Construction of Segmental Concrete Bridge

  • Upload
    jaffna

  • View
    239

  • Download
    1

Embed Size (px)

Citation preview

  • 8/12/2019 Construction of Segmental Concrete Bridge

    1/72

    METHOD OF CONSTRUCTION OF

    SEGMENTAL CONCRETE BRIDGE

    By ,

    P P AMBEDKAR

  • 8/12/2019 Construction of Segmental Concrete Bridge

    2/72

    Objective Of Dissertation work

    Construction of segmental bridge involves use of different machineries

    and requires huge amount of skilled manpower. Hence the intention of

    dissertation is to study the Methods & techniques used in Construction

    of Segmental Bridge by Under Slung Methodwhich consist of

    following activities.

    1.Construction of Sub-structure

    2. Construction of super-structure

  • 8/12/2019 Construction of Segmental Concrete Bridge

    3/72

    Development of precast segmental bridge construction

    First segmental bridge

    Second segmental bridge

    Segmental bridges in India

  • 8/12/2019 Construction of Segmental Concrete Bridge

    4/72

    What is segmental construction

    Pier

    PC segments

    Prestressing cables

  • 8/12/2019 Construction of Segmental Concrete Bridge

    5/72

    Method of construction of segmental bridge

    1.Cast-in-Place Segmental Construction (Balance Cantilever method)

    Bridge across the Lahn River in Germany

  • 8/12/2019 Construction of Segmental Concrete Bridge

    6/72

    2. Precast Segmental Construction

    Flyover at Agriculture College Pune

  • 8/12/2019 Construction of Segmental Concrete Bridge

    7/72

    General design consideration

    Principal Dimension of Segment

    W = Top Slab width

    D = Construction depth

    B = Bottom slab width

    L = Segment length

  • 8/12/2019 Construction of Segmental Concrete Bridge

    8/72

  • 8/12/2019 Construction of Segmental Concrete Bridge

    9/72

    Construction of substructure

    Cast-in-situ Pile

    Detailed breakdown of activities is mentioned below

    1. Setting Out

    2. Removal of Overburden3. Driving Permanent Liner

    4. Boring / Chiseling

    5. Reinforcement Cage Lowering

    6. Concreting

  • 8/12/2019 Construction of Segmental Concrete Bridge

    10/72

    1. Setting Out

  • 8/12/2019 Construction of Segmental Concrete Bridge

    11/72

    2. Removal of overburden

    3. Driving permanent liner

    Tripod

    Driving cap

    Drivingmonkey

    Liner

  • 8/12/2019 Construction of Segmental Concrete Bridge

    12/72

    4. Boring/ Chiseling

    BAILER

    CHISEL

  • 8/12/2019 Construction of Segmental Concrete Bridge

    13/72

    BailerExcavated mud

    Removing of excavated material with help of bailer

  • 8/12/2019 Construction of Segmental Concrete Bridge

    14/72

    5. Reinforcement cage lowering

    6.Concreting

    Chute

    Funnel

    Tremie pipe

  • 8/12/2019 Construction of Segmental Concrete Bridge

    15/72

    Major Equipment Required

    1) F 35d/d winch - 4 no2) Pile driving tools & accessories - 4 set

    3) Tripod - 4 set

    4) Generator 70 KVA - 2 no

    5) Welding machine - 2 no

    6) Concreting equipments - 2 set

    7) Batching Plant - 1 no

  • 8/12/2019 Construction of Segmental Concrete Bridge

    16/72

    TIME CYCLE

    Sr.No. Activity Duration

    1 Road breaking/removal of top overburden/

    Identification of utility services.

    2 days

    2 Positioning tripod / winch 2 hours

    3 Survey & setting out 2 hours

    4 Permanent liner driving/ boring 20 hours

    5 Chiseling(6m @ 0.1m/hour) 60 hours

    6 Cage lowering 2 hours

    7 Tremie Pipe lowering/flushing 2 hours

    8 Concreting 3 hours9 Removal of tripod/winch 2 hours

    Total time for pilling 93 hours

    There fore total time for one pile @ 20hours per day

    working

    4.5 days

  • 8/12/2019 Construction of Segmental Concrete Bridge

    17/72

    Construction Of Pile Cap

    Detailed breakdown of activities is mentioned below

    1. Clear area for excavation and marking

    2. Exaction up to pile cap bottom level

    i. Excavation in soft soil

    ii. Chiseling in hard strata

    3. Simultaneously chipping of pile

    4. Preparation of bed with PCC

    5. Cutting and bending and preparation of reinforcement

    cage

    6. Shuttering for pile cap

    7. Concreting

  • 8/12/2019 Construction of Segmental Concrete Bridge

    18/72

    1. Clear area for excavation and marking

    2. Exaction up to pile cap bottom level

    i. Excavation in soft soilii. Chiseling in hard strata

    3. Chipping of pile

    Bottom of

    Pile cap Pile chipping by jack

    hammer

  • 8/12/2019 Construction of Segmental Concrete Bridge

    19/72

    4. Preparation of bed with PCC

    Bed preparation

    for pile cap by

    laying PCC

  • 8/12/2019 Construction of Segmental Concrete Bridge

    20/72

    5. Cutting and bending and preparation of reinforcement

    cage

    Pile reinforcement

    bar

    Tying ofreinforcement

  • 8/12/2019 Construction of Segmental Concrete Bridge

    21/72

    6. Shuttering

    7. Concreting of pile cap

    Shuttering

    Haizen cloth for

    curing

  • 8/12/2019 Construction of Segmental Concrete Bridge

    22/72

    MAJOR EQUIPMENTS REQUIRED

    1. JCB Excavator 1 No.

    2. Dumper 1 No.

    3. Breaker (Jack hammer) 2 Nos.

    4. Bar bending and cutting machine 1 No.5. Concrete batching plant 1 No.

    6. Transit Mixer 2 Nos.

    7. Needle vibrators (60 mm) 2 Nos.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    23/72

    TIME CYCLESr.No. Activity Duration

    1 Waiting period for curing of pile 7 Days

    2 Clearing area, survey and marking for excavation 2 Hours

    3 Excavation in soft soil 12 Hours

    4 Chiseling in hard rock 2 Days

    5 Cutting and removing liner 4 Hours

    6 Chipping piles up to pile cap bottom level PCB) 4 Days

    7 Preparation of bed with PCC as leveling course 8 Hours

    8 Reinforcement cutting, bending and fabricating cage 1 Day

    9 Placing and fixing shuttering 3 Hours

    10 Concreting 1 Hour

    Total time = 8.5 days

  • 8/12/2019 Construction of Segmental Concrete Bridge

    24/72

    Construction of Pier

    Job breakdown1. Cutting, and bending of reinforcement

    2. Preparation of reinforcement cage

    3. Casting Pier starter

    4. Erection of staging and simultaneously fixing

    shutters

    5. Concreting of pier

    6. De-shuttering and dismantling staging

    7. Curing

  • 8/12/2019 Construction of Segmental Concrete Bridge

    25/72

    1. Cutting, and bending of reinforcement & preparation of

    reinforcement cage

    2.CastingPierstarter3. Erection of staging and simultaneously fixing shutters

    Pier shutter

    Staging for supporting pier shutter

    & providing working platform at

    top for concreting

  • 8/12/2019 Construction of Segmental Concrete Bridge

    26/72

    4. Concreting of pier

    5. Curing

    MAJOR EQUIPMENTS REQUIRED

    1. HM 101 Crane -1 No

    2. Bar bending and cutting machine-1 No.

    3. Concrete batching plant -1 No.

    4. Transit Mixer - 2 Nos.5. Concrete Pump -1 No.

    6. D.G. Set -1 No.

    7. Compressor - 2 Nos.

    8. Needle vibrators (60 mm) - 2 Nos.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    27/72

    TIME CYCLE

    Sr. no. Activity Duration

    1 Cutting and Bending Reinforcement 2 Days

    2 Tying and Cage Preparation 1 Day

    3 Casting Starter and Curing 2 Hrs.

    4 Staging and Simultaneously Shuttering 1 Day

    5 Concreting 3 Hrs.

    6 Waiting till achieving strength for deshuttering 1 Day

    7 Deshuttering 12 Hrs.

    8 Curing 28 Days

    Total time required excluding curing = 3 days

  • 8/12/2019 Construction of Segmental Concrete Bridge

    28/72

    CONSTRUCTION OF APPROCHES

    Construction of approach involve two major activity that are

    as follows:

    i) Construction of Abutment wall.

    ii) Construction of Wing wall (Retaining wall)

  • 8/12/2019 Construction of Segmental Concrete Bridge

    29/72

    Types of abutment:

    Masonry abutments:

    RCC abutments:

  • 8/12/2019 Construction of Segmental Concrete Bridge

    30/72

    R.C.C Abutments

    In this case abutment wall is directly rest over raft /pile foundation.

    Whole abutment wall made of rich mix concrete. Abutment wall

    construction involves following activity:

    1. Cutting, and bending of reinforcement

    2. Preparation of reinforcement cage

    3. Casting abutment starter

    4. Erection of staging and simultaneously fixing

    shutters

    5. Concreting of abutment.

    6. De-shuttering and dismantling staging

    7. Curing

  • 8/12/2019 Construction of Segmental Concrete Bridge

    31/72

    Staging

    arrangement

    Shuttering

    RCC Abutment

  • 8/12/2019 Construction of Segmental Concrete Bridge

    32/72

    The wings walls are of masonry or RCC masonry, now days wings wall are constructed

    with new technique that is Geosynthetic Soil Retaini ng wallin which precast RCC

    panel is used. The advantage of this construction system is given below.

    1. It requires very limited construction space compared to the conventional wall

    systems.

    2. The completed structure occupies less space compared to the conventional wallsystems.

    3. By using a facing of high rigidity, the stability of the wall system is increased while the

    deformation is minimized.

    4. The geosynthetic layers are closely spaced so that a wide range of backfill can be

    used without affecting performance.

    Wing wall

  • 8/12/2019 Construction of Segmental Concrete Bridge

    33/72

    Component of part of GSR Wall

    1.Concrete leveling Pad:

    2.Precast concrete facing panels

    3.Joint material

    4.Geogrids

    5.Backfill

  • 8/12/2019 Construction of Segmental Concrete Bridge

    34/72

    Construction of Superstructure

    Construction of Superstructure of segmental bridge involves two

    major activities that are as follows:

    1) Segment Casting

    2) Segment Erection

    Different method of segment casting:

    1)Long line casting

    2)Short line casting

  • 8/12/2019 Construction of Segmental Concrete Bridge

    35/72

    Long line casting

  • 8/12/2019 Construction of Segmental Concrete Bridge

    36/72

    Short line casting

  • 8/12/2019 Construction of Segmental Concrete Bridge

    37/72

    Segment casting involves following activities

    1) Base mould preparation

    2) Surveying and marking

    3)Reinforcement cage leveling

    4)Lowering and positioning stopend

    5)Placing and fixing inner formwork

    6)Concreting and finishing

    7)Deshuttering of inner formwork and stopends

    8)The segment used for match casting is then placed in the stacking yard and the newlycasted segment is used for next match casting.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    38/72

    1)Pre-cast Bed Survey and Setting out of moulds as per

    the co-ordinates.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    39/72

    2)Changing/re-fixing of linermaterial where required and

    cleaning of beds.

    RUBBER LINER

    3)Surveying and marking

    4)Reinforcement cage lowering:

    LIFTING FRAME

    REINFORCEMENT CAGE

    EOTCRANE

  • 8/12/2019 Construction of Segmental Concrete Bridge

    40/72

    5)Lowering and positioning stopend:

    Turn buckels

    False work

    Stopend

    REINFORCEMENT CAGE

  • 8/12/2019 Construction of Segmental Concrete Bridge

    41/72

    6. Placing and fixing inner-

    formwork:

    Inner formwork

    7.Concreting and finishing:

  • 8/12/2019 Construction of Segmental Concrete Bridge

    42/72

    8.Deshuttering INF& Stopend:

    9. Lifting and stacking of segments:

    MAJOR EQUIPMENTS REQUIRED FOR SEGMENT

    CASTING

    1) EOT 120T Capacity - 1 No.

    2) Welding Machine - 2 No.

    3) Gas-cutting Equipment - 2 No.

    3) Concreting Equipments - 2 Sets

    4) Batching Plant - 1 No.

    5) Transit Mixer - 2 No.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    43/72

    TIME CYCLESr. No. Activity Description Time

    Required

    in Hrs.

    1 Base mold cleaning, rectification of rubber liner and applying

    POP

    6

    2 Survey and marking 1

    3 Lowering reinforcement cage 1/2

    4 Lowering and aligning stopend with jacks and knuckle bolts 1

    5 Placing and fixing inner-formwork 8

    6 Concerting and finishing 3

    7 Curing till deshuttering stopend 248 Deshuttring stopend 2

    9 Curing till deshuttering inner-formwork 46

    10 Lifting and stacking segment 1

    Total time= 92 Hrs

  • 8/12/2019 Construction of Segmental Concrete Bridge

    44/72

    Segment Erection

    Probably the most significant classification of segmental bridges is bymethod of construction. Although construction methods may be varied as

    ingenuity of the designers and the contractor they fall into two basic

    categories:

    1) Cast-in-Place segmental construction. (Balance Cantilever method)

    2) Precast segmental construction.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    45/72

  • 8/12/2019 Construction of Segmental Concrete Bridge

    46/72

    Precast segmental construction

    1)Segment erection by Crane

    2) Segment erection byWinch and Beam

  • 8/12/2019 Construction of Segmental Concrete Bridge

    47/72

    3)Launching Gantry(Over head method)

    4)Segment erection by Under-slung

    method

  • 8/12/2019 Construction of Segmental Concrete Bridge

    48/72

    Segment erection by Under Slung Method

    Segment erection involves following activities

    1. Survey and Barricading

    2. Erection of EOT

    3. Fabrication and erection of staging

    4. Erect sliding trolley with jack arrangement5. Launch precast segments

    6. Temporary pre stressing of segments

    7.Permanent pre stressing

  • 8/12/2019 Construction of Segmental Concrete Bridge

    49/72

    1. Survey and Barricading

    2. Erection of EOT

    Rail track alignment

    EOT crane of 125 tone

    capacity

  • 8/12/2019 Construction of Segmental Concrete Bridge

    50/72

    3. Fabrication and Erection of Staging

    Main girder

    Seating girder

    Concrete block

    Cribs

    Bracing

  • 8/12/2019 Construction of Segmental Concrete Bridge

    51/72

    4. Erect Sliding Trolley with Jack Arrangement

    Screw jacks arrangement

    with pot bearing

    Main girder

    Tie box

  • 8/12/2019 Construction of Segmental Concrete Bridge

    52/72

  • 8/12/2019 Construction of Segmental Concrete Bridge

    53/72

    Inside temporary prestressing

  • 8/12/2019 Construction of Segmental Concrete Bridge

    54/72

    8. Bearing Installation

  • 8/12/2019 Construction of Segmental Concrete Bridge

    55/72

  • 8/12/2019 Construction of Segmental Concrete Bridge

    56/72

    C S d

  • 8/12/2019 Construction of Segmental Concrete Bridge

    57/72

    Case Study

    NAME OF PROJECT:

    PUNE FLYOVER ATUNIVERSITY CIRCLE

    & AGRICULTURE COLLAGE.

    SITE ADDRESS:

    GANESHKHIND ROAD,

    UNIVERSITY CIRCLE,

    PUNE 411 007

    NAME OF CONTRACTOR:

    AFCONS INFRASTRUCTURE LIMITED

    NAME EMPLOYER:

    MAHARASTRA STATE ROAD

    DEVELOPMENT CORPORATION

    NAME CONSULTANT:

    DAR CONSULTANTS (U.K) LTD.

    in association with

    DAR CONSULTANTS (I) PVT. LTD

  • 8/12/2019 Construction of Segmental Concrete Bridge

    58/72

  • 8/12/2019 Construction of Segmental Concrete Bridge

    59/72

    UNIVERSITY CIRCLE JUNCTION:

    GENERAL FEATURES OF UNIVERSITY CIRCLE FLYOVER

    1) Length = 700 M between abutments

    2) Carriageway = Single three lane carriageway

    3) Foundation = Bored cast-in situ piles resting on rock

    4) Substructure = RCC Piers

    5) Superstructure = Segmental, Deck width 12 M

  • 8/12/2019 Construction of Segmental Concrete Bridge

    60/72

    AGRICULTURE COLLEGE JUNCTION

    GENERAL FEATURES OF AGRICULTURE COLLEGE FLYOVER

    1) Length = 210 M between abutments

    2) Carriageway = Dual two lane carriageway

    3) Foundation = Bored cast-in situ piles resting on rock

    4) Substructure = RCC Piers

    5) Superstructure = Segmental, Deck width 16.4 M

  • 8/12/2019 Construction of Segmental Concrete Bridge

    61/72

    The pre-casting Yard includes the following:

    Casting Bay : For casting deck segments.

    Curing Yard : For curing deck segments.

    Stacking Yard : For stacking deck segments.

    Reinforcement Yard : For fabrication of reinforcement of all structural elements

    like pile, pile cap, pier, precast segment, etc.

    Casting, Curing & : For casting, curing & stacking of Parapet, Retaining

    Stacking Bay wall & Kerbs.

    Fabrication workshop: For fabrication of structural steel for shuttering,

    supportive elements & temporary works.

    Mechanical workshop : For fabrication of tie rod

    CLASSIFICATION OF SEGMENTS

  • 8/12/2019 Construction of Segmental Concrete Bridge

    62/72

    No TypeSegment

    widthLocation & Function

    1

    End Diaphragm (ED) 1.45 ED rest on Abutment. It also has a

    downstand that enables it to sit onbearings. It has a wall ... It houses

    coupler cones for pre-stressing

    cables which are locked here.

    2Adjacent to End Diaphragm

    (EDA)

    2.095It is located adjacent to ED segment.

    3 Internal Diaphragm (ID)

    2

    ID segment rest on all the piers except

    expansion piers.

    4Standard Segment(SS) 2.725 There are 3 nos. SS in the middle of

    every span.

    5

    Coupling segment stressing

    end (CSS)

    2.917 CSS segment last segment of

    intermediate span which has

    stressing

    6Coupling segment coupling

    end (CSC)

    2.917 CSC Segment is starting segment of

    next span

  • 8/12/2019 Construction of Segmental Concrete Bridge

    63/72

    TYPICAL SECTION THROUGH DECK SEGMENT (CS) 16.4M WIDE

  • 8/12/2019 Construction of Segmental Concrete Bridge

    64/72

    SEGMENT ERECTIONThere are 3 types of spans to be erected i.e.:

    Type A-Beginning span of each bridge unit,

    Type B-Internal spans,

    Type C- End of each unit.

    Type A has 13 segments to be erected with an End diaphragm at the start of

    the span. And a CSS segment at the end of the span.

    Type B Span start with CSC segment & end with CSS segment.

    Type C Span start with CSC segment & end with ED segment.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    65/72

  • 8/12/2019 Construction of Segmental Concrete Bridge

    66/72

    For erection of 16.4 m wide segment involves following activities

    1. Survey and Barricading

    2. Erection of EOT

    3. Fabrication and erection of staging

    4. Erect sliding trolley with jack arrangement

    5. Launch precast segments

    6. Temporary pre stressing of segments

    7. Permanent pre stressing

    MAJOR EQUIPMENTS DEPLOYED

  • 8/12/2019 Construction of Segmental Concrete Bridge

    67/72

    MAJOR EQUIPMENTS DEPLOYED

    1) EOT 60T Capacity - 1 No.

    2) EOT 120 T capacity - 1 No.

    3) Service crane PH 320 - 2 No

    4) JCB Excavator -

    2 Nos.

    5) Trailer of 40 T capacity - 3 No.

    6) Trailer of 100 T capacity - 1 No.

    Labour required for segment erection including staging& gluing :

    Welder = 01

    Grinder = 01

    Gas cutter = 01

    Skilled labour = 17

    Unskilled labour = 10

    TOTAL NO. = 30

  • 8/12/2019 Construction of Segmental Concrete Bridge

    68/72

  • 8/12/2019 Construction of Segmental Concrete Bridge

    69/72

    Following were the main reasons to delay in the completion of project

    Land acquisition problem

    Improper matching of segment

    Delay in decision making

    Labour strike

    Delay in approval of drawings from consultant

    Delay in diversion of utilities

  • 8/12/2019 Construction of Segmental Concrete Bridge

    70/72

    CONCLUSION

    After studying detail procedure segmental construction that

    segmental bridges posses following advantages

    Rapid erection of superstructure.

    High quality & high strength of concrete can be achieved.

    Whenever we need to allow traffic underneath even during

    construction.

    The structural geometry may be adopted to any horizontal or vertical

    curvature or any roadway super-elevation.

    Concrete shrinkage & creep substantially reduced.

    Segmental construction relatively insensitive to weather condition.

    Enhanced durability of bridge.

    Segmental bridge reveals following disadvantages

  • 8/12/2019 Construction of Segmental Concrete Bridge

    71/72

    Segmental bridge reveals following disadvantages

    Need for higher level of technology in design

    Necessity for a high degree of dimensional control.

    The possible solution to the problems discussed in the case

    study can be enlisted as follows:

    Perfect matching of segment at site can be achieved by considering vertical &

    horizontal alignment of bridge profile at the time of segment casting.

    Whenever the segments are not matched properly considerable time is lost in

    chipping out the segment faces. Hence the segment casting should be done

    accurately in accordance with drawings.

  • 8/12/2019 Construction of Segmental Concrete Bridge

    72/72

    Thank You