Upload
mehdi-mir
View
231
Download
0
Embed Size (px)
Citation preview
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 1/53
1
Construction of Earth Dam
P. Ghosh
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 2/53
2
Phases of Construction
• Evaluation of plans, specifications, basic
requirements, and features of the site
• Planning and scheduling of the job
• Making the site ready
• Building the structure
• Clean up
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 3/53
3
• The first phase of evaluation consists of a detailedstudy of the requirements of design and of the site
itself, including topography, weather and river flow
and of the problems of labour, materials, and
equipment supply
• The second phase is most important if the job is to
be done economically. The plant, labour, and
materials for each stage of construction process
must be available at the correct time; if they are too
early there is unnecessary down time, while if toolate the remaining schedule suffers
Phases of Construction
Contd..
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 4/53
4
Phases of Construction
• Site readying includes developing access roads and
the provision of the fixed construction plants such
as ware houses, crushers, concrete mixers, offices
and housing for the staff and workers
• The major part of the time and money is spent on
the building phase
Contd..
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 5/53
5
Site Preparartion
Clearing:
• It is the removal of tress, boulders, fences,
buildings, and other structures from the area. This
is for the borrowpits, and the area to be occupied by
the dam
Grubbing:
• It is the removal of roots, stumps and organic
matter. Scattered and isolated roots can be left, but
stumps and matted roots should be removed.
Grubbing is done only in the actual borrow pits and
within the outline of embankments
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 6/53
Stripping:
• It is the removal of all topsoil, organic materials and
soft pockets which are unsuitable for the borrow inthe borrow pit areas or unsuitable for supporting
structure within the embankment outlines
Scaling:
• It is the removal of loose materials, weathered rock
and weak materials from the abutments. It also
includes the shaping of abutments to eliminate
overhangs and provide uniform slopes 6
Contd..
Site Preparation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 7/53
Diversion:
• Diversion is the re-routing of the river around the
construction area. This is done with a temporary dam or
cofferdam which walls off and protects the area, and a
diversion channel or tunnel which carries the watearound the site
Cofferdam fills:
• Many types of cofferdams are used depending on the
materials available and the river currents which flow
past it 7
Diversion and Cofferdamming
Di i d C ff d i
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 8/53
Diversion and Cofferdamming
• The simplest is a fill of rock and earth dumped in
place to form a crude dam, Fig. 1
• The heart of this is a triangular mound of the
coarsest material obtainable such as boulders and
large broken rock
8
Contd..
Fig. 1
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 9/53
• This is dumped, starting from the abutments on both
sides and working toward the centre of the cofferdam
• If it is constructed in a flowing stream, the rocks
placed on the bottom must be coarse enough to resist
being carried away by the water velocity
• As the centre of the stream is approached, larger rock
must be used since the velocity increases as the flow
is restricted
• The final closure is effected with very large rocks o
even pre-cast blocks of concrete which are quickly
dumped in the gap9
Contd..
Diversion and Cofferdamming
Di i d C ff d i
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 10/53
Combined coffer-dam:
• In some dams it is possible to utilize a rock toe of the
permanent embankment as the rock core of the coffer-
dam and thus reduce the overall cost of the cofferdam
(Fig. 2)
• Alternatively the rock toe can be made wider than
normal to compensate for the poor foundation andplaced directly on the un stripped ground
10
Contd..
Diversion and Cofferdamming
Fig. 2
Di i d C ff d i
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 11/53
Combined coffer-dam:
• In dams with an upstream core it is frequently possibleto use the upstream part of the dam itself as a second
stage cofferdam to protect the remaining foundation
area• A small cofferdam, quickly built after the flood season
is over, permits construction of the upstream part of
the dam
• This becomes the cofferdam for the next flood season
(Fig. 3)
11
Contd..
Diversion and Cofferdamming
Fig. 3
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 12/53
Diversion and Cofferdamming
• When the currents are swift and no coarse rock orboulders are available, cellular cofferdams of stee
sheet piling are used, Fig. 4
• Several patterns of cells are used depending on the
height. The circular cells are the most stable since
each cell is structurally independent of its neighbor
Contd..
Fig. 4
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 13/53
Cut-off trench:
• The soil-filled trench is most widely used form of cut-
off for earth dams on an earth foundation. It is also
used for the earth dams on rock where the upper
surface of the rock is weathered or cracked
• The construction procedure is employed is governed
by the nature of the foundation material, and in
particular by the ground water and the stable
excavation slope 13
Foundation Preparation
F d ti P ti
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 14/53
• For greatest economy an open excavation is used.
This is dewatered by pumping from sumps when the
foundation is made up of rock, clayey soils, or gravels
• The sumps, which are merely collecting pits, shouldbe dug just outside the trench line so that their
pumping will not interfere with the surface
preparation for the trench
• In silty soils and sands, sump pumping often creates
an unstable condition including seepage erosion, sandboils, and quick sand. To avoid this water table must
be lowered ahead of the excavation work so that
there is never an upward flow of water in to the
excavation14
Contd..
Foundation Preparation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 15/53
• This is best done by well points, Fig. 5, if the water table is to be lowered by 50ft or less
15
Contd..
Foundation Preparation
Fig. 5
F d ti P ti
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 16/53
Impervious contact:
• The preparation of the contact between the cut-off (or
core when no cut-off is used) and the impervious
foundation requires careful hand work
• All loose materials and porous materials are removed.
Pits and crevices are cleaned out as deep as possible
• Thin horns and over hanging projections are removed
because they will interface with compaction and may
break off under the action of heavy equipment 16
Contd..
Foundation Preparation
F d ti P ti
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 17/53
• If foundation is rock, it can be cleaned cheaply by a
combination of water-jetting and compressed air
• The small pits and cracks in rock must be filled with an
impervious material that resists washing so that a zone
of seepage will not develop along the contact
• Cement-sand mortar is best because it penetrates the
cracks easily and then sets up as a solid
• A clay paste can be used for the same purpose in the
smallest cracks 17
Contd..
Foundation Preparation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 18/53
Shell foundation:
• The foundation preparation beneath the shell is less
critical. Seepage is not a factor and no crack sealing
or pit filling is required
• All soft zones are removed and the embankment
placed in layers on the virgin surface
• Scarifying and rolling the foundation is sometimes
advocated, but it is an unnecessary expense whencontact is not a problem
18
Contd..
Foundation Preparation
F d ti P ti
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 19/53
• If the foundation is of a loose, cohesionless soil with
a relative density of less than 70%, densification is
desirable
• Certainly a blanket of dense material 25 to 30 ft
thick is desirable to minimize the effects of any
structural readjustments in a loose foundation
• Three methods have been used to densify existing
deposits of cohesion less soil: a) pile driving,
b) explosives, and c) vibrofloatation19
Contd..
Foundation Preparation
G ti
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 20/53
Grouting
• Grout is a fluid mixture of Portland cement, water and
various admixtures such as sand, clay and rock dust,
which hardens to form a semi-solid or solid mass that
is impervious and which has some degree of rigidity
and strength
• Clay grout is a viscous fluid mixture of clay and water,
plus sand and other filters, which tends to stiffen
slightly by the squeezing of water from the mix 20
G ti
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 21/53
• Chemical grouts are fluid mixtures of various
chemicals which solidify by chemical reaction after
their injection
• The process of injecting any of these materials in to
the ground is grouting
• Grouting is a complex process, an art in which the
experience and judgment of the operator is the most
important guide21
Contd..
Grouting
Grouting
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 22/53
Objectives:
a) Make the formation impervious
b) Improve its structural capabilities (strength,
compressibility)
• This is done by filling cracks, fissures, cavities and
even the voids between the grains with the grouting
material
• In most earth or rock fill dams the stress
concentrations are not sufficiently severe to require
structural improvement; in masonry dams, however this is a major factor
22
Contd..
Grouting
G ti
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 23/53
Consolidation grouting:
• Consolidation grouting is the injection of a larger area
of the foundation to shallow depth to reduce its
compressibility, increase its strength, and particularly
to minimize seepage in slightly fractured or
weathered zone which is so often present in the
uppermost few feet of rock
• In earth dams it is limited to the contact zone with
the core or cut-off or to a limited portion of the
contact if it is wide23
Contd..
Grouting
Grouting
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 24/53
Curtain grouting:
• It is the establishment of a cut-off wall by grouting
• The depth of the curtain is determined from a
consideration of the seepage characteristics of the
foundation
• When the fissure pattern is so erratic that no rationa
analysis is possible the depth in rock is oftenestablished by an empirical procedure such as:
Depth = 0.5∆h to 1.5∆h
or 0.33∆h + c
where, ∆h is the head on the foundation, c is a constant
equal to 25 ft in sound rock and 75 ft in fissured rock24
Contd..
Grouting
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 25/53
• Excavation of the embankment materials, processing
them, and hauling them to the job are important from
considerations of both cost and the quality of the
materials delivered into the embankment
Excavation method:
• The selection of excavation procedure depends on
the type of available materials and on the
configuration of borrow pits
• Five principal methods for handling the materials
hand, power shovel, dragline, scraper and elevatinggrader
25
Borrow Pit Excavation
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 26/53
Hand excavation
• It has been used throughout the history and is still
important in areas where labour is cheap
• Most types of soils can be excavated; but coarse
gravels, boulders, and even soft rock cannot be
handled so efficiently
26
Contd..
Borrow Pit Excavation
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 27/53
Power shovel
• It is well adapted to a wide variety of materials from
soft soil to boulders and layered rock
• It is also suitable for hard rock that has been
shattered by explosives
• Stratified materials are easily mixed since the shovel
makes a vertical cut or slice
Borrow Pit Excavation
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 28/53
Drag line
• It is adapted to most soils except soft sticky clays and
very hard or cemented materials
• Stratified materials can be mixed or they can be
segregated, depending on the mode of operation
Borrow Pit Excavation
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 29/53
Scraper
• It is most efficient in slightly clayey sands, silts, non-sticky clays and it can even function in some soft
rocks
• Hard materials such as cemented soils and layeredrock can frequently be broken up with a rooter (a giant
hooked plough drawn by a tractor) and then excavated
with the scraper
29
Contd..
Borrow Pit Excavation
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 30/53
Elevated grader
• The working of an elevated grader is similar to that of a scraper so far as the handling of various types of
materials is concerned
• It has, however, some tendency to provide more
pulverizing than the scraper
• A long level borrow pit is required for best operation
Contd..
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 31/53
Moisture control:
• Moisture control is necessary in the borrow pit to
permit efficient operation of the excavation
equipment and to condition the soil for its future
compaction
• Drainage is necessary for pits below ground water.
This should be done far enough in advance of the
construction so that the soil is not water logged
• Otherwise the soil must be stockpiled on higher
ground to drain and then re-excavated for use in the
embankment31
Contd..
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 32/53
• All pits should be so excavated that the surface
water drains away from them and does not collect in
them
Material control:
• The operation of the borrow pit must be carefully
controlled for better quality
• A testing laboratory is set up at the borrow pit where
the moisture content, gradation, and even plasticity
can be determined in minimum time32
Contd..
Borrow Pit Excavation
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 33/53
Modification:
• In some cases modification or processing is necessary
before the materials can be used
• The materials necessary for filters rarely occur in the
correct gradation
• Even though natural sand-gravel mixtures are found
which approximate the requirements, they are variable
and should be screened to provide more exact control33
Contd..
Fill Placement
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 34/53
• The placement of materials in the fill depends on
the method of hauling, the processing which will be
done in-place before compaction, and the size of the
area to be filled
• The materials hauled by hand are dumped in small
piles to form a reasonably level surface
• The materials hauled by trucks and wagons are
dumped in uniformly spaced piles
• Certain side dump wagons can also form long
narrow piles or wind-rows34
Fill Placement
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 35/53
In-place processing:
• All objectionable materials are removed during and
immediately after the spreading operation
• These include roots, clumps of grass and the other
organic matter, and large stones which would
interfere with compaction
• In some cases it is necessary to mix two materials.
An examples in core construction when a limited
amount of highly impervious clay can reduce the
permeability of more abundant but less water-tight
soils35
Contd..
Fill Placement
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 36/53
• If the materials are hauled by trucks or wagons they
are placed in alternate piles or in parallel adjacent
wind-rows
Moisture control:
• moisture control is necessary when placing the soil,
even though it may leave the borrow pit at the proper
water content
• The soil can be dried by spreading it in layers and
turning and aerating it in the sunshine36
Contd..
Fill Placement
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 37/53
• The pulverizing and mixing machines can help the
drying because they beat air through the soil during
the process
• Moisture addition is done by sprinkling water
followed by mixing with ploughs or the pulverizing
mixers
• If possible, moisture addition should be done several
hours before compaction, so that the soil will have
time for absorbing water 37
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 38/53
• Compaction is the process by which the required
density is obtained in an embankment
• Two different phenomena are involved in this process:
1.Movement of the particles into new positions
2.Distortion of the particles, particularly the flaky ones
with their adsorbed layers, so that the voids between
them become smaller 38
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 39/53
Compaction methods:
• The oldest method of soil compaction is tamping. This
provides pressure at the moment of impact and some
vibration. Because of this dual action, tamping can be
used on all types of soil, but best in clayey sands,
sandy clays and similar soils of low (but notnegligible) cohesion
• The hard tamper , a block of iron, stone, or woodweighing 6 to 10 lb., is the simplest. The compaction
effort is small and so the soil must be compacted in
thin layers, from 1 to 2 in. 39
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 40/53
• Pneumatic tampers , with the tamping part weighing
about 6lb., are faster than the hand tampers but are
only slightly more effective in producing high
compaction
• Jumping tampers weighing from 160 to 500lb.,
powered by gasoline, are more effective. These jumpfrom 6 to 18 in. in to the air and then drop back by
gravity to produce substantial impact pressure
• They are capable of compacting soils in layers of 6 to
12 in. thickness to densities of 100% of standard
proctor maximum at optimum moisture 40
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 41/53
• The sheep foot roller consists of a steel drum with
projecting lugs or feet. It applies high static pressures
over a relatively small area: 1 to 9 sq. in. or an
equivalent diameter of 3 to 3.5 in.
• Rollers with foot pressures as low as 150 psi and as
high as 1,200 psi are available
• Because of high pressure and the small width of
application the sheep foot roller is the best adapted to
the highly cohesive soils like clays 41
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 42/53
• Low plasticity soils can be compacted with the sheep
foot rollers but lower pressures must be employed to
avoid a bearing capacity failure
• A modified sheep foot roller with wider feet, 6 to 8 in.
across, is far more effective in silty soils
42
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 43/53
• The heavy pneumatic-tired roller consists of four large
pneumatic tires, mounted side by side on a
suspension system which permits them to move up
and down independently
• These support a ballast box which exerts loads of 50
to 200 tons depending on the types of tires, the box
sizes and the earth or rock ballast
• The pneumatic tired roller develops pressures of 80 to
150 psi over an area of 250 to 700 sq.in. or equivalent
diameters of 18 to 30 in 43
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 44/53
• It is very well adapted to cohesive soils of low
plasticity, such as clayey sands and silts, and to
cohesion less soils such as sands and gravels where
the bearing capacity depends on width of the area of
application
44
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 45/53
• Various forms of vibrating rollers are available. One is
a two-wheeled rubber-tired roller with a gasoline-
powered vibrator on the axis
• Another is smooth steel drum , ballasted with water,
and with a vibrating unit in the supporting frame
• Both the types are effective in compacting cohesion
less sands and gravels
• Layers from 12 to 18 in, thick can be compacted to
100% of the standard proctor maximum, often in one or
two passes of the machine 45
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 46/53
46
Contd..
• Ordinary pavement rollers with steel drum wheels can
be used for soil compaction. They exert a moderate
degree of pressure across a wide drum
• They can be used in most soils provided the layersare very thin. Their main disadvantages are
¾ The tendency of the drum to bridge over small soft
pockets
¾ The formation of a ver smooth surface
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 47/53
• Flooding of sands and puddling of clays are
sometimes mentioned as compaction methods. While
these are better than no compaction at all, the degree
of compaction produced seldom exceeds 85% of the
standard proctor maximum
47
Contd..
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 48/53
Fill operation:
• The selection of the proper methods of compaction,
the layer thickness, pressure of the equipment, and
the best moisture is the joint responsibility of the
designer and the constructor
• The most important factor is the pressure distribution
in the layer being compacted. Based on Boussinesq
equation, the pressure beneath the compaction
device decreases with depth48
A hi h li d ll d
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 49/53
• A high pressure applied over a small area decreases
rapidly with increasing depth (as in a sheep foot roller)Fig. 6
• The tendency is to produce better compaction on the
surface of the compacted layer than at the bottom, i
the layer is very thick
49
Fig. 6
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 50/53
• The wide compaction device with a smaller surface
pressure produces a more uniform pressure
throughout the layer. This is the characteristic of
rubber-tired roller
• The average pressure in a layer being compacted can
be increased by increasing the surface pressure or by
decreasing the layer thickness
• For earth dam cores, where uniformity is needed, the
moisture should be kept as high as possible. For the
shell where strength is most important, the moistureshould be as low as possible
50
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 51/53
• The surface pressure, however, is limited by the
soil bearing capacity. Once that is exceeded, the
soil compaction is less
• Before any part of the embankment is compacted a
test strip should be set up where the best
equipment, moisture, layer thickness, and number
of passes are determined by experiment
• A little money spent on this may well save much
time, money and argument later 51
Contd..
Stage compaction:
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 52/53
Stage compaction:
• The maximum pressure which can be exerted by the
compaction equipment is limited by the soil bearing
capacity. The uncompacted soil with its loose
structure has very low bearing
• If heavy equipment is used in an attempt to compact
this soil, a bearing capacity failure is likely. If,
however, the soil is first partially compacted with thelight equipment, the bearing strength will be
increased sufficiently to permit the use of heavy
equipment52
Soil Compaction
7/27/2019 Construction of Earth Dam
http://slidepdf.com/reader/full/construction-of-earth-dam 53/53
Stage compaction:
• Such stage compaction can be very effective in higly
cohesive soils which require high pressures for
compaction, and it is useful for all soils when very
high degree of compaction are required
53
Contd..