Construction on the Bing Kong Tong Building

For CCHE Quarterly Report1/1/2014 – 3/31/2014

Page 2: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

Prior to beginning of construction, abatement of hazardous materials took place.Karen Willig of Enercore Services is removing roof materials to test for asbestos.

Page 3: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

Abatement proceeds with removal of three layers of old roofing.

Page 4: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

Doors and windows are removed from the site to storage.Some went to Sacramento for restoration, these were returned wrapped in protective material. Others were placed directly into storage.

Page 5: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

On March 3rd, a gala start of construction event was held in front of the Tong Building.It began with a traditional Chinese lion dance.

Page 6: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

The celebration featured speakers who represented agencies key to the successful launching of Phase 1.The speaker at the podium is Don Nottoli, Sacramento District 5 County Supervisor. On the right is Mimi Morris, Executive Officer of the CCHE. On the left is Mark Bettencourt, Mayor of Isleton.

Page 7: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

A temporary center wall was constructed to help stabilize the building during construction. Tilt-up jacks used to erect concrete tilt-up buildings were employed to bring the structure back to vertical.

Page 8: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

Existing concrete was broken up and removed to make way for footings for restoration of the façade.

Page 9: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

The metal siding as well as the shiplap siding that was under it were removed.These will be replaced by 1/2 inch plywood sheets and new metal siding.

Page 10: Construction on the Bing Kong Tong Building For CCHE Quarterly Report 1/1/2014 – 3/31/2014

Forms are completed and ready for concrete to be poured