Construction of Water Bound Macdam Road

Embed Size (px)

Citation preview

  • 8/2/2019 Construction of Water Bound Macdam Road

    1/22

    BY

    CHAITHRA .N. KOWSHIK

    1

  • 8/2/2019 Construction of Water Bound Macdam Road

    2/22

    John Loudon McAdam

    Term Mcadam in the present day means, the

    pavement base course made of crushed or broken

    aggregate mechanically interlocked by rolling and thevoids filled with screening and binding material with

    the assistance of water.

    Base, subbase.

    The thickness of WBM ranges from 10cm to 7.5cm.

    Design details.

    2

  • 8/2/2019 Construction of Water Bound Macdam Road

    3/22

    When used as a surfacing course,Deterioted rapidly

    under adverse traffic conditions of traffic and

    weather.

    It is desirable to provide a bituminous surfacingcourse over WBM layer in order to prolong life.

    3

  • 8/2/2019 Construction of Water Bound Macdam Road

    4/22

    Types of course aggregates

    Hard varieties of crushed aggregate or broken stone.

    Soft aggregates like over burnt bricks metal or

    naturally occurring soft aggregates like kankar maybe used.

    Weaker varieties of aggregates gets crushed during

    rolling. Hence no need of filler materials.

    4

  • 8/2/2019 Construction of Water Bound Macdam Road

    5/22

    Property Sub-base Base course Surfacing course

    i) Los angelsabrasion valuemax value in %

    60 50 40

    ii) Aggregateimpact maxvalue in %

    50 40 30

    iii) Flakinessindex max valuein %

    15 15

    5

  • 8/2/2019 Construction of Water Bound Macdam Road

    6/22

    Hard,durable and of acceptable shape

    Free from flaky and elongated particles.

    IRC specifies the following physical requirements of

    course aggregates for WBM construction.

    6

  • 8/2/2019 Construction of Water Bound Macdam Road

    7/22

    Gradingno Size range, mm Sieve size, mm % passing thesieve, by weight1 90 to 40 100

    806340

    20

    10065-8525-600-15

    0-5

    2 63 to 40 80635040

    20

    10090-10030-700-15

    0-53 50 to 20 63

    50402010

    10095-10035-700-100-5

    7

  • 8/2/2019 Construction of Water Bound Macdam Road

    8/22

    Classification ofgrading Size ofscreenings inmmSieve size, mm % passing thesieve, by weight

    A 12.5 12.510.0

    4.750.15

    10090-100

    10-300-8

    B 10.0 10.04.750.15

    10085-10010-30

    8

  • 8/2/2019 Construction of Water Bound Macdam Road

    9/22

    Fine grained material

    Kankar nodules or lime stone

    Plasticity index value 4 to 9%

    WBM layers used as base course or sub base course,with bituminous surfacing.

    9

  • 8/2/2019 Construction of Water Bound Macdam Road

    10/2210

  • 8/2/2019 Construction of Water Bound Macdam Road

    11/22

    Apprroximate loose quantities of materials in m3 for 10cm compacted thickness of WBM sub base using

    course aggregate of grading no 1 per 10m2 area are

    a) Course aggregate size 90 to 40 mm = 1.21 to 1.43

    b) stone screening type A, 12.5 mm size= 0.40 to 0.44

    Or

    Crushable type screenings(moorum/gravel)=0.44 to 0.47

    c) Binding material for sub-base course = 0.88 to 0.10

    11

  • 8/2/2019 Construction of Water Bound Macdam Road

    12/22

    12

  • 8/2/2019 Construction of Water Bound Macdam Road

    13/22

    Preparation of foundation for receiving the WBMcourse.

    The foundation which is receiving either the sub grade or sub

    base course.

    Foundation layer is prepared to the required grade and camber

    and the dust either loose materials are cleaned.

    On existing road surfaces deprssions and pot holes are filled

    and the corrugations are removed.

    If the existing roads is bituminous surface means 50mm depthand 50 mm cut at 1.0 m interval and at 45 degrees to the

    centre of line of the carriage way before laying the course

    aggregate.

    13

  • 8/2/2019 Construction of Water Bound Macdam Road

    14/22

    Lateral confinement is to be provided before stating

    WBM construction.

    Construction shoulders in advance

    14

  • 8/2/2019 Construction of Water Bound Macdam Road

    15/22

    uniform spreading

    10 cm compacted thickness

    15

  • 8/2/2019 Construction of Water Bound Macdam Road

    16/22

    By using three wheeled power roller 6 to 10 tones or

    alternatively by an equivalent vibratory roller.

    Rolling started from the edges, the roller being run

    forward and backward until the edges are compacted.Then the run of the roller is shifted towards the centre

    of the line roads.

    16

  • 8/2/2019 Construction of Water Bound Macdam Road

    17/22

    17

  • 8/2/2019 Construction of Water Bound Macdam Road

    18/22

    18

    Used to fill up the voids in the compacted layer of the

    course aggregates.

    Sprinkling and groutingAfter screening the water is sprinkled over the

    surface, swept into the voids using hand brooms.

  • 8/2/2019 Construction of Water Bound Macdam Road

    19/22

    Binding material is applied at a applied at a uniform

    and slow rate at two or more successive thin layers.

    After each application of binding material surface is

    sprinkled with water and wet slurry swept withbroom to fill the voids.

    19

  • 8/2/2019 Construction of Water Bound Macdam Road

    20/22

    After final compaction, the WBM course is allowed

    to set over night.

    On the next day spots were filled with screenings or

    with the binding material, lightly sprinkled withwater and rolled if necessary

    In case of WBM base course, the layer is allowed to

    dry completely without permitting traffic.

    20

  • 8/2/2019 Construction of Water Bound Macdam Road

    21/22

    Surface evenness of longitudinal direction ischecked by 3.0m straight edge and the number of

    undulations exceeding 12mm of grading no 1.

    10 mm in the case of grade 2 and 3. Maximum number of undulations permitted in each

    case is 30.

    The cross profile is checked using camber template

    and the max variation from special profile should notexceed 12mm.