    What is a project?

    A project is a collection of activities and events with

    a definable beginning and a definable end (the

    goal). For example: getting a college degree,

    building a bridge, or installing new machinery.

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    2/21

    Terms used..

    Activity:

    An activity is an effort that requires resources and takes acertain amount of time for completion. Examples of activitiesare: studying for an examination, designing a part, or

    training an employee.

    Critical activity:

    A critical activity is an activity that, if even slightly de-layed, will hold up the scheduled completion date of the

    entire project.

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    3/21

    Cont..

    Path:

    A path is a series of adjacent activities leading

    from one event to another.

    Critical path:

    A critical path is the sequence of critical activities

    that forms a continuous path between the start of a

    project and its completion.

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    4/21

    Cont..

    Event:

    An event is a specific accomplishment at arecognizable point in time; for example, passing acourse at a university, submission of engineering drafts,completion of a span on a bridge, or the arrival of anew machine. To reach an event, all the activities thatprecede it must be completed. An event can be viewedas a goal attained, while the activities leading to it canbe viewed as the means of achieving it.

    Network:

    A network is a logical and chronological set ofactivities and events.

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    5/21

    Components of a project cycle

    initiation;

    planning and design;

    execution and construction; monitoring and controlling systems;

    completion.

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    6/21

    Cont..

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    7/21

    Design and layout of building

    First floor of Chemical Engineering Departmentincludes:4 classrooms

    3 laboratories3 faculty rooms

    1 conference cum tea room

    1 kitchen

    1 store

    3 stair cases

    2 wash rooms

    1 reception

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    8/21

    Cont..

    Entrance & exits

    1 lobby

    Outside Lawn

    Connectivity of admin office and chairman office

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    9/21

    Set of activities

    1.Start

    2.Selection of architect

    3.Selection of layout4.Design approval from LDA

    5.Procurement for construction

    6.Excavation for foundation

    7.brickwork foundation

    8.Installation of DPC

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    10/21

    9.Sand filling

    10.Brick masonary of ground floor

    11.Procurement of windows and doors12.Fixing door frames

    13.Fixing window frames

    14.Shattering of roofs

    15.Roof steel lining

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    11/21

    16.Electrical conduits as per diagram

    17. Concrete 124 RCC

    18.Slab of roof

    19. Curing of roof

    20. Electrical wiring

    21. Roof plaster

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    12/21

    22.Plaster of walls and curing

    23. Plumbing and sanitation

    24. Plastering and rough brooming25. Preparation of bed

    26. Compaction with compacter

    27. Brick blast

    28. Water proofing

    29. Tiling work

    30.Draindown pipes

    31.C

    ementing32. Smoothening with sand papers

    33. Whitewashing

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    13/21

    34. Wall painting

    35. Wood work

    36. Procurement of machinery37. Installation of machinery

    38. Application for phone

    39. Installation of phone

    40. Procurement for washroom

    41.Installation of washroom

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    14/21

    42. Installation of electrical sockets

    43. installation of fans and tubes

    44. Application for sui gas

    45. Installation of gas lines

    46. Exterior finishing

    47. Installation of AC,water coolers

    48. Installation of boards49. Assessories of building

    50. End project

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    15/21

    Activity details

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    16/21

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    17/21

    BAR CHART

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    18/21

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    19/21

    PERT

  • 8/3/2019 Construction Project for the 1st Floor of Chemical

    20/21

    Number of activities = 50

    Total duration = 1 year and 65 days.