ConstructionClaim – A

Marathon Race

Unmesh Kulkarni, Vice President

Head Contracts,

Reliance Infrastructure Ltd

www.thebig5constructindia.com

Page 2: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Outline of the Discussion

Prerequisite of Claims

Timelines of Claims (Submission and Resolution)

Drivers for decisions of Claims

www.thebig5constructindia.com

Page 3: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

What is a Claim ?As per the various scenarios in the Industry, various definition / understanding of claim are:

Claim - A demand or assertion made by a Party for compensation (time and / or cost)

for a loss under a contract occurred due to other Party.

Claim - means a written demand or written assertion by one of the contracting parties

seeking, as a matter of right, the payment of money in a sum certain, the adjustment

of time, the adjustment or interpretation of contract terms, or other relief arising under

or relating to the contract

Claim is defined as unresolved issue raised either by Contractor and /or Owner

arises during the performance of the Contract but do not get mitigated either in

part or in full through provision of the Contract.

www.thebig5constructindia.com

Page 4: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

www.thebig5constructindia.com

Page 5: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Prerequisite of Claims

Visualization

Trending and identification of potentials

Preparation / Positioning / Getting ready

www.thebig5constructindia.com

Page 6: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

VisualizationThe Process of imagining and conceiving

Brainstorming

• At peer level, department level, company level

• Formal as well as informal levels

Hand holding

• Involving the concerns (Keeping

confidentiality in mind)

• Walk the talk

Capturing and sharing lessons learnt

Training

• Through internal sources and information.

• External Experts

www.thebig5constructindia.com

Page 7: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Trending and identification of potentials

Identifying / recording the potential Claim at pre-tender stage

Read thoroughly the Contract Document

Identify the soft spots / Potential reasons

Carefully examine letters, reports, MoMs

Examine the Industry trend of Construction Claim

Input for Claim

Reports (Daily,

weekly, Monthly)

MoM’s Letters

www.thebig5constructindia.com

Page 8: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Source: Root-cause Analysis of Construction-Cost Overruns / Journal of Construction Engineering and management Vol 140, Issue No 1, Jan, 2014

Industry trend of causes for

Construction Claim

www.thebig5constructindia.com

Page 9: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Preparation / Positioning / Getting ready

Claims shall get triggered on occurrence of the following events –

Variations arising out of different situations which are not approved by the Client.

Additional Work / Instructions of Client beyond the requirements of the Contract.

Deviations / Differences in Site Conditions which are beyond the Contract.

Disagreement / difference in interpretation from the Contracts conditions /

Spécifications

Delay in approvals of Engineering documents, Sub Vendor approvals.

Delays in execution and completion of the Contract for various reasons beyond

control of Contractor.Cond..

www.thebig5constructindia.com

Page 10: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Preparation / Positioning / Getting ready

Biased Contracts Conditions

Conditions not anticipated under the Contract.

Non-performance of crucial / time bound obligations

by Client resulting in cost and time overruns.

Incomplete mitigation on account of

Change in Law.

Work Suspension.

Force Majeure conditions

Local unrests

www.thebig5constructindia.com

Page 11: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Preparation

Strategy / selection of potential event

Types of Claim event

Drivers of strategy / selection

Cost / time gain

Positioning (Keeping upper hand in

the relationship)

Counter balance

www.thebig5constructindia.com

Page 12: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Position / Getting ready

Get aligned at all levels for selected / major event

Creating / Identifying potential event

Creating documents

Instruments of Communications

Author of Communications

Effective Communication

www.thebig5constructindia.com

Page 13: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Timelines of Claims (Submission / Resolution)

Claim is a Continuous process, sufficient time is required for generating quality document,

However Legitimately starts with either issuing or receipt of notice.

Notice of Event

Duration is varying & also depends on case to case

Tendency to defer timely notification on account of maintaining a good boy

image to be overcome

Substantiation of Claim document

Sufficiency & adequacy of supporting document

Clarity & non ambiguous preparation

Avoid unnecessary fatting

Effective coordination within various stakeholders

www.thebig5constructindia.com

Page 14: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Essentials of Resolution

Basic understanding prior to submission

Convincing working level teams of client for better

resolution

Clarity on give and take

Effective presentation in front of decision member committee

www.thebig5constructindia.com

Page 15: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Typical Resolution Timeline For Claim Life Cycle

Most of the Contracts have lack of clarity on timelines.

Event

• Fixed

Claim

• Not Fixed

Dispute

• Fixed

ADR

• Not Fixed

Solution

www.thebig5constructindia.com

Page 16: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Dependencies for Resolution of the Claim

Client’s Intent to resolve

Contractor’s requirement

Stage / essentiality of Project

Who is having upper hand in

relationship at that Instance

Quality of Claim document

Quantum of Claim/s

www.thebig5constructindia.com

Page 17: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Drivers for making decision of Claim

Negotiation for mutual benefit

Intent to Close

www.thebig5constructindia.com

Page 18: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Drivers for making decision of Claim

Power Play

Arm twisting

Patience Testing

www.thebig5constructindia.com

Page 19: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Drivers for making decision of Claim

Agree to disagree

Alternate Dispute Resolution Mechanism

Conciliation Arbitration Legal recourse

Long drawn decision making process with lot of

Cost & time impact

www.thebig5constructindia.com

Page 20: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Source: Global Construction Disputes report 2017 By ARCADIS

Trend of Disputes Resolution in World

Global Average for

Year 2011 to 201639.3 13

www.thebig5constructindia.com

Page 21: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Source: Global Construction Disputes report 2017 By ARCADISwww.thebig5constructindia.com

Page 22: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Top 5 reason Construction Claims / Disputes in World

Source: Global Construction Disputes report 2017 By ARCADISwww.thebig5constructindia.com

Page 23: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Questions & Queries !!!

www.thebig5constructindia.com

Page 24: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Letters- Information, notifications, conveying agreements/ disagreements

Minutes of Meetings- recording proceedings of the Meetings

Reports- Daily, weekly, Monthly

Transmittals- details of data transferred

Site Instruction Book- instruction, suggestions, observations related to actual Works

Request for Information (RFI)- Technical Clarifications/ observations on data provided

Instruments of Communications

www.thebig5constructindia.com

Page 25: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Cardinal Change claim

Constructive Change Claim

Impact ClaimPrice

Escalation Claim

Damage Claim (General damage /

Consequential)

Loss of profit Claim

Delay claimPerformance Quality Claim

Bad Faith Claim

Types of Claim

www.thebig5constructindia.com

Page 26: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Who should be Author of Communications:

Reports

Daily - Site Supervisors/ Const. Manager / Project Planner

Weekly- Site Supervisors/ Const. Manager /Project Planner

Monthly- Project Manager/ Project Planner

Letters- Contracts Manager/Project Manager

Minutes of Meetings- Project Planner/ Construction Manager / Contracts Manager

Transmittals- Project Document Controller

Field Instruction thru’ Site Book- Project Manager/ Construction Manager

Request for Information (RFI)- Technical Manager/ Engineering Manager

www.thebig5constructindia.com

Page 27: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Effective Communication can be developed by

Standardization -certain advantages for standardization

Ease in understanding and conveying

Lesser variety documents and Records are easy to handle

Training is simpler and more uniform

Communication planning and especially -control is simpler

Better utilization of documents and the compiling thereof

Saves time

Easy to use in one project or another, although these are totally different projects.

www.thebig5constructindia.com

Page 28: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Effective Contract communication can be developed by

Communication plan-

The communication plan should outline to address -

Who (lines of communication sender- and receiver-responsibility and authority)

What (scope of communication and format)

How (e-mail, facsimile, letter, Memo document, telephone, meeting, presentation)

When (schedule/ frequency)

Feedback (confirm message received and understood – document control)

Filing (retrieval, storing, disaster recovery)

www.thebig5constructindia.com

Page 29: Construction Claim A Unmesh Kulkarni, Vice President ... Claim –A Marathon Race Unmesh Kulkarni, Vice President Head Contracts, Reliance Infrastructure Ltd

Request a copy of our presentations at

www.theBig5ConstructIndia/presentations

PLEASE DON’T FORGET TO COLLECT YOUR ATTENDANCE

CERTIFICATE

THANK YOUFOR

ATTENDING

www.thebig5constructindia.com