Construction Coordination Meeting #012 10/01/15

DeLaSalle

Page 1 of 3

Construction Coordination Meeting

Project [419901] – DeLaSalle

McGough Construction 2737 Fairview Avenue North St. Paul, MN 55113-1372 Phone: (651) 633-5050

Meeting No. 012 Date: 10/01/15 Time: 9:30 AM

Meeting Attendance

Company - Attendee Attended Company - Attendee Attended

DeLaSalle - Barry Lieske X McGough – John Haggenmiller X

DeLaSalle - Nicholas Grue McGough – Joe Hassenfritz X

DeLaSalle - Sean McMenomy X McGough – Shannon Kelley

DeLaSalle - John McFarling Halbach - Kevin Halbach X

DeLaSalle - Jay Heffern Nasseff – Steve Treptow

DeLaSalle – Tim Dolan Nasseff – Tom Johnson

DeLaSalle – Timothy J. Keane Nasseff – Andy Hesselink X

DeLaSalle – Brian Lynch Northstar Electric – Pat Reak X

DeLaSalle/Fairview – Pat Stockhaus Wells Concrete – Gary Pooley

HGA-Andy Weyenberg Twin City Glass – Dan Welty X

HGA-Cheryl Amdal X Midwest Fire Protection – Dan Haley

HGA-Greg Anderson

Safety/Security:

• Hard hats and high visibility vests are required on site.

• The next site safety meeting is scheduled for 10/1/15 at 12:30 PM.

Disruption Avoidance:

• McGough submitted provided DAP #5 regarding precast delivery and erection to DeLaSalle. Specific dates will be identified

once the delivery date is finalized.

• McGough will also provide a DAP for the steel delivery and erection.

Schedule – 3 Week Look Ahead Week of 9/28/15

• Finishes in P.E. Locker Room

• Punch List in P.E. locker room

• Misc. demo for Steel

• Form last footing

� PE Locker Room punchlist inspection was done Thursday 10/1/15 at 9:00 AM.

Week of 10/5/15

• Misc. Demo For Steel

• Pour last footing

• CMU Walls

Week of 10/12/15

• Steel Delivery and erection

• Saw cutting at existing building (during MEA)

Page 2: Construction Coordination Meeting - DeLaSalle High Schooldelasalle.com/wp-content/uploads/2015/10/CIL-McGough-Project... · Construction Coordination Meeting #012 10/01/15 DeLaSalle

Construction Coordination Meeting #012 10/01/15

DeLaSalle

Page 2 of 3

Workforce: McGough - 5 Belair – 2 Nasseff – 0 Northstar Electric – 1 Superior Painting - 0 Total -8

Submittals:

• Submittal Log dated 09/30/15 was reviewed, critical items: o Need sample of actual window mullions o Need sample of black cap flashing metal

RFIs:

• RFI Log dated 09/30/15 was reviewed, critical items:

o Flynn – Roofing

o RFI #40 – 6 inch sanitary main location – John H and Andy to verify there are 2 4” mains and what fixtures

are on the main we are wanting to tie into.

CCDs: CCD 7R – was issued, Nasseff is pricing CCD-7R

Old Business:

Item Description Action By Date Required

By

9.02

North Entry Building Signage Layout 10/01/15: Sean stated the letters are missing. He will check with Nicholas on their location.

9/10/15: DLS will be using existing signage letters at the north entry. DLS asked HGA to provide a layout for the signage.

DLS 10/08/15

9.03

Temporary Door at Field Exit 10/01/15: Sean to review with Nicholas.

9/10/15: Pat Reak asked if DLS wants to provide at new 48” door at the existing 36” temporary door location. DLS will review logistics (ie locking the Womens locker room door) and respond.

DLS 10/08/15

9.04

Door Pairs to be Same Height 10/01/15: Cheryl to follow up with Nicholas.

9/24/15: Cheryl noted that new door pairs are NOT all at matching heights. Cheryl and Nicholas need to meet to discuss. 9/17/15: Cheryl will confirm, all new door pairs are same height. 9/10/15: Nicholas asked HGA to confirm that both doors in door pairs will be the same height, at connection to existing building. HGA will issue revisions as needed.

HGA 9/17/15

9.07

Mezzanine Door Opening 10/01/15: Kevin to forward revised Mezzanine drawings. McGough to document in confirming RFI.

0/24/15: The mezzanine door opening location is shown on the precast shop drawings. McGough will send these to Kevin Halbach for coordination.

9/10/15: The location of the mezzanine door opening has been identified per field dimensioning on precast shop drawings. John H will send a confirming RFI to document the location.

McG

10/08/15

9.08 Glass Marker Boards

Page 3: Construction Coordination Meeting - DeLaSalle High Schooldelasalle.com/wp-content/uploads/2015/10/CIL-McGough-Project... · Construction Coordination Meeting #012 10/01/15 DeLaSalle

Construction Coordination Meeting #012 10/01/15

DeLaSalle

Page 3 of 3

New Business:

The next meeting is scheduled for Thursday, October 8th 2015, at 9:30 AM at DeLaSalle High School.

10/01/15: Dan Welty brought in new samples and everyone tested the markers on them and the glass cleaned easily. Dan to forward electronic resubmittal information and Cheryl to take the physical samples with her today. The team approved the glass. Dan said there was no additional cost for any of the changes to the detailing or materials for the marker boards.

9/24/15: Correction: the gap at the wall behind glass will be ¼”. Cheryl said caulk isn’t required at the perimeter gap. Foam pad should be held back ¼” from the edge of glass. 9/17/15: There was discussion about the glass marker boards with Dan Welty from Twin City Glass

1. The proposed mounting system will have a 3/16” gap at the wall, which will be caulked. The mounting system suggested by HGA would not be structurally adequate and would only reduce the gap by 1/16”

2. Twin City Glass will get a revised sample with a different glass finish which will be non-glare, but allow erasing (without using water).

A foam pad will be installed behind the glass marker board to help prevent bowing/breakage if accidentally hit.

Information

11.01

PE Locker Room Specialties 10/01/15: Sean said he would get John a sanitary napkin dispenser. McGough to return the one from Bartley. Final inspection John has scheduled for tomorrow. Pat and Andy to get their respective inspection done prior to that. John and Sean to work out the logistics of moving the lockers out of the Casanova room so the PE locker rooms can be put in use next week.

9/24/15: McGough will need TP, paper towel and soap dispensers from DLS for installation next week. Sean will coordinate with John. No code signage is required at the PE Locker Rooms. Identification signage will be provided by DLS as needed. DLS requested that HGA coordinate code signage with existing DLS building signage when code signage submittals (from McGough Sub) are reviewed.

Information

11.02

Tree Removal at School Entry 10/01/15: Sean to contact Rainbow regarding the tree removal and get on their schedule while waiting to confirm with Nicholas.

9/24/15: Existing trees at the front of the building will need to be transplanted in the next coupld of weeks (prior to cold weather). DLS will confirm who they want to do this work.

DLS 10/1/15

11.03

Student Tours 10/01/15: Shannon passed on the waiver last week. DLS to let McGough know when they want to schedule the tours.

9/24/15: Nicholas asked about the possibility of giving Student Council members a tour of the jobsite. McGough can work with the school on this. Any visitors must sign a waiver form (Guardians must sign for minors), and wear vests/hard hats! McGough will forward a copy of the form.

Information

11.04

Roofing at Library 10/01/15: Sean & John to meet with Flynn next week Tuesday or Wednesday to look at the existing roof and get some pricing options.

9/24/15: DLS is interested in having Flynn Roofing work on the existing library roof during Learning Commons construction.

Information

Item Description Action By Date Required

By

12.01

Movable Partition 10/01/15: Cheryl needs a decision from Nicholas as to which movable partition DLS wants in the learning center.

DLS

10/08/15