Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

  • Upload
    -

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    1/37

    Construction Crane Safety(new requirements 2010)

    September 2, 2010

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    2/37

    Why?

    Crane accidents killed an average of 78people per year between 2003 and 2005

    The new standard is located at

    http://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-construction#h-15

    OSHA expects the final standard toprevent 22 fatalities and 175 non-fatalinjuries each year.

    http://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-construction
  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    3/37

    When?

    Intention to develop the rule in July 2002.

    Used negotiated rulemaking committeeconsisting both industry and labor.

    The committee completed its work in 2004. Released July 28, 2010

    Published August 9, 2010

    Effective November 8, 2010

    Phased in over four years August 9, 2014 Certification of operators phased in over four years.

    No grandfathering of those past certification.

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    4/37

    Key Hazards

    Four main causes of worker death and

    injury:

    Electrocution,

    Crushed by parts of the equipment,

    Struck-by the equipment/load, and

    Falls. (See Subpart M 1926.500-503)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    5/37

    Largest Impact

    Mandatory crane operator certification -qualification

    200,000 construction crane operators in

    the industry OSHA allowing four years to meet the

    certification requirement.

    It will take time for certifying organizationsto gain enough capacity to cover so manyoperators.

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    6/37

    Other Significant Requirements

    Use of synthetic slings in accordance with

    the manufacturers instructions during

    assembly/disassembly work;

    Assessment of ground conditions;

    Procedures for working in the vicinity of

    power lines.

    Pre-erection inspection of tower crane

    parts;

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    7/37

    OSHA State - Local

    Employers must comply with local and

    state operator licensing requirements

    which meet the minimum criteria specified

    in 1926.1427.

    Some state had existing Crane standards

    that exceeded the old standard. In state

    plan states, please see the rules for thatstate.

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    8/37

    Who Pays?

    Employers must pay for certification orqualification of their currently uncertified orunqualified operators. 1926.1427 (a)(4)

    Reasonable that employees, who have alreadybeen sufficiently trained in crane operation andmay have many years' experience, certainly

    need no more than a short preparation tosuccessfully pass the crane operator certificationtests. FR Preamble

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    9/37

    Crane or Not Crane?

    Functional description

    Can hoist,

    Lower and

    Horizontally move asuspended load

    Forklifts configured to hoist

    and lower (by means of a

    winch OR hook) and

    horizontally move a suspended

    load are covered

    Backhoes are excluded even if

    used like a crane.1926.1400

    (c)(2)

    Forklift with attached

    boom. 1926.1400 (c)(8)

    See 1926.1441 if using

    equipment with a rated

    hoisting/lifting capacity of 2,000

    pounds or less

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    10/37

    10

    OPTION 1:Accredited testing organization

    OPTION 2:

    Employer qualification program OPTION 3:

    U.S. military

    OPTION 4:State/local govt license

    Operator Qualifications and

    Certifications - 4 Options

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    11/37

    11

    Operator Qualifications and

    Certifications (contd)

    Accredited testing

    organization

    YES * 5 years

    Employer Qualification

    Program

    NO 5 years

    US Military license NO * Set by issuing

    entity

    State/local license NO *

    Valid only

    in entitys

    jurisdiction

    Set by issuing

    entity, not > 5years

    Portable Valid

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    12/37

    Written Certification Tests

    Administered in any language understoodby the operator candidate.

    Test must cover:

    Controls/performance characteristics

    Calculate capacity (w/ or w/out calculator)

    Preventing power line contact

    Ground support Read and locate info in operating manual

    Appendix Q subjects

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    13/37

    Practical Examination

    Must be well designed and sufficiently

    comprehensive

    Must have the demonstrated the skills and

    knowledge needed to operate the equipmentsafely.

    An operator's ability to handle unusual worksite

    conditions, such as adverse weather or working

    on crowded jobsites, are hazards that are not

    commonly part of this exam.

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    14/37

    14

    1926.1408 Power Lines

    Step 1: Identify Work

    Zone

    Work Zone = Marking

    boundaries OR 360 degrees around

    crane up to maximum

    working radius

    Make the power linehazard assessment

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    15/37

    15

    Could you get within 20

    feet of power line?

    YES NO

    Option #1

    Deenergize &

    GroundEncroachment

    Prevention measures

    Option #3

    Ask Utility for

    Voltage and

    Use Table A

    (with minimum

    clearance distance)

    Option #2

    20 foot

    clearance

    No further

    action

    Planning meeting

    If tag lines used Non-conductive

    Elevated warning lines, barricade

    or line of signs

    PLUS (Choose one):

    Proximity alarm, spotter, warning

    device, range limiter, or insulating link

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    16/37

    16

    Table A Minimum Clearance Distances

    Voltage (nominal, kV,

    alternating current)

    Minimum clearance

    distance (feet)

    up to 50 10

    over 50 to 200 15

    over 200 to 350 20over 350 to 500 25

    over 500 to 750 35

    over 750 to 1000 45

    over 1000 (as established by the power lineowner/operator or registered

    professional engineer who is a

    qualified person with respect to

    electrical power transmission and

    distribution)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    17/37

    Intentionally Working Closer

    Than Table A Zone 1910.1410 Paragraph (b) requires the employer to consult

    with the utility owner/operator before decidingthat it infeasible to deenergize and ground thelines or relocate them.

    Employer can establish this distance by eitherhaving the utility owner/operator determinethe minimum clearance distance that must bemaintained or by having a registeredprofessional engineerwho is a qualifiedperson with respect to electrical transmissionand distribution determine the minimumclearance distance that must be maintained.

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    18/37

    18

    Must show:

    Staying outside zone

    is infeasible Infeasible to

    deenergize and

    ground

    Intentionally Working Closer Than Table A Zone

    All of the following are required:

    1. PL owner sets minimum approachdistance

    2. Planning meeting procedures

    3. Dedicated spotter

    4. Elevated warning line or barricade

    5. Insulating link/device

    6. Non-conductive rigging

    7. Range limiter (if equipped)

    8. Non-conductive tag line (if used)

    9. Barricades - 10 feet from equipment

    10. Limit access to essential employees

    11. Ground crane

    12. Deactivate automatic re-energizer

    1926.1410

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    19/37

    Assembly Disassembly

    Employers must use a qualified rigger for

    rigging operations during assembly &

    disassembly

    Two options:

    Manufacturer procedures or

    Employer procedures (criteria requirements)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    20/37

    Assembly/Disassembly Supervisor

    Must understand procedures

    Review procedures (unless theyve used

    them before)

    Check that crew members understand

    their tasks, hazards

    Follow manufacturers prohibitions When using outriggers - fully extended or

    deployed per the load chart

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    21/37

    21

    A/D supervisor addresses 12 key hazards,

    including:

    Adequate site and ground conditions

    Sufficient blocking for load and stability

    Suitable boom and jib pick points

    Identify center of gravity

    Stability for pin removal Consider wind speed and weather

    Assembly/Disassembly (contd)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    22/37

    22

    The suitability of blocking material

    Verification of the loads for assist cranes

    Snagging of cables or components Struck by counter weights

    Boom hoist brake failure

    Loss of backwards stability

    Assembly/Disassembly (contd)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    23/37

    Qualified Rigger

    1926.1404 (r)

    Meets the criteria for a qualified person

    Possession of a recognized degree,certificate, or professional standing, or

    extensive (rigging) knowledge, training

    and experience

    Successfully demonstrated the ability to

    solve/resolve problems (relating to rigging)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    24/37

    Tower Cranes

    Employers must perform a pre-erection

    inspection of tower cranes.

    Extensive requirements under 1926.1435

    and other sections.

    Beyond scope of this presentation

    Numerous accidents such as Seattle in

    85, San Francisco in 89, Manhattan in 08,

    Hong Kong in 08, New York in 06,

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    25/37

    Ground Conditions

    1926.1402 (b)

    Ground conditions must be firm, drained,and graded

    Use supporting materials,

    Use equipment manufacturer'sspecifications for adequate support

    Use equipment manufacturer'sspecifications for degree of level of theequipment

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    26/37

    Controlling Entity

    1926.1402 (c)(3)

    Must ensure that ground preparations are safe

    Must inform the user of the equipment and the

    operatorof the location of known hazardsbeneath the equipment set-up area (such as

    voids, tanks, utilities)

    If there is no controlling entity then the employerthat has authority at the site to make or arrange

    for ground preparations must do so.

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    27/37

    27

    Signals

    Signal personwhen requ ired:

    Point of operation not

    in full view of operator

    View of direction oftravel is obstructed

    Site specific safetyconcerns

    1926.1428 Signalperson qualifications

    Signal Types: Hand, voice, audible

    or new

    Only time an operator

    can use a cell phone iswhile lifting as part of aplanned procedure

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    28/37

    28

    Signals (contd.)

    Signal person qualifications

    3rd party qualified

    evaluator

    Yes Yes

    Employer Qualified

    Evaluator

    Yes No

    Qualified how Documentation Portable

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    29/37

    29

    QualificationRequirements:

    Know & understand signals

    Competent in using signals

    Basic understanding of crane

    operation

    Verbal or written test +practical test

    Signals (contd.)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    30/37

    30

    1926.1412 Inspections

    Modified or Repaired/

    adjusted

    Qualified

    Post-assembly Qualified

    Shift Competent

    Monthly Competent

    Annual Qualified

    Type of Inspection: Who Inspects:

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    31/37

    31

    Inspections (contd)

    Shift= visual inspection for apparent

    deficiencies

    Monthly= documented shift inspection

    Annual= comprehensive, every 12 months

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    32/37

    Each Shift Inspection

    1926.1412 (d)

    Apparent deficiencies

    Control and Drive

    mechanisms Hydraulics

    Hooks

    Wire Rope

    Electrical

    Ground Conditions

    Levelness of thecrane

    Operator view

    All Safety Devices Operational Aids are

    working

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    33/37

    Operators

    1926.1417 has many requirements. Some highlights are: Must not engage in any activity that diverts his/her

    attention while operating the equipment,

    No cell phones (other than when used for signalcommunications)

    Must not leave the controls while the load issuspended, (four exceptions)

    Must verify that the load is within the rated capacity ofthe equipment (2 methods)

    Must obey a stop (or emergency stop) signal,irrespective of who gives it.

    Told of any employee entering the crane work area1926.1424(a)(3)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    34/37

    Employer Training

    1926.1430 Employee

    Training Issues

    Powerline safety

    Signal persons

    Operators

    Competent Person

    Qualified Persons

    Crush Pinch pointhazards

    Tagout for repair

    Must confirm that the

    employee understands

    the information provided

    in the training

    Provide the training at nocost to the employee

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    35/37

    Work Area Control

    1926.1424

    Train each employee assigned to work on

    or near the equipment

    Erect and maintain control lines, warning

    lines, railings or similar barriers to mark

    the boundaries of the hazard area (1

    Exception)

  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    36/37

    36

    Resources

    Cranes and Derricks in Construction Final Rule http://www.osha.gov/cranes-derricks/index.html

    Associated Training Service Network

    http://www.operator-school.com/

    National Commission for the Certification of Crane Operators http://www.nccco.org/

    National Association of Heavy Equipment Training Schools

    http://www.heavy-equipment-school.com/

    North American Crane Bureau Group

    http://www.cranesafe.com/history.htm

    California Crane School

    http://www.californiacraneschool.com/

    http://www.osha.gov/cranes-derricks/index.htmlhttp://www.operator-school.com/http://www.nccco.org/http://www.heavy-equipment-school.com/http://www.cranesafe.com/history.htmhttp://www.californiacraneschool.com/http://www.californiacraneschool.com/http://www.cranesafe.com/history.htmhttp://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.nccco.org/http://www.operator-school.com/http://www.operator-school.com/http://www.operator-school.com/http://www.osha.gov/cranes-derricks/index.htmlhttp://www.osha.gov/cranes-derricks/index.htmlhttp://www.osha.gov/cranes-derricks/index.html
  • 8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)

    37/37

    Further

    This ppt was prepared by John Newquist as a preliminary aid for the newstandard. Please check the OSHA website for Crane Outreach Material thatwill be developed in the coming months.

    This is not an official OSHA publication. Those will be on the OSHA.govwebsite.

    [email protected] is my email if you see any errors

    312-353-5977 Brian Sturtecky is our Region V Certified Crane Inspector and has provided

    key assistance on this standard. He can be reached at 312-353-2220.

    Several slides were obtained from the OSHA Training Institute from theirWebinar August 30, 2010.

    Every aspect from inspecting, repairing, operating, rigging and signalingthese cranes require extensive training. Please take classes with hands on

    training if you are expected to perform any of these activities. I want to thank Brian, Lisa, Tom, Bill, Cathy for all their assistance in

    answering questions and providing issues that are coming from the public.

    mailto:[email protected]:[email protected]