CONSTRUCTION PROGRESS UPDATE Vol. 13 December 2016 TO VALUED BUYERS OF BODAIJU RESIDENCES

CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

CONSTRUCTION PROGRESS

UPDATE

Vol. 13December 2016

TO VALUED BUYERS OF BODAIJU RESIDENCES

Page 2: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd.

Construction Schedule Payment Schedule

Mar

Nov.

2015

Oct.

Dec

2016

Jan

Feb

Mar

Apr

May

Jun

Sep

Oct

Nov

Dec

2017

Jan

Feb

Jul

Aug

Vol. 13 December 2016

Bodaiju Site Progress Report - Building A and B -

1

GENERAL SCHEDULE (October 2015 – June 2017) CONSTRUCTION PROGRESS

We are completed the 8th Floor Structure Work in this

October. Structure Work of RF Floor plan to complete by

end of Feb 2017.

Piling works

Architectural

works

Interior works

MEP

works

Completion of

RF floor structure

preliminary

works - Mine investigation

- Ultimate load test, etc.

RC

Superstructure

※Construction’s Schedule might vary to take weather conditions and other factors into account.

Building ABuilding B

※The diagram above only serves to illustrate the construction progress. Actual construction may not be

carried out as per the illustration.

P1

P2

1F

2F

3F

5F

6F

7F

8F

9F

10F

11F

12F

13F

RF

P1

P2

1F

2F

3F

5F

6F

7F

8F

9F

10F

11F

12F

13F

RF

FOUNDATION WORK

COMPLETED. MARCH-2016

Completion of

foundation

Parking 1

Parking 2

Garden Deck

1st FLOOR STRUCTURE

COMPLETED. JUNE-2016

Completion of

1st floor structure

7th FLOOR STRUCTURE

COMPLETED. SEP-2016

Completion of

7th floor structure

NOW 10th FLOOR STRUCTURE

Page 3: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd. Vol. 13 December 2016

Bodaiju Site Progress Report - Building A and B -

2

FOUNDATION COMPLETION – March 2016 PHOTOS OF PROGRESS COMPLETION

Page 4: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd. Vol. 13 December 2016

Bodaiju Site Progress Report - Building A and B -

3

1FL. SUPER-STRUCTURE COMPLETION-June 2016 PHOTOS OF PROGRESS COMPLETION

Page 5: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd. Vol. 13 December 2016

Bodaiju Site Progress Report - Building A and B -

4

7FL. SUPER-STRUCTURE COMPLETION-Sep. 2016 PHOTOS OF PROGRESS COMPLETION

Page 6: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

5

NOVEMBER 2016 SITE VIEW (BUILDING A & B)

In November 2016 we already complete the 10th Floor Structure Work and reinforcement work of 11th Floor for Building A & B.

Vol. 13 December 2016

B1 View – Building B

A1

A2

B1

B2

A1 View – Building A

A2 View – Building AB2 View – Building B

Page 7: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

6

11FL-BEAM & SLAB FORM WORK (BUILDING A & B) 11FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)

Reinforcement Work site activities of Building A & B on 11th

Floor which completed in this November.Slab and Beam Form Work installation activities in our constructionsite in November 2016.

Vol. 13 December 2016

Page 8: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

7

10FL-RE-BAR CHECK & CLEANING (BUILDING A & B) 10FL-CONCRETE TEST AT SITEMixed-Concrete was tested at site before casting building A& B Structure, 10FL Slab and Beam.

Re-Bar Checking activates of Building A & B at construction site byour engineer.

Vol. 13 December 2016

Page 9: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

8

MEP WORK (BUILDING A & B) 10FL-CONCRETE WORK (BUILDING A & B)

This is Water Piping Work of Building A & B was completed inNovember 2016.

Pipe for electricity in 10th Floor Slab was laid to be ready forconcreting and laid water piping system under the stab.

Vol. 13 December 2016

Page 10: CONSTRUCTION PROGRESS UPDATE - Bodaiju Residencesbodaiju-residences.com/wp-content/uploads/2016/12/201611_Bodaij… · 8F 9F 10F 11F 12F 13F RF P1 P2 1F 2F 3F 5F 6F 7F 8F 9F 10F 11F

©Torreya Asset Holdings Co., Ltd.

Bodaiju Site Progress Report - Building A and B -

9

MASONRY WORK (BUILDING A & B) PLASTERING WORK (BUILDING A & B)

PLASTERING WORK is the a layer of wall after brick work. Nowwe are processing Plastering Work from this November 2016.

MASONRY WORK is the brick work after finish structure work ineach floor. This is our site activities in November 2016.

Vol. 13 December 2016