Upload
-
View
214
Download
0
Embed Size (px)
Citation preview
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
1/37
Construction Crane Safety(new requirements 2010)
September 2, 2010
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
2/37
Why?
Crane accidents killed an average of 78people per year between 2003 and 2005
The new standard is located at
http://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-construction#h-15
OSHA expects the final standard toprevent 22 fatalities and 175 non-fatalinjuries each year.
http://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-constructionhttp://www.federalregister.gov/articles/2010/08/09/2010-17818/cranes-and-derricks-in-construction8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
3/37
When?
Intention to develop the rule in July 2002.
Used negotiated rulemaking committeeconsisting both industry and labor.
The committee completed its work in 2004. Released July 28, 2010
Published August 9, 2010
Effective November 8, 2010
Phased in over four years August 9, 2014 Certification of operators phased in over four years.
No grandfathering of those past certification.
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
4/37
Key Hazards
Four main causes of worker death and
injury:
Electrocution,
Crushed by parts of the equipment,
Struck-by the equipment/load, and
Falls. (See Subpart M 1926.500-503)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
5/37
Largest Impact
Mandatory crane operator certification -qualification
200,000 construction crane operators in
the industry OSHA allowing four years to meet the
certification requirement.
It will take time for certifying organizationsto gain enough capacity to cover so manyoperators.
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
6/37
Other Significant Requirements
Use of synthetic slings in accordance with
the manufacturers instructions during
assembly/disassembly work;
Assessment of ground conditions;
Procedures for working in the vicinity of
power lines.
Pre-erection inspection of tower crane
parts;
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
7/37
OSHA State - Local
Employers must comply with local and
state operator licensing requirements
which meet the minimum criteria specified
in 1926.1427.
Some state had existing Crane standards
that exceeded the old standard. In state
plan states, please see the rules for thatstate.
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
8/37
Who Pays?
Employers must pay for certification orqualification of their currently uncertified orunqualified operators. 1926.1427 (a)(4)
Reasonable that employees, who have alreadybeen sufficiently trained in crane operation andmay have many years' experience, certainly
need no more than a short preparation tosuccessfully pass the crane operator certificationtests. FR Preamble
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
9/37
Crane or Not Crane?
Functional description
Can hoist,
Lower and
Horizontally move asuspended load
Forklifts configured to hoist
and lower (by means of a
winch OR hook) and
horizontally move a suspended
load are covered
Backhoes are excluded even if
used like a crane.1926.1400
(c)(2)
Forklift with attached
boom. 1926.1400 (c)(8)
See 1926.1441 if using
equipment with a rated
hoisting/lifting capacity of 2,000
pounds or less
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
10/37
10
OPTION 1:Accredited testing organization
OPTION 2:
Employer qualification program OPTION 3:
U.S. military
OPTION 4:State/local govt license
Operator Qualifications and
Certifications - 4 Options
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
11/37
11
Operator Qualifications and
Certifications (contd)
Accredited testing
organization
YES * 5 years
Employer Qualification
Program
NO 5 years
US Military license NO * Set by issuing
entity
State/local license NO *
Valid only
in entitys
jurisdiction
Set by issuing
entity, not > 5years
Portable Valid
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
12/37
Written Certification Tests
Administered in any language understoodby the operator candidate.
Test must cover:
Controls/performance characteristics
Calculate capacity (w/ or w/out calculator)
Preventing power line contact
Ground support Read and locate info in operating manual
Appendix Q subjects
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
13/37
Practical Examination
Must be well designed and sufficiently
comprehensive
Must have the demonstrated the skills and
knowledge needed to operate the equipmentsafely.
An operator's ability to handle unusual worksite
conditions, such as adverse weather or working
on crowded jobsites, are hazards that are not
commonly part of this exam.
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
14/37
14
1926.1408 Power Lines
Step 1: Identify Work
Zone
Work Zone = Marking
boundaries OR 360 degrees around
crane up to maximum
working radius
Make the power linehazard assessment
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
15/37
15
Could you get within 20
feet of power line?
YES NO
Option #1
Deenergize &
GroundEncroachment
Prevention measures
Option #3
Ask Utility for
Voltage and
Use Table A
(with minimum
clearance distance)
Option #2
20 foot
clearance
No further
action
Planning meeting
If tag lines used Non-conductive
Elevated warning lines, barricade
or line of signs
PLUS (Choose one):
Proximity alarm, spotter, warning
device, range limiter, or insulating link
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
16/37
16
Table A Minimum Clearance Distances
Voltage (nominal, kV,
alternating current)
Minimum clearance
distance (feet)
up to 50 10
over 50 to 200 15
over 200 to 350 20over 350 to 500 25
over 500 to 750 35
over 750 to 1000 45
over 1000 (as established by the power lineowner/operator or registered
professional engineer who is a
qualified person with respect to
electrical power transmission and
distribution)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
17/37
Intentionally Working Closer
Than Table A Zone 1910.1410 Paragraph (b) requires the employer to consult
with the utility owner/operator before decidingthat it infeasible to deenergize and ground thelines or relocate them.
Employer can establish this distance by eitherhaving the utility owner/operator determinethe minimum clearance distance that must bemaintained or by having a registeredprofessional engineerwho is a qualifiedperson with respect to electrical transmissionand distribution determine the minimumclearance distance that must be maintained.
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
18/37
18
Must show:
Staying outside zone
is infeasible Infeasible to
deenergize and
ground
Intentionally Working Closer Than Table A Zone
All of the following are required:
1. PL owner sets minimum approachdistance
2. Planning meeting procedures
3. Dedicated spotter
4. Elevated warning line or barricade
5. Insulating link/device
6. Non-conductive rigging
7. Range limiter (if equipped)
8. Non-conductive tag line (if used)
9. Barricades - 10 feet from equipment
10. Limit access to essential employees
11. Ground crane
12. Deactivate automatic re-energizer
1926.1410
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
19/37
Assembly Disassembly
Employers must use a qualified rigger for
rigging operations during assembly &
disassembly
Two options:
Manufacturer procedures or
Employer procedures (criteria requirements)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
20/37
Assembly/Disassembly Supervisor
Must understand procedures
Review procedures (unless theyve used
them before)
Check that crew members understand
their tasks, hazards
Follow manufacturers prohibitions When using outriggers - fully extended or
deployed per the load chart
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
21/37
21
A/D supervisor addresses 12 key hazards,
including:
Adequate site and ground conditions
Sufficient blocking for load and stability
Suitable boom and jib pick points
Identify center of gravity
Stability for pin removal Consider wind speed and weather
Assembly/Disassembly (contd)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
22/37
22
The suitability of blocking material
Verification of the loads for assist cranes
Snagging of cables or components Struck by counter weights
Boom hoist brake failure
Loss of backwards stability
Assembly/Disassembly (contd)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
23/37
Qualified Rigger
1926.1404 (r)
Meets the criteria for a qualified person
Possession of a recognized degree,certificate, or professional standing, or
extensive (rigging) knowledge, training
and experience
Successfully demonstrated the ability to
solve/resolve problems (relating to rigging)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
24/37
Tower Cranes
Employers must perform a pre-erection
inspection of tower cranes.
Extensive requirements under 1926.1435
and other sections.
Beyond scope of this presentation
Numerous accidents such as Seattle in
85, San Francisco in 89, Manhattan in 08,
Hong Kong in 08, New York in 06,
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
25/37
Ground Conditions
1926.1402 (b)
Ground conditions must be firm, drained,and graded
Use supporting materials,
Use equipment manufacturer'sspecifications for adequate support
Use equipment manufacturer'sspecifications for degree of level of theequipment
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
26/37
Controlling Entity
1926.1402 (c)(3)
Must ensure that ground preparations are safe
Must inform the user of the equipment and the
operatorof the location of known hazardsbeneath the equipment set-up area (such as
voids, tanks, utilities)
If there is no controlling entity then the employerthat has authority at the site to make or arrange
for ground preparations must do so.
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
27/37
27
Signals
Signal personwhen requ ired:
Point of operation not
in full view of operator
View of direction oftravel is obstructed
Site specific safetyconcerns
1926.1428 Signalperson qualifications
Signal Types: Hand, voice, audible
or new
Only time an operator
can use a cell phone iswhile lifting as part of aplanned procedure
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
28/37
28
Signals (contd.)
Signal person qualifications
3rd party qualified
evaluator
Yes Yes
Employer Qualified
Evaluator
Yes No
Qualified how Documentation Portable
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
29/37
29
QualificationRequirements:
Know & understand signals
Competent in using signals
Basic understanding of crane
operation
Verbal or written test +practical test
Signals (contd.)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
30/37
30
1926.1412 Inspections
Modified or Repaired/
adjusted
Qualified
Post-assembly Qualified
Shift Competent
Monthly Competent
Annual Qualified
Type of Inspection: Who Inspects:
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
31/37
31
Inspections (contd)
Shift= visual inspection for apparent
deficiencies
Monthly= documented shift inspection
Annual= comprehensive, every 12 months
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
32/37
Each Shift Inspection
1926.1412 (d)
Apparent deficiencies
Control and Drive
mechanisms Hydraulics
Hooks
Wire Rope
Electrical
Ground Conditions
Levelness of thecrane
Operator view
All Safety Devices Operational Aids are
working
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
33/37
Operators
1926.1417 has many requirements. Some highlights are: Must not engage in any activity that diverts his/her
attention while operating the equipment,
No cell phones (other than when used for signalcommunications)
Must not leave the controls while the load issuspended, (four exceptions)
Must verify that the load is within the rated capacity ofthe equipment (2 methods)
Must obey a stop (or emergency stop) signal,irrespective of who gives it.
Told of any employee entering the crane work area1926.1424(a)(3)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
34/37
Employer Training
1926.1430 Employee
Training Issues
Powerline safety
Signal persons
Operators
Competent Person
Qualified Persons
Crush Pinch pointhazards
Tagout for repair
Must confirm that the
employee understands
the information provided
in the training
Provide the training at nocost to the employee
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
35/37
Work Area Control
1926.1424
Train each employee assigned to work on
or near the equipment
Erect and maintain control lines, warning
lines, railings or similar barriers to mark
the boundaries of the hazard area (1
Exception)
8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
36/37
36
Resources
Cranes and Derricks in Construction Final Rule http://www.osha.gov/cranes-derricks/index.html
Associated Training Service Network
http://www.operator-school.com/
National Commission for the Certification of Crane Operators http://www.nccco.org/
National Association of Heavy Equipment Training Schools
http://www.heavy-equipment-school.com/
North American Crane Bureau Group
http://www.cranesafe.com/history.htm
California Crane School
http://www.californiacraneschool.com/
http://www.osha.gov/cranes-derricks/index.htmlhttp://www.operator-school.com/http://www.nccco.org/http://www.heavy-equipment-school.com/http://www.cranesafe.com/history.htmhttp://www.californiacraneschool.com/http://www.californiacraneschool.com/http://www.cranesafe.com/history.htmhttp://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.heavy-equipment-school.com/http://www.nccco.org/http://www.operator-school.com/http://www.operator-school.com/http://www.operator-school.com/http://www.osha.gov/cranes-derricks/index.htmlhttp://www.osha.gov/cranes-derricks/index.htmlhttp://www.osha.gov/cranes-derricks/index.html8/22/2019 Construction Crane Safety - New Requirements 2010 (Craig Schumann, CH)
37/37
Further
This ppt was prepared by John Newquist as a preliminary aid for the newstandard. Please check the OSHA website for Crane Outreach Material thatwill be developed in the coming months.
This is not an official OSHA publication. Those will be on the OSHA.govwebsite.
[email protected] is my email if you see any errors
312-353-5977 Brian Sturtecky is our Region V Certified Crane Inspector and has provided
key assistance on this standard. He can be reached at 312-353-2220.
Several slides were obtained from the OSHA Training Institute from theirWebinar August 30, 2010.
Every aspect from inspecting, repairing, operating, rigging and signalingthese cranes require extensive training. Please take classes with hands on
training if you are expected to perform any of these activities. I want to thank Brian, Lisa, Tom, Bill, Cathy for all their assistance in
answering questions and providing issues that are coming from the public.
mailto:[email protected]:[email protected]