28
2011 Texas Land Title Institute – Page 1 of 19 Construction Retainage and Lien Waivers Construction Retainage and Lien Waivers Thomas J. Walthall, Jr. The Gardner Law Firm, A Professional Corporation 745 E. Mulberry, Suite 500 San Antonio, Texas 78212-3149 (210)733-8191 Facsimile: (210)733-5538 Email: [email protected] www.tglf.com Texas Land Title Institute December 1, 2011

Construction Retainage and Lien Waivers · 2011 Texas Land Title Institute – Page 1 of 19 Construction Retainage and Lien Waivers Construction Retainage and Lien Waivers Thomas

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • 2011 Texas Land Title Institute – Page 1 of 19 Construction Retainage and Lien Waivers

    Construction Retainage and Lien Waivers

    Thomas J. Walthall, Jr.

    The Gardner Law Firm,

    A Professional Corporation

    745 E. Mulberry, Suite 500

    San Antonio, Texas 78212-3149

    (210)733-8191

    Facsimile: (210)733-5538

    Email: [email protected]

    www.tglf.com

    Texas Land Title Institute

    December 1, 2011

    mailto:[email protected]://www.tglf.com/

  • 2011 Texas Land Title Institute – Page 2 of 19 Construction Retainage and Lien Waivers

    BIOGRAPHY

    of

    Thomas J. Walthall, Jr.

    Thomas J. “Tom” Walthall, Jr. has widely regarded expertise in construction law and lien

    and bond claims. He has practiced in the San Antonio area since 1980, and became a

    member of The Gardner Law Firm in 1991 upon a merger with his former law firm. Mr.

    Walthall’s practice consists primarily of representation of contractors, subcontractors,

    and owners in construction law area, concentrating in mechanic’s liens, bond claims,

    defect litigation, engineer and architect defense, delay claims, and related litigation in the

    Courts and in arbitration.

    Mr. Walthall is experienced in arbitration and court trials in the construction law area,

    including subcontract breach and delay claims, bond claims, lien claims, Prompt Pay Act

    claims, Texas Construction Trust Fund cases for subcontractors and suppliers,

    delay/impact litigation, Miller Act litigation, bankruptcy discharge litigation regarding

    the Texas Construction Trust Fund Act and construction defect litigation. He regularly

    counsels clients in the negotiation and preparation of subcontracts, construction contracts,

    purchase and supply orders and related construction documents.

    Mr. Walthall has served for over ten years on the State Bar’s Real Estate Forms

    Committee, which prepares and publishes the Texas Real Estate Forms Manual, and has

    been responsible for Ch. 28, Texas mechanic’s liens, of the Forms Manual. Mr. Walthall

    gives several seminars each year to local construction trade organizations (including the

    American Subcontractor’s Association, the National Association of Credit Managers, and

    the United States Tennis Court & Track Builders Association) regarding construction

    contracting and contracts, mechanics liens, and bond claims. He also has made frequent

    presentations on mechanic’s lien, construction bond claims and related topics at the State

    Bar of Texas continuing legal education seminars, including the Advanced Real Estate

    and the Advanced Real Estate Drafting Courses, and at the University of Texas Law

    School’s Mortgage Lending Institute.

    Mr. Walthall is licensed to practice law in Texas before all the state courts, and the

    United States District Courts for the Eastern, Southern and Western Districts of Texas,

    and before the 5th U.S. Circuit Court of Appeals. He is a member of the Texas Bar

    Association (Construction Law Section, Real Estate, Probate and Trust Law Section), and

    is chapter attorney for the American Subcontractors Association, San Antonio, Texas.

  • 2011 Texas Land Title Institute – Page 3 of 19 Construction Retainage and Lien Waivers

    TABLE OF CONTENTS

    Overview- Mechanic’s Lien Liability for Retainage; Lien Waivers;

    2011 Legislation . . . . . . . . . . . . . . . . . . . . . . . . ………………… . . . . . . . . . . . . . . . . . 5

    1. Retainage Legislation HB 1390... .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    1.1 Statutory Retainage (“Owner Statutory Retainage”). . . . . . . . …. . . . . . . . . 5

    1.2 Owner Liability on Mechanic’s Lien Claims.. . . . . . …. . . . . . . . . . . . . . . . . 7

    1.3 Contract Retainage – the Lien Notice Problem……………….. . . . . ... . . . 7

    1.4 Owner’s Statutory Retainage –Problem with Filing Deadline for

    Lien Affidavit……….………………………….. . . . . . . . . . . . . . . … . . . 8

    1.5 New Retainage Legislation Revising §53.057 and related Provisions. . . .. 9

    1.5.1 New Optional Notice of Contractual Retainage Deadlines……. .. 9

    1.5.2 Lien Affidavit Filing Deadline Changes………………………... 10

    1.5.3 Application……………………………………...………….....….10

    1.5.4 Owner Failure to Withhold Retainage

    – §53.052 Deadlines apply. . . . . . . . ……………………... . . . . . .11

    1.5.5 “Final Completion”………………………...…………………….11

    1.5.6 Request for Information to Owner – Date of original contract

    execution – Effective Date.. . . . . . . . . . . . . . ... . . . . …….. . . . . . . . 12

    1.5.7 Grounds for Removal of Lien, §53.160 – Retainage Deadlines

    Expired……………………………………………. . . . . . . . . . . . . 12

    2. “Shall” vs “May” Award Attorneys Fees……... . . ………………. . . . . . . . . . . . . 12

    3. Release of Mechanic’s Liens. New Statutory Forms. No enforceable release in

    advance of collection.. . . . …………………………………………... . . . . . . . . . .13

    4. Ch. 12 Texas Civil Practice and Remedies Code. The Fraudulent Lien Act . . . 14

    5. Construction Trust Funds Liability – Residential Construction. . . . . .……….. . . 16

    5.1 Basics and Bank Exemption.. . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . ... . 16

  • 2011 Texas Land Title Institute – Page 4 of 19 Construction Retainage and Lien Waivers

    5.2 Accounting – Residential Homesteads…………… . . . . . . . . . . . . . . ... . . 17

    5.3 Trust Fund Act Litigation – Cause of Action and Limitations Clarified...17

  • 2011 Texas Land Title Institute – Page 5 of 19 Construction Retainage and Lien Waivers

    OVERVIEW- MECHANIC’S LIEN LIABILITY

    FOR RETAINAGE; LIEN WAIVERS; 2011

    LEGISLATION

    This presentation covers the 2011 Legislation

    impacting construction claims in Texas. Three

    basic areas will be discussed: significant

    Legislation effecting mechanic’s lien claims and

    retainage, the new Legislation on mechanic’s

    lien and bond claim waivers, and the Texas

    Property Code Ch. 162 (the Texas Construction

    Trust Funds Act). Several important bills

    effecting the construction industry passed this

    2011 Legislative Session. This paper will focus

    on mechanic’s lien related legislation, including

    the new retainage bill (HB 1390) and the lien

    waiver bill (HB 1456). The passage of

    construction industry related matters is

    incredible and amazing due to all the other

    hubbub this past session, including the budget

    cutting, voter id, sanctuary cities etc. etc. We

    will also re-visit the application of Texas

    Property Code Chapter 162, the Construction

    Trust Funds Act and its provisions.

    1. Retainage Legislation HB 1390.

    The 2011 Leg. passed wholesale changes to the

    mechanic’s lien law dealing with retainage. The

    intent was to simplify and clarify retainage claim

    procedure. The result, as we’ll see, is a complex

    compromise bill accommodating several

    competing interest groups in the construction

    business. The new legislation introduces some

    clarity but also added some interesting questions

    about how all this new stuff is going to work as

    a practical matter. The world of owner liability

    for mechanic’s liens and retainage has changed

    dramatically due to HB 1390 (Deshotel).

    Before launching into the details of HB 1390,

    we will first get a historical perspective to “set

    the scene”.

    1.1 Statutory Retainage (“Owner

    Statutory Retainage”).

    When originally drafted the early versions of the

    Texas Mechanic’s Lien statute provided limited

    liability for owners. Lien claimants were to be

    paid on their perfected lien claims out of the

    remaining undisbursed funds in the Owners’

    hands, such that Owners would not have to pay

    twice for their projects. This concept is referred

    to in the case law as “fund trapping”. Owners

    are given lien notices which tell them to “trap

    funds” still in their hands, and withhold the

    money from the contractor until the lien claims

    are resolved or paid off.

    Under the old version of the law, some Texas

    contractors and owners employed the creative

    and abusive strategy of avoiding the trapping of

    funds by quick or immediate payment by the

    owner to the contractor. If no funds were left

    available to “trap” when lien notices arrived,

    then the owner had no liability. If the owners

    disbursed their funds to the contractor before

    receipt of a lien notice, the owners had no

    liability to the lien claimants.

    To plug this hole, the Texas Legislature in 1909,

    enacted the first concept of a required statutory

    retainage by Owners. The early Statute

    required owners to withhold a minimum amount

    from the contractor until completion of the

    project. This minimum withholding, or owner

    statutory retainage, was 10% of the contract

    price as adjusted for change orders and

    modifications. In 1961, passage of the

    Hardeman Act1 refined the owner statutory

    retainage concept, broadened its scope to include

    all claimants, and provided rights to perfect liens

    against this owner statutory retainage fund.

    Owners were declared personally liable for

    failure to comply with the retainage provisions –

    withholding 10% for the minimum time, 30 days

    after “final completion” of their project.

    Owner statutory retainage is intended to assure

    suppliers and subcontractors that there will be a

    little something still left in the cupboard, when

    1 The Act of 1961, known as the Hardeman Act,

    revised Article 5452 et seq. and ushered in sweeping

    changes in the manner of perfecting a claimant's

    statutory mechanic's lien within the statutory scheme. 17 Ch. 382, § 1, 57th Leg., 1961 Tex. Gen. Laws 863

    (1961).

  • 2011 Texas Land Title Institute – Page 6 of 19 Construction Retainage and Lien Waivers

    they do not get paid and have to file claims on

    projects. Claimants share the owner statutory

    retainage on a pro rata basis.

    The owner’s statutory retainage requirement is

    discussed in Page v. Structural Wood

    Components, 102 S.W.3d 720 (Tex. 2003):

    “The Texas Property Code requires

    owners to retain either "10 percent of

    the contract price of the work to the

    owner" or "10 percent of the value of

    the work . . . using the contract price or,

    if there is no contract price, using the

    reasonable value of the completed

    work" for "30 days after the work is

    completed." TEX. PROP. CODE

    §53.101. These retained funds "secure

    the payment of artisans and mechanics

    who perform labor or service," including

    subcontractors such as Structural Wood.

    Id. §53.102. A subcontractor or other

    claimant who wants to make a claim on

    that retainage must properly give notice

    and file [**5] "an affidavit claiming a

    lien not later than the 30th

    day after

    the work is completed." Id. §53.103.

    The period during which a claimant can

    and must file a lien affidavit under

    section 53.103 is therefore the same

    period that an owner can and must hold

    retainage under section 53.101 - thirty

    days after the completion of work. It is

    consequently in the best interest of all

    construction participants to know when

    the thirty-day period terminates - the

    owner so that it can release the

    remaining funds, the original contractor

    so that it can budget for its final

    payment, and the claimant so that it can

    file the lien affidavit before that date.”

    Page v. Structural Wood Components, supra, at

    722

    Owners may elect not to withhold retainage.

    However they are liable for the amount they

    should have retained, and the 30 day period to

    file claims (within 30 days of final completion,

    termination or abandonment under Texas

    Property Code, Subchapter E) no longer applies.

    This means that if the owner does not withhold

    retainage, claimants have until the Subchapter C

    deadlines to file lien affidavits. The Subchapter

    C deadlines run from the claimants last month of

    work/delivery for the job. “Residential” projects

    have a different Subchapter C deadline than non-

    residential projects. “Residential” jobs are

    defined by the mechanic’s lien statute in

    §53.001(8) as involving a single family, duplex,

    triplex, quadraplex, or unit in a multi-unit

    structure occupied or intended to be occupied by

    at least one of the owners. The shorthand way to

    remember the definition is to simply think,

    “owner-occupied”. The Subchapter C lien filing

    deadlines therefore are:

    Residential claims: 15th of 3rd

    month after

    claimant’s last month of work/delivery to the

    project., Texas Property Code §53.052 (b), and

    §53.053 ( c); and

    Non-Residential claims: 15th of 4th month

    after claimant’s last month of work/delivery to

    the project., Texas Property Code §53.052 (a),

    and §53.053 ( c).

    See Hadnot v. Wenco Distributors, 961 S.W.2d

    232 (Tex.App.-Hous. (1 Dist.), 1997), rehearing

    overruled (Jul 23, 1997).

    “When the owner does not retain the

    10% fund, the 30-day period for

    claiming liens is inapplicable. General

    Air Conditioning Co. v. Third Ward

    Church of Christ, 426 S.W.2d 541, 544

    (Tex.1968). The owner becomes

    personally liable to the claimant if the

    owner does not retain the 10% fund.

    James Mechanical Contractors v. Tate,

    647 S.W.2d 347, 350 (Tex.App.--

    Corpus Christi 1982, no writ);

    Donahue v. Rattikin Title Co., 534

    S.W.2d 156, 159 (Tex.Civ.App.--Fort

    Worth 1976, no writ); W & W Floor

    Covering Co. v. Project Acceptance

    Co., 412 S.W.2d 379, 382

    (Tex.Civ.App.--Austin 1967, no writ).”

    Hadnot, supra @ 235

    http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=102+S.W.3d+720%2520at%2520722http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=102+S.W.3d+720%2520at%2520722http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1968133987&ReferencePosition=544http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1968133987&ReferencePosition=544http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1968133987&ReferencePosition=544http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1968133987&ReferencePosition=544http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1968133987&ReferencePosition=544http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1968133987&ReferencePosition=544http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1983114893&ReferencePosition=350http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1983114893&ReferencePosition=350http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1983114893&ReferencePosition=350http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1976117041&ReferencePosition=159http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1976117041&ReferencePosition=159http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1976117041&ReferencePosition=159http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1976117041&ReferencePosition=159http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1967131812&ReferencePosition=382http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1967131812&ReferencePosition=382http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1967131812&ReferencePosition=382http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1967131812&ReferencePosition=382http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1967131812&ReferencePosition=382

  • 2011 Texas Land Title Institute – Page 7 of 19 Construction Retainage and Lien Waivers

    1.2 Owner Liability on Mechanic’s Lien

    Claims.

    Therefore the owner’s liability to

    subcontractor/supplier lien claimants is the sum

    of two figures described in §53.084. First, an

    owner is liable for the 10% owner’s statutory

    retainage. Second, an owner is further obligated

    for “trapping” remaining contract funds once

    he/she receives a mechanic’s lien notice letter

    (§53.056 (b) and (d)) containing language

    requiring the owner to withhold payment from

    the contractor for the claim amount. The owner

    who ignores a “trap” lien notice letter and fails

    to withhold payment from the contractor and

    releases funds in spite of receipt of notice in

    compliance with the “fund trapping” section of

    the statute is personally liable and his/her

    property subject to a lien for such amounts paid.

    This is in addition to the owners’ liability for the

    10% retainage.

    Review of Aiken v. State of Texas, 36 S.W.3d

    131 (Tex. App.—Austin, 2000, no writ.),

    provides an instructive illustration of how owner

    liability works out when the lien statutes are

    applied. Aiken involved criminal prosecution of

    a Contractor in connection with a residential

    construction project. The Contractor was

    accused of taking a bank loan advance for the

    construction and misapplying the funds by not

    using them to pay project bills due on the job.

    This is ordinarily a violation of Chapter 162,

    Texas Property Code (the Texas Construction

    Trust Funds Act). However, in this case, the

    prosecution chose to pursue a conviction

    pursuant to Texas Penal Code Section 32.45,

    misapplication of fiduciary property. One of the

    elements of this offense is to prove that the

    Defendant dealt with property “in a manner that

    involves substantial risk of loss to the owners”.

    In this case because the owners had withheld,

    through their interim lender, ten (10%) percent

    retainage, the Court determined that the owners

    suffered no substantial risk of loss. Their

    liability for mechanic’s liens was limited to the

    ten percent (10%) retainage because no funds

    had been trapped by lien claimants, as described

    above. The case provides a good example of

    how owner liability is calculated.

    To summarize, Owners have to withhold ten

    percent (10%) retainage from the general or

    original builder/contractor for thirty days

    following final completion of the project, or its

    termination or abandonment. If Owners fail to

    retain the 10%, they are liable for it anyway, and

    claimants in that case are not required to perfect

    claims within the 30 day retainage withholding

    period. The owners in such case will not be able

    to “cut off” lien claims.

    1.3 Contract Retainage – the Lien Notice

    Problem

    The owner’s statutory retainage described above

    is not the same as, separate and distinct from

    retainage agreed to by contract. General

    Contractors normally insist on withholding

    retainage from subcontractors by the terms of

    their subcontracts. The percentage of retainage

    withheld in the subcontracts is normally ten

    percent, which is the same percentage as the

    owner statutory retainage withheld from the

    contractor per Texas Property Code §53.101.

    Contract retainage is not required by statute. It’s

    a creature of the subcontract agreement.

    Contractors withhold retainage from their Subs

    for many reasons, but the construction “urban

    legend” that subcontract retainage is “required

    by law” is false. Only owners are required by

    statute to withhold retainage on private works

    that are not bonded.

    A special problem exists for all “derivative”

    claimants (subcontractors) who have claims for

    unpaid contractual retainage withheld pursuant

    to their subcontracts. The problem is with the

    lien notice deadlines required under Texas

    Property Code. The required notices are

    required at different times based on whether the

    project is residential or non-residential. (See

    definition in section 1.1, above). Residential

    project notices are set in Subchapter K,

    §53.252, which requires Owner and Contractor

    notice of lien claims by the 15th of the second

    month following each month the labor or

    material comprising the claim is furnished to the

  • 2011 Texas Land Title Institute – Page 8 of 19 Construction Retainage and Lien Waivers

    job site. Non-residential notices, set by §53.056

    (b), as follows: Contractor notice of lien claims

    by the 15th of the second month following each

    month the labor or material comprising the claim

    is furnished to the job site, and owner is required

    by the 15th of the third month following each

    month labor or material is furnished.

    The problem is that the notices to owners and

    contractors are required based on each month of

    unpaid work, not the last month of work. If the

    claimant works on a job for more than a couple

    of months, and contractual retainage is withheld

    by the subcontract terms, then each month only

    90% of the amount earned is being billed and

    paid. The retainage portion accrues each month,

    but is not billed. In spite of not billing retainage,

    the lien notice deadlines run on unabated. They

    are not based on billing dates or when

    applications for payment are submitted. They

    are tied to delivery or furnishing of work or

    material to the jobsite, and are unrelated to the

    dates of invoicing, or subcontract retainage or

    payment provisions. Claimants sometimes are

    paid in accordance with their subcontract terms

    for their 90% progress billing amounts all along

    during the job, only to find that the retainage bill

    is not paid timely. Under the prior statutory

    provisions, if Claimants waited until their

    completion date to begin to worry about sending

    their owner notice for a lien claim for retainage,

    it is most likely too late.

    Under the old statute, to solve this issue, the

    Legislature added an advance retainage notice

    provision. Rather than send notices every month

    during the job for the retainage portion,

    Claimants have had the option under this

    provision, Texas Property Code §53.057, to

    send a one time, up front notice warning the

    owner and contractor that the claimant has

    signed a subcontract providing for contractual

    retainage. Remember now, this is not owner

    statutory retainage. This is retainage by

    subcontract contractual agreement. Texas

    Property Code §53.057 says claimants have the

    option to perfect retainage by a one time, up

    front certified mail notice, at the time the

    claimant commences work2. The §53.057

    notice is sent in lieu of sending the repeated

    monthly notices covering each month’s

    retainage portion. If this upfront §53.057 notice

    is sent, then further notice about retainage is not

    required, and the claimant perfects his/her claim

    by filing a lien affidavit within thirty days of

    final completion, termination or abandonment.

    §53.052.

    Subcontractor and other “derivative” claimants

    (downstream of the original contractor) have

    been oftentimes reluctant to send this early

    §53.057 retainage notice. The old-law notice

    content also required divulging the amount of

    the retainage, and percentage of retainage,

    revealing the claimant’s pricing.

    This was the impetus for new contractual

    retainage notice procedures.

    1.4 Owner’s Statutory Retainage –

    Problem with Filing Deadline for Lien

    Affidavit.

    The previous section identified the problem with

    the notice deadlines for a claimant’s contractual

    retainage. This section visits the problems with

    filing deadlines for lien affidavits for claimants

    seeking a share of the owner’s 10% statutory

    retainage fund.

    The problems are set up in Page v. Structural

    Wood Components, Inc., 102 S.W.3d 720, 46

    Tex. Sup. Ct. J. 561 (Tex. 2003) and Page v.

    Marton Roofing, Inc., 102 S.W.3d 733, 46 Tex.

    Sup. Ct. J. 571 (Tex. 2003). In the Page cases

    the Supreme Court held that the thirty day

    period owners must withhold 10% statutory

    retainage occurred upon final completion,

    abandonment, or termination of the first

    contractor, and not upon final completion of the

    owner’s project by the replacement contractor.

    To share in the owner’s statutory retainage fund,

    claimants had to know the date of final

    completion, termination or abandonment of the

    2 Due by the 15

    th of the 2

    nd month following

    Claimant’s first month of delivery/work on

    the job §53.057 (b)

  • 2011 Texas Land Title Institute – Page 9 of 19 Construction Retainage and Lien Waivers

    project by their original contractor in order to

    track their lien affidavit filing deadline. Paying

    attention only to project final completion is too

    late if the first contractor is terminated, or

    abandons the job.

    The Legislature, after the two Page cases

    provided some help by adding section §53.103,

    and added §53.107 requiring owner notices to

    claimants of the date of a termination or date of

    abandonment, but only for non residential

    projects. For original contracts executed after

    September 1, 2005, involving non residential

    projects only, a notice of termination or

    abandonment is required of owners §53.107.

    The non-residential job notice must be sent not

    later than the 10th day after the date an original

    contract is terminated or the original contractor

    abandons the project. The owner is required to

    send this notice only to claimants who have first

    (a) sent owner lien notices, or (b) have sent a

    request to the owner for notice of termination or

    abandonment. Tex. Property Code §§53.103,

    53.107. Claimants not requesting the notice, or

    who have not sent lien notices, do not get the

    date of termination or abandonment.

    If the non-residential claimant fails to file a lien

    affidavit within the thirty days of the deadlines

    in §53.103 (completion, termination or

    abandonment), but the owner has also failed to

    give the required notice of termination or

    abandonment (§ 53.107) to the claimant entitled

    to such notice, then that particular claimant will

    nevertheless have a lien for his share of retained

    funds if he has otherwise complied with the

    statutory prerequisites for lien perfection. If the

    owner fails to send the notice of termination or

    abandonment to a claimant then that particular

    claimant is not required to file the lien affidavit

    under §53.103, within thirty days of termination

    or abandonment, in order to have a lien under

    §§53.101 – 106. The claimant can merely

    comply with the Subchapter C filing deadline.

    (See section 1.1).

    1.5 New Retainage Legislation Revising

    §53.057 and related Provisions

    The Legislature this session drafted wholesale

    changes to the above described provisions

    dealing with contract retainage claims, and the

    affidavit deadlines for sharing owner statutory

    retainage. These changes were intended to

    alleviate difficulty in the notice of contractual

    retainage claims, and in addition, attempt to

    clarify the deadline(s) for claimants to file their

    affidavits claiming liens, in order to share in the

    owner’s statutory retainage fund.

    1.5.1 New Optional Notice of Contractual

    Retainage Deadlines

    The deadline for the up front, optional notice of

    contract retainage (§53.057) was relaxed

    considerably in the new statute, from the 15th of

    the second month following the subcontractor

    commencing its work, until the earlier of:

    → 30th day after claimant’s agreement (i.e. the

    subcontract work) is completed, terminated or

    abandoned ; OR

    →30th day after date the original

    owner/contractor agreement is terminated or

    abandoned.

    The notice is sent to the owner. It is also sent to

    the original contractor if the claimant is not

    already in privity with the contractor. The

    contents of this retainage have also been relaxed

    so that under the new statute, the notice need

    only contain limited info:

    →the “existence of a requirement for retainage”

    →name and address of claimant

    →name/address of the subcontractor if the

    claimant’s agreement is with a subcontractor

    rather than the original contractor

    This does not require disclosure of the “sum to

    be retained”, due date for the retainage, or nature

    of the agreement, as under the existing law.

    So notice of contractual retainage withheld in a

    subcontract is moved to the end of the Sub’s job.

    This is of considerable benefit to the

    subcontractor claimant. Subs can now wait to

    send retainage notice to the end of their work,

    when they are considerably more likely to know

    whether they have a problem, or potential

  • 2011 Texas Land Title Institute – Page 10 of 19 Construction Retainage and Lien Waivers

    problem with collecting their contractual

    retainage.

    1.5.2 Lien Affidavit Filing Deadline

    Changes.

    This is the complicated part of the new bill,

    especially for owners. The section provides that

    the Claimant has a lien on the owner’s statutory

    10% retainage fund, if the notices are sent as

    described above, or according to the old monthly

    notice requirements of §53.056 (non-residential)

    and §53.252 (residential), and the lien affidavit

    is filed:

    → in accordance with “Subchapter E”; OR

    → by the earliest of 4 different new deadlines!!

    Subchapter E is the old law scheme for filing

    lien affidavits in time to share owner statutory

    retainage – they are due by 30th day following

    final completion, termination or abandonment of

    the original contract. Tex. Prop. Code

    §§53.103(2), as described above in this paper

    §1.4.

    The four alternate new deadlines provided are

    the earliest of:

    1. The “normal” lien filing date

    provided by Tex. Prop. Code §53.052:

    Residential claims: 15th of 3rd

    month after

    claimant’s last month of work/delivery to the

    project., Texas Property Code §53.052 (b), and

    §53.053 ( c); and

    Non-Residential claims: 15th of 4th month

    after claimant’s last month of work/delivery to

    the project., Texas Property Code §53.052 (a),

    and §53.053 ( c); OR

    2. 40th day after the date stated in

    the Affidavit of Completion for the original

    contract, if the Owner sent the Claimant notice

    of the Affidavit. This Affidavit of Completion is

    provided for in §53.106, which allows, but does

    not require, the owner to file such an Affidavit

    stating the date of final completion for the

    project. The Affidavit is “prima facie” evidence

    of the actual final completion date for the project

    if it is sent to claimants as required; OR

    3. For non-residential projects

    only, 40th day after the date of termination or

    abandonment of the original contract if notice of

    termination or abandonment was sent by the

    owner to claimants as required by §53.107.

    Notice of termination or abandonment is not

    applicable to residential projects. Tex. Prop.

    Code §53.107 (e); OR

    4. 30th day after the day the owner

    sends written notice to the claimant demanding

    that the Claimant file its mechanic’s lien

    affidavit. The demand must contain a legal

    description of the project property, owner’s

    name and address, and it must say that the lien

    affidavit must be filed within 30 days of when

    the notice was sent.

    Interestingly, this fourth section (new

    §53.057 (g)) says that the notice “is effective

    only for the amount of contractual retainage

    earned by the claimant as of the day this owner

    notice was sent.” The 4th deadline and §53.057

    (g) indicate that claimants who fail to file within

    30 days of the demand may only have their

    earned contract amount of retainage impacted.

    1.5.3 Application.

    Assume that the Claimant sends its lien notices

    on time, and complies with the new contractual

    retainage notice (within 30 days for claimant’s

    completion). The Owner withheld the statutory

    10% retainage, but no funds were “trapped”

    because the Owner had paid out the adjusted

    contract price to the Contractor prior to receipt

    by the Owner of the Claimant’s notice letters. If

    the Owner sends the “demand” to file the lien

    under this 4th deadline, then in order to share a

    piece of owner statutory retainage with other

    perfecting claimants, the claimant must file his

    lien affidavit by the earliest of the 4 new

    deadlines, per §53.057, or alternatively still can

    file its affidavit within thirty days of project

    completion / termination / abandonment under

    subchapter E, §53.103.

  • 2011 Texas Land Title Institute – Page 11 of 19 Construction Retainage and Lien Waivers

    Analysis of the various kinds of

    claimants, and the required withholding period

    for owner statutory retainage is now a matter of

    applying the alternative deadlines prescribed by

    the new law amendments, depending on what

    owners do in the way of sending the three

    alternate notices: affidavit of final completion,

    or demand to file lien affidavit. If owners want

    to smoke out potential lien claims, in order to

    shorten the time they must withhold statutory

    retainage, then they can consider the alternate

    new deadlines:

    →Owners can file an affidavit of

    completion per §53.106 and send copies to all

    potential claimants. This will trigger the

    §53.057 (f) (1) (b) (ii) deadline for lien affidavits

    which is the 40th day from the date of

    completion stated in the affidavit. This will

    effect claimants who are sent a copy of the

    completion affidavit.

    →The owners can send the new 30 day demand

    for lien filing to all the potential claimants. This

    triggers the §53.057 (f) (1) (b) (iv) deadline,

    which is only effective as to the claimant’s

    contract retainage portion of its claim.

    Problem is, if the owner has not heard from a

    supplier or subcontractor at all (no notices of

    retainage, or other monthly lien notices have

    been received), this may be because the claimant

    has no contractual retainage being withheld

    from it. For these folks, the owner must account

    for the first alternative deadline, §53.057 (f) (1)

    (b) (i), which is the old §53.052 date = 15th of

    the 3rd

    month (for residential) or 15th of the 4

    th

    month (non residential construction) following

    the last month of the claimant’s delivery or work

    on the job.

    Owners are helped somewhat here by the lien

    notice letters required by §53.056 (non

    residential) and §53.252 (residential) deadlines

    for owner lien notice from potential claimants:

    → 15th of the 3

    rd month after each month

    of delivery or work (§53.056)

    →15th of the 2

    nd month after each month

    of delivery or work (§53.252)

    1.5.4 Owner Failure to Withhold

    Retainage – §53.052 Deadlines apply

    If the Owner fails to withhold statutory

    retainage, for the required period of time, then

    the Claimants are entitled to perfect their claims

    by notice and affidavit either by the deadlines

    for progress billings (15th of 3

    rd month

    (residential) and 15th of the 4

    th month (non-

    residential) following last month on the job) or

    new §53.057, either way. So the Hadnot ruling

    was codified. No 30 or 40 day deadlines are

    applicable if the Owners fail to properly

    withhold the statutory retainage.

    1.5.5 “Final Completion”

    TDIndustries, Inc. v. NCNB Texas National

    Bank, 837 S.W.2d 270 (Tex. App. - Eastland

    1992, no writ) contains a discussion of the actual

    final completion date. TDIndustries held that

    actual completion did not occur until the last

    pocket door was installed in the last apartment

    on the apartment project construction. An

    architect’s certificate that the project had been

    completed was not the actual completion date.

    Likewise, substantial completion, or beneficial

    occupancy, is not a good definition. Actual

    completion under TDIndustries does not occur

    until all items required by the contract, plus

    contemplated change orders and extras, have

    actually been installed once. On the other hand,

    a contractor going back out to the site to repair

    items already installed, or perform other

    warranty work, does not thereby extend the

    actual completion date. A claimant may refute

    an affidavit of completion by evidence of later

    completion, in actuality, such as the installation

    of the pocket door in the TDIndustries case.

    The recent case of a Texas Wood Mill Cabinets,

    Inc. v. Butter, 117 S.W.3d 98 (Tex. App.-Tyler

    Aug 06, 2003) - addresses “final completion”.

    The issue in Texas Wood involved whether final

    completion of the cabinetry worked had

    occurred. The Cabinetry installation folks

    returned to the property because there were a

    couple of drawers that were hitting on the cook

    top and the drawers had to be modified to fit

  • 2011 Texas Land Title Institute – Page 12 of 19 Construction Retainage and Lien Waivers

    beneath it. The Court looked at the contract

    scope or work language in order to determine

    final completion. Because the contract required

    that the cabinets be constructed, installed and

    "functional", the court held that this drawer

    adjustment work was the final completion even

    though it otherwise was "punch list" work only.

    1.5.6 Request for Information to Owner –

    Date of original contract execution – Effective

    Date.

    The legislative amendment to “requests for

    information” (§ 53.159) adds a new section

    requiring Owners, upon written Claimant

    request, to furnish a statement including the

    legal description, whether the job was bonded by

    the contractor, identification of prior recorded

    liens on the property, and the new info: the date

    the original contract was signed. This is to be

    provided by owners within ten days. The

    contract signing date is key to determining

    application of the new amendments, which apply

    only to original contracts (between the owner

    and contractor) signed after the effective date

    September 1, 2011.

    The interesting part of this is that Owner failure

    to supply the original contract execution date,

    renders the statutory retainage 30 and 40 day

    deadlines inapplicable, allowing claimants to file

    affidavits by the old §53.052, deadline, 15th of

    the 3rd

    month following their last month of

    work/delivery (residential) and 15th of the 4

    th

    month (non-residential).

    1.5.7 Grounds for Removal of Lien, §53.160

    – Retainage Deadlines Expired

    The list of grounds for removing mechanic’s

    liens was amended to provide that if the

    deadlines for filing lien affidavits, to share in the

    owner’s retainage have all expired, and the

    Owner has already paid the Contractor, without

    first receiving the trap funds or other lien notice,

    then the lien can be removed. §53.160(b)(4).

    2. “Shall” vs “May” Award Attorneys

    Fees

    Mechanics lien claims perfected in accordance

    with the Texas Property Code require judicial

    foreclosure. Mechanics liens are "discharged of

    record " if suit is not timely filed. Tex. Prop.

    Code §53.157. Suits for foreclosure of statutory

    mechanics liens on residential projects must be

    filed within one year of the last day a valid lien

    claim could be filed pursuant to 53.052, or if

    earlier, within one year from completion,

    termination or abandonment of the original

    contract under which the mechanics lien is

    asserted. On non-residential projects, the

    limitations period is two years from the same

    dates.

    Consequently claimants should be aware that

    unless they timely file suit their claims are

    discharged. Naturally the first question is, "How

    am I going to recover the expense of suing just

    to get my money?” The new legislation

    provides that in any action to foreclose a lien (or

    enforce a bond claim) on a job covered by Ch.

    53, or to declare a lien invalid, “in whole or

    part”, the Court “shall” award attorneys fees

    which are "equitable and just"

    So the punch line is that claimants and

    defendants (owner/contractor's) both need to

    evaluate their claims and positions carefully, and

    sufficiently in advance of the relatively short

    fused statute of limitations applicable. Too

    many times claimants hold out hope that

    someone is going to voluntarily pay them off

    without incurring litigation costs, and wind up

    procrastinating themselves up against their one-

    year or two-year limitation period. To avoid

    “discharge” they must file the foreclosure action

    simply to preserve some time to investigate

    whether or not they have a valid claim. Under

    the new statute a hasty, incorrect choice to sue

    will result in fees paid by the claimant to the

    owner or contractor defending against the lien

    claim. Owners on the other hand now know they

    get a mandatory award of attorney’s fees if they

    remove an invalid claim.

    In an important “carve out”, the Court still is

    allowed to use discretion before awarding fees

    against the residential project owner. See new

    Texas Property Code §53.156.

  • 2011 Texas Land Title Institute – Page 13 of 19 Construction Retainage and Lien Waivers

    So if the lien is partially good and partially bad,

    does the owner get all the fees, or what do you

    do? Gill Savings Association v. International

    Supply Co., Inc., 759 S.W.2d 697 (Tex. App.--

    Dallas 1988, writ denied) addressed the question

    about whether a lien overstating the amount due

    as of the time of trial was invalid. In this case,

    the claimant had not applied a $15,000 payment

    received about one month prior to the affidavit

    filing date. Also a credit due of $3,000 had not

    been applied. The affidavit amount of

    $75,986.03 was reduced at trial, after credits and

    corrections to $57,365.32.

    The Court held that the affidavit was in

    substantial compliance with the statute:

    “We hold that under the facts of this

    case, International's lien affidavit was in

    substantial compliance with the property

    code statute when it filed its lien for an

    amount greater than the actual amount

    reconciled by the time of trial two years

    later. See First National Bank in

    Graham v. Sledge, 653 S.W.2d 283, 285

    (Tex.1983) (a subcontractor's lien rights

    are totally dependent on compliance

    with the statutes authorizing the lien;

    however, substantial compliance is

    sufficient to perfect a lien); see also and

    compare Mathews Construction

    Company, Inc. v. Jasper Housing

    Construction, 528 S.W.2d 323, 329

    (Tex.Civ.App.--Beaumont 1975, writ

    ref'd n.r.e.) (holding that a "general

    statement" of the total price in lump sum

    is in substantial compliance with

    mechanic's and materialman's lien

    statutes).”

    Remember, also that “substantial compliance”

    with the mechanics lien statutes has always been

    the test for validity.

    3. Release of Mechanic’s Liens. New

    Statutory Forms. No enforceable release in

    advance of collection.

    One of the most contentious topics in all of

    construction subcontracting over the last several

    years involves releases of liens. Contractors and

    owners sometimes require unconditional lien

    releases before paying a draw or final payment.

    Subcontractors and suppliers often require

    collected funds before signing unconditional

    releases. Some builder/contractors require

    advance waivers of liens as a part of their

    standard subcontract agreements.

    The 2011 Legislature took on the release of lien

    issue and has regulated, verbatim, the language

    of lien waivers, by adding Texas Property Code,

    Subchapter L, §§53.281--.286. This new section

    provides that releases are unenforceable unless

    they comply with the statute. The heart of the

    section is §§53.282 and .283 providing that

    releases are unenforceable unless they (1)

    comply with the forms in the statute, and (2) the

    claimant must have actually received payment in

    good and sufficient funds for an unconditional

    release of lien to be enforceable. No one can

    require a release unless the Claimant has

    collected funds for payment for its work.

    The four new statutory form releases are for

    conditional and unconditional partial payment,

    and for conditional and unconditional final

    payment. The conditional releases are

    ineffective until the check tendered is “properly

    endorsed” and “paid by the bank on which it is

    drawn”. The payment request or statement must

    be attached to the release, and the statute says

    these releases cover the work in the attached pay

    request, except for retainage, pending changes,

    or “other items furnished”.

    The claimant must represent in the release that it

    has paid, or will pay its bills to the extent

    covered by the attached pay request.

    Unconditional releases contain a notice at the

    top of the form warning that unconditional

    releases are prohibited if the Claimant has not

    collected payment.

    The new release forms take effect for “a

    contract” executed on or after January 1, 2012.

    The act contains a “substantial compliance”

    http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1983130245&ReferencePosition=285http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1983130245&ReferencePosition=285http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1975135214&ReferencePosition=329http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1975135214&ReferencePosition=329http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1975135214&ReferencePosition=329http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1975135214&ReferencePosition=329http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1975135214&ReferencePosition=329http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=713&FindType=Y&ReferencePositionType=S&SerialNum=1975135214&ReferencePosition=329

  • 2011 Texas Land Title Institute – Page 14 of 19 Construction Retainage and Lien Waivers

    provision effective through August 31, 2012.

    This provision gives contractors, subcontractors

    and owners until August 31, 2012 to find and

    start using the statutory forms verbatim. Until

    then release forms provided in “attempted

    compliance” are effective. However any attempt

    to jigger with (expand or restrict the rights as

    stated in the statute) the requirement that the

    releases are only effective upon payment

    collected, are banned. The statute terms are

    read into the release forms, and altering

    language is “disregarded”. Any contractual

    provision purporting to waive the new statutory

    requirements are void. Copies of the prescribed

    forms are attached as Exhibit A to this paper.

    Once a lien affidavit is filed or bond claim

    submitted the prescribed forms are not

    applicable.

    The tract home, or spec home builders received

    a special exemption from the provisions of the

    statute. If the project involves construction of

    “single-family houses, townhouses, duplexes, or

    land development for such construction”, the

    new statute specifically sanctions advance

    contractual waiver of mechanic’s lien rights,

    provided the waiver is contained in the written

    agreement or subcontract and such agreement is

    made before the work under that agreement

    commences. However suppliers of material who

    do not furnish any labor are not subject to this

    special home builder advance waiver.

    If a lien is filed anyway by a subcontractor with

    a subcontract with one of these advance waivers

    in it, the filing is declared not to be a violation of

    the fraudulent lien statute, Ch. 12, Civil Practice

    and Remedies Code, as long as the lien is

    released within 14 days in response to an owner

    demand containing an explanation of the reason

    for non-payment on the job, and a copy of the

    contract wavier. See new §§53.282 (b)

    4. Ch. 12 Texas Civil Practice and

    Remedies Code. The Fraudulent Lien Act.

    The Texas Civil Practice and Remedies Code

    Fraudulent Lien provisions were passed to deal

    with fictitious or fraudulent documents creating

    false liens against real property. The Act

    provides that if the document is fraudulent, then

    civil penalties, actual damages, attorney’s fees

    and exemplary damages are recoverable. After

    passage, the Act was employed against

    mechanic’s lien claims. The cases of Centurion

    Planning Corp., Inc. v. Seabrook Venture II, 2004 WL 2823125 (Tex.App.--Hous. (1 Dist.)

    Dec 09, 2004) , and Taylor Elec. Services, Inc.

    v. Armstrong Elec. Supply Co., 167 S.W.3d 522

    (Tex.App.-Fort Worth, 2005) have arguably

    expanded these civil penalty provisions of the

    statute cited beyond the original intent.

    Centurion holds that the civil penalties section

    of the statute can be enforced even if the

    document, and the conduct of the lien claimant

    in question, does not rise to the level of finding

    that the lien violates the fraud test in 51.091 (c)

    Texas Gov’t. Code. Section 51.901(c) of the

    Government Code provides that,

    "[f]or purposes of this section, a

    document or instrument "is presumed to

    be fraudulent" if:

    [T]he document or instrument purports

    to create a lien or assert a claim against

    real or personal property or an interest in

    real or personal property and:

    (A) is not a document or instrument

    provided for by the constitution or laws

    of this state or of the United States;

    (B) is not created by implied or express

    consent or agreement of the obligor,

    debtor, or the owner of the real or

    personal property or an interest in the

    real or personal property, if required

    under the laws of this state, or by

    implied or express consent or agreement

    of an agent, fiduciary, or other

    representative of that person; or

    (C) is not an equitable, constructive, or

    other lien imposed by a court with the

    jurisdiction created or established under

    the construction or laws of this state or

    of the United States.

    Tex. Gov't Code Ann. § 51.901(c)(2)

    (Vernon 1998).

    The Centurion Court held:

    http://www.westlaw.com/Find/Default.wl?rs=dfa1.0&vr=2.0&FindType=0&SerialNum=2006766005http://www.westlaw.com/Find/Default.wl?rs=dfa1.0&vr=2.0&FindType=0&SerialNum=2006766005http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000301&DocName=TXGTS51.901&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000301&DocName=TXGTS51.901&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000176&DocName=TXGTS51.901&FindType=L

  • 2011 Texas Land Title Institute – Page 15 of 19 Construction Retainage and Lien Waivers

    “However, section 51.091(c) does not

    define the term "fraudulent"; it

    establishes a "presumption" that a

    document or instrument is fraudulent

    under certain circumstances. Moreover,

    section 12.006, entitled "Plaintiff's

    Costs," simply provides the

    circumstances under which a plaintiff

    "shall" recover the "costs of bringing the

    action" in addition to the plaintiff's

    damages awarded under section 12.002.

    If the Legislature had wanted to define

    the term "fraudulent" as used for all

    purposes in Chapter 12, it could have

    done so. Instead, the Legislature

    referenced the term fraudulent "as

    described" in Government Code section

    51.901(c) in regard only to the recovery

    of plaintiff's costs in section 12.006. We

    cannot read section 12.006's reference to

    the term fraudulent "as described by

    Section 51.901(c), Government Code"

    as providing a definition of the term for

    all of Chapter 12.”

    The error of the lienor’s ways in Centurion was

    that the claim was made for engineering fees.

    The claimant did not have a written contract

    with the owner for engineering services,

    required as a prerequisite to filing a valid

    engineer’s lien, Tex. Prop. Code §53.021.

    Centurion found the requisite intent for filing a

    fraudulent lien because the claimant admitted

    that he knew he had no written contract. The

    fact that he didn’t know a written contract was

    required for an engineer’s lien was not important

    to the Court. Knowledge of the statutory

    requisites was imputed.

    Ch. 12 was further expanded in Taylor Electric.

    In Taylor the claimant filed a lien for an amount

    which did not account for a payment made prior

    to filing. Also the claimant had substantially

    delayed delivery of materials on the job, which

    was found to be fraudulent conduct by the jury.

    The Court concluded that this evidence of fraud

    was sufficient to make a finding that rendered

    the mechanic’s lien fraudulent as well, violating

    Ch. 12, and supporting award of the $10,000

    civil penalty. The Plaintiff in this case was the

    original contractor on the job, not the owner.

    The Court said the contractor had standing to

    bring a case under the fraudulent lien statute

    because of the contractor’s indemnity obligation

    to protect the owner from liens.

    Walker & Assocs. Surveying v. Roberts, 306

    S.W.3d 839 (Tex. App. Texarkana 2010),

    clarifies the proof required for a violation of Ch.

    12, as follows:

    Thus, to establish a fraudulent lien in

    this case, Roberts was required to show

    that Walker or WAS (1) made,

    presented, or used a document with

    knowledge that it was a fraudulent lien;

    (2) intended the document be given

    legal effect; and (3) intended to cause

    Roberts financial injury. See TEX. CIV.

    PRAC. & REM. CODE ANN. §

    12.002(a). n8

    Walker & Assocs. Surveying v. Roberts,

    306 S.W.3d 839, 848 (Tex. App.

    Texarkana 2010)

    …….Next, Roberts cites Taylor

    Electrical Services for the proposition

    that Walker's letter informing Roberts of

    the lien stating, "Upon receipt of

    payment in full this lien will be

    removed" was evidence of intent to

    cause financial harm. 167 S.W.3d 522.

    There are two key differences

    distinguishing this case from Taylor.

    First, Taylor involved a jury finding. Id.

    at 525. Second, the evidence of intent in

    Taylor was a letter threatening to file a

    lien and stating, "We do not wish you

    any harm in your business," evidencing

    knowledge that the filing of a lien could

    potentially cause financial harm. Id. at

    531. We decline to find that the letter

    sent by [**20] Walker in this case

    established intent as required by the

    fraudulent lien statute. At most, it

    creates a genuine issue of material fact

    for a jury's resolution.

    Consequently the Taylor and Walker cases teach

    http://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000170&DocName=TXCPS12.006&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000170&DocName=TXCPS12.002&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000301&DocName=TXGTS51.901&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000301&DocName=TXGTS51.901&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000170&DocName=TXCPS12.006&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000170&DocName=TXCPS12.006&FindType=Lhttp://www.westlaw.com/Find/Default.wl?rs=++++1.0&vr=2.0&DB=1000301&DocName=TXGTS51.901&FindType=Lhttp://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=306+S.W.3d+839%2520at%2520848http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=306+S.W.3d+839%2520at%2520848http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=306+S.W.3d+839%2520at%2520848http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=306+S.W.3d+839%2520at%2520848http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=306+S.W.3d+839%2520at%2520848https://www.lexis.com/research/buttonTFLink?_m=8e5b19ba4f4886aeca513d157500d6af&_xfercite=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b306%20S.W.3d%20839%5d%5d%3e%3c%2fcite%3e&_butType=3&_butStat=2&_butNum=101&_butInline=1&_butinfo=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b167%20S.W.3d%20522%5d%5d%3e%3c%2fcite%3e&_fmtstr=FULL&docnum=1&_startdoc=1&wchp=dGLzVzk-zSkAl&_md5=74fd85562eabb578b9882237edda039chttps://www.lexis.com/research/buttonTFLink?_m=8e5b19ba4f4886aeca513d157500d6af&_xfercite=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b306%20S.W.3d%20839%5d%5d%3e%3c%2fcite%3e&_butType=3&_butStat=2&_butNum=102&_butInline=1&_butinfo=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b167%20S.W.3d%20522%2c%20525%5d%5d%3e%3c%2fcite%3e&_fmtstr=FULL&docnum=1&_startdoc=1&wchp=dGLzVzk-zSkAl&_md5=7dccc0566c13d1e528d5812bc5c05406https://www.lexis.com/research/buttonTFLink?_m=8e5b19ba4f4886aeca513d157500d6af&_xfercite=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b306%20S.W.3d%20839%5d%5d%3e%3c%2fcite%3e&_butType=3&_butStat=2&_butNum=102&_butInline=1&_butinfo=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b167%20S.W.3d%20522%2c%20525%5d%5d%3e%3c%2fcite%3e&_fmtstr=FULL&docnum=1&_startdoc=1&wchp=dGLzVzk-zSkAl&_md5=7dccc0566c13d1e528d5812bc5c05406https://www.lexis.com/research/buttonTFLink?_m=8e5b19ba4f4886aeca513d157500d6af&_xfercite=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b306%20S.W.3d%20839%5d%5d%3e%3c%2fcite%3e&_butType=3&_butStat=2&_butNum=103&_butInline=1&_butinfo=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b167%20S.W.3d%20522%2c%20531%5d%5d%3e%3c%2fcite%3e&_fmtstr=FULL&docnum=1&_startdoc=1&wchp=dGLzVzk-zSkAl&_md5=7e12bf7a92be06bdf81bce74ff0beb73https://www.lexis.com/research/buttonTFLink?_m=8e5b19ba4f4886aeca513d157500d6af&_xfercite=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b306%20S.W.3d%20839%5d%5d%3e%3c%2fcite%3e&_butType=3&_butStat=2&_butNum=103&_butInline=1&_butinfo=%3ccite%20cc%3d%22USA%22%3e%3c%21%5bCDATA%5b167%20S.W.3d%20522%2c%20531%5d%5d%3e%3c%2fcite%3e&_fmtstr=FULL&docnum=1&_startdoc=1&wchp=dGLzVzk-zSkAl&_md5=7e12bf7a92be06bdf81bce74ff0beb73

  • 2011 Texas Land Title Institute – Page 16 of 19 Construction Retainage and Lien Waivers

    that to trigger Ch. 12, there must be evidence the

    Claimant intended financial harm.

    Further complicating this area the Legislature

    amended Ch. 12 in 2009 to specifically exempt

    mechanic’s lien Claimants by adding §12.002

    (c):

    A person claiming a lien under Chapter

    53, Property Code, is not liable under

    this section for the making, presentation,

    or use of a document or other record in

    connection with the assertion of the

    claim unless the person acts with intent

    to defraud.

    Given the fraudulent intent requirements as

    identified in Taylor and Walker the mechanic’s

    lien exemption does not absolve Claimants of

    exposure for Ch. 12 violations.

    In fact, under the new release of lien bill, Texas

    Property Code §53.282 (discussed above, §3), in

    cases where an advance release of lien is

    included in a residential contract, (see above §3,

    page 16) it is an express violation of §12.002 if

    the lien claimant fails to release a lien within 14

    days of the day the owner sent the request for

    release and other items required.

    5. Construction Trust Funds Liability –

    Residential Construction

    5.1 Basics and Bank Exemption.

    Texas Property Code §162.001 provides an

    additional, and separate remedy over and above

    the involuntary mechanic’s lien rights. Under

    this statute, construction payments or loan

    receipts to pay for construction (including such

    funds in the hands of an owner, general

    contractor, a sub, or any officer or director or

    agent of the same) are "trust funds". Recipients

    (i.e., the owner, contractor, subcontractor) are

    “trustees” for the construction funds which come

    into their possession on the job. Owners are

    trustees if they receive loan draws and such loan

    is secured by a lien on the project property.3

    3 Texas Property Code §162.001(b).

    Anybody who furnishes labor or material to

    improve real property in Texas, is a beneficiary

    of this "trust fund." The purpose of this "fund"

    is to pay for the work or materials.

    It is a felony to retain, use, or divert trust funds

    in excess of $500.00, unless the trustee has paid

    all current or past due obligations respecting the

    trust funds. The case law provides a private

    civil action for violation of the Trust Fund

    Statute.4 There are some affirmative defenses to

    suit or prosecution under this law. The holder of

    funds is allowed to use them to pay actual

    expenses directly related to the construction

    project. He is also allowed to retain them upon

    the basis of a "reasonable belief" that the party

    claiming is not entitled to be paid the money, or

    because the funds are retained because a lien

    claim has been filed.

    Again, keep in mind that the beneficiary under

    this theory is not required to establish any kind

    of valid mechanic’s lien. This is a wholly

    separate and additional right of the claimant.

    More special interest legislation occurred with

    passage of the Trust Funds Act, because Banks

    are totally exempt from its application. In re

    Waterpoint International, 330 F.3rd

    339 (5th Cir.

    (Tex. 2003). In this case, the bankruptcy court

    decision was affirmed by the 5th Circuit

    regarding a fight between the Subcontractor and

    Comerica Bank as to the debtor-contractor’s

    accounts receivables. Waterpoint, Debtor,

    contracted with Exxon to improve a certain

    parcel of land. The Subcontractor to Waterpoint

    was not paid for its work, but also never

    perfected a mechanic’s lien. Contractor filed

    bankruptcy. Comerica Bank asserted it had a

    perfected security interest in the Contractor’s

    receivables, including the money owed by

    Exxon. The Subcontractor claimed a priority to

    these receivables under the Texas Construction

    Trust Fund Statute as outlined above. Citing

    4 Lively v. Carpet Services, Inc., 904 S.W.2d 868

    (Tex.App. -- Houston [1st Dist.] 1995, writ denied)

    and Tacon Mechanical Contractors, Inc. v. Grant

    Sheet Metal, Inc., 889 S.W.2d 666 (Tex.App. –

    Houston [14th Dist.] 1994, writ denied).

  • 2011 Texas Land Title Institute – Page 17 of 19 Construction Retainage and Lien Waivers

    Texas Property Code 162.004 (exempting Banks

    from the Trust Fund Statute) and the Texas

    Supreme Court in Republicbank Dallas, N.A. v.

    Interkal, Inc., 691 S.W.2d 605, 607-08 (Tex.

    1985), the Court held that banks are not subject

    to the Construction Trust Fund Statue. The

    court then considered the subcontractor’s next

    argument, that the legislature, after the Interkal

    decision, had passed Texas Property Code

    Section 53.151, providing that a creditor cannot

    enforce a security interest to the prejudice of a

    subcontractor. The court held that Interkal is

    still the law in spite of 53.151. The Court held

    further that if the subcontractor had perfected its

    mechanic’s lien against the project, then with a

    perfected mechanic’s lien it would have been

    able to keep the bank from intercepting the

    construction payment from the owner to the

    contractor. Without a perfected mechanic’s lien

    however, the Court held that the subcontractor

    was without a remedy. Under such

    circumstances the bank could take the

    construction funds with impunity by exemption

    from the trust fund statute.

    “The courts interpreting article 5466, the

    predecessor to §53.151, demonstrate the

    presumption (at least under article 5466)

    that a derivative claimant must comply

    with the lien perfection procedures in

    order to assert rights to funds held by

    the owner. See, e.g., Youngstown Sheet

    & Tube Co. v. Lucey Prod. Co., 403

    F.2d 135, 142 (5th Cir.1968) (discussing

    (under the Hardeman Act) the need for

    proof of a materialman's compliance

    with the procedures for lien perfection

    before liens can affix to an account

    receivable of a debtor); Crutcher,

    Rolfs, Cummings, Inc. v. Big Three

    Welding Equip. Co., 224 S.W.2d 884

    (Tex.Civ.App.-Galveston 1949), rev'd

    on other grounds, 149 Tex. 204, 229

    S.W.2d 600 (1950) (discussing article

    5466 as referring to only funds

    subjected to mechanics' and

    materialmen's liens); see also

    Baumann v. Cibolo Lumber Co., 226

    S.W.2d 210, 212 (Tex.Civ.App.-San

    Antonio 1950, no writ) (same). These

    cases further persuade us to reject

    Exchanger's argument that §53.151 was

    meant to overrule Interkal as

    inconsistent with the framework and

    function of Chapters 53 and 162.” Supra

    @ 348.

    5.2 Accounting – Residential

    Homesteads.

    If the project is for construction of

    improvements to a residential homestead

    exceeding $5,000, the builder is required to

    deposit the construction payments into a

    "construction account". The bank statement

    must identify the account as the "construction

    account".

    The builder must maintain an account record

    showing the source and amount of trust funds

    come including date of deposit, the date and

    amount of each disbursement from the account

    and the payee, and current balance. A separate

    "account record" for each project must be

    maintained which specifies direct costs and

    indirect costs. All invoicing and other supporting

    documents regarding construction costs for

    which trust funds were disbursed, must be

    retained. The deposit and payment documents

    must reference the construction account number

    or other link to the construction account. The

    accounting information must be preserved for at

    least one year from completion.

    5.3 Trust Fund Act Litigation – Cause of

    Action and Limitations Clarified.

    The use of the Texas construction trust fund act

    in civil litigation has dramatically expanded in

    the last several years. Different appellate

    decisions however have applied different causes

    of action to enforcement of the act. See Lively v.

    Carpet Services, Inc., 904 S.W.2d 868

    (Tex.App. -- Houston [1st Dist.] 1995, writ

    denied) and Tacon Mechanical Contractors,

    Inc. v. Grant Sheet Metal, Inc., 889 S.W.2d 666

    (Tex.App. -- Houston [14th Dist.] 1994, writ

    denied).

  • 2011 Texas Land Title Institute – Page 18 of 19 Construction Retainage and Lien Waivers

    However in Polk Mech. Co., LLC v. Jones,

    2009 Tex. App. LEXIS 4939, 9-11 (Tex. App.

    San Antonio, 2009, pet. Review denied, 2009)

    the cause of action, and applicable limitations

    statute were addressed. The San Antonio Court

    4th Court of Appeals clarified that the Trust Fund

    act creates a fiduciary relationship between the

    trustee and beneficiary, and the cause of action

    therefore is a claim for breach of fiduciary duty.

    The four year statute of limitations applies, and

    is subject to the "discovery rule". Therefore the

    cause of action must be “inherently

    undiscoverable” but “objectively verifiable”.

    Limitations does not commence until the

    plaintiff knew, or should have known, of the

    facts giving rise to the claim.

    “Polk Mechanical's claim against

    Jones arises under the Texas

    Construction Trust Fund Act. Under

    section 162.003 of the Act, a

    subcontractor who labors or who

    furnishes labor or material for the

    construction or repair of an

    improvement on real property is a

    beneficiary of any trust funds paid by or

    received in connection with the

    improvement. TEX. PROP. CODE

    ANN. § 162.003 (Vernon 2007). A

    contractor, or an officer of a contractor

    who receives trust funds or who has

    control or direction over trust funds, is a

    trustee of the trust funds. Id. § 162.002.

    The Act, therefore, creates a

    beneficiary/trustee relationship between

    a subcontractor and a contractor who

    receives payment from a project owner.

    See id. In other words, the Act

    "imposes fiduciary responsibilities on

    contractors to ensure that Texas

    subcontractors . . . are paid for work

    completed." Kelly v. Gen. Interior

    Constr., Inc., 262 S.W.3d 79, 84-85

    (Tex. App.--Houston [14th Dist.] 2008,

    pet. granted on other grounds); In re

    Faulkner, 213 B.R. 660, 666 n. 10

    (Bankr. W.D. Tex. 1997) (noting that a

    trust relationship arises under Texas law

    at the time payments are made to the

    contractor for construction).

    A variation to the inherently

    undiscoverable element arises when

    applying the discovery rule to a

    fiduciary relationship. Computer

    Assocs. Int'l, Inc. v. Altai, Inc., 918

    S.W.2d 453, 456 (Tex. 1996); see also

    S. V. v. R. V., 933 S.W.2d 1, 8 (Tex.

    1996). In the fiduciary context, "a

    person to whom a fiduciary duty is owed

    is either unable to inquire into the

    fiduciary's actions or unaware of the

    need to do so." S V., 933 S.W.2d at 8.

    When a trustee breaches its duty to a

    beneficiary, the nature of the injury is

    considered inherently undiscoverable

    because of the fiduciary nature of the

    relationship. See id. However, the

    person owed a fiduciary relationship still

    must exercise reasonable diligence

    "when the fact of misconduct becomes

    [so] apparent it can no longer be

    ignored." n1 Id.; see also Computer

    Assocs. Int'l, 918 S.W.2d at 456;

    [*11] Slay v. Burnett Trust, 143 Tex.

    621, 187 S.W.2d 377, 394 (Tex. 1945);

    G. Prop. Mgmt., Ltd. v. Multivest Fin.

    Servs. of Tex., Inc., 219 S.W.3d 37, 48-

    49 (Tex. App.--San Antonio 2006, no

    pet.).

    Because Jones owed fiduciary

    responsibilities to Polk Mechanical, the

    inherently undiscoverable requirement

    for applying the discovery rule is

    satisfied. See S V., 933 S.W.2d at 8.

    Moreover, the injury in this case is

    objectively verifiable as it can be

    objectively established through bank

    records and cancelled checks. See

    HECI Exploration Co., 982 S.W.2d at

    886. Accordingly, we hold the

    discovery rule applied to Polk

    Mechanical's claim against Jones, and

    Jones was required to conclusively

    negate its application to be entitled to

    summary judgment. See Pustejovsky, 35

    S.W.3d at 646 Polk Mech. Co., LLC v.

    Jones, 2009 Tex. App. LEXIS 4939, 9-

    http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939

  • 2011 Texas Land Title Institute – Page 19 of 19 Construction Retainage and Lien Waivers

    11 (Tex. App. San Antonio, 2009,

    review denied)

    Polk Mech. Co., LLC v. Jones, 2009

    Tex. App. LEXIS 4939 (Tex. App. San

    Antonio July 1, 2009)

    Polk Mechanical discusses, in reversing

    summary judgment for the defendants on

    limitations, that the discovery rule may not have

    been tripped until the defendants’ bank records

    were produced showing the expenditures on

    other projects, taking the balance below the

    deposits on the project in question.

    END.

    http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939http://www.lexis.com/research/xlink?app=00075&view=full&searchtype=get&search=2009+Tex.+App.+LEXIS+4939

  • EXHIBIT “A”

    (Page 1 of 4)

    Conditional Partial Release - During Construction

    §53.284 (b), Tex. Property Code:

    If a contractor (or other potential lien claimant) is required to execute a waiver

    and release in exchange for or to induce payment of a progress payment and is not

    paid in exchange for the waiver and release or if a single payee check or joint payee

    check is given in exchange for the waiver and release, the waiver and release must

    read:

    CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT

    Project ___________________

    Job No. ___________________

    On receipt by the signer of this document of a check from ________________

    (maker of check) in the sum of $__________ payable to _____________________ (payee or

    payees of check) and when the check has been properly endorsed and has been

    paid by the bank on which it is drawn, this document becomes effective to release any

    mechanic's lien right, any right arising from a payment bond that complies with a state

    or federal statute, any common law payment bond right, any claim for payment, and

    any rights under any similar ordinance, rule, or statute related to claim or payment rights

    for persons in the signer's position that the signer has on the property of

    ________________ (owner) located at ______________________ (location) to the following

    extent: ______________________ (job description).

    This release covers a progress payment for all labor, services, equipment, or

    materials furnished to the property or to __________________ (person with whom signer

    contracted) as indicated in the attached statement(s) or progress payment request(s),

    except for unpaid retention, pending modifications and changes, or other items

    furnished.

    Before any recipient of this document relies on this document, the recipient

    should verify evidence of payment to the signer.

    The signer warrants that the signer has already paid or will use the funds received

    from this progress payment to promptly pay in full all of the signer's laborers,

    subcontractors, materialmen, and suppliers for all work, materials, equipment, or

    services provided for or to the above referenced project in regard to the attached

    statement(s) or progress payment request(s).

    Date ____________________________

    _________________________________ (Company name)

    By ______________________________ (Signature)

    _________________________________ (Title)

  • EXHIBIT “A”

    (Page 2 of 4)

    Unconditional Partial Release - During Construction

    §53.284 (c), Tex. Property Code:

    If a contractor (or other potential lien claimant) is required to execute an

    unconditional waiver and release to prove the receipt of good and sufficient funds for

    a progress payment and the claimant or potential claimant asserts in the waiver and

    release that the claimant or potential claimant has been paid the progress payment,

    the required statutory form of waiver and release is as follows. The form must include

    the Notice at the top:

    NOTICE:

    This document waives rights unconditionally and states that you have been paid

    for giving up those rights. It is prohibited for a person to require you to sign this

    document if you have not been paid the payment amount set forth below. If you have

    not been paid, use a conditional release form.

    UNCONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT

    Project ___________________

    Job No. ___________________

    The signer of this document has been paid and has received a progress

    payment in the sum of $___________ for all labor, services, equipment, or materials

    furnished to the property or to _____________________ (person with whom signer

    contracted) on the property of _______________________ (owner) located at

    ______________________ (location) to the following extent: ______________________ (job

    description). The signer therefore waives and releases any mechanic's lien right, any

    right arising from a payment bond that complies with a state or federal statute, any

    common law payment bond right, any claim for payment, and any rights under any

    similar ordinance, rule, or statute related to claim or payment rights for persons in the

    signer's position that the signer has on the above referenced project to the following

    extent:

    This release covers a progress payment for all labor, services, equipment, or

    materials furnished to the property or to __________________ (person with whom signer

    contracted) as indicated in the attached statement(s) or progress payment request(s),

    except for unpaid retention, pending modifications and changes, or other items

    furnished.

    The signer warrants that the signer has already paid or will use the funds received

    from this progress payment to promptly pay in full all of the signer's laborers,

    subcontractors, materialmen, and suppliers for all work, materials, equipment, or

    services provided for or to the above referenced project in regard to the attached

    statement(s) or progress payment request(s).

    Date ____________________________

    _________________________________ (Company name)

    By ______________________________ (Signature)

    _________________________________ (Title)

  • EXHIBIT “A”

    (Page 3 of 4)

    Conditional Final Release

    §53.284 (d), Tex. Property Code:

    If a contractor (or other potential lien claimant) is required to execute a

    waiver and release in exchange for or to induce the payment of a final payment

    and is not paid in good and sufficient funds in exchange for the waiver and

    release or if a single payee check or joint payee check is given in exchange for

    the waiver and release, the waiver and release must read:

    CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT

    Project ___________________

    Job No. ___________________

    On receipt by the signer of this document of a check from

    ________________ (maker of check) in the sum of $____________ payable to

    _____________________ (payee or payees of check) and when the check has

    been properly endorsed and has been paid by the bank on which it is drawn,

    this document becomes effective to release any mechanic's lien right, any right

    arising from a payment bond that complies with a state or federal statute, any

    common law payment bond right, any claim for payment, and any rights under

    any similar ordinance, rule, or statute related to claim or payment rights for

    persons in the signer's position that the signer has on the property of

    _____________________ (owner) located at ______________________ (location) to

    the following extent: ______________________ (job description).

    This release covers the final payment to the signer for all labor, services,

    equipment, or materials furnished to the property or to __________________

    (person with whom signer contracted).

    Before any recipient of this document relies on this document, the

    recipient should verify evidence of payment to the signer.

    The signer warrants that the signer has already paid or will use the funds

    received from this final payment to promptly pay in full all of the signer's laborers,

    subcontractors, materialmen, and suppliers for all work, materials, equipment, or

    services provided for or to the above referenced project up to the date of this

    waiver and release.

    Date ____________________________

    _________________________________ (Company name)

    By ______________________________ (Signature)

    _________________________________ (Title)"

  • EXHIBIT “A”

    (Page 4 of 4)

    Unconditional Release – Final Payment

    If a contractor (or o