45
Construction OSH Management Guidelines Amree Bin Ghazi Construction Safety Division Department of Occupational Safety and Health

Construction OSH Management Guidelines 6_Construction OSH Mgmt...Construction OSH Management Guidelines - Significance Across US, 42% of construction fatalities were related to design

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

  • Construction OSH Management

    Guidelines

    Amree Bin Ghazi

    Construction Safety Division

    Department of Occupational Safety and Health

  • Pilot Project On OSHCIM

    2

  • What is the contributing factors to

    accident/incident?

    3

  • Slope Failure , Tanjung Bungah , 2017

    • Failure to identify risk

    • Failed to recognize the

    significance of earlier

    incident

    4

  • Falsework failure, Penang, 2013

    • Installation of falsework

    component

    • Falsework system

    unstable(curved, skewed)

    • Unclear method

    statement

    • Lack of information on

    falsework design

    • Failed to recognize

    complexity of the work

    5

  • Falsework failure, JB, 2013

    • Installation of falsework is

    not according to design

    • Lack of competence

    people during installation,

    inspection

    • Insufficient SOP during

    concreting – no person to

    inspect while concreting,

    inspection must be done

    before concreting

    6

  • Roof structure collapse, Terengganu 2013

    • Incomplete method

    statement –

    MS2318:2012

    • Incompetent contractor

    • Failure to identify risk due

    to change of process

    • Failure to recognize the

    significance of previous

    report

    • Failure to recognize the

    complexity of work

    7

  • Viaduct toppled during installation, Selangor,

    2014

    • Lack of supervision

    • Failure to identify risk due

    to change of process

    • Lack of inspection and

    testing

    • Effective communication

    failure

    • Lack of sub-contractor

    management

    • Unsafe SOP

    8

  • Fatal accident cases from the

    DOSH’s website (http://www.dosh.gov.my/index.php/en/fatal-accident-case)

    If you analyse the cases, you will realise that:

    Accidents are commonly repeating

    Lower level of control measures are commonly cited

    Ensuring safety needs common sense

    http://www.dosh.gov.my/index.php/en/fatal-accident-case)

  • 10

    HSE Research Report 2003

  • 5 key elements to construction safety

    Managing the risks by applying the risk management approach and the general principles of prevention;

    Appointing the right people and organisations at the right time;

    Making sure everyone has the information, instruction, training and supervision they need to carry out their jobs in a way that secures safety and health;

    Duty holders cooperating and communicating with each other and coordinating their work; and

    Consulting workers and engaging with them to promote and develop effective measures to secure safety, health and welfare

  • 12

  • 13

    Fundamental to future construction legislation

    Catalyst for improving industry’s poor OSH performance

    Signify policy shift – self-regulated, cooperation, performance-based approach, duty holders

  • Occupational Fatalities 1999-2017

    146 15989 88 95 81 81 64 76

    11347

    88 109 73 84 89140 160

    187

    1004958

    858 822 846

    716 696754 730 746

    689726 755

    582 617 573

    668 688 650

    0

    200

    400

    600

    800

    1000

    1200

    Construction All Industries

    Source: DOSH, SOCSO, DoL, CIDB

    14

  • Occupational Fatality Rate 2011-2017

    9.62

    6.276.75

    7.26

    10.94

    12.78 12.9

    6.17

    4.64 4.624.21

    4.84 4.84 4.49

    0

    2

    4

    6

    8

    10

    12

    14

    2011 2012 2013 2014 2015 2016 2017

    Construction All IndustriesSource: DOSH

    15

  • Characteristics of the industry

    multifacettransient

    work sites

    fragmentedstage and process

    dependent

    work and people are constantly changing

    movement of people and

    plant

    dynamiccomplex

    multiple contractors/ employers

    labour intensive

    contractual arrangement

    movement of people and

    plant

    foreign workers

    complex product

    varying working culture

    16

  • Biggest challenges to OSH in construction

    Changing the working culture of stakeholders

    Primary responsibility lies with business who creates risk

    DOSH should influence & encourage - punitive actions only to deter

    17

  • Construction OSH Management Guidelines -

    Significance

    Managing OSH at planning and design stage is more effective

    Provide practical guidance to the client, designer and contractor

    OSH is shared responsibilities & team work to design hazards out

    18

  • 19

    Encourage all parties to take responsibility, by better planning, design & management

    Those who can influence OSH during project lifecycle are made responsible

    OSH should be treated as an essential, but normal part of the project

    Ability to influence safety1

    1 R. Szymberski, “Construction Project Safety Planning” TAPPI Journal, 1997.

  • Construction OSH Management Guidelines -

    Significance

    Across US, 42% of construction fatalities were related to design issues between the years 1990 and 20031

    A 1991 study done in Europe found that 60% of fatalities were the result of decisions made before the site work even began2

    63% of all fatalities and injuries could be attributed to design decisions of lack of planning3

    1 Behm, M., Linking construction fatalities to the design for construction concept (2005)2 European Foundation for the Imrpovement of Living and Working Conditions (1991)3 NSW WorkCover, CHAIR Safety in Design Tool, 2001

    20

  • Ability to influence safety1

    Ability to Influence on safety

    Costs

    Resources Deployed

    Conception Detailed Design Procurement Construction Start Up

    Low

    High

    Project Schedule

    Maximum

    return on

    efforts Maximum

    resources

    deployment

    1 R. Szymberski, “Construction Project Safety Planning” TAPPI Journal, 1997.21

  • Construction OSH Management Guidelines -

    Overview

    22

  • Construction OSH Management Guidelines -

    Fundamental

    the right information

    at the right time

    for the right people

    23

  • Individual competency1.• Those appointed must have the skills, knowledge, training and

    experience to carry out the work they will be employed

    Organisational capability2.• Appointed organisation must have the policies and systems in place to

    set acceptable safety and health standards which comply with the law, & resources and people to ensure the standards are delivered

    Right time3.• Appointing consultant or contractor at the right time, so that they have

    enough time to plan and manage for safety and health

    Appointing the right people and organisations at

    the right time

    24

  • Appointing the right people and organisations at

    the right time

    • In a proposed mix development, a client required five high-rise buildings to be designed and connected at the mid and top floors via curved sky bridges.

    .

    • The client initially appointed a building designer for the design, but subsequently realised that the building designer did not have the experience and knowledge to design the curved sky bridges.

    .

    • The client then appointed a bridge designer to design the curved sky bridges while the building designer designed the building.

    .

    25

  • Appointing the right people and organisations at

    the right time

    A client awarded a contract to a principal contractor for the demolition of an old shopping complex.

    While it was unknown during the tender stage, it was later discovered that the building that was to be demolished had a pre-stressed floors.

    With this new information, the principal contractor would need more time to engage and work with contractors who are pre-stressed specialists to help demolish this building.

    Hence, the client should provide the principal contractor with additional time and resources to resolve this situation.

    26

  • Appointing the right people and organisations at

    the right time

    All person should:

    Ensure persons who are appointed are competent

    Not accept in appointment unless they are competent

    Not instruct a worker to carry out/ manage design/ work unless he is competent

    27

  • Managing the risk by applying the risk

    management approach & general principles of

    preventionAvoidance of risks

    Eliminations of hazards or substitution for something

    less hazardous

    Reducing or limiting the duration of exposure to the

    hazard

    Isolation/ segregation

    Engineering controls

    Safe systems of work

    Training and information

    PPE

    Welfare

    Monitoring and supervision

    Hazard

    Prevention

    through

    Design

    28

  • Managing the risk by applying the risk

    management approach & general principles

    of prevention

    1. Avoid risks

    2. Evaluate risks which cannot be avoided

    3. Combat the risks at source

    4. Adapt the work to the individual

    5. Adapt to technical progress

    6. Replace dangerous by non-dangerous or less

    dangerous

    7. Develop a coherent overall prevention policy

    8. Give collective protective measures priority over

    individual protective measures

    9. Give appropriate instructions to employees

    29

  • Managing the risk by applying the risk

    management approach & general principles of

    prevention

    Avoid risk where possible;

    evaluate those risks that cannot be avoided; and

    put in place proportionate measures that control them at source.

    30

  • How designer can contribute to safety?

    Parapet vs. roof anchor1

    • The study compared the cost and risk of installing parapet system or roof anchor system to prevent falls from roof edge hazard.

    • The parapet system was found to be an expensive, but safer alternative compared with the roof anchor system.

    • The roof anchor system is the least expensive option, but the fall hazard is not eliminated when using a personal fall arrest system. A fall restraint system should be used to prevent the fall, but not feasible for all roofs.

    • The roof anchor system creates more risk during installation of temporary guardrails, and reduces productivity by 15%

    • Both the anchor and parapet options do not affect the quality of the product.

    • Study allows owners and designers to make an informed decision while choosing design solutions

    1 Rajendran & Gambatese (2013), Risk and financial impacts of prevention through designs solutions.31

  • Information

    Information

    Instruction

    Instruction

    Training

    Training

    Supervision

    Supervision

    Required level will depend on the risks involved in the

    project, complexity and scale of the project and the

    level of skills, knowledge, training and experience of

    the workforce

    Making sure everyone has the information,

    instruction, training and supervision

    32

  • Making sure everyone has the information,

    instruction, training and supervision

    PRE-CONSTRUCTION INFORMATION

    •Descr ipt ion of the project;

    •Client ’s considerat ions and management requirements;

    •Environmental restr ic t ions and exist ing on-site r isks;

    •Signif icant design and construct ion hazards; and etc.

    CONSTRUCTION PHASE PLAN

    •Descr ipt ion of the project;

    •Safety and health management of the work ;

    • Ident i f icat ion of signif icant s i te r isks.

    SAFETY AND HEALTH FILE

    •A br ief descr ipt ion of the work carr ied out;

    •Histor ic s i te data;

    •Any hazards that have not been el im inated;

    • Invest igat ion reports & records;

    •Statement of design phi losophy, key structural pr inciples; and etc.

    33

  • Information

    Information

    Instruction

    Instruction

    Training

    Training

    Supervision

    Supervision

    Workers are provided with information and instruction that include:

    a. suitable site induction;

    b. emergency procedures; and

    c. information on hazards, risks and control measures put in place.

    Making sure everyone has the information,

    instruction, training and supervision

    34

  • Information

    Information

    Instruction

    Instruction

    Training

    Training

    Supervision

    Supervision

    Establishing training needs to workers:

    a. assess the existing safety and health skills, knowledge, training

    and experience;

    b. compare these attributes with the range of skills, knowledge,

    training and experience they will need for the job; and

    c. identify any shortfall between (a) and (b). The difference between

    the two will be the ‘necessary training’.

    As a general rule, if the person being assessed demonstrates the

    required qualities, no further training should be needed.

    Making sure everyone has the information,

    instruction, training and supervision

    35

  • Information

    Information

    Instruction

    Instruction

    Training

    Training

    Supervision

    Supervision

    Appropriate supervision must be provided.

    a. Closer supervision if they are inexperienced/ starting new work

    b. Assess level of safety awareness, education, physical agility,

    literacy and attitude

    Let them know how to get supervisory help, even when supervisor is

    not present.

    BOWECS Reg. requires SSS and CSS, for several work activities

    designated person must be appointed to provide supervision

    Making sure everyone has the information,

    instruction, training and supervision

    36

  • • to ensure safety and health

    • to ensure everyone complies with the law

    Cooperating

    • to make sure everyone understands the risks and the measures to control those risk

    • between main coontractors of different sites

    Communicating

    • among sub-contractors who start at different stages

    • flow of information and instruction

    Coordinating

    Everyone cooperating and communicating with

    each other and coordinating their work

    37

  • Revie

    w m

    eeting b

    y c

    lients with designers and contractors, who may affect design,

    construction and maintenance at various key stages of the project

    during which indentified foreseeable design risk, if not eliminated, is reduced, and residual risks are recorded and communicated

    is typically conducted during pre-construction phase, but can be done during construction phase

    looks at design risks which begins on the drawing board, and considers how a building or structure can be constructed, maintained, cleaned and demolished safely

    Everyone cooperating and communicating with

    each other and coordinating their work

    38

  • Everyone cooperating and communicating with

    each other and coordinating their work

    During the review, one of the items discussed was the installation of glossy ceramic floor tiles

    which would get wet and slippery during washing or when water got spilled onto them, in the kitchen, cold rooms and toilet areas

    Installation of the tiles in these areas would possibly lead to cleaners or kitchen staff slipping or falling

    With this consideration, the team agreed that floor finishes at these areas should be of non-slip material to reduce the risk of slips and falls

    39

  • Co

    nsu

    lta

    tio

    n a

    nd

    e

    ng

    ag

    em

    en

    tIt is required under the law!

    Helping spot workplace risks and knowing what to do about them

    Making sure safety and health controls are appropriate

    Increasing level of commitment to working in a safe and healthy way

    Consulting workers and engaging with them to

    promote and develop effective measures

    40

  • MILESTONE FOR OSHCIM 2017 - 2020

    41

    Launched by HR Minister

    (28 Feb 2017)

    Promotional works

    (since Mar 2017)

    Embedded into CITP

    (Jun 2017)

    Embedded into Construction OSH

    Strategic Plan (Nov 2017)

    Development of Training

    Modules for Duty Holders (2018)

    Implementation of Training Modules

    (2019)

    Enactment of OSHCIM

    regulations and ICOP (2020)

    Enforcement of OSHCIM and

    ICOP (post 2020)

    • Training modules for client, designer, contractors

    • Case study

    • Industry/professional involvement

    • OSHCIM becomes mandatory

  • Good practices

  • 43

  • 44

  • Thank You

    Q & A