    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    05.23.08 student pin-up and structural discus-sion with architect, Thom Mayne.

    05.23.08 meeting with Nassar Saebi, developeof Saebi Alternative Building System [SABS],which was used for the floating foundation.

    06.10.08 first quarter [urban research] final

    review, Spring 2008.

    06.10.08 first quarter [architectural research]final review, Spring 2008.

    11.20.08 tent installation, UCLA south campusfoam arrival.

    11.24.08 organization and inventory of foamblocks.

    12.03.08 shoring installation, configuration offoam blocks.

    12.03.08 organization and layout of foamblocks.

    02.13.09 review with UCLA chancellor, GeneBlock, and AUD chair, Hitoshi Abe.

    02.13.09 study model and construction/assembly model.

  • 8/3/2019 Construction Sequence_reduced Size

    2/8

    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    02.24.09 infill of MEP [mechanical, electrical,plumbing] lines, foam chassis.

    03.03.09 conduit embed, foam shell.

    04.02.09 MEP embed in stem wall, master

    bath.

    04.14.09 clean up and preparation of rainwatertank pockets.

    04.21.09 Hilti adhesive application, joint andcrack sealant for foam systems, side gallery.

    14.28.09 bathtub design and assembly, masterbath.

    04.28.09 Hilti adhesive infill of seams andjoints, stem wall castellations, side gallery.

    04.28.09 Hilti adhesive application, masterbath.

    06.16.09 GFRC [Glass-Fiber Reinforced Con-crete] application, stem wall.

    06.17.09 GFRC application, topping slab, mas-ter bed and bath.

  • 8/3/2019 Construction Sequence_reduced Size

    3/8

    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    06.17.09 Wacco shoring and cribbing blocksinstall.

    06.18.09 anchor embed, installation of sillplates (double).

    07.02.09 topping slab poured, crib blocking

    replaced, crane preparation.

    07.06.09 crane and truck arrival for shipmentof chassis and shell/roof.

    07.06.09 strap connection from crane to steeljoists.

    07.06.09 chassis lifted from construction site.

    07.06.08 chassis clears the fence.

    07.06.08 chassis rotated for placement.

    07.06.09 chassis lowered onto truck.

    07.06.09 chassis craned into place.

  • 8/3/2019 Construction Sequence_reduced Size

    4/8

    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    07.06.09 team from Los Angeles gathers priorto house departure.

    07.06.09 final preparation for shipment to NewOrleans, rainwater tanks fitted in the chassis.

    07.07.09 en route to New Orleans.

    07.08.09 I10, passing through the desertof California and by the San Bernardinomountains.

    11.20.08 I10, travelling by windmills, west ofPalm Springs, CA.

    11.24.08 I10, arrival in New Orleans, passingthe Superdome.

    07.09.09 arrival to the Make It Right site in theLower Ninth Ward.

    07.10.09 site work complete, concrete footings

    and steel masts in place, crane preparation.

    07.13.09 chassis ready for lifting.

    07.13.09 final check before straps connected.

  • 8/3/2019 Construction Sequence_reduced Size

    5/8

    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    07.14.09 connection of gallery supports,SIPS [Structural Insulated Panels] wall panelinstallation, geothermal line preparation.

    07.21.09 roof joists craned into place.

    07.13.09 truck drives onto the site.

    07.13.09 straps lowered to the chassis.

    07.13.09 straps connected, chassis cranedfrom the truck.

    07.13.09 chassis rotated on site.

    07.13.09 chassis fitted on the steel masts.

    07.13.09 chassis lowered into place.

    07.13.09 final check, connection between steemasts welded and finalized.

    07.13.09 straps ready to be released.

  • 8/3/2019 Construction Sequence_reduced Size

    6/8

    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    07.27.09 final roof touch-ups, ready for water-proofing.

    07.31.09 clerestory framing erected, standing

    seam roof preparation.

    08.20.09 polycarbonate windows and alumi-num frame installation.

    08.20.09 connection of SwissPearl facade tofirring strips.

    07.21.09 last of the roof joists installed.

    07.22.09 roof joists finalized. SIPS roof panelpreparation.

    07.23.09 SIPS roof panels craned into place.

    07.24.09 final installation of roof panels.

    07.27.09 scaffolding erected, view of the eastside of the house.

    07.27.09 view of the north side of the house.

  • 8/3/2019 Construction Sequence_reduced Size

    7/8

    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    09.04.09 standing seam roof installation.

    09.04.09 finalization of the SwissPearl facade.

    09.21.09 interior window and door trim

    complete; Demode kitchen casework install.

    09.21.09 polycarbonate storm shutter paneland exterior lighting preparation.

    09.29.09 storm shutters arrive to site.

    09.30.09 interior lighting installation.

    09.30.09 site work prep for exterior stairs.

    09.30.09 final window check.

    09.30.09 install of thesolar panals, electricwiring.09.30.09 final check of the solar panals.

  • 8/3/2019 Construction Sequence_reduced Size

    8/8

    FLOAT HOUSE: CONSTRUCTION SEQUENCEALL PHOTOS AVAILABLE AS HIGH RESOLUTION FILES UPON REQUEST I [email protected]

    09.30.09 landscaping complete.

    09.30.09 final site preparations.