. Sub Sea Pipeline Drilling Procurement Construction Others Total

Page 20: Contract Change Control9000 PRC EM 0006_BP

9000-PRC-EM-0006 Attachment 2 Page 4 of 4 Rev 0C

TANGGUH GAS PRODUCTION FACILITIES

CONTRACT CHANGE NOTICE (CCN)

CCN No:

Rev:

Date:

Part 4 – Consolidated Cost - To be completed by Contractor's Engineering / Responsible Manager Summary of Estimated Costs US $ Management Engineering Procurement Materials Construction Indirect Others Total Schedule Impact - Weeks (Provide additional information as necessary): Contractor Approval of CCN for submission to COMPANY: CCN Approved CCN Rejected Contract Change Proposal Required? Yes / No Engineering Manager

Responsible Manager

Name : Name :

Signature : Signature :

Date : Date :

This Contract Change Notice is not an authorization to proceed or an authorization for the expenditure of monies under the Contract. CONTRACTOR shall submit a copy of all documents related to the origin if this proposed change, a detailed estimate in a format acceptable to COMPANY, or as may be attached hereto, of the cost and schedule impacts, if any, of this proposed change to COMPANY no later than: Part 5 – COMPANY INSTRUCTION CCN APPROVED CCN REJECTED Does this change affect Regulatory Approval? YES NO Does this change affect SOR Document? YES NO 1. COMPANY Cost Control Name: Signature: Date:

2 COMPANY Chief of Facilities Engineering Name: Signature: Date:

3. COMPANY GPF PMT Manager Name: Signature: Date:

4. COMPANY Senior PMT Manager Name: Signature: Date:

NOTE: Original Copy with master signatures to be held by Originator NOTE: Submit copy to COMPANY for Approval. Original held by Contractor

Page 21: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Attachment 3 Page 1 of 3

Revision: 0C

ATTACHMENT 3

CONTRACT CHANGE PROPOSAL PRO FORMA

Page 22: Contract Change Control9000 PRC EM 0006_BP

9000-PRC-EM-0006 Rev 0C Attachment 3 Page 2 of 3

TANGGUH GAS PRODUCTION FACILITIES PROJECT CONTRACT No. ---------------------

CONTRACT CHANGE PROPOSAL (CCP)

CCP Title: PCN No:

BP Berau Limited CCP No. Rev: Date:

CONTRACTOR:

Sheet 1 of ______________

1. CCP originated by (delete as appropriate): COMPANY / CONTRACTOR

2. Description of Contract Change Proposal (Attach additional sheets if necessary):

3. Evaluation Summary: Cost Basis: lump sum / unit rate / day rate / other: _____________ Total Price of Contract: ________________ (lump sum / estimate) Schedule Impact (full detailed to be attached): ____________________ Basis of Estimate: (full supporting documentation, technical assessment and or justification to be attached) This Contract Change Notice is not an authorization to proceed or an authorization for the expenditure of monies under the Contract. CONTRACTOR shall submit a copy of all documents related to the origin if this proposed change, a detailed estimate in a format acceptable to COMPANY, or as may be attached hereto, of the cost and schedule impacts, if any, of this proposed change to COMPANY no later than:

Signed for and on Behalf of CONTRACTOR : Name: ( ) CONTRACTOR REPRESENTATIVE Date: ______________________________

Page 23: Contract Change Control9000 PRC EM 0006_BP

9000-PRC-EM-0006 Rev 0C Attachment 3 Page 3 of 3

TANGGUH GAS PRODUCTION FACILITIES PROJECT CONTRACT No. ---------------------

CONTRACT CHANGE PROPOSAL CONTINUATION SHEET

CCP Title:

BP Berau Limited CCP No.

CONTRACTOR:

Sheet __ of ______________

Page 24: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Attachment 4 Page 1 of 2

Revision: 0C

ATTACHMENT 4

CONTRACT CHANGE NOTICE REGISTER

Page 25: Contract Change Control9000 PRC EM 0006_BP

CCN Number Date Raised Description of Change (10 words max)

Originating Discipline

Change Owner

Approval status (Parts 1&2 of PCN)

Approval status (Parts 3&4 of PCN)

BP Approval status (Part 5 of CCN)

Date of CCP CCP Number Status (Open/Pending/Implemented)

TANGGUH GAS PRODUCTION FACILITIES PROJECTCONTRACT CHANGE REGISTER

9000-PRC-EM-0006Rev 0C Attachment 4 Page 2 of 2

Page 26: Contract Change Control9000 PRC EM 0006_BP

9000-PRC-EM-0006Rev 0C Attachment 4 Page 2 of 2

Page 27: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Attachment 5 Page 1 of 2

Revision: 0C

ATTACHMENT 5

CONTRACT CHANGE ORDER

Page 28: Contract Change Control9000 PRC EM 0006_BP

BP BERAU LTD

Document No: 9000-PRC-EM-0006 Attachment 5 Page 2 of 2

Revision: 0C

BP BERAU LTD.

CONTRACT No.

FOR ________________________________________________________

CHANGE ORDER NO.: _____ Page 1 of 1 Effective Date:__________________

CONTRACTOR NAME / ADDRESS ORIGINATOR CONTRACTOR COMPANY Name Dept./ Section Telephone No. EXCEPT AS OTHERWISE EXPRESSLY PROVIDED HEREIN, CONTRACTOR HEREBY AGREES TO PERFORM THE BELOW DESCRIBED WORK IN ACCORDANCE WITH ALL OF THE TERMS AND CONDITIONS OF THE CONTRACT REFERENCED ABOVE. DESCRIPTION OF PROPOSED CHANGE (Use Continuation Sheets as Required ) CCN No: CCP No:

SCHEDULE IMPACT

COST IMPACT

Performance of the Work described hereinabove shall commence on the Contract Effective Date and be completed not later than ___________________ Current Completion Dates: __________________ (Provisional) __________________ (Final) Revised Completion Date: __________________ (Provisional) __________________ (Final)

Original Approved Contract Lump Sum Price: US$ Total of Prior Approved Change Orders: US$ Amount Under This Change Order: US$ Total Revised Contract Lump Sum Price: US$

CONTRACTOR BP BERAU LTD BY BY NAME: NAME:

TITLE: TITLE:

DATE: DATE: