Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
CONSTRUCTION PROGRESS
UPDATE
Vol. 13December 2016
TO VALUED BUYERS OF BODAIJU RESIDENCES
©Torreya Asset Holdings Co., Ltd.
Construction Schedule Payment Schedule
Mar
Nov.
2015
Oct.
Dec
2016
Jan
Feb
Mar
Apr
May
Jun
Sep
Oct
Nov
Dec
2017
Jan
Feb
Jul
Aug
Vol. 13 December 2016
Bodaiju Site Progress Report - Building A and B -
1
GENERAL SCHEDULE (October 2015 – June 2017) CONSTRUCTION PROGRESS
We are completed the 8th Floor Structure Work in this
October. Structure Work of RF Floor plan to complete by
end of Feb 2017.
Piling works
Architectural
works
Interior works
MEP
works
Completion of
RF floor structure
preliminary
works - Mine investigation
- Ultimate load test, etc.
RC
Superstructure
※Construction’s Schedule might vary to take weather conditions and other factors into account.
Building ABuilding B
※The diagram above only serves to illustrate the construction progress. Actual construction may not be
carried out as per the illustration.
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
FOUNDATION WORK
COMPLETED. MARCH-2016
Completion of
foundation
Parking 1
Parking 2
Garden Deck
1st FLOOR STRUCTURE
COMPLETED. JUNE-2016
Completion of
1st floor structure
7th FLOOR STRUCTURE
COMPLETED. SEP-2016
Completion of
7th floor structure
NOW 10th FLOOR STRUCTURE
©Torreya Asset Holdings Co., Ltd. Vol. 13 December 2016
Bodaiju Site Progress Report - Building A and B -
2
FOUNDATION COMPLETION – March 2016 PHOTOS OF PROGRESS COMPLETION
©Torreya Asset Holdings Co., Ltd. Vol. 13 December 2016
Bodaiju Site Progress Report - Building A and B -
3
1FL. SUPER-STRUCTURE COMPLETION-June 2016 PHOTOS OF PROGRESS COMPLETION
©Torreya Asset Holdings Co., Ltd. Vol. 13 December 2016
Bodaiju Site Progress Report - Building A and B -
4
7FL. SUPER-STRUCTURE COMPLETION-Sep. 2016 PHOTOS OF PROGRESS COMPLETION
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
5
NOVEMBER 2016 SITE VIEW (BUILDING A & B)
In November 2016 we already complete the 10th Floor Structure Work and reinforcement work of 11th Floor for Building A & B.
Vol. 13 December 2016
B1 View – Building B
A1
A2
B1
B2
A1 View – Building A
A2 View – Building AB2 View – Building B
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
6
11FL-BEAM & SLAB FORM WORK (BUILDING A & B) 11FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 11th
Floor which completed in this November.Slab and Beam Form Work installation activities in our constructionsite in November 2016.
Vol. 13 December 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
7
10FL-RE-BAR CHECK & CLEANING (BUILDING A & B) 10FL-CONCRETE TEST AT SITEMixed-Concrete was tested at site before casting building A& B Structure, 10FL Slab and Beam.
Re-Bar Checking activates of Building A & B at construction site byour engineer.
Vol. 13 December 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
8
MEP WORK (BUILDING A & B) 10FL-CONCRETE WORK (BUILDING A & B)
This is Water Piping Work of Building A & B was completed inNovember 2016.
Pipe for electricity in 10th Floor Slab was laid to be ready forconcreting and laid water piping system under the stab.
Vol. 13 December 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
9
MASONRY WORK (BUILDING A & B) PLASTERING WORK (BUILDING A & B)
PLASTERING WORK is the a layer of wall after brick work. Nowwe are processing Plastering Work from this November 2016.
MASONRY WORK is the brick work after finish structure work ineach floor. This is our site activities in November 2016.
Vol. 13 December 2016