Upload
nguyencong
View
214
Download
0
Embed Size (px)
Citation preview
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
Young to Wagga Wagga Looping Pipeline
Stage 2 (Bethungra to Young)
APT Management Services Pty Ltd
09-Nov-2015
Construction Noise and Vibration Management Plan
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
Construction Noise and Vibration Management Plan
Client: APT Management Services Pty Ltd
ABN: 58 091 668 110
Prepared by
AECOM Australia Pty Ltd
Level 2, 60 Marcus Clarke Street, Canberra ACT 2600, Australia
T +61 2 6201 3000 F +61 2 6201 3099 www.aecom.com
ABN 20 093 846 925
09-Nov-2015
Job No.: 60431900
AECOM in Australia and New Zealand is certified to the latest version of ISO9001, ISO14001, AS/NZS4801 and OHSAS18001.
© AECOM Australia Pty Ltd (AECOM). All rights reserved.
AECOM has prepared this document for the sole use of the Client and for a specific purpose, each as expressly
stated in the document. No other party should rely on this document without the prior written consent of AECOM.
AECOM undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this
document. This document has been prepared based on the Client’s description of its requirements and AECOM’s
experience, having regard to assumptions that AECOM can reasonably be expected to make in accordance with
sound professional principles. AECOM may also have relied upon information provided by the Client and other
third parties to prepare this document, some of which may not have been verified. Subject to the above
conditions, this document may be transmitted, reproduced or disseminated only in its entirety.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
Quality Information (AECOM)
Document Construction Noise and Vibration Management Plan
Ref 60431900
Date 09-Nov-2015
Prepared by Lauren Lambert and Patrick Martinez
Reviewed by Gayle Greer and Guillaume Prudent-Richard
Revision History
Revision Revision
Date Details
Authorised
Name/Position Signature
4-0 9/11/15 For submission to DP&E Guillaume Prudent-
Richard
Associate Director -
Environment
Document Control
Document: Construction Noise and Vibration Management Plan
The following table is to be updated with details of each revision of this document. Revised copies of this
document to be provided to all relevant stakeholders and approval agencies.
Revision and Approval History
Revision Revision
Date Details
Authorised
Name/Position Signature
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
Table of Contents
Acronyms i 1.0 Background 1
1.1 Introduction 1 1.2 Purpose and Scope 1 1.3 Objectives 1
2.0 Document Structure 2 3.0 Legislative and Regulatory Requirements 3
3.1 Relevant Legislation 3 3.1.1 State 3 Environmental Planning and Assessment Act 1979. 3
3.2 Guidelines and Standards 3 3.3 Conditions of Approval and Statement of Commitments 4
4.0 Project Description 6 5.0 Risk Assessment 8
5.1 Evaluation and Assessment of Construction Noise and Vibration Impacts 8 5.1.1 Assessment Methodology 8 5.1.2 Existing Environment 8 5.1.3 Noise Management Levels 8 5.1.4 Vibration Management Levels 9
5.2 Potential Noise and Vibration Impacts 12 6.0 Environmental Management 13
6.1 Construction Hours of Work 13 6.1.1 Impulsive or Tonal Noise Emissions 13 6.1.2 Permission for Varied Construction Hours (Out of hours works) 13
6.2 Construction Noise and Vibration Management Objectives 13 6.2.1 Construction Noise Management Levels 13 6.2.2 Maximum levels for Plant and Equipment 14 6.2.3 Construction Vibration Management Objectives 15
6.3 Environmental Management Controls 15 6.4 Roles and Responsibilities 16 6.5 Training and Awareness 17 6.6 Community and Stakeholder Consultation 17
7.0 Monitoring and Reporting 18 7.1 Monitoring and Reporting Schedule 18
7.1.1 Attended noise monitoring procedure 18 7.1.2 Monitoring of equipment procedure 18 7.1.3 Equipment 18 7.1.4 Attended noise monitoring schedule 19 7.1.5 Reporting on attended noise monitoring 19
7.2 Auditing 19 7.3 Non-compliance and Corrective Action 19
8.0 Complaints Management 20 9.0 Sub-Plan Review 21 10.0 Summary of Environmental Controls 22
Appendix A Glossary A
Appendix B Noise Contours and Receivers B
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
i
Acronyms
ABL Assessment background level
APA APA Group
CEMP Construction Environmental Management Plan
CNVMP Construction Noise and Vibration Management Plan
dB Decibel
dB(A] A Weighted decibels
DEC NSW Department of Environment and Conservation
DECC NSW Department of Environment & Climate Change
DECCW Department of Environment, Climate Change and Water
DP&E NSW Department of Planning and Environment
EPA NSW Environment Protection Authority
EP&A Act Environmental Planning and Assessment Act
EPL Environment Protection License
f Frequency
HDD Horizontal Directional Drilling
HSEMS APA’s Health and Safety Environmental Management System
Hz Hertz
ICNG Interim Construction Noise Guideline
INP Industrial Noise Policy
MSP Moomba to Sydney Pipeline System
POEO Act Protection of the Environment Operations Act 1997
RBL Rating background level
ROW Right of Way
VDV Vibration Dose Value
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
1
1.0 Background
1.1 Introduction
In April 2013, the Minister for Planning and Infrastructure granted approval for the construction and operation of a
new 18-inch (450 mm) natural gas pipeline from Young to Bethungra, NSW (approximately 70 km in length) within
the easement of the existing pipeline which extends from Young to Wagga Wagga (the Project). The Project
would connect to the Moomba to Sydney Pipeline System (MSP) mainline at its north east end in Young.
The Project is Stage 2 of the duplication of Young to Wagga Wagga pipeline, with the first stage, Wagga Wagga
to Bethungra, previously approved under Part 3A of the Environmental Planning and Assessment Act 1979
(EP&A Act) and constructed.
The proponent of the Project is APA Group (APA), comprising the Australian Pipeline Trust and APT Investment
Trust. East Australian Pipeline Limited, which is the holder of the Pipeline Licence for the Young to Wagga Wagga
Pipeline (PL 19) is also a subsidiary of APA Group.
1.2 Purpose and Scope
The project approval is subject to a number of conditions including the preparation and implementation of a
Construction Environmental Management Plan (CEMP). The CEMP must be approved by the Secretary of the
Department of Environment and Planning (DP&E) (the Secretary) or their nominee prior to commencement of
construction.
In accordance with the Conditions of Project Approval, the CEMP shall include a Construction Noise and Vibration
Management Plan (CNVMP). This document addresses this requirement and is provided as one of a number of
sub-plans to an overarching CEMP document. See Section 2.0 for more information on the CEMP structure. The
CEMP and associated sub-plans form management guides that clearly identify required environmental
management actions for easy reference by project personnel.
The purpose of this CNVMP is to describe how APA will manage construction noise and vibration during the
construction of the pipeline. The sub-plan has been developed to ensure the requirements of the project approval
and associated environmental documentation requirements are achieved to ensure the successful delivery of the
Project.
This sub-plan is only applicable to the pre-construction and construction phase of the Project and does not include
the management of operational noise and vibration. Noise and vibration from blasting activities during
construction is also excluded from this sub-plan. Should blasting activities be required they will be subject to a
separate Blasting Management Plan.
The key components covered in this sub-plan include:
- Identification of background noise levels and construction noise and vibration management criteria.
- Evaluation and assessment of potential noise and vibration impacts on receptors.
- Description of environmental management controls to mitigate potential noise and vibration impacts on
receptors.
- Procedures for monitoring and auditing of noise and vibration impacts against noise and vibration goals.
- Procedures for the management of complaints and non-compliances.
A description of acoustic terms used within this CNVMP is provided within Appendix A.
1.3 Objectives
The objectives of the CNVMP are to:
- Minimise unreasonable noise and vibration impacts on receptors.
- Avoid structural damage to buildings as a result of construction vibration.
- Comply with relevant construction noise and vibration management levels as described in Section 6.2.
- Undertake active community consultation and maintain positive working relationships.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
2
2.0 Document Structure
The CNVMP forms a sub-plan of the overarching CEMP for the Project. An overview of the structure of the CEMP
and sub-plans is illustrated in Figure 1.
This sub-plan shall be reviewed and updated as necessary throughout the construction phase of the Project. The
review process is detailed within Section 9.0.
Revised copies of this document will be provided to all relevant stakeholders and approval agencies.
Figure 1 Structure of CEMP and Sub-Plans
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
3
3.0 Legislative and Regulatory Requirements
APA and the Construction Contractor have an obligation to ensure that construction work complies with all
relevant regulatory requirements and guidelines. All site employees and construction personnel will be made
aware of environmental regulations and best industry practices as part of an environmental induction process and
construction management system. The relevant legislation, policies and approvals are identified in the following
sections.
3.1 Relevant Legislation
3.1.1 State
Environmental Planning and Assessment Act 1979.
The Environmental Planning and Assessment Act 1979 (EP&A Act) is the overarching environmental planning
and assessment legislation for the proper management, development and conservation of the State's natural and
built environment. Part 3A of the EP&A Act provides an assessment and approval process for major projects. The
Project is declared to be a major project under State Environmental Planning Policy (Major Development) 2005
(Major Projects SEPP) (Schedule 1, clause 26(a)) because it is development for the purpose of a pipeline in
respect of which a license has been granted under the Pipelines Act 1967. The Project is therefore subject to Part
3A of the EP&A Act and the Minister for Planning is the determination authority.
The existing pipeline licence for the Young to Wagga Wagga Pipeline (PL 19) requires a variation to address the
proposed pipeline duplication (or looping).
Protection of the Environment Operations Act 1997.
The Protection of the Environment Operations Act 1997 (POEO Act) details offences and penalties for a range of
environmental aspects, including noise, and sets out the duty to notify the Environment Protection Authority (EPA)
of any actual or potential environmental harm. The Act also details scheduled activities that require an
Environment Protection Licence (EPL).
3.2 Guidelines and Standards
This sub-plan has been prepared in accordance with the following standards and guidelines:
NSW Environment Protection Authority (EPA), Industrial Noise Policy (INP), January 2000 and relevant
application notes, 2013
NSW Department of Environment, Climate Change and Water (DECCW), Road Noise Policy (RNP), 2011
NSW Department of Environment & Climate Change (DECC), Interim Construction Noise Guideline (ICNG), 2009.
NSW Department of Environment and Conservation (DEC), Assessing Vibration: A technical guideline (AVATG),
2006
Standards Australia AS1055-1997™ (AS1055) - Description and Measurement of Environmental Noise, Parts 1, 2
and 3
Standards Australia AS IEC 61672.1-2004™ (AS61672) - Electro Acoustics - Sound Level Meters Specifications
Standards Australia AS 2436-2010™ (AS2436) - Guide To Noise And Vibration Control On Construction,
Demolition And Maintenance Sites
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
4
3.3 Conditions of Approval and Statement of Commitments
The following table lists the statutory conditions of approval, which are applicable to the content and scope of this
sub-plan.
Table 1 Minister's Conditions of Approval and Statement of Commitments
Approval
reference Commitment/requirement Sub-plan reference
Minister’s Conditions of Project Approval
Construction Hours
B24 Construction activities associated with the project (except as provided in
Condition B25 and B26) shall be undertaken on a standard industry work
cycle during the following standard daytime construction hours:
Section 6.1
B24 a) 7:00am to 6:00pm daily for a maximum period of 28 days at a time,
separated by
a minimum respite period of nine days; and
B24 b) at no time on public holidays.
B25 The hours of construction specified under condition B24 may be varied
with the prior written approval of the Director-General. Any request to
alter the hours of construction shall be:
Section 6.1.2
B25 a) considered on a case-by-case basis;
B25 b) accompanied by details of the nature and need for activities to be
conducted during the varied construction hours and any other information
necessary to reasonably determine that activities undertaken during the
varied construction hours will not adversely impact on the acoustic
amenity of receptors in the vicinity of the site; and
B25 c) commenced only affected residential receivers are informed of the timing
and duration of work approved under this condition at least 48 hours
before that work commences.
B26 Except as expressly permitted by an EPL, activities resulting in impulsive
or tonal noise emission (such as rock blasting, pile driving) shall only be
undertaken:
Section 6.1.1
B26 a) Between the hours of 8:00 am to 5:00 pm Monday to Friday;
B26 b) Between the hours of 8:00 am to 1:00 pm Saturday; and
B26 c) In continuous blocks not exceeding three hours each with a minimum
respite from those activities and works of not less than one hour between
each block.
Construction Noise and Vibration Limits
B27 The Project shall be constructed with the aim of achieving the
construction noise management levels detailed in the Interim
Construction Noise Guideline (DECC, 2009). All feasible and reasonable
noise mitigation measures shall be implemented and any activities that
could exceed the construction noise management levels shall be
identified and managed in accordance with the CEMP.
Section 6.2.1 and 6.3
B28 The Project shall be constructed with the aim of achieving the following
construction vibration goals for human exposure: the acceptable vibration
values set out in the Environmental Noise Management Assessing
Vibration: A Technical Guideline (Department of Environment and
Conservation, 2006).
Section 6.2.3 and 6.3
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
5
Approval
reference Commitment/requirement Sub-plan reference
B29 The Proponent shall ensure that air blast overpressure generated by
blasting associated with the Project does not exceed the criteria specified
in Table 1, when measured at the most affected residence or other
sensitive receiver.
Table 1 – Airblast overpressure criteria
Airblast overpressure
(dB(Lin Peak))
Allowable exceedance
115 5% of total number of blasts over a 12 month
period
120 Never
Blasting
Management Plan (if
blasting is required)
B30 Ground vibration generated by blasting associated with the Project does
not exceed the criteria specified in Table 2, when measured at the most
affected residence or other sensitive receiver.
Table 2 – Peak particle velocity criteria
Peak Particle
Velocity (mm/s)
Allowable exceedance
5 5% of total number of blasts over a 12 month
period
10 Never
Blasting
Management Plan (if
blasting is required)
Construction Environmental Management Plan
C2 As part of the Construction Environmental Management Plan required
under condition C1 of this approval, the Proponent shall prepare and
implement the following:
-
C2 d) a Construction Noise and Vibration Management Plan to manage noise
and vibration impacts during construction and to identify all feasible and
reasonable noise and vibration mitigation measures. The Plan shall be
developed in accordance with NSW Interim Construction Noise
Guidelines (DECC, July 2009) and shall include, but not necessarily be
limited to:
This document
C2 d) (i) details of all potentially noise-affected receivers; Appendix B
C2 d) (ii) an analysis of all feasible mitigation measures to reduce construction
noise and vibration impacts including the use of noise attenuation
barriers, alternative construction methods and work practices where
potential noise impacts exceed the relevant objectives;
Section 6.3
C2 d) (iii) procedures for notifying residents of construction activities that are
likely to affect their noise and vibration amenity;
Section 6.6
C2 d) (iv) contingency plans to be implemented in the event of non-compliance
and / or noise and vibration complaints; and
Section 7.3 and 8.0.
C2 d) (v) details of a contact person to follow up complaints. Section 6.4
Statement of Commitments
NV1
Construction noise and vibration management strategies will be outlined in the CEMP. Construction and operation measures will include:
-
- Liaising with community to advise on likely timing and duration of
noisy activities.
Section 6.6
- Resolving complaints received from residents and landowners. Section 8.0
- Using noise abatement measures where reasonable and feasible. Section 6.3
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
6
4.0 Project Description
The Project will involve the installation of a new 18-inch (450 mm) natural gas transmission ‘looping pipeline’
between the townships of Young and Bethungra (see Figure 2). The new pipeline will be installed adjacent to an
existing 12-inch (305 mm) pipeline over a distance of approximately 70 km, and will be constructed within the
existing 20 m wide gas pipeline easement and an additional 10m of working space.
The pipeline would be a buried, class 600 (10.2 MPa) gas transmission pipeline which would initially be operated
at 8.5 MPa. The pipeline would be designed, constructed and operated in accordance with AS 2885 – The
Australian Pipeline Standard.
The construction of the pipeline would require a number of activities to be undertaken sequentially along the
length of the route. Typical equipment required for pipeline construction includes: bulldozers, loaders, graders,
side-boom tractors, trucks, padding machines, excavators, wheel ditching machines, welding units and light
vehicles.
Construction activities will be undertaken by a range of specialist construction personnel. The majority of the
pipeline will be installed via the excavation of a trench, laying of the pipe and backfilling of the trench. Where
required, other methods such as horizontal directional drilling (HDD) will be used for sections where minimal
disturbance to significant features is required such as sealed roads or major waterways.
Construction of the proposed pipeline will involve clearing and grading the entire pipeline easement. Such clearing
will result in total surface disturbance over the areas where it is employed, which will likely consist of the majority
of the route. It should be noted that the study area has already been subject to such an impact when the original
pipeline was constructed in 1980, and subsequently in 2006 when an optical fibre cable was constructed in part of
the study area. Since 1980, the area has also been subject to ongoing maintenance activities, including
vegetation clearing and maintenance in accordance with safety requirements for gas pipelines of this
specification.
A brief outline of the construction activities is provided below:
- Establishment of a temporary construction depot, pipe storage area, temporary gateways, and security
fencing
- Clear and Grade: Clearance of vegetation and levelling for right of way (ROW). Graders, backhoes and
bulldozers would be used for levelling.
- Trenching: A wheel trencher, rock saw or excavator would be used to dig the trench in which the pipe would
lie. This method is used everywhere except for major road and watercourse crossings where directional
drilling would normally be employed.
- Stringing and Bending: Laying out of the pipe adjacent to the trench in preparation for welding. Prior to
welding, the pipes would be bent to match the required vertical/horizontal profile.
- Welding, Inspection and Coating: Pipes would be welded in several segments, typically in one kilometre
lengths. Following welding and inspection, the pipe would be cleaned by grit blasting and an external coating
applied.
- Lowering In: Lowering of the pipe into the trench using side-boom tractors.
- Backfilling: The trench would be backfilled with screened trench spoil, which would sift around the pipe
providing a stone free covering. The remaining subsoil would then be placed in the trench in layers (typically
two layers) with compaction between each layer.
- Hydrostatic testing: Large single volumes of water to be pumped into the pipe in sections and pressurised to
a minimum of 125% of the maximum allowable operating pressure.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
7
Figure 2 – Project Location
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
8
5.0 Risk Assessment
5.1 Evaluation and Assessment of Construction Noise and Vibration
Impacts
5.1.1 Assessment Methodology
Potential construction noise and vibration impacts have been assessed using a quantitative approach. The
assessment has identified potential sensitive receptors, likely noise levels and feasible and reasonable noise
mitigation measures. The quantitative noise and vibration assessment was undertaken through the following
steps:
- Review of the proposed construction activities (e.g. clearing, trenching, drilling) to identify those which are
likely to generate significant noise and vibration. The parameters taken into account include proposed
techniques and equipment, hours of operation and duration of each phase.
- Assessment of the potential noise and vibration impacts as a consequence of the identified construction
activities.
- Development of off-set distances for the proposed construction activities using criteria outlined in Interim
Construction Noise Guideline (ICNG) and other guideline documents.
- Identification of sensitive receptors, such as residences and other noise sensitive receptors within off-set
distances that could experience noise levels and vibration above recommended management levels.
- Evaluation of feasible and reasonable noise and vibration mitigation measures.
5.1.2 Existing Environment
The vast majority of the pipeline route is located in open countryside where the noise Rating Background Level
(RBL) is likely to be around 30 dB(A). The location of identified sensitive receptors in relation to the proposed
pipeline route is illustrated in Error! Reference source not found..
Although the background noise levels may actually be less in some areas, the Industrial Noise Policy states that
where the rating background level is found to be less than 30 dB(A), the level used for assessment purposes is
set to 30 dB(A). This RBL has also been used for the suburban/urban areas as no direct monitoring of noise
background level has been undertaken. A RBL of 30 dB(A) is very conservative for suburban/urban environments.
5.1.3 Noise Management Levels
The ICNG provides noise management levels for consideration in assessing noise impacts for a project and noise
levels for different types of receptors (Table 2).
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
9
Table 2 – Noise management level for residential and sensitive receivers (ICNG)
Receptor
Time when
management
level applies
Rating
Background
Level (RBL)
Management level LAeq (15 min)
Residence
Standard
construction
hours1
30 dB(A) 40 dB(A)
(Noise affected / RBL + 10 dB(A))
Highly Noise
Affected2
N/A 75 dB(A)
(Highly noise affected)
Out of hours 30 dB(A) 35 dB(A)
(Noise affected / RBL + 5 dB(A))
Sensitive Receivers
Classrooms at schools and other
educational institutions Internal
noise level
When
properties are
being used
N/A 45 dB(A) (Internal noise level)
Hospital wards and operating
theatres N/A 45 dB(A) (Internal noise level)
Places of worship N/A 45 dB(A) (Internal noise level)
Active recreation areas (e.g. sports) N/A 65 dB(A) (External noise level)
Passive recreation areas (e.g.
reading, meditation)
N/A 60 dB (External noise level)
Community Centre
N/A Depends on the intended use of the
centre. Refer to the recommended
‘maximum’ internal levels in
AS2107 for specific uses.
5.1.4 Vibration Management Levels
The relevant standards/guidelines used for assessing construction vibration are summarised in Table 3.
Table 3 Standards/guidelines used for assessing construction vibration
Item Standard/Guideline
Structural Damage DIN4150-Part 3:1999 ‘Structural Vibration Part 3 – Effects of vibration
on structures
Human Comfort (tactile vibration) NSW Department of Environment and Conservation (2006) document
“Assessing Vibration: A Technical Guideline” 3
In the absence of Australian based vibration criteria for structural damage, German Standards and British
Standards have been considered. DIN4150 structural damage criteria are more conservative (i.e. more onerous)
than the British Standard BS7385-Part 2:1993 ‘Evaluation and Measurement for Vibration in Buildings’ and have
been adopted for this assessment.
1 Standard construction hours in the ICNG are weekdays 7am – 6pm and Saturdays 8am-1pm, no work on Sundays or public
holidays. 2 Highly Noise Affected level represents the point above which there may be strong community reaction to noise. This can
happen at any time. 3 This document is based upon the guidelines contained in British Standard 6472:1992, “Evaluation of human exposure to vibration in buildings (1-
80 Hz)”. This British Standard was superseded in 2008 with BS 6472-1:2008 “Guide to evaluation of human exposure to vibration in buildings – Part 1: Vibration sources other than blasting” and the 1992 version of the Standard was withdrawn. Although a new version of BS 6472 has been published, the EPA still requires vibration to be assessed in accordance with the 1992 version of the Standard at this point in time.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
10
5.1.4.1 Structural damage
Structural damage ground vibration criteria are defined in terms of levels of vibration that would minimise the risk
of damage to buildings and other structures.
Most commonly specified ‘safe’ structural vibration levels are designed to minimise the risk of threshold or
cosmetic surface cracks and are set well below the levels that have the potential to cause damage to the main
structure. Examples of threshold or cosmetic cracking include minor non-structural effects such as superficial
cracking in cement render or plaster. Larger exceedances of structural damage criteria increase the risk of more
significant damage to a building’s underlying structure.
Structural damage criteria are presented in German Standard DIN 4150-Part 3 in terms of recommended
maximum levels of vibration that reduce the likelihood of structural damage caused by vibration. These levels are
presented in Table 4. Receivers classified as Group 1, Group 2 and Group 3 have been identified as being
potentially affected by construction vibration.
It should be noted that the vibration criteria presented below are conservative. DIN 4150 states that:
“exceeding the values in table 1 (Table 4) does not necessarily lead to damage; should they be
significantly exceeded, however, further investigations are necessary”.
Table 4 DIN4150 structural damage vibration criteria
Group Type of structure
Guideline values for velocity in mm/s
Vibration at the foundation Vibration at
the
horizontal
plane of
highest
floor at all
frequencies
1 H to 10 Hz 10 H to
50 Hz
50 H to
100 Hz
1
Buildings used for commercial
purposes, industrial buildings
and buildings of similar design
20 20-40 40-50 40
2 Dwellings and buildings of
similar design and/or use 5 5-15 15-20 15
3
Structures that, because of
their particular sensitivity to
vibration, cannot be classified
under Group 1 or 2 and are of
great intrinsic value (e.g.
listed buildings under a
preservation order)
3 3-8 8-10 8
5.1.4.2 Human comfort
In general, human response to vibration is a complex phenomenon. There are wide variations in vibration
tolerance of humans. Accordingly, acceptance goals for human comfort are hard to define and quantify.
Acceptable values of human exposure to vibration are primarily dependent on the activity taking place in the
occupied space (e.g. workshop, office, or residence) and the character of vibration (e.g. continuous or
intermittent). In addition, specific values are dependent upon social and cultural factors, psychological attitudes,
expected interference with privacy, and ultimately the individual’s perception.
The procedure outlined in “Assessing Vibration: A Technical Guideline” has been used in this assessment.
Disturbance caused by vibration will depend on its duration as well as its magnitude. This method involves the
calculation of a Vibration Dose Value (VDV) which is used to evaluate the cumulative effects of bursts of
intermittent vibration. Various studies have shown that VDV assessment methods far more accurately assess the
level of disturbance than methods which assess the vibration magnitude only.
The VDV is the fourth root of the integral of the fourth power of vibration with respect to time. The VDV represents
an ‘amount’ of vibration. In assessing the VDVs, criteria detailed in BS6472:1992 ‘Guide to evaluation of human
exposure to vibration in buildings (1 Hz to 80Hz)’ are used, however the base values and multiples are converted
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
11
into VDVs assuming constant levels over a 15 hour day and a 9 hour night. The resulting VDV criteria are shown
in Table 5.
Table 5 Acceptable vibration dose values for intermittent vibration (m/s1.75
)
Location Daytime Night-time
Preferred Maximum Preferred Maximum
Critical areas (e.g. hospital
operating theatres, precision
laboratories)
0.10 0.20 0.10 0.20
Residences 0.20 0.40 0.13 0.26
Offices, schools, educational
institutions and places of
worship
0.40 0.80 0.40 0.80
Workshops 0.80 1.60 0.80 1.60
The guideline states:
“There is a low probability of adverse comment or disturbance to building occupants at vibration values
below the preferred values. Adverse comment or complaints may be expected if vibration values
approach the maximum values. Activities should be designed to meet the preferred values where an
area is not already exposed to vibration. Where all feasible and reasonable measures have been
applied, values up to the maximum range may be used if they can be justified. For values beyond the
maximum value, the operator should negotiate directly with the affected community.”
Safe working distances for typical vibration inducing equipment are listed in Table 6 below.
Table 6 – Examples of safe working distances for typical vibration intensive plant
Plant Rating/Description Safe Working Distance
Cosmetic Damage Human Response
Vibratory Roller
< 50 kN (Typically 1-2 t) 5 m 15-20 m
< 100 kN (Typically 2-4 t) 6 m 20 m
< 200 kN (Typically 4-6 t) 12 m 40 m
< 300 kN (Typically 7-13 t) 15 m 100 m
> 300kN (Typically 13-18 t) 20 m 100 m
> 300 kN (> 18 t) 25 m 100 m
Small Hydraulic
Hammer (300 kg – 5-12 t excavator) 2 m 7 m
Medium Hydraulic
Hammer (900 kg – 12-18 t excavator) 7 m 23 m
Large Hydraulic
Hammer (1,600 kg – 18-34 t excavator) 22 m 73 m
Vibratory Pile
Driver Sheet piles 2–20 m 20 m
Pile Boring ≤ 800 mm 2 m N/A
Jackhammer Handheld 1 m nominal Avoid contact with
structure
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
12
5.2 Potential Noise and Vibration Impacts
Noise receptors have been identified using a quantitative approach, whereby likely noise levels during
construction and offset distances were modelled, indicating how many receptors are located within each offset
distance. Noise levels were modelled for the noisiest equipment to be used on site and for other equipment such
as excavators and trenchers.
A total of 179 residences have been identified as within a “noise affected” offset distance (i.e. would experience a
noise level of between 40 dB(A) to 75dB(A)). These have been identified in Appendix B. No residences have been
identified within the “highly noise” affected offset distance (i.e. would experience a noise level of 75 dB(A) or
greater). No sensitive receivers have been identified within a noise affected distance.
Due to the transient nature of the construction works, whereby construction activities move along the pipeline
alignment as they progress, noise impacts on receptors will not be constant over the construction period and will
rather be during short term, temporary periods.
Traffic noise has not been assessed as it is expected that construction traffic is likely to be very low in volume.
The expected vibration levels from normal construction activities would not cause structural damage to buildings.
Furthermore, vibration levels at receptors are unlikely to cause adverse human response.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
13
6.0 Environmental Management
6.1 Construction Hours of Work
In accordance with the Conditions of Project Approval, construction activities will be undertaken during the
following standard daytime construction hours4:
a) 7:00am to 6:00pm daily for a maximum period of 28 days at a time, separated by a minimum respite
period of nine days; and
b) at no time on public holidays, unless prior approval received from DP&E and works are carried out in
accordance with the Out of Hours Work Protocol identified within the CEMP.
6.1.1 Impulsive or Tonal Noise Emissions
In accordance with the Conditions of Project Approval, activities resulting in impulsive or tonal noise emission
(such as rock blasting, pile driving) shall only be undertaken:
a) between the hours of 8:00 am to 5:00 pm Monday to Friday;
b) between the hours of 8:00 am to 1:00 pm Saturday; and
c) in continuous blocks not exceeding three hours each with a minimum respite from those activities and
works of not less than one hour between each block.
6.1.2 Permission for Varied Construction Hours (Out of hours works)
The hours of construction may be varied with the prior written approval of the Secretary. Any request to alter the hours of construction shall be:
a) considered on a case-by-case basis;
b) accompanied by details of the nature and need for activities to be conducted during the varied
construction hours and any other information necessary to reasonably determine that activities
undertaken during the varied construction hours will not adversely impact on the acoustic amenity of
receptors in the vicinity of the site; and
c) commenced only affected residential receivers are informed of the timing and duration of work approved
under this condition at least 48 hours before that work commences.
6.2 Construction Noise and Vibration Management Objectives
6.2.1 Construction Noise Management Levels
The Project shall be constructed with the aim of achieving the construction noise management levels detailed in
the ICNG, as detailed in Table 7 below.
Table 7 – Noise management level for residential and sensitive receivers (ICNG)
Receptor
Time when
management
level applies
Rating
Background
Level (RBL)
Management level LAeq (15 min)
Residence
Standard
construction
hours5
30 dB(A) 40 dB(A)
(Noise affected / RBL + 10 dB(A))
Highly Noise
Affected N/A
75 dB(A)
(Highly noise affected)
Out of hours 30 dB(A) 35 dB(A)
(Noise affected / RBL + 5 dB(A))
4 This does not apply in the event of a direction from police or other relevant authority for safety reasons, in an emergency to
prevent loss of life or to prevent environmental harm. 5 Standard construction hours in the ICNG are weekdays 7am – 6pm and Saturdays 8am-1pm, no work on Sundays or public
holidays.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
14
Receptor
Time when
management
level applies
Rating
Background
Level (RBL)
Management level LAeq (15 min)
Sensitive Receivers
Classrooms at schools and other
educational institutions Internal
noise level
When
properties are
being used
N/A 45 dB(A) (Internal noise level)
Hospital wards and operating
theatres N/A 45 dB(A) (Internal noise level)
Places of worship N/A 45 dB(A) (Internal noise level)
Active recreation areas (e.g. sports) N/A 65 dB(A) (External noise level)
Passive recreation areas (e.g.
reading, meditation)
N/A 60 dB (External noise level)
Community Centre
N/A Depends on the intended use of the
centre. Refer to the recommended
‘maximum’ internal levels in
AS2107 for specific uses.
6.2.2 Maximum levels for Plant and Equipment
All plant and equipment used throughout the works should have an operating sound power level less than or
equal to those in Table 8. These sound power levels are largely based on information in AS2436-1981 “Guide to
Noise Control on Construction, Maintenance and Demolition Sites”.
Table 8 – Typical Constriction Equipment Sound Power Levels, dB (A)
Plant description LAeq Sound Power Levels
Range
Rock Breaker 112
Piling Drilling 116
Pneumatic Jack Hammer 108
Mobile Crane 104
Scraper 109
Front End Loader 108
Pneumatic Hand Tools (general) 108
Bulldozer 109
Tracked Excavator 108
Grader 109
Vibratory Roller 110
Dump Trucks 105
Water Cart 100
Rollers 105
Concrete Pump 106
Backhoe 102
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
15
6.2.3 Construction Vibration Management Objectives
The Project shall be constructed with the aim of achieving the construction vibration goals as detailed in Table 4
and Table 5.
6.3 Environmental Management Controls
The controls to be implemented during the construction of the project are provided in Table 9. Table 12 provides
further detail with respect to timing and responsibility for each control, as well as monitoring and reporting
requirements.
Table 9 Environmental Management Controls
Control
Ref # Environmental Management Controls
NV1 All potentially affected residences as identified in Error! Reference source not found. will be
informed by letterbox drop of the construction works including working hours to be adhered to, and
the level and duration of noise to expect during construction.
NV2 All potentially affected residences as identified in Error! Reference source not found. will be kept
informed of any significant changes to construction activities or if out of hours of work is required.
NV3 Any complaints received related to noise or vibration will be dealt with in accordance with Section
7.3.
NV4 All site personnel will be instructed during a general induction as to their responsibilities in
minimising noise and adhering to the noise minimisation measures.
NV5 Equipment operators are to be report any faulty equipment to Construction Contractor Site
Supervisor.
NV6 Works will be undertaken during the hours of:
a) 7:00am to 6:00pm daily for a maximum period of 28 days at a time, separated by a
minimum respite period of nine days; and
b) at no time on public holidays.
Any works outside of these hours shall be governed by the approved Out of Hours Work Protocol.
NV7 Activities resulting in impulsive or tonal noise emission (such as rock blasting, pile driving) shall only be undertaken:
a) between the hours of 8:00 am to 5:00 pm Monday to Friday;
b) between the hours of 8:00 am to 1:00 pm Saturday; and
c) in continuous blocks not exceeding three hours each with a minimum respite from those
activities and works of not less than one hour between each block.
NV8 In the case of an activity that requires work to be undertaken outside the specified hours, written approval must be sought from the Secretary. Any request to alter the hours of construction shall be:
a) considered on a case-by-case basis;
b) accompanied by details of the nature and need for activities to be conducted during the
varied construction hours and any other information necessary to reasonably determine
that activities undertaken during the varied construction hours will not adversely impact
on the acoustic amenity of receptors in the vicinity of the site; and
c) commenced only affected residential receivers are informed of the timing and duration of
work approved under this condition at least 48 hours before that work commences.
NV9 The noise levels of plant and equipment must have operating Sound Power or Sound Pressure
Levels compliant with the criteria in Table 8.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
16
Control
Ref # Environmental Management Controls
NV10 Vibration intensive activities should not be located closer to sensitive receptors than the safe
working distances presented in Table 6 – Human response.
NV11 Construction equipment will be fitted with adequate noise and vibration control equipment where
possible. Measures include earth moving equipment fitted with residential class mufflers, and
acoustic enclosures for any diesel generators and/or air compressors.
NV12 Any equipment not in use for extended periods during construction work will be switched off.
NV13 All vehicles and equipment will be regularly serviced, as per manufactures instructions and
maintained in proper working order.
NV14 Ensure deliveries are within the standard hours of works
NV15 Simultaneous operation of noisy plant will be avoided wherever practicable.
NV16 Wherever practicable, noisy equipment will be:
a) Positioned behind structures that act as barriers to identified receptors
b) Positioned at the greatest distance from identified receptors
c) Oriented to directed noise emissions away from identified receptors
NV17 “Quiet” practices will be employed wherever practicable when operating equipment
NV18 Any noise construction activities will be completed in the shortest time possible.
NV19 There will be no swearing or unnecessary shouting or loud stereos/radios on site.
NV20 There will be no dropping of materials from heights, throwing of metal items, or slamming of doors.
6.4 Roles and Responsibilities
The overarching CEMP provides details of the roles and responsibilities relevant to the CEMP and all sub-plans.
The roles and responsibilities relevant for only the CNVMP are provided below in Table 10 and are consistent with
the overarching CEMP.
Table 10 Roles and Responsibilities
Role Responsibilities Contact Phone
Number
APA Project Manager - Overall implementation of the Construction Noise and
Vibration Management Plan
- Authorise and confirm the implementation of mitigation
measures
Construction
Contractor Project
Manager
- Implement methodology for avoiding excessive noise
emissions
- Coordinate monitoring and compile reports
- Maintain internal records of monitoring
- Collate and maintain records of complaints, respond to
complainant
- Identify Non Conformances
- Review and update the Noise Management Plan as
required
Independent
Environmental
Representative
- Undertake audits to ensure implementation of the CNVMP
- Communication with EPA, as required
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
17
6.5 Training and Awareness
All Project personnel, subcontractors, consultants and visitors will receive inductions into APA’s and the
Construction Contractor's environmental obligations prior to commencing on site. All environmental inductions will
be conducted as part of APA’s Health and Safety Environmental Management System (HSEMS). Project
induction and training will fall under the following categories:
- General project induction
- Visitor induction
- Job specific environmental training
Information specific to construction noise and vibration will be included in the general project induction and will
include:
- All relevant project specific and standard noise and vibration mitigation measures;
- Relevant licence and approval conditions;
- Permissible hours of work;
- Location of nearest receptors;
- Designated loading/unloading areas and procedures;
- Site opening/closing times (including deliveries); and
- Environmental incident and complaint procedures.
All inductions will be recorded in the training register held by the Construction Contractor.
6.6 Community and Stakeholder Consultation
This sub-plan has been prepared in accordance with the requirements of the Minister’s Conditions of Approval
and Statement of Commitments for the Project (Section 3.3).
Prior to implementation of this sub-plan and commencement of construction, this document will have been
reviewed by the DP&E and approved by the Secretary or his nominee prior to commencement of construction.
At least 14 days prior to construction, all potentially affected residences, as identified in Appendix B will be
informed by letterbox drop and/or email of the construction works including working hours to be adhered to, and
the level and duration of noise to expect during construction. They will also be informed if there are any changes
to construction activities and timing, including out of hours work.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
18
7.0 Monitoring and Reporting
7.1 Monitoring and Reporting Schedule
Monitoring will be undertaken through daily and weekly inspections and may be undertaken by a variety of
personnel including the Construction Contractor, APA’s environmental representative and third-party
environmental inspectors. It is the Construction Contractor Project Manager that is responsible for ensuring the
scheduled monitoring is undertaken in accordance with this CNVMP. The inspectors will be required to report
compliance to the CNVMP to the APA Project Manager, in the form of checklists. These checklists are provided
as an appendix to the overarching CEMP.
The Project Construction Contractor will additionally prepare a weekly report, separate to the weekly inspection
checklist, which will include a summary of the results of the daily and weekly inspections, results of the attended
noise monitoring, and summary any complaints. More information on the weekly reporting requirements for the
project as a whole is provided in the overarching CEMP.
Table 12 lists all of the environmental controls for this CNVMP, along with associated measurement criteria,
timing for monitoring and reporting, and the person responsible for the monitoring and reporting. The following
sections provide details specific to attended noise monitoring which is part of the monitoring program for this
CNVMP.
7.1.1 Attended noise monitoring procedure
The measurements will be conducted in accordance with the procedures outlines in Australian Standard AS 1055
Acoustics – Description and measurement of environmental noise and in accordance with methods outlined in the
NSW Industrial Noise Policy (INP). The following points should be followed when conducting noise monitoring:
- A field calibration should be conducted before and after measurements;
- The sound level meters must be set to an A-weighting and Fast;
- The sound level meters sample period should be set to 15 minutes;
- The following descriptors should be measured as a minimum: LA1, LAeq and LA90; and
- Measurements should be conducted a minimum of 3 metres from the nearest façade and/or solid fence/wall.
If it is not possible to do this, corrections for façade reflection should be applied to the measurement results.
7.1.2 Monitoring of equipment procedure
In addition to the residential noise monitoring procedures described above, the following equipment
measurements will be undertaken:
- Noise emission levels of all critical items of mobile plant and equipment will be checked for compliance by
the site environmental officer for compliance with noise limits appropriate to those items prior to the
equipment going into regular service;
- For equipment and mobile plant used for construction works, LAeq measurements will be taken at an
appropriate distance, normally 7m and converted to a Sound Power Level;
- An Equipment Noise Certificate, presenting relevant sound levels of the equipment tested, will be issued by
the Construction Contractor’s site environmental officer within the first week of the equipment commencing
at the construction site.
The equipment sound power levels will be compared to the levels contained in Table 8. If noise checks on any
equipment result in a prediction of non-compliance, noise mitigation strategies to achieve compliance will be
developed.
7.1.3 Equipment
All acoustic instrumentation employed throughout the monitoring programme will comply with the requirements of
AS IEC 61672.1-2004 Electroacoustics - Sound level meters – Specifications. All sound level meters must have
current calibration certificate from a NATA accredited laboratory in accordance with NATA guidelines. Instrument
calibration shall be checked before and after each measurement survey, with the variation in calibrated levels not
exceeding ±0.5 dB.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
19
7.1.4 Attended noise monitoring schedule
Table 11 below provides a preliminary monitoring schedule for construction.
Table 11 Construction noise monitoring schedule
Monitoring
Schedule Action Reporting
During first month
of construction
Complete one round of operator-attended 15 minute noise monitoring on
separate days at site boundaries and closest residences
Reporting as
detailed in
Section
7.1.5 to be
included in
monthly
report.
Carry out equipment noise level checks on all critical items of plant and
issue Equipment Noise Certificates
During
subsequent
months of
construction
period
Carry out equipment noise level checks on any new (untested) items of
critical plant and issue Equipment Noise Certificates
7.1.5 Reporting on attended noise monitoring
The following information must be included in the weekly reports when applicable:
- Field calibration results (before and after measurements)
- Measurement times and dates
- Qualitative description of the noise environment during the measurements
- LA1, LAeq and LA90 levels
- Meteorological conditions during the measurements
- Estimation of or recorded noise contribution from other major noise sources.
The Construction Contractor Project Manager shall establish and maintain a system of records which provides full
documentation of all noise monitoring results, complaint handling and responses to non-compliances. The
Construction Contractor Project Manager shall establish and maintain procedures for the collection, indexing,
filing, storage and maintenance of the records.
7.2 Auditing
The Independent Environmental Representative will undertake monthly audits to ensure compliance to the
CNVMP. This will involve checking the daily, weekly and monthly checklists have been completed and evaluation
of compliance with the CNVMP. This includes analysis of the attended noise measurements against noise
management objectives in 6.2.
The Independent Environmental Representative will report the outcomes of the audit to the APA Project Manager.
Any external auditing is to be undertaken in accordance with the Compliance Tracking Program.
7.3 Non-compliance and Corrective Action
Non-compliances identified through the daily and weekly inspections should be responded to with a corrective
action. This is the responsibility of the Construction Contractor Project Manager. Corrective actions should be
documented in the inspection checklist.
If a non-compliance has been identified during monthly audits that has not been corrected, the Independent
Environmental Representative will issue a non-conformance notification to the APA Project Manager. The APA
Project Manager will issue a request for corrective action to the Construction Contractor Project Manager who will
action the request as appropriate and provide updates on progress in addressing the issue at contractor meetings
or as requested by the APA Project Manager.
The Construction Contractor Project Manager is responsible for the initial reporting of significant non-compliances
with this CEMP or relevant legislation to the APA Project Manager. The APA Senior Programme Manager will
report such events to the relevant statutory authorities in accordance with legislative requirements.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
20
8.0 Complaints Management
In the event of an environment-related complaint from the community regarding noise, the Independent
Environmental Representative will notify the APA Project Manager. The APA Project Manager may issue a
request for corrective action to the Construction Contractor Project Manager who will action the request as
appropriate. A response should be provided to the complainant within 24 hours. Corrective actions may involve
supplementary monitoring to identify any non-compliances, and/or may involve modification of construction or
operational techniques to avoid any recurrence or minimise impacts. Complaints will be managed on an individual
basis. Corrective actions which do not adversely impact the construction programme will be implemented as a
priority.
Responses and actions to manage the complaint will be documented through the Incident Management process.
All incidents will be recorded and managed according to APA’s Management of Incidents procedure (MAN 297).
When a complaint is made, the Independent Environmental Representative will complete an Environmental
Incident Report Form to record details of the occurrence and actions taken. Where applicable, completed forms
should detail the following:
- The date and time of the complaint;
- The method by which the complaint was made;
- Any personal details of the complainant which were provided by the complainant or, if no such details were
provided, a note to that effect;
- The nature of the complaint;
- Description of noise source that is the subject of complaint, duration of event;
- Location of complainant during time of incident, and general area in which the noise source was located;
- Identification of project related noise activities and locations that could have or are known to have
contributed to the incident;
- If known, identification of non-project related noise emission activities and location at time of incident;
- Meteorological conditions at the time of the incident;
- The action taken in relation to the complaint;
- Any follow-up contact with the complainant; and
- If no action was taken, the reason why no action was taken.
All records are to be kept in a legible form, or in a form that can readily be reduced to a legible form and kept for
at least 4 years after the complaint or event to which they relate took place. A complaints register should also be
kept up to date with details of any complaints.
The Independent Environmental Representative will make available a report on complaints received to the
relevant Government Agencies upon request. A summary will be included in the monthly environmental report.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
21
9.0 Sub-Plan Review
This sub-plan is a living document which should be revised and updated as necessary throughout the construction
phase of the Project and in accordance with the pipeline licence requirements.
At a minimum it shall be reviewed by the Construction Contractor Project Manager on a monthly basis and if
necessary revised.
The review should assess all relevant information to the CNVMP including but not limited to:
- Historical monitoring data;
- Changes in land use; and
- Incidents related to noise emission exceedance and complaints.
The CNVMP would need to be modified to reflect any variation in monitoring frequency or variation in the
monitoring procedure (for example, to take account of a new noise issue being introduced to site).
The CNVMP should be viewed as a live document and updated as necessary, noting that revision of the NMP
may result in the monitoring regime increasing or decreasing.
All revisions of this document will be prepared in consultation with APA and relevant regulatory authorities, and
are to be approved by APA Project Manager. For each revision, the Quality Information table at the beginning of
this document should be updated.
All personnel indicated in Table 10 should be made aware of revisions to the CEMP, and regulatory authorities
notified where relevant.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
22
10.0 Summary of Environmental Controls Table 12 Summary of environmental controls including implementation and monitoring and reporting requirements.
Control
Ref # Environmental Control
Implementation Monitoring and Reporting
Timing Person
Responsible
Measurement
Criteria
Monitoring
Schedule Reporting Person Responsible
NV1 All potentially affected residences as identified in
Error! Reference source not found. will be
informed by letterbox drop of the construction
works including working hours to be adhered to,
and the level and duration of noise to expect
during construction.
At least 14
days prior to
construction
APA Land and
Environment
Manager
Letterbox drop is
recorded in the
environmental
consultation log.
Two weeks
prior to
construction
N/A – notify
APA Land
and
Environment
Manager and
APA Project
Manager
Construction Contractor
Project Manager
NV2 All potentially affected residences as identified in
Error! Reference source not found. will be kept
informed of any significant changes to
construction activities or if out of hours of work is
required.
As required APA Land and
Environment
Manager
Environmental
consultation log is
maintained and kept
up-to-date.
Weekly
inspection
Weekly
checklist
Construction Contractor
Project Manager
NV3 Any complaints received related to noise or
vibration will be dealt with in accordance with
Section 7.3.
Construction APA Project
Manager
Record of
complaints,
investigations and
responses in
Environmental
Incidents Reports
and complaints
register.
Weekly
inspection
Weekly
checklist
Construction Contractor
Project Manager
NV4 All site personnel will be instructed during a
general induction as to their responsibilities in
minimising noise and adhering to the noise
minimisation measures.
Construction Construction
Contractor
Project
Manager
Records of
inductions in training
register.
Weekly
inspection
Weekly
checklist
Construction Contractor
Project Manager
NV5 Equipment operators are to be report any faulty
equipment to Construction Contractor Site
Supervisor.
Construction Construction
Contractor Site
Supervisor
Records of faulty
equipment in vehicle
maintenance
register.
Monthly
inspection
Weekly
checklist
Construction Contractor
Project Manager
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
23
Control
Ref # Environmental Control
Implementation Monitoring and Reporting
Timing Person
Responsible
Measurement
Criteria
Monitoring
Schedule Reporting Person Responsible
NV6 Works will be undertaken during the hours of:
a) 7:00am to 6:00pm daily for a maximum
period of 28 days at a time, separated by
a minimum respite period of nine days;
and
b) at no time on public holidays, unless
prior approval received from DP&E and
works are carried out in accordance with
the Out of Hours Work Protocol
identified within the CEMP.
Construction Construction
Contractor Site
Supervisor
No work is
undertaken outside
allowed hours.
Daily
inspection
Daily
checklist
Construction Contractor
Project Manager
NV7 Activities resulting in impulsive or tonal noise emission (such as rock blasting, pile driving) shall only be undertaken:
a) between the hours of 8:00 am to 5:00
pm Monday to Friday;
b) between the hours of 8:00 am to 1:00
pm Saturday; and
c) in continuous blocks not exceeding three
hours each with a minimum respite from
those activities and works of not less
than one hour between each block.
Construction Construction
Contractor Site
Supervisor
No activities
resulting in impulsive
or tonal noise
emission is
undertaken outside
allowed hours.
Daily
inspection
Daily
checklist
Construction Contractor
Project Manager
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
24
Control
Ref # Environmental Control
Implementation Monitoring and Reporting
Timing Person
Responsible
Measurement
Criteria
Monitoring
Schedule Reporting Person Responsible
NV8 In the case of an activity that requires work to be undertaken outside the specified hours, written approval must be sought from the Secretary. Any request to alter the hours of construction shall be:
a) considered on a case-by-case basis;
b) accompanied by details of the nature
and need for activities to be conducted
during the varied construction hours and
any other information necessary to
reasonably determine that activities
undertaken during the varied
construction hours will not adversely
impact on the acoustic amenity of
receptors in the vicinity of the site; and
c) commenced only affected residential
receivers are informed of the timing and
duration of work approved under this
condition at least 48 hours before that
work commences.
Prior to varied
hours of
construction
Construction
Contractor Site
Supervisor
Written approval
from the Secretary is
obtained.
Weekly
inspection
Weekly
checklist
Construction Contractor
Project Manager
NV9 The noise levels of plant and equipment must
have operating Sound Power or Sound Pressure
Levels compliant with the criteria in Table 8.
Construction Construction
Contractor
Project
Manager
Attended noise
measurements as
per Section 7.1.1 to
7.1.4.
As per
noise
monitoring
schedule in
Section
7.1.3.
Monthly
report
Construction Contractor
Project Manager
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
25
Control
Ref # Environmental Control
Implementation Monitoring and Reporting
Timing Person
Responsible
Measurement
Criteria
Monitoring
Schedule Reporting Person Responsible
NV10 Vibration intensive activities should not be located
closer to sensitive receptors than the safe
working distances presented in Table 6.
Construction Construction
Contractor Site
Supervisor
Vibration intensive
activities are not
located closer to
sensitive receptors
than the safe
working distances
presented in Table
6.
Daily
inspection
Daily
checklist
Construction Contractor
Project Manager
NV11 Construction equipment will be fitted with
adequate noise and vibration control equipment
where possible. Measures include earth moving
equipment fitted with residential class mufflers,
and acoustic enclosures for any diesel generators
and/or air compressors.
Construction Construction
Contractor
Project
Manager
Construction
equipment fitted with
noise and vibration
control equipment
where possible.
Monthly
inspection
Monthly
checklist
Construction Contractor
Project Manager
NV12 Any equipment not in use for extended periods
during construction work will be switched off.
Construction Construction
Contractor Site
Supervisor
No equipment is left
running without
active use for more
than 15 minutes.
Daily
inspection
Daily
checklist
Construction Contractor
Project Manager
NV13 All vehicles and equipment will be regularly
serviced, as per manufactures instructions and
maintained in proper working order.
Construction Construction
Contractor
Project
Manager
Vehicles maintained
in accordance with
manufacturers
requirements.
Records of
equipment
maintenance logged
in vehicle
maintenance
registers.
Monthly
inspection
Weekly
checklist
Construction Contractor
Project Manager
NV14 Ensure deliveries are within the standard hours of
works
Construction Construction
Contractor
Project
Manager
No deliveries occur
outside standard
hours of works.
Daily
inspection
Daily
checklist
Construction Contractor
Project Manager
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
26
Control
Ref # Environmental Control
Implementation Monitoring and Reporting
Timing Person
Responsible
Measurement
Criteria
Monitoring
Schedule Reporting Person Responsible
NV15 Simultaneous operation of noisy plant will be
avoided wherever practicable.
Construction Construction
Contractor Site
Supervisor
Attended noise
measurements as
per Section
Attended noise
measurements as
per Section 7.1.1 to
7.1.4 to confirm all
measures to reduce
noise emissions are
effective and noise
management levels
are not exceeded.
As per
noise
monitoring
schedule in
Section
7.1.3.
Monthly in
the weekly
report as
applicable.
Construction Contractor
Project Manager
NV16 Wherever practicable, noisy equipment will be:
a) Positioned behind structures that act as
barriers to identified receptors
b) Positioned at the greatest distance from
identified receptors
c) Oriented to directed noise emissions
away from identified receptors
Construction Construction
Contractor Site
Supervisor
NV17 “Quiet” practices will be employed wherever
practicable when operating equipment.
Construction Construction
Contractor Site
Supervisor
NV18 Any noise construction activities will be completed
in the shortest time possible.
Construction Construction
Contractor Site
Supervisor
NV19 There will be no swearing or unnecessary
shouting or loud stereos/radios on site.
Construction Construction
Contractor Site
Supervisor
NV20 There will be no dropping of materials from
heights, throwing of metal items, or slamming of
doors.
Construction Construction
Contractor Site
Supervisor
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
Appendix A
Glossary
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
A-1
Appendix A Glossary
Term Description
A Weighted decibels [dB(A]) The A weighting is a frequency filter applied to measured noise levels to
represent how humans hear sounds. The A-weighting filter emphasises
frequencies in the speech range (between 1kHz and 4 kHz) which the
human ear is most sensitive to, and places less emphasis on low
frequencies at which the human ear is not so sensitive. When an overall
sound level is A-weighted it is expressed in units of dB(A).
Ambient noise The all-encompassing noise at a point composed of sound from all sources
near and far.
Assessment background level
[ABL]
The overall background level for each day, evening and night period for
each day of the noise monitoring.
Background noise The underlying level of noise present in the ambient noise when
extraneous noise (such as transient traffic and dogs barking) is removed.
The L90 sound pressure level is used to quantify background noise.
Day The period from 0700 to 1800 h Monday to Saturday and 0800 to 1800 h
Sundays and Public Holidays.
Decibel [dB] The measurement unit of sound.
Decibel scale The decibel scale is logarithmic in order to produce a better representation
of the response of the human ear. A 3 dB increase in the sound pressure
level corresponds to a doubling in the sound energy. A 10 dB increase in
the sound pressure level corresponds to a perceived doubling in volume.
Examples of decibel levels of common sounds are as follows:
0dB(A)
30dB(A)
40dB(A)
50dB(A)
70dB(A)
80dB(A)
90dB(A)
100dB(A)
110 dB(A)
115dB(A)
120dB(A)
Threshold of human hearing
A quiet country park
Whisper in a library
Open office space
Inside a car on a freeway
Outboard motor
Heavy truck pass-by
Jackhammer/Subway train
Rock Concert
Limit of sound permitted in industry
747 take off at 250 metres
Evening The period from 1800 to 2200 h Monday to Sunday and Public Holidays.
Equivalent continuous sound
level [Leq]
The constant sound level which, when occurring over the same period of
time, would result in the receiver experiencing the same amount of sound
energy.
Frequency [f] The repetition rate of the cycle measured in Hertz (Hz). The frequency
corresponds to the pitch of the sound. A high frequency corresponds to a
high pitched sound and a low frequency to a low pitched sound.
Lmax The maximum sound pressure level measured over the measurement
period.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
A-2
Term Description
Lmin The minimum sound pressure level measured over the measurement
period.
L10 The sound pressure level exceeded for 10% of the measurement period.
For 10% of the measurement period it was louder than the L10.
L90 The sound pressure level exceeded for 90% of the measurement period.
For 90% of the measurement period it was louder than the L90.
Night The period from 2200 to 0700 h Monday to Saturday and 2200 to 0800 h
Sundays and Public Holidays.
Rating background level
[RBL]
The overall background level for each day, evening and night period for the
entire length of noise monitoring.
Sound power level The total sound emitted by a source.
Sound pressure level The amount of sound at a specified point.
Traffic noise The total noise resulting from road traffic. The Leq sound pressure level is
used to quantify traffic noise.
*Definitions of a number of terms have been adapted from Australian Standard AS1633:1985 “Acoustics –
Glossary of terms and related symbols”, the EPA’s NSW Industrial Noise Policy and Road Noise Policy.
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
Appendix B
Noise Contours and Receivers
AECOM
Young to Wagga Wagga Looping Pipeline Stage 2 (Bethungra to Young)
Construction Noise and Vibration Management Plan
09-Nov-2015 Prepared for – APT Management Services Pty Ltd – ABN: 58 091 668 110
B-1
Appendix B Noise Contours and Receivers
!( !( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö ×Ö
×Ö×Ö
×Ö
×Ö×Ö
×Ö ×Ö×Ö
×Ö
×Ö×Ö ×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
BLAYNEY DEMONDRILLE RLY
MM aa ii mm uurraa RRdd
Scen
ic Rd
Scen
ic Rd
Henry Lawson Way
Henry Lawson Way
BURRANGONG
MAIMURU
YOUNG3
7
6
52
4 1.1
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
1
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!( !(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö×Ö×Ö
×Ö×Ö×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö×Ö
×Ö
×Ö×Ö
×Ö×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö
BURRANGONG
BLAYNEY DEMONDRILLE RLY
MMaaiimmuurraa RRdd
Henr
y Law
son
Way
Henr
y Law
son
Way
MMii ll vvaa llee RRdd ((TTeemmoorraa YYoouunngg RRdd))
BERTHONG
BURRANGONG
MAIMURU
YOUNG
8
7
15
14
13
12 11 109
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
2
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
MMiillvvaallee RRdd ((TTeemmoorraa
YYoouunngg RRdd))
BERTHONG
BURRANGONG
MAIMURU
16
15
22 21
20
19
18
17
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
3
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
BERTHONG
NUBBA
27
26
25
24
2330
2928
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
4
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
Olympic HwyOlympic Hwy
BERTHONG
COOTAMUNDRA
NUBBA
WALLENDBEEN
3736
31
30
3534 33 32
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
5
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(
!(!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!( !(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!( !(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!( !(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!( !(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(!(
!(!(
!(
!(!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!( !(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö ×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
MAINSOUTHERN
RLY
SSttoocckkiinnbbiinnggaall WWaalllleennddbbeeeennRRdd
((BBuurrlleeyy GGrriiffffiinnHHwwyy))
COOTAMUNDRA
WALLENDBEEN
45
3944 3843
42
4140
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
6
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!( !(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(!(!(
!(!(
!(!(
!(
!(!( !(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!( !(!( !(
!( !(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(!(
!(!(
!(
!(
!(!(
!(
!(
!( !(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!( !(!( !(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(!(
!(
!(!(
!(!(
!(
!(
!(
!(!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(!(!(
!(
!(
!(!(
!(
!( !(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!( !(
!( !(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!( !(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!( !(
!(
!(!(
!(!(
!(
!(
!( !(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö ×Ö
×Ö
×Ö
MAIN SOUTHERN RLY
Berthong Rd
Berthong Rd
West Jindalee Rd
West Jindalee Rd
COOTAMUNDRA
4645
5049
48
52
47
51
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
7
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(!(
!( !(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!( !(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(!(!(
!(!(
!(!(
!(
!(!( !(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!( !(!( !(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!( !(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!( !(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(!(
!(!(
!(
!(!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!( !(
!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
ÝÝ
IH
ñ
Ý
Ý
Ý ÝÝ
ñ
I$
å
å
å
å
å
å
å
å
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö ×Ö
×Ö
×Ö
×Ö×Ö ×Ö
×Ö ×Ö
×Ö×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
MAIN SOUTHERN RLY
COOTAMUNDRA LAKE CARGELLIGO RLY
HHaarrooll ddCCoonnkkee yy DD rrDillon Av
Dillon Av
SSaalltt CCllaayy RRddWW
South B
ertho
ng R
d
South B
ertho
ng R
d
OOlldd TTeemmoorraa RRdd
West Jindalee RdWest Jindalee Rd
BB ee rr tt hh oo nn gg RR dd
Dirnaseer Rd
Dirnaseer Rd
Temo
ra R
dTe
mora
Rd
SS tt oocc kk ii nn bb ii nn gg aa ll RR dd (( TT ee mm oo rr aa RR dd ))
Temo
ra S
tTe
mora
St
COOTAMUNDRA57
53
56 5554
60 5958
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
8
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(!(
!( !(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!( !(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(!( !(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!( !(!( !(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!( !(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(!(
!(!(
!(!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(!(
!(!(
!(
!(!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(!(
!(
!(!(
!(!(
!(
!(
!(
!(!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(!(!(
!(
!(
!(!(
!(
!(!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(!( !(
!(
!(!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
×Ö×Ö
×Ö
×Ö
MAIN SOUTHERN RLY
DDiirrnnaasseeeerr RRdd
Frampton RdFrampton Rd
COOTAMUNDRA
67
66
65 64 63 62 61 60
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
9
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö
×Ö×Ö
MAIN SOUTHERN RLYMAIN SOUTHERN RLY
Eage
r St
Eage
r St
FFr ra ammp pttoonn
RRdd
Olympic Hwy
Olympic Hwy
BETHUNGRA
COOTAMUNDRA
DIRNASEER
6766
70 69 68
0 0.5 10.25km
YOUNG - WAGGA WAGGA PIPELINE SECTION 2Construction Noise Contours and Receivers within the Noise Affected Area
24 Sep 2015
Source: LPMA (2010), StreetPro (2009)60431900
¯
Pg.
FERNDALE COOTAMUNDRA
WALLENDBEEN
BERTHONG
YOUNGMEMAGONG MAIMURU
GDA94 - MGA Zone 55
10
AECO
M P:\
CBR\
6043
1900
\4. Te
ch w
ork ar
ea\4.
7_GI
S\Ma
ps\R
evise
d_Ma
ps\15
0918
_G00
4_01
_Aco
ustic
s_wi
th_ne
w_ae
rial_r
evise
d.mxd
Draf
ted: 2
4/09/2
015
Construction NoiseContour Levels (dB)
75654540
×Ö Residence/Homesteadå EducationI$ HospitalIH Library
ñ MuseumÝ Place Of Worship
Active Recreation
Gas Pipeline Section 2!( 100m Interval Points
HighwayMain RoadConnector RoadLocal RoadRailway
BridgeSuburbLocality