Upload
klynchelle
View
215
Download
0
Embed Size (px)
Citation preview
7/28/2019 ConstructionContract-ShortForm
1/2
Contract Agreement - Short Form
THIS AGREEMENT made the day of , in the year Two Thousand and , by andbetween the acting on behalf of the University of Maine System, duly authorized and empoweredby virtue of the laws of the State of Maine, hereinafter called the Owner, and hereinafter called theContractor.
WITNESSETH: That the Owner and the Contractor for the considerations hereinafter namedagree as follows:
ARTICLE 1. SCOPE OF THE WORK
The Contractor shall furnish all of the materials and perform all of the work shown on thedrawings and described in the Specifications entitled , prepared by , acting as and in theseContract Documents entitled the Architect and/or Engineer; and shall do everything required by thisAgreement, the General Conditions and Special Provisions of the Contract, the Specifications and theDrawings.
ARTICLE 2: TIME OF COMPLETION
The work to be performed under this Contract shall be substantially completed on or before.
ARTICLE 3: THE CONTRACT SUM
The Owner shall pay the Contractor for the performance of the Contract, subject to additions anddeductions provided by approved change orders in current funds as follows Dollars ($ ).ARTICLE 4: CONTRACT BOND
The Contractor shall furnish the Owner the approved Contract Bonds (as per Article 23 of theStandard General Conditions) in the amount of 100% of the Contract sum.
ARTICLE 5: PROGRESS PAYMENTS
The Owner shall make payments on account of the contract as provided therein as follows: Eachmonth 95% of the value, based on Contract prices of labor and materials incorporated in the work and ofmaterials suitably stored at the site thereof up to the first day of that month, as certified by the Architectand/or Engineer.
The Owner may cause contractor to be paid such portion of the amount retained hereunder asdeemed advisable. (See Article 19 of the Standard General Conditions).
ARTICLE 6: FINAL PAYMENT
Final payment shall be due 60 days after completion and acceptance of the work, provided thecontractor has submitted evidence satisfactory to the Owner that all payrolls, material bills and otherindebtedness connected with the work has been paid.
ARTICLE 7: THE CONTRACT DOCUMENTS
The General Conditions of the Contract, Instructions to Bidders, the Proposal, the Special
UMSOF.10/24/00r
1
7/28/2019 ConstructionContract-ShortForm
2/2