Contact Point Corrosion inspection on uninsulated & Insulated piping Presented by: Brian K. Beresford Author: Brian K. Beresford President VIR Inspection Co- Author: Quinn Hanson Chief Executive Officer VIRAMID-CPC-CS® Contact Point Corrosion on Carbon Steel Material VIRAMID-CPC-SS® Contact Point Corrosion on Stainless Steel Martial looking for SCC VIR Inspection LLC 320 Dayton Street Suite 260 Edmonds, WA. 98020 Carbon Steel Piping: Inspecting for Corrosion & Pitting. Stainless Steel Piping: inspecting for stress corrosion cracking (SCC)

Contact Point Corrosion - ASNT

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Contact Point Corrosion - ASNT

Contact Point Corrosioninspection on uninsulated & Insulated piping

Presented by: Brian K. Beresford

Author: Brian K. BeresfordPresident VIR Inspection

Co- Author: Quinn HansonChief Executive Officer

VIRAMID-CPC-CS®Contact Point Corrosion on

Carbon Steel Material

VIRAMID-CPC-SS®Contact Point Corrosion on Stainless

Steel Martial looking for SCC

VIR Inspection LLC320 Dayton Street Suite 260

Edmonds, WA. 98020

Carbon Steel Piping: Inspecting for Corrosion & Pitting. Stainless Steel Piping: inspecting for stress corrosion cracking (SCC)

Page 2: Contact Point Corrosion - ASNT

• A non-destructive technique that utilizes the basic laws of electricity to inundate the conductive material being inspected with AC or DC current

• Results are repeatable and consistent to provide trending inspections and life assessments

• Two Position Test Method

• Current electrodes connect to the voltage source or current source

• Potential electrodes measure a voltage drop along the area of concern of the test specimen in the direction of charge flow (current)

What is Contact Point Corrosion

Page 3: Contact Point Corrosion - ASNT

INDUSTRY WIDE ISSUES

• Process, transfer lines and structural piping hangers and supports create potential corrosion sites. "Touch Point Corrosion“

• Insulated Support, Hangers and Pads require significant amount of time and resources to remove and inspect

• Difficult to find reliable on-line inspection techniques

Page 4: Contact Point Corrosion - ASNT

ADVANTAGES OF USING

• Quick inspection

• User friendly

• Conventional training

• Cost effective

• Repeatable results

• Process does not need to be shutdown in order to perform inspection

• Needs to be bare metal contact so surface must be clear of dust, debris, paint, rust, etc.

Page 5: Contact Point Corrosion - ASNT

APPLICATIONS

•Pads/Clamps•Beam Locations•Saddle Supports•T-connector Supports•Hangers

• Water lines • Water Mains• Flair Stacks• Off Shore• CUI

Page 6: Contact Point Corrosion - ASNT

CALIBRATION CORRECTION FACTORS

• Temperature reading is needed before each set of data• Temperature correction factor Rs=Rm/e(Ts-TM) *In K

where:• RM is the measured resistance• RS is the resistance at the desired temperature• TM is the measured temperature• TS is the desired temperature• K is the coefficient of the given material

Page 7: Contact Point Corrosion - ASNT

INSPECTION VARIABLES

• OD and Nominal Wall of the Test Specimen• Conductivity of the Material• Temperature• Volume(Distance between Electrodes)• Vibration• Test Specimen Condition of Testing Area (Clear of

Debris, Rust, Water, Etc.)• Surface Resistance• Distance of Contacts to measure Potential Drop

Page 8: Contact Point Corrosion - ASNT

T-PIPE AREA

• Inspect T-pipe on different levels of a deck

• Pulled T-Pipe results plus or minus 10%

• Radiography, Digital Radiography and GUL was performed and was unsuccessful

Page 9: Contact Point Corrosion - ASNT

HIGH PRESSURE PIPING “INSPECTION DONE WHILE UNIT IS RUNNING”

Page 10: Contact Point Corrosion - ASNT

HIGH PRESSURE PIPING

Pulled Tube Results

Page 11: Contact Point Corrosion - ASNT

I-BEAMS AND Y-PIPEPipes in Racks

Page 12: Contact Point Corrosion - ASNT

Piping at Supports

Corrosion at I-Beams

Page 13: Contact Point Corrosion - ASNT

Reporting

Page 14: Contact Point Corrosion - ASNT

INSPECTION INTERVALS

• A routine inspection should take place every year or two in order to replicate a trending inspection compared to the original baseline inspection

• This inspection will give us a time frame of degradation decay and thus we will be able to extrapolate to present the predicted life cycle of the test specimen

• CPC testing is recommended after installation of a new test specimen after process is started

• This will accurately determine a baseline inspection in order to provide a precise trending inspection and life expectancy

Page 15: Contact Point Corrosion - ASNT

COST SAVINGS

• Quick inspection• User friendly• Conventional training• Cost effective• Repeatable results• Process does not need to be

shutdown in order to perform inspection