Artificial Intelligence 121 (2000) 211–250 Constraint-directed techniques for scheduling alternative activities J. Christopher Beck a,* , Mark S. Fox b a ILOG, SA, 9 rue de Verdun, 94253 Gentilly Cedex, France b Department of Mechanical and Industrial Engineering, University of Toronto, Toronto, Ontario, Canada M5S 3G9 Received 12 October 1999 Abstract In this paper, we expand the scope of constraint-directed scheduling techniques to deal with the case where the scheduling problem includes alternative activities. That is, not only does the scheduling problem consist of determining when an activity is to execute, but also determining which set of alternative activities is to execute at all. Such problems encompass both alternative resource problems and alternative process plan problems. We formulate a constraint-based representation of alternative activities to model problems containing such choices. We then extend existing constraint- directed scheduling heuristic commitment techniques and propagators to reason directly about the fact that an activity does not necessarily have to exist in a final schedule. Experimental results show that an algorithm using a novel texture-based heuristic commitment technique together with extended edge-finding propagators achieves the best overall performance of the techniques tested. 2000 Elsevier Science B.V. All rights reserved. Keywords: Scheduling; Heuristic search; Constraints; Problem structure; Alternative activities 1. Introduction The scheduling problems addressed in the constraint-directed scheduling literature typically have a static activity definition: each activity must be scheduled on its specified resource(s). It is common, however, in real-world scheduling problems to have a wider space of choices. Typically, in a manufacturing setting, there are choices to be made in scheduling among alternative resources on which to run an activity or among * Corresponding author. E-mail addresses: [email protected] (J.C. Beck), [email protected] (M.S. Fox). 0004-3702/00/$ – see front matter 2000 Elsevier Science B.V. All rights reserved. PII:S0004-3702(00)00035-7

Constraint-directed techniques for scheduling alternative activities

Embed Size (px)

Citation preview

Page 1: Constraint-directed techniques for scheduling alternative activities

Artificial Intelligence 121 (2000) 211–250

Constraint-directed techniques forscheduling alternative activities

J. Christopher Becka,∗, Mark S. Foxba ILOG, SA, 9 rue de Verdun, 94253 Gentilly Cedex, France

b Department of Mechanical and Industrial Engineering, University of Toronto,Toronto, Ontario, Canada M5S 3G9

Received 12 October 1999

Abstract

In this paper, we expand the scope of constraint-directed scheduling techniques to deal withthe case where the scheduling problem includes alternative activities. That is, not only does thescheduling problem consist of determining when an activity is to execute, but also determining whichset of alternative activities is to execute at all. Such problems encompass both alternative resourceproblems and alternative process plan problems. We formulate a constraint-based representation ofalternative activities to model problems containing such choices. We then extend existing constraint-directed scheduling heuristic commitment techniques and propagators to reason directly about thefact that an activity does not necessarily have to exist in a final schedule. Experimental results showthat an algorithm using a novel texture-based heuristic commitment technique together with extendededge-finding propagators achieves the best overall performance of the techniques tested. 2000Elsevier Science B.V. All rights reserved.

Keywords:Scheduling; Heuristic search; Constraints; Problem structure; Alternative activities

1. Introduction

The scheduling problems addressed in the constraint-directed scheduling literaturetypically have a static activity definition: each activitymustbe scheduled on its specifiedresource(s). It is common, however, in real-world scheduling problems to have a widerspace of choices. Typically, in a manufacturing setting, there are choices to be madein scheduling among alternative resources on which to run an activity or among

∗ Corresponding author.E-mail addresses:[email protected] (J.C. Beck), [email protected] (M.S. Fox).

0004-3702/00/$ – see front matter 2000 Elsevier Science B.V. All rights reserved.PII: S0004-3702(00)00035-7

Page 2: Constraint-directed techniques for scheduling alternative activities

212 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

alternative process plans (also called “routings”) of an order through a factory. While thischaracteristic is ubiquitous in industry, there has been little examination of such alternativesin the constraint-directed scheduling literature.

The central contribution of this paper is the expansion of scope of scheduling problemsthat can be addressed by constraint-directed scheduling techniques. This expansion isdone by integrating the representation of activity alternatives into the constraint graphrepresentation of the scheduling problems. We then extend heuristic techniques andsophisticated propagators to account for the richer representation.

There are two primary motivations for the work in this paper. The first is the expansion ofthe scope of constraint-directed scheduling techniques. While there have been considerableadvances over the past few years in the scope and difficulty of scheduling problems thatcan be successfully addressed with constraint technology [6], there are still a number ofproblem characteristics that have been examined only partially or not at all in the literature.These characteristics are nonetheless important from the practical perspective of modelingand solving problems as they existin situ. Choosing resources on which to schedule anactivity as well as amongst different sets of activities with which to achieve the samegoals, are two such characteristics. The second motivation for the work in this paper isthe investigation of the problem structure hypothesis due to Simon [41]. Theproblemstructure hypothesisstates that as a problem becomes more complex, understanding ofits structure becomes increasingly important for successful heuristic search. While theproblem structure hypothesis has been pursued in the context of scheduling by Fox etal. [4,5,7,8,10,21,22,36,37], the inclusion of activity alternatives results in an additionaldimension of complexity. Therefore, scheduling with alternative activities is a primeapplication for the investigation of the hypothesis.

1.1. Plan of paper

The plan of this paper is as follows: in the following section, we provide the necessarybackground for the work in this paper. In Section 3, the representation of alternatives ispresented, while Section 4 and Section 5, respectively, examine propagators and heuristiccommitment techniques for alternative activity problems. Our empirical evaluations appearin Section 6 through Section 8 with the discussion of our results appearing in Section 9.In Section 10, we briefly note future work stemming from this paper before concluding inSection 11.

2. Background

Before presenting the extensions to constraint-directed scheduling representation andtechniques to incorporate the activity alternatives, we define the problems of alternativeresources and alternative process plans, and discuss previous work that has examinedthese two characteristics. In addition, we introduce two components of constraint-directed scheduling algorithms that have been previously applied to non-alternative activityproblems: texture-based heuristic commitment techniques and propagators.

Page 3: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 213

Table 1Notation

Symbol Description

STi a variable representing the start time ofAi

STDi the discrete domain of possible values forSTi

esti earliest start time ofAi

lsti latest start time ofAi

duri duration ofAi

efti earliest finish time ofAi

lft i latest finish time ofAi

2.1. Notation

For an activity,Ai we use the notation in Table 1 through the balance of this paper. Wewill omit the subscript unless there is the possibility of ambiguity.

2.2. Problem definition

In a basic scheduling problem (such as the job shop scheduling problem [23]) eachactivity must be assigned a time to execute on a predefined resource. As each activity mustbe executed and the resource is already specified, the only component of the problem thatmust be decided is when each activity will execute.

In analternative resource scheduling problem, rather than having a unique resource thatit must execute on, each activity may have a set of alternative resources and may execute onany member of the alternative set. Depending on the resource chosen, other characteristicsof the activity (e.g., duration) may also change. A solution to the problem must specifywhich resource the activity executes on as well as when it executes.

In an alternative process plan scheduling problem, the choices are expanded toencompass multiple sets of activities. Fig. 1 displays four alternative process plans

Fig. 1. Four alternative process plans.

Page 4: Constraint-directed techniques for scheduling alternative activities

214 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

(PP1, . . . ,PP4). The label in the upper-left corner of each activity represents the activity’sresource requirement while the lower-right label is the identifier of the activity. Thus,activities with the same identifier (e.g.,A3 in PP1 andA3 in PP2) are the same. The firsttwo process plans,PP1 andPP2, are simply different orderings of the same activities. Thethird process plan,PP3, is a completely different recipe while the fourth,PP4, is a variationon the third: the first and last activities are identical, but the middle ones are different. Onlyone of the alternative process plans is to be executed. Therefore, the scheduling problemnot only consists of decidingwhento execute the activities butwhich of the alternativeprocess plans will be executed at all.

2.3. Previous work

2.3.1. Alternative resourcesIn its most basic form, the alternative resource problem can be represented with the use

of multi-capacity resources [31]. A resource of capacityk can be used to model a resourceset ofk identical unary capacity resources and the activities can simply be scheduled onthe multi-capacity resource without representing the unary capacity resources. Significantrepresentational savings can be gained from this type of representation. Unfortunately, it isunclear if elaborations of the resource model, such as requiring changeover activities [11],can be represented in this way.

ISIS [21] provided representation for alternative resources within an order-basedIncre-mental Decomposition and Incremental Scheduling(IDIS) [27] approach. All the activitiesfor one order are assigned start times and resource assignments before the next orderis selected for scheduling. A similar order-based decomposition is used in the DynamicScheduling System (DSS) [26] in the context of on-line scheduling. Based on a black-board system and stochastic order arrival, DSS instantiates process plans with resourcealternatives that include preference information. Based on analyses of the existing scheduleand the preferences, resource reservations are created for each of the newly instantiatedactivities. While the scheduling process typically assigns activities to resources in oneorder before moving to the next, in more challenging scheduling problems, DSS maycancel previous reservations in order to search for a global solution among the currentlyinstantiated activities.

In a constraint programming language, such as ILOG Solver and Scheduler [1],alternative resources can be modeled with one boolean variable for each resource-choiceof an activity. An activity uses a resource only if the corresponding demand variableis TRUE. By using a constraint stating that only one of the demand variables can beTRUE, the alternative resource requirements can be modeled and demand variables canbe incorporated into solution techniques.

A combination of the multi-capacity representation and the boolean representationcan be done by using multiple representations of the same resource requirements [31].Multi-capacity resources are used to represent resource sets while the unary capacityresources are directly represented. A multi-capacity version of the edge-finding exclusionpropagator has been implemented and used on the multi-capacity resources at the sametime as edge-finding and other propagators are used on the unary capacity resources.Extensions of these techniques allow activities to have overlapping resource sets and allow

Page 5: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 215

the duration of an activity to depend on the assigned resource alternative. Building onthe use of multiple representations, Davenport et al. [19] formulate a number of heuristiccommitment techniques for the alternative resource problems. Again, both the multi-capacity resource and unary capacity resources are explicitly represented. The centralalgorithm for scheduling has two phases: in the first, all the activities are assigned to oneof their resource alternatives, and in the second phase the activities on the unary capacityresources are sequenced using job shop scheduling techniques.

2.3.2. Alternative process plansKott and Saks [27] introduce a spectrum of approaches to alternative process plan

scheduling. At one extreme, theMultiple Alternative Decomposition(MAD) approach,the alternatives are fully represented and integrated in the scheduling process. The otherextreme is theComplete Decomposition Prior to Scheduling(CDPS) approach where allalternatives are decided in a pre-scheduling phase of the search. An intermediate approachalong this spectrum is theIncremental Decomposition and Incremental Scheduling(IDIS)approach where the search through the alternatives and the scheduling is interleaved.

The order-based decomposition approach of ISIS discussed above can be applied toproblems containing alternative process plans [21]. In addition to alternative resources,the order representation in ISIS allows alternative routings of a single order. After suchan order is chosen for scheduling, the resource allocation heuristics are used to choose asingle routing and resource reservations for all activities along the chosen routing.

The KBLPS scheduling system [14,39] builds on the order-based decomposition of ISISby the direct representation of alternative process plans and the incorporation of alternativeinformation into texture-based heuristics. In KBLPS, a probabilistic representation of allactivities similar to that of Sadeh [36,37] was used. The innovation was to recognize thatthe probability that a particular routing is chosen depends on the number of alternativeroutings that are available: the individual resource demand for each activity in a routingwas therefore biased to represent the likelihood that the routing itself was chosen. Theresource reservation heuristics, therefore, have deeper information on which to base theircommitments. Kott and Saks [27] extend the KBLPS work by embedding alternativeprocess plan scheduling in the context of combined planning and scheduling. Viewingalternative process plans as the result of goal decomposition, the authors examine thescheduling of multiple, alternative decompositions. Using domain specific rules, a set ofalternative process plans are constructed for each goal to create the scheduling problem.Then, based on the contention and reliance texture measurements, the activity most relianton the most contended-for resource is selected. As in KBLPS, the individual demand ofeach activity is biased by its probability of execution given the alternative process plans thatare available to achieve the same goal. The critical activity is used to identify the criticalgoal, and a single process plan is selected to achieve that goal based on a combination ofdomain specific rules and the reliance of the critical activity. All the activities in the chosenprocess plan are scheduled.

A higher-level approach to alternative process plan scheduling can be seen in workthat integrates the process planning task with scheduling. Systems such as Design-to-Criteria [43,44] and IP3S [38] dynamically create process plans according to a numberof criteria. The Design-to-Criteria work takes into account a combination of uncertainty,

Page 6: Constraint-directed techniques for scheduling alternative activities

216 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

cost, and time-to-completion in exploring the space of plans with which a set of goals canbe achieved. Based on the high-level evaluation, a set of activities without alternatives isselected and scheduled. Depending on the quality of the resulting schedule, decisions fromthe planning phase may be revisited in order to achieve a better overall schedule. Similarly,IP3S uses a black-board architecture to integrate process planning and scheduling. IP3Sachieves this integration by taking into account the resource contention when formulatingprocess plans. As with Design-to-Criteria, non-alternative process plans are generated andscheduled; however, based on the quality of the schedule, process plans may be generatedspecifically to route process plans away from highly contended-for resources. In bothsystems, however, the alternative process plans are represented only in the planning phase:no representation of alternatives is present during the actual scheduling.

Le Pape [28] extends the activity representation of ILOG Scheduler to allow an activity’sduration to be 0 to represent that the activity does not execute. In an application thatrepresents activities with varying durations, all activities are initially present in the problemand the heuristic commitment technique has the choice of setting an activity’s duration to0, setting it to some lower-bound, and/or assigning a start time. This technique allowsthe representation alternative activities; however, no information is given on what, if any,propagation is done to reason about activity dependencies.

2.3.3. DiscussionWe draw two general themes from the literature on activity alternatives. The first is the

constraint programming approach represented by ILOG Scheduler where an alternativeis represented by a full variable in the constraint representation of the problem. Thesecond theme is the heuristic approach present in KBLPS and [27]: resource and starttime reservations are made with texture-based heuristics which take into account the factthat alternative choices change the individual demand an activity has for a resource. Thesetwo themes are consistent with the work on scheduling non-alternative activities wherepropagators and sophisticated heuristic techniques are two key solution techniques.

Based on the foundation provided by the literature, our approach to scheduling withalternative activities is as follows:

(1) Represent the fact that an activity has alternatives and therefore may not actuallyexecute in the constraint graph.

(2) Formulate and/or adapt texture-based heuristics so that they take into account theexistence of alternatives and directly reason about them in generating heuristiccommitments.

(3) Formulate and/or adapt propagators so that they too can take into account theexistence of alternatives yet still derive implied commitments that can be addedto the constraint graph.

3. Representation of alternative activities

In order to represent the fact that an activity present in the problem definition may not bepresent in a final schedule, we introduce the notion of an activity’sprobability of existence(PEX). Informally, PEX is defined to be the probability that an activity will be present in the

Page 7: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 217

Fig. 2. Modification of the temporal network to directly model the alternatives implicit in Fig. 1.

final solution (assuming such a solution exists). The PEX of each activity is represented bya PEX variable, which is a standard domain variable with an initial domain of{0,1}. In eachsearch state, we calculate the expected value1 of the PEX variable and use it to representthe activity’s probability of existence. In addition, the temporal network is modified sothat the expected PEX values and temporal values are propagated among activities. One ofthe key components of this extension is a modification of the temporal graph to explicitlyrepresent alternative activities.

A general idea of the representational approach can be seen in Fig. 2. The XorNodes inthe constraint graph directly represent the alternative process plans (and sub-process plans)from Fig. 1. We discuss the addition of XorNodes and PEX variables to the constraint graphin this section.

3.1. Extending the temporal graph

To represent activity alternatives directly in the temporal graph, we introduce AndNodesand XorNodes in additional to the regular Activity nodes. The temporal graph has multipleinstances of AndNodes, XorNodes, and Activities connected via temporal constraints.

3.1.1. AndNodeThe AndNode has start time and end time temporal variables just as an Activity

does. The duration of an AndNode is 0. There are two semantic components in theAndNode corresponding to its functionality in temporal and PEX propagation. From aPEX perspective, all the TemporalNodes linked to an AndNode exist in a solution if theAndNode exists. Similarly, if one of the non-XorNodes directly linked to an AndNodeexists in a solution, then the AndNode must exist. In terms of expected PEX values,therefore, all non-XorNodes directly connected to an AndNode must have the sameexpected PEX value as the AndNode itself. Since all the nodes an AndNode is connectedto are either going to be present in a solution, or all the nodes, including the AndNodeitself, are removed, it is valid to perform standard temporal propagation.

1 We use the phrases “expected value” and “expected PEX value” informally here, by analogy to the usualstatistical definition of the expected value of a random variable. A formal justification for the use of the phrasesin their statistical sense is beyond the scope of this document.

Page 8: Constraint-directed techniques for scheduling alternative activities

218 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

3.1.2. XorNodeLike the AndNode, the XorNode has a duration of 0, and start and end time temporal

variables. As the name indicates, the logical semantics of a XorNode are such that if theXorNode itself is present in the final solution then one and only one of the nodes directlyconnected upstream (respectively, downstream) to the XorNode can also be present. Also,if a node directly connected upstream (or downstream) to a XorNode exists in a solution,so must the XorNode. From a PEX propagation perspective, these semantics mean that,in a consistent network, the expected PEX value of the XorNode is equal to the sum ofthe expected PEX values from the nodes directly connected upstream and the XorNodeexpected PEX value must also be equal to the sum of the PEX values from the nodesdirectly connected downstream.

Fig. 3 represents a small temporal graph with XorNodes,X1, X2, andX3. Assumingthat the expected PEX value ofX1 andX3 are both 0.5, the rest of the temporal nodes havethe expected PEX values shown (above or below each node).

From a temporal perspective, the fact that only one of the upstream and one of thedownstream links are to be present in a solution means that temporal propagation isdifferent from that of the AndNode. A XorNode must end before themaximumlatest starttime of all the nodes directly connected downstream while it must start after theminimumearliest end time of all activities connected upstream. Assuming that the nodes betweenX1 andX3 must be scheduled within a scheduling horizon of[0,100], Table 2 displaysthe start and end time windows of each node. Note that for the temporal propagation ofthe AndNodes, they are treated simply as activities with zero duration. The XorNodes alsohave zero duration, but a more complicated treatment within temporal propagation due totheir semantics. We revisit the issue of PEX and temporal propagation in Section 4.

3.1.3. Illegal temporal networksWe have extended our temporal network representation to allow definition of AndNodes

and XorNodes. Not all temporal networks that are expressible are valid networks, however.The basic requirement for legality is that for any XorNode,X, in the graph withk upstreamandl downstream links (k, l > 1), there must be:• a corresponding XorNode,X−, upstream ofX with k downstream links, and• a corresponding XorNode,X+, downstream ofX with l upstream links.

Fig. 3. A temporal graph with XorNodes.

Page 9: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 219

Table 2The time windows for the activities in Fig. 3

Node Start time domain End time domain

X1 [0 90] [0 90]

A6 [0 70] [25 95]

A1 [0 80] [15 95]

A3 [0 90] [5 95]

X2 [5 95] [5 95]

A5 [5 90] [15 100]

A7 [5 95] [10 100]

X3 [10 100] [10 100]

Fig. 4. An illegal temporal network.

For example, the temporal network in Fig. 4 clearly breaks our basic requirement forcorresponding linkage of XorNodes. The first XorNode has 3 downstream links while thereare no other XorNodes in the network with 3 upstream links. Intuitively, the reason that thisnetwork is illegal is an ambiguity for expected PEX values. What should the expected PEXvalues be for the middle three activities? Starting from the upstream activity, we wouldassign a PEX of 1 to it and to the first XorNode. Following the PEX propagation rulesfor XorNodes we would then calculate that each of the middle three activities have anexpected PEX value of 0.33. Consider, however, starting from the last node and doing thePEX propagation upstream. The final XorNode will have an expected PEX value of 1. Thetwo nodes directly connected to the final XorNode (i.e., the penultimate XorNode and thebottom activity) would then have an expected PEX value of 0.5 each and then propagatingfrom the penultimate XorNode, the top two middle activities would have an expected PEXvalue of 0.25 each. The ambiguity over the expected values is the reason that network Bis illegal and therefore the reason for the “matching links” requirement for XorNodes in alegal temporal network.

3.2. Probability of existence

The probability of existence(PEX) for an activity is the estimated probability at apoint in the search that an activity will be present in a final solution to the problem. Thisprobability is in the range[0,1]with 1 indicating that an activity will certainly be part of thesolution and 0 indicating that it certainly will not. PEX is represented by the expected valueof boolean demand variables such as were used by Baptiste and Le Pape [1]. While theboolean PEX variables themselves can only take on the value of 0 or 1, the expected value

Page 10: Constraint-directed techniques for scheduling alternative activities

220 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

of the PEX variable is on the interval[0,1]. The expected PEX value is a representation ofadditional information about each activity which can then be incorporated into the heuristiccommitment techniques based on texture measurements.

It is important to make clear the fact that the PEX variable is a standard booleanconstrained variable: in any solution, each PEX variable must be assigned either to 0 or to 1.The expected PEX value, however, is a number in the interval[0,1]. When a PEX variableis assigned, its expected value is equal to its assigned value. When unassigned, however,the expected PEX value varies according to the propagation rules presented below.

In order to simplify the implementation for our model of alternative activities, we haveplaced one major limitation on the PEX representation: if a XorNode has an expectedPEX value ofx, k upstream andl downstream links, the expected PEX value of eachdirectly connected upstream node isx/k and the expected PEX value of each directlyconnected downstream node isx/l. The only exception to the rule of even division is whenan upstream or downstream node has a PEX variable assigned to 0 or 1. If a neighboring,without loss of generality, upstream node has a PEX variable assigned to 0, it is removedfrom the graph: the expected PEX value at the XorNode is simply divided among theupstream nodes with unassigned PEX variables. Similarly, if the neighboring, without lossof generality, upstream node has its PEX variable assigned to 1, the PEX variables of all theother directly linked upstream nodes must be assigned to 0: the XorNode acts as if it onlyhas a single upstream node. We discuss issues surrounding the removal of this limitationin Section 10.

4. Propagators for alternative activities

The power of propagators is well-recognized in the constraint-directed schedulingliterature. It appears likely, therefore, that the use of propagators in problems with PEXvariables will lead to improved search performance.

In this section, we discuss three types of propagation on the extended temporal network:(1) PEX propagation—The expected PEX values of different nodes are related via

the topology of the temporal network. When the network is modified (e.g., bya commitment that sets the PEX variable of an activity to 0), the effects of thecommitment must be propagated to the expected PEX values of the other nodes inthe network.

(2) Temporal propagation—Standard temporal propagation enforces arc-B-consistency[29] on the temporal constraints in the scheduling problem. For example, ifAi andAj are directly connected via a precedence constraint such thatAj is a successor ofAi , temporal propagation enforces thatestj > esti + duri andlft i 6 lftj − durj . Toaccount for nodes that do not necessarily exist in a final solution, we must adapt thestandard temporal propagation algorithm.

(3) PEX-edge-finding propagation—Edge-finding propagators (both exclusion [12,13,15,16,31] and not-first/not-last [2,3,12,13,15,31]) have been shown to significantlyimprove scheduling performance in a number of types of scheduling problems. Weextend edge-finding here to incorporate activities that do not necessarily execute ina final solution.

Page 11: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 221

Fig. 5. A process plan with a choice of activities. The duration of each activity is shown in the lower left cornerof the activity.

The small example in Fig. 5 serves to illustrate the first two types of functionality. Thefigure represents a single process plan with a choice of activities: eitherA1 can be followedbyA2, A3, A4, and thenA5 orA1 can be followed byA6, A7, and thenA5. The durationof each activity is indicated by the number in its lower left corner. Assuming thatA1 andA5 must be executed, we assign their PEX variables to 1. Further, we split the probabilityof existence equally between the two choices. Therefore,A2, A3, A4, A6, andA7 haveexpected PEX values of 0.5. The PEX propagation must ensure that if we were to make anarbitrary assignment of a PEX variable, such as assigning the PEX variable ofA3 to 1, theexpected PEX values of the related activities and, perhaps, the PEX variables themselves,would be appropriately reset. In our example, the PEX variables ofA2 andA4 should alsobe set to 1, and the PEX variables ofA6 andA7 should be set to 0.

Returning to the original graph in Fig. 5 (i.e., before assigning the PEX variable ofA3 to1), the standard temporal propagation algorithm would derive that the start time window ofA1 is [0, 45]. The latest start time ofA1 is found by the calculation of the longest path fromA1 toA5 which happens to includeA6 andA7. If A1 were to start at time point 46, andA6andA7 were to be executed,A5 would end at time point 101, which is after the end of thehorizon. The difference in this graph, however, is the presence of the alternative path fromA1 toA5. It is possible forA1 to start at time 46 if the path going throughA2,A3, andA4 ischosen. In fact, with this choice,A1 can consistently start as late as time point 55. Clearly,then, we need to modify the temporal propagation (or the temporal network) to account forthe possibility that some activities may not be present in the final solution. Furthermore,assume that the two alternatives in Fig. 5 are still possible and that through some otherscheduling decision the earliest start time ofA1 is increased to 46. Temporal propagationshould detect that such a change makes one of the alternative paths inconsistent: there isno way thatA6 andA7 can execute.

4.1. Propagation of expected PEX values

The basic PEX propagation algorithm is achieved through the PEX propagation behaviorat each temporal node. As described above, at an AndNode (or Activity),A, all the non-XorNodes directly linked toA must have the same expected PEX value asA. Therefore,when PEX propagation enters an AndNode, the local expected PEX value can be modifiedand the new local value is propagated to all neighboring nodes. For XorNodes, the sumof the expected PEX values for all nodes directly connected upstream must be equal to

Page 12: Constraint-directed techniques for scheduling alternative activities

222 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

the sum for all nodes directly connected downstream which in turn must be equal to theexpected PEX value of the XorNode.

The basic PEX propagation algorithm presented here ignores the current expected PEXvalues and re-propagates the entire network. In practice, we also have an incrementalalgorithm that updates the expected PEX values after a local change. Details of theincremental algorithm can be found in Beck [4].

Given our temporal networks, if a node has either no upstream or no downstream linksit cannot be subject to a XorNode and so must be present in the final solution. Any tempo-ral node that either has no upstream links or no downstream links must, therefore, have itsPEX variable assigned to 1. Also since a requirement of a legal temporal network is that theexpected PEX values are unambiguous, initial propagation may begin with all nodes withno upstream links or all nodes with no downstream links. We have arbitrarily chosen to per-form the initial propagation from all nodes with no upstream links. Recall that the expectedPEX value of any node that has its PEX variable assigned is equal to the assigned value.

Pseudo-code for the initial propagation algorithm is given in Fig. 6. Lines 4, 8, and 17make use of active nodes and active links. Anactive link is a binary temporal constraintsuch that the PEX variable of each of its nodes is not assigned to 0. Anactive nodeis a nodeconnected via an active link. Recall that a topological sort (line 1) in an acyclic, directednetwork is an ordering of the nodes such that if there is a path from nodeY to nodeX inthe graph thenY < X in the sort order [33]. In our case, the topological sort establishesthat if Y is upstream ofX in the temporal graph, thenY < X in the sort order. In the loopbeginning at line 2, therefore, we are guaranteed that all upstream nodes already have theirexpected PEX values assigned.

1: create downstream topological sort of temporal nodes2: for each temporal node with unassigned PEX variable in sort

order3: if the node is an AndNode OR Activity4: upstreamNode = any directly connected, active upstream node5: set ExpPEX = downstreamExpPEXValue (upstreamNode)6: if the node is an XorNode7: set ExpPEX = 08: for upstreamNode = all directly connected, active upstream

nodes9: set ExpPEX += downstreamExpPEXValue (upstreamNode)10:11:12: procedure downstreamExpPEXValue (Node node)13:14: if the node is an AndNode OR Activity15: return ExpPEX16: if the node is an XorNode17: return (ExpPEX / number active downstream links)

Fig. 6. Pseudocode for the basic PEX propagation algorithm.

Page 13: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 223

The complexity of the initial propagation givenn nodes andm temporal constraints isO(max(m,n)). The topological sort (implemented with a depth-first search) and the for-loop are both O(max(m,n)) as all nodes and constraints must be visited.

4.2. Temporal propagation with PEX

There are two differences in temporal propagation when XorNodes are present in thenetwork.

(1) Propagation through a XorNode is different than propagation through an Activity.(2) It is possible to derive a dead-end in the search by emptying the domain of a variable

during temporal propagation. When there are nodes with unassigned PEX variablesin the graph, such a state may not be a dead-end, but rather may indicate an impliedPEX commitment.

4.2.1. Temporal propagation through a XorNodeThe temporal propagation through a XorNode is straightforward given the temporal

semantics of a XorNode. A XorNode enforces the temporal relationship that it must start atthe same time as or after the end time of at least one of its upstream neighbors, and it mustend at the same time as or before the start time of at least one of its downstream neighbors.During downstream propagation, therefore, the XorNode sets the lower-bound on its starttime domain based on the minimum earliest finish time of its upstream neighbors. Thisstart time is then propagated further downstream. Similarly, during upstream propagationthe upper-bound on the end time of a XorNode is set based on the maximum latest starttime of its downstream neighbors and this value is further propagated upstream.

4.2.2. Deriving implied PEX commitments from temporal propagationIn standard temporal propagation algorithms, if a variable’s domain has been emptied,

a dead-end is derived. When PEX variables are present, emptying a domain may not be adead-end. Rather it may indicate that a particular PEX variable must have a value of 0.

When a domain is emptied in temporal propagation, the PEX variable of the temporalnode with the emptied domain is examined. If the PEX variable is unassigned, the nodeis marked to indicate that the PEX variable has been determined to be 0 and temporalpropagation does not continue from that node. After temporal propagation, a separatealgorithm examines all the temporal nodes to determine if any have been marked to indicatethe derivation of an implied PEX constraint. If such a temporal node is found, a new unaryPEX constraint is asserted, and the usual PEX propagation and temporal propagation isdone.

If the domain of a temporal node with PEX of 1 is emptied, a dead-end is derived asin the standard temporal propagation. To see why this is the case, imagine emptying thestart time domain of an activity,A, with a PEX variable assigned to 1. By definition, itcannot have any enclosing XorNodes. Assume that the presence of some activity,B, withan unassigned PEX variable caused the empty domain. The temporal propagation fromB

to A must occur through one of the XorNodes enclosingB. If that propagation emptiesA, then it must be the case that not onlyB but all its alternatives are inconsistent withA.Therefore, it is a true dead-end. Note that this reasoning holds even if activityB is nested

Page 14: Constraint-directed techniques for scheduling alternative activities

224 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

inside a number of alternatives: the temporal propagation fromB to A must pass throughthe outer-most XorNode enclosingB. This XorNode,X, must have a PEX variable equalto 1. Since all the alternatives ofX are inconsistent withA, we have a true dead-end.

4.3. PEX-edge-finding propagation

Two types of edge-finding have been widely used in the constraint-directed schedulingliterature [12,13,15,16,31]. The reasoning in edge-finding is based on examining the set ofactivities on a resource and deriving temporal constraints that enforce new upper and lowerbounds on the end and start times of activities.

Clearly, edge-finding can be used with activities with PEX variables assigned to 1.Imagine the situation, however, where the set,S, of activities on a resource contains asingle activity,A, whose PEX variable is not assigned. Further assume that edge-findingcan infer no new commitments or dead-ends when only considering the activities in the setS \ {A}. When considering all activities inS:

(1) If edge-finding derives a dead-end, we can soundly infer that activityA cannotexecute and therefore set the PEX variable ofA to 0.

(2) If edge-finding derives new unary temporal constraints onA, they can be soundlyasserted. Clearly ifA is to execute, it must be consistent with the rest of the activitiesthat execute on the same resource. Therefore, any unary temporal constraints onA

are sound: they must be true ifA is to execute and ifA does not execute they do notaffect any other activities.

(3) If edge-finding derives any unary temporal constraints on activities other thanA,they must be discarded. Since it is possible forA not to execute, and since the

1: procedure PEXEdgeFinding2: list-of-commitments = EdgeFinding()3: if list-of-commitments is not empty4: return list-of-commitments5:6: for each activity A such that 0 < A PEX < 17: temporarily set A PEX = 18: tmp-list = EdgeFinding()9: for each commitment in tmp-list10: if dead-end11: list-of-commitments.insert (set A PEX to 0)12: else if new commitment on activity A13: list-of-commitments.insert (commitment)14: else15: discard commitment16: reset A PEX17:18: return list-of-commitments

Fig. 7. Pseudocode for PEX-Edge-finding.

Page 15: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 225

temporal constraints are derived on the assumption thatA would execute, we cannotsoundly constrain the other activities.

This reasoning leads to the PEX-edge-finding algorithms presented in Fig. 7. Note thatthis function uses the usual edge-finding algorithms as sub-routines (line 2 and line 8). Thatis, the calls toEdgeFinding() are calls to the standard edge-finding functions, whichreturn a list of commitments that are implied by the current search state. Given that thestandard edge-finding worst-case complexity is O(n2), wheren is the number of activitieson a resource, the PEX-edge-finding worst-case complexity is O(n3) for one resource.

5. Incorporating alternative activities into scheduling heuristics

With the ability to represent and propagate the fact that some temporal nodes may notbe present in a final schedule, it is necessary to extend the heuristic search techniques toallow direct reasoning about an activity’s probability of existence. The obvious extensionis to expand the type of commitments that a heuristic can make to include setting the PEXvariable of an activity. This, indeed, is the basic extension to existing heuristics.

Before presenting our extensions to texture measurement-based heuristic commitmenttechniques, it is necessary to briefly present two texture-based heuristic commitmenttechniques from the literature.

5.1. Texture measurement-based heuristics

A texture measurementis an analysis of the constraint graph underlying a problem statein order to distill information that can be used by the heuristic commitment technique [22].For example,contention[36,37] is the extent to which variables linked by a disequalityconstraint compete for the same value. In the context of scheduling, contention is theextent to which activities compete for the same resource over the same time interval. Twotexture-based heuristic commitment techniques, SumHeight [8,10] and VarHeight [4,7],are extended in this paper to address scheduling problems with alternative activities.

The SumHeight texture measurement estimates the contention on each resource, overtime, by summing the probabilistic individual demand curves that each activity has for theresource. If an activity does not require a resource, its demand is 0. Otherwise, a uniformprobability distribution over the possible start times of the activity is assumed: each starttime has a probability of 1/|STD| whereSTD is the domain of the activity’s start timevariable. The individual demand,ID(A,R, t), is the probabilistic amount of resourceR,required by activityA, at timet . It is calculated as follows:

ID(A,R, t)=∑

t−durA<τ6tσA(τ ), (1)

where

σA(τ)=

1

|STDA| if τ ∈ STDA,

0 otherwise.(2)

Page 16: Constraint-directed techniques for scheduling alternative activities

226 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

Fig. 8. Calculating the probability of breakage at eventt with VarHeight.

The VarHeight texture measurement makes use of the same underlying individualdemand curve as SumHeight. Rather than estimating aggregate demand, however, theVarHeight texture estimates the probability of breakage of a constraint based on theexpected value of the aggregate demand and a distribution around the expected value. Theexpected value at each event point is provided by the aggregate curve on a resource ascalculated by SumHeight. The distribution is created by the aggregation of the variance ofthe individual demands. In considering resourceR, a time pointt , and an activityA, wecan associate a random variableX with the demand thatA has forR at timet . For unaryresources the domain ofX is {0, 1}. The expected value forX, EX, assuming a uniformprobability distribution for the start time ofA, is ID(A,R, t) as calculated in Eq. (1). Wecalculate the variance ofX, VX, as follows (see [4] for the derivation):

VX=EX× (1−EX). (3)

With a number of assumptions [4,7], two curves, representing the aggregate expectedvalue and aggregate variance are formed by summation of the individual curves. Furtherassuming that the aggregate random variable is normally distributed around the aggregateexpected value, the expected value and the standard deviation of the random variable definea distribution at timet . This is illustrated in Fig. 8. The area under the curve greater thanthe maximum capacity constraint is used as an estimate of the probability of breakage.

SumHeight and VarHeight texture measurements are both used to indicate the resourceand time point with maximum criticality. In the case of SumHeight, criticality is definedusing aggregate demand while for VarHeight, it is defined using the estimate probability ofconstraint breakage. A heuristic technique can then be used to derive a new commitmentwhich attempts to decrease that maximum criticality. For example, in [10], the individualand aggregate curves created by the SumHeight texture are used to identify and sequencea pair of activities which contend for the critical resource at the critical time point.

5.2. Extending texture-based heuristics

The texture measurements presented above are based on an analysis of the constraintgraph to identify the critical points where a commitment should be made, followed bya commitment that attempts to decrease that criticality. Expected PEX values representpotentially important search information and therefore should be embedded in the texturemeasurements to ensure that they are taken into account in the estimation of criticality at asearch state.

The PEX variables affect texture-based heuristics in two ways. First, it is desirable toincorporate the expected PEX values into the underlying texture measurement estimation

Page 17: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 227

technique. The criticality of an activity may be very different if it has a 0.125 probabilityof executing than if it has a 0.5 probability. Second, once textures have been calculated, thepresence of PEX variables expands the types of heuristic commitments that can be made.

5.2.1. Adding PEX to texture curvesThe sole modification to texture measurements to incorporate expected PEX values is

to apply a vertical scaling factor to the individual activity demand. If the expected PEXvalue of activityA is 0.5, the individual demand at any time pointt , estA 6 t < lftA, ishalf what the demand would be if the PEX variable were assigned to 1. This modificationfits with our semantic interpretation of individual demand to be the probabilistic demandof an activity at a time point. Because we interpret an expected PEX value as an activity’sprobability of existence, an activity that has only a 50% likelihood of existing has halfthe probabilistic demand of an identical activity that will definitely exist. This is the sameway that the probability of existence of an activity is taken into account in the KBLPSscheduler [14].

Recall that the individual demand,ID(A,R, t), is (probabilistically) the amount ofresourceR, required by activityA, at time t as calculated in Eq. (1). The modificationto this calculation that incorporates PEX,IDPEX(A,R, t) simply multiplies byAPEX, theexpected PEX value of activityA:

IDPEX(A,R, t)=APEX× ID(A,R, t). (4)

Clearly, when the expected PEX value is equal to 1,IDPEX is equal toID.

5.2.2. New heuristic commitmentsIndependent of the texture measurement used, the basic texture algorithm remains the

same (withIDPEX replacingID) up to the point where a commitment is chosen. That is,the individual demands are calculated and aggregated, and the resource and time point withhighest criticality is identified. To incorporate PEX variables, we follow the same intuitionas in our non-PEX, texture-based heuristics: make a commitment that will tend to mostreduce the criticality of the most critical resource.

The procedure for generation of heuristic commitment techniques in the presence ofPEX variables is as follows. We identify three activities:

(1) The activity, A, with unassigned PEX variable,APEX, and with the highestindividual demand for the critical resource,R∗, at the critical time point,t∗, of allactivities with unassigned PEX variables.

(2) The pair of activities,B andC, that are not currently sequenced, with PEX variablesBPEX= 1 andCPEX= 1, and with the highest individual demand for the criticalresource at the critical time point of all activities with a PEX variable assigned to1. Without loss of generality, assume that the individual demand of activityB atthe critical time point is greater than or equal to the individual demand ofC at thecritical time point.

The heuristic commitment is found by comparing the individual demand ofA at t∗ withthat ofB. If the individual demand ofA is higher, then it is the most critical activity. SinceA has a possibility of not existing, the heuristic decision to reduce criticality is to remove

Page 18: Constraint-directed techniques for scheduling alternative activities

228 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

A from the schedule by setting its PEX variable to 0. On the other hand, ifB has the higherindividual demand, then it is necessary to sequenceB andC to attempt to reduce criticality.

If the heuristic PEX commitment is retracted via a complete retraction technique, wesoundly post its opposite, setting the PEX variable ofA to 1. Similarly, if the sequencingcommitment is retracted, we post the opposite sequence.

The adaptation of the SumHeight and VarHeight heuristics by adding the PEX reasoningresults in two new heuristic commitment techniques which we refer to as SH-PEX and VH-PEX, respectively.

5.2.3. Sequencing the critical activitiesThe final detail of the texture-based heuristics are the heuristics for sequencing activities

B andC, that is, the pair of critical activities, both of which have a PEX variable assignedto 1. We use the sequencing heuristics presented in Beck [8,10].

5.3. Other heuristics

To form a basis of comparison for the quality of the texture-based heuristics for PEX, wemodify other heuristics to incorporate the PEX variables. Here we present the modificationsto PCP and LJ heuristics.

5.3.1. PCP-PEXThe Precedence Constraint Posting(PCP) heuristic [17,42] identifies the pair of

activities on the same resource that are not sequenced and that have the minimum biased-slack measurement. These two activities are sequenced to preserve the maximum amountof slack. To adapt the PCP heuristic to activities with PEX variables, we follow the intuitionthat a commitment should preserve the maximum amount of slack.

The adaptation first specifies that the biased-slack measurement is calculated only foractivity pairs such that neither activity has its PEX variable assigned to 0. The followingthree conditions then apply to the activity pair with the smallest biased-slack:

(1) If both activities have a PEX variable assigned to 1, follow the PCP heuristic andpost the sequencing constraint that preserves the most slack.

(2) If one activity,A, has a PEX variable assigned to 1 and the other,B, has anunassigned PEX variable, the greatest amount of slack will be preserved by settingthe PEX variable ofB to 0.B will be completely removed from competition withAthereby maximizing the resulting slack.

(3) If both activities have unassigned PEX variables, the greatest amount of slack willbe preserved by setting the PEX variable of the activity with the longest durationto 0. By removing the activity with maximum duration, we maximize the resultingslack between the critical activity pair.

If any of these commitments is retracted, we can post its opposite (the other sequencefor case (1), or setting the PEX variable to 1 in cases (2) and (3)) to guarantee a completesearch.

5.3.2. LJ-PEXTheLeft-Justified Random(LJ) heuristic [31,32], finds the smallest earliest finish time

of all the unscheduled activities and then identifies the set of activities which are able to

Page 19: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 229

start before this time. One of the activities in this set is selected randomly and scheduledat its earliest start time. When backtracking, the alternative commitment is to update theearliest start time of the activity to the minimum earliest finish time of all other activitieson that resource.

Our modification of LJ to incorporate PEX variables, LJ-PEX, performs the followingsteps:

(1) Find the smallest earliest finish time of all activities with PEX variable not assignedto 0.

(2) Identify the set of activities with PEX variable not assigned to 0 that can start beforethe minimum earliest finish time.

(3) Randomly select an activity,A, from this set.(4) AssignA to start at its earliest start time and assign its PEX variable,APEX, to 1.The alternative commitment, should backtracking undo the commitment on activityA,

is to update the earliest start time ofA to the minimum earliest finish time of all otheractivities with the PEX variable not assigned to 0, on the same resource asA. Note that thealternative does not contain a PEX commitment, which means that subsequent heuristic andimplied commitments can still assignAPEX to either 1 or 0. This ensures completeness ofthe search. With chronological backtracking, if the commitment on activityA is undone, ithas been derived thatA cannot start at its earliest start time in any schedule. The alternativethen is thatA starts later or thatA does not execute at all. For a complete search we needto preserve these two alternatives when backtracking.

5.4. The information content of heuristic commitment techniques

One of the key differences among the heuristics that incorporate PEX is the extent ofthat incorporation. The texture-based heuristics use the expected PEX value to calculatethe underlying individual demand of an activity and so it has a deep impact on the heuristiccommitments that are made. LJ-PEX and PCP-PEX, in contrast, only use the PEX variable,not its expected value: these heuristics do not use the fact that one activity may have anexpected PEX value of 0.125 while another an expected PEX value of 0.5. We predict that,because the texture-based heuristics take into account the information represented by theexpected value, they will outperform heuristics that do not use that information.

6. Empirical evaluation

The empirical evaluation of the PEX techniques in this paper focuses on problems withalternative process plans and problems with both alternative process plans and alternativeresources. The PEX techniques presented are applicable, without extension, to both typesof problems as an activity with alternative resources is simply treated as a nested alternativewithin a process plan.

6.1. Experimental design

The primary purpose of the experimental evaluation is to determine the efficacy of usingexpected PEX values as part of the information underlying heuristic commitments. As

Page 20: Constraint-directed techniques for scheduling alternative activities

230 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

noted above, among the heuristic commitment techniques, only SH-PEX and VH-PEXuse the expected value of the PEX variable in each search state to inform their decisionmaking. An important component of the empirical evaluation is to determine if using thisextra information results in better heuristic commitments and overall search performance.A second purpose is the evaluation of the PEX-edge-finding techniques. Given therelatively high time-complexity of the propagators, we want to evaluate their efficacy interms of overall search performance.

Two of the obvious interesting parameters for alternative process plan problems is thenumber of alternatives in each process plan and the size of the overall scheduling problems.In Experiment 1 we look at the former while examining the latter in Experiment 2. Bothexperiments use a fully crossed design with makespan factor as the second independentvariable.

The overall pattern we predict in Experiment 1 is that as the number of alternativesincreases, the requirement for direct reasoning about the alternatives will become moreimportant to good algorithmic performance. For Experiment 2, we focus on a more globalfactor of difficulty: the problem size. Our primary interest is to see how the algorithmswith higher complexity components (such as PEX-edge-finding) are able to scale in termsof problem solving ability in relation to the lower complexity algorithms.

In our final experiment, Experiment 3, we incorporate alternative resources into thealternative process plan problem sets from Experiment 1 (see Section 8.1.1 for a detaileddescription of this incorporation). The primary impact of the addition of alternativeresources is to greatly increase the range of expected PEX values across the activities in theproblem. As with the increase in the number of alternatives per process plan, we predictthe increase in the range of expected PEX values to favor the heuristics that make detaileduse of them in their heuristic commitment techniques.

6.2. The reporting of time-outs

The experiments in this paper are run with a bound on the CPU time. Each algorithmmust either find a schedule or prove that no schedule exists for a problem instance. If analgorithm is unable to do so within the CPU time limit (in all our experiments the limit is20 minutes), a time-out is recorded. A time-out indicates that the algorithm was unable tofind a solution or prove that no solution exists for a particular scheduling problem instance.

The primary reason for reporting time-out results is that it allows us to use problemsets that contain both soluble and over-constrained problems. The phase transition workin combinatorial problems such as SAT and CSP [24,25] demonstrates that the hardestproblem instances are found in locations of the problem space where approximately halfof the problems are over-constrained. While the space of scheduling problems is not aswell-understood as SAT or CSP in terms of phase transition phenomena [9], we wantto take advantage of this insight in order to generate challenging problem instances. Weconstruct our problem sets so that as the independent variable varies, the problem instancesmove from an over-constrained area in the problem space to an under-constrained area. Inthe former area, proofs of insolubility can often be easily found while in the latter area,solutions can be easily found. It is in the middle range of problems where we expect to findthe most difficult problems.

Page 21: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 231

The use of time-outs as a search statistic allows us to integrate search performance onover-constrained problems and soluble problems into a single statistic. The intuition is thatalgorithms fail when they can neither find a solution nor a proof of insolubility. By usingthe number of failures, in this way, we get a clearer picture of the algorithm performance.For example, plotting the number of problems for which a solution is found obscures thefact that some algorithms may be performing very well on over-constrained problems (byfinding proofs of insolubility) whereas others are not able to find any such proofs.

6.3. Summary of algorithms

Eight algorithms are used in the experiments. Each is an instantiation of the ODOconstraint-directed scheduling framework [5].

All algorithms use chronological backtracking and therefore can each be specified byidentifying the heuristic commitment and set of propagators used. Two sets of propagatorsare used:

(1) PEX Propagators: Temporal propagation, PEX-edge-finding exclusion, PEX-edge-finding not-first/not-last, and Constraint-Based Analysis (CBA).

(2) Non-PEX Propagators: Temporal propagation, Edge-finding exclusion, Edge-find-ing not-first/not-last, and Constraint-Based Analysis (CBA).

Table 3 presents the names by which we refer to each algorithm in the balance of thispaper.

In our experiments, each algorithm is run until it finds a solution or until a 20 minuteCPU time limit has been reached in which case failure is reported. The machine for allexperiments is a Sun Ultra-Sparc-IIi, 270 MHz, 128 M memory, running SunOS 5.6.

6.4. Performance measures

A number of performance measures are reported:• Fraction of problems timed-out—A primary measure of performance is the fraction

of problems that each algorithm was neither able to find a solution nor show that noneexists within the experimental time-limit.• Mean CPU time—For each problem set, we report the mean CPU time for each

algorithm.

Table 3The eight algorithms used in the alternative process plan experiments (see the textfor the components of the propagator sets)

Algorithms

Heuristic With PEX propagators With non-PEX propagators

SH-PEX SH-PEX-P SH-PEX-NP

VH-PEX VH-PEX-P VH-PEX-NP

PCP-PEX PCP-PEX-P PCP-PEX-NP

LJ-PEX LJ-PEX-P LJ-PEX-NP

Page 22: Constraint-directed techniques for scheduling alternative activities

232 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

• Mean number of backtracks—We also report the mean number of times that analgorithm backtracked while searching for a solution to the problems at a point inthe parameter space.• Mean number of heuristic commitments—The mean number of commitments found

by the heuristic commitment technique. A heuristic commitment is a commitmentmade by a heuristic technique. Unlike implied commitments, heuristic commitmentscan be mistaken and therefore represent a branching in the search tree.• Mean number of implied commitments—The mean number of commitments found by

the propagators. An implied commitment is a constraint that is added to the constraintgraph because it is already implied by the problem state. Implied commitmentsinclude those found by all propagators with the exception of temporal propagation.The temporal propagation commitments are omitted because they are implemented asthe removal of possible values from the domains of the start- and end-time variablesrather than the explicit addition of a constraint.• Mean number of total commitments—The mean total number of commitments (found

by the heuristic commitment technique and the propagators).When an algorithm times-out on a problem instance, the performance measures for

that problem are included in the calculation of the mean. While this inclusion means thatour results represent a lower-bound on performance, it avoids skewing results based ondiscarding data for a problem that some algorithm times-outs on.

Unless otherwise noted, statistical significance for each performance measure isevaluated with the boot-strap paired-t test [18] withp 6 0.0001.

Our interest in these experiments is the comparison of the four heuristic commitmenttechniques (SH-PEX, VH-PEX, PCP-PEX, and LJ-PEX) and an evaluation of the efficacyof PEX-edge-finding. The statistical analysis therefore compares the four heuristics witheach other in two conditions: with and without PEX-edge-finding. To address the questionof the usefulness of PEX-edge-finding, we also compare its use in four conditionscorresponding to each of the heuristics. A summary of these groups is shown in Table 4.

7. Alternative process plans

7.1. Experiment 1: Scaling with the number of alternatives

7.1.1. ProblemsWe expect that the number of alternatives in each process plan will have an impact

on the search performance. To examine algorithm performance under varying numbersof alternatives, we constructed four problem sets with varying maximum numbers ofalternatives in each process plan. To illustrate this construction we use a problem set witha maximum of three alternatives.

Each problem begins with an underlying job shop problem. All problems in thisexperiment have 10 activities per process plan and 10 resources. For a problem witha maximum of three alternatives per process plan, we generate 30 jobs of 10 activitieseach. These 30 jobs are then transformed into 10 process plans with alternatives. For eachjob we randomly choose the number of alternatives,k, it will have uniformly from the

Page 23: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 233

Table 4The groups of algorithms used in the statistical tests

Comparison group Purpose

SH-PEX-P

VH-PEX-P Compare heuristics when used with PEX-edge-finding

PCP-PEX-P

LJ-PEX-P

SH-PEX-NP

VH-PEX-NP Compare heuristics when used without PEX-edge-finding

PCP-PEX-NP

LJ-PEX-NP

SH-PEX-P Evaluate PEX-edge-finding with SH-PEX heuristic

SH-PEX-NP

VH-PEX-P Evaluate PEX-edge-finding with VH-PEX heuristic

VH-PEX-NP

PCP-PEX-P Evaluate PEX-edge-finding with PCP-PEX heuristic

PCP-PEX-NP

LJ-PEX-P Evaluate PEX-edge-finding with LJ-PEX heuristic

LJ-PEX-NP

interval [0,3]. We then combine randomly chosen portions of the nextk jobs with ouroriginal job to produce a single process plan withk alternatives. The combination processrandomly chooses the to-be-combined portion and the location in the original process planwhere the alternative is to be inserted. The only requirements are that each path betweena pair of XorNodes representing an alternative must have the same number of activitiesand that number must be greater than 1. The latter requirement avoids problem structuresthat are better categorized as alternative resources while the former requirement avoidssituations where an entire ten-activity process plan can have a two-activity alternative.Such a situation would lead to scheduling problems with essentially a single easy decisionto make (choose the shorter process plan). We prefer to generate harder problems and soavoid such situations. Fig. 9 illustrates the combination of three process plans into a singleprocess plan with two alternatives.

Sets of problems with a maximum of one, three, five, and seven alternatives per processplan were generated. Each set contains 20 problems. For each problem the job lower boundwas calculated taking into account the alternatives. This calculation finds the shortest path(where path length is determined by the sum of the durations of activities on a path) in eachjob. We then use a makespan factor spanning 1.0 to 1.5 (in steps of 0.1) to generate a totalof six problem sets of 20 problems each for each number of alternatives.

Page 24: Constraint-directed techniques for scheduling alternative activities

234 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

Fig. 9. Generating a single process plan with two alternatives.

Table 5The characteristics of the problems in Experiment 1

Problem set Number of activities per problem

(Max. # of alternatives) Minimum Mean Maximum

1 116 131.6 156

3 142 171.8 200

5 172 204.7 251

7 167 224.2 280

One of the results of this method of problem generation is that a solution to a problemwill have exactly the same number of activities as the underlying job shop problem. Priorto scheduling, however, each problem has a different number of activities depending on therandomly chosen number and size of alternatives. Table 5 shows the characteristics of theproblem sets in terms of the number of activities in the problem definition.

Page 25: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 235

Fig. 10. The fraction of problems in each problem set for which each algorithm timed-out.

7.1.2. ResultsThe proportion of the problems in each set for which each algorithm times-out is shown

in Fig. 10. Slightly obscured by the graph is the result that SH-PEX-P and VH-PEX-Pdo not time-out on any problems across all problem sets, and that there is no differencebetween PCP-PEX-P and PCP-PEX-NP. Statistical analysis indicates that regardless of theuse of PEX-edge-finding, the algorithms using VH-PEX, SH-PEX, and PCP-PEX eachtime-out on significantly fewer problems than the corresponding algorithm using LJ-PEX.With PEX-edge-finding there are no significant differences among SH-PEX-P, VH-PEX-P, and PCP-PEX-P, while without PEX-edge-finding the only significant difference notinvolving LJ-PEX is that PCP-PEX-NP times-out on significantly fewer problems than SH-PEX-NP (p 6 0.0005). In terms of the usefulness of PEX-edge-finding, SH-PEX-P, VH-PEX-P, and LJ-PEX-P time-out on significantly fewer problems than SH-PEX-NP, VH-PEX-NP, and LJ-PEX-NP respectively. There is no significant difference in performancebetween PCP-PEX-NP and PCP-PEX-P.

Turning to mean CPU time, Fig. 11 displays the mean CPU time across all problemsets. Overall, there is no significant difference between SH-PEX-P and VH-PEX-P. Bothalgorithms use significantly less mean CPU time than PCP-PEX-P, which in turn usessignificantly less mean CPU time than LJ-PEX-P. When PEX-edge-finding is not used,there is no difference among SH-PEX-NP, VH-PEX-NP, and PCP-PEX-NP, but all threeare significantly better than LJ-PEX-NP.

Holding the heuristic component constant, we see that SH-PEX-P, VH-PEX-P, and LJ-PEX-P all incur a lower mean CPU time than their corresponding non-PEX-edge-findingalgorithms, while there is no difference between PCP-PEX-P and PCP-PEX-NP.

Page 26: Constraint-directed techniques for scheduling alternative activities

236 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

Fig. 11. The mean CPU time in seconds for each problem set.

Other search statisticsOther search statistics reveal the following results:• VH-PEX-P makes significantly fewer backtracks (p 6 0.001), commitments (p 6

0.005), and heuristic commitments (p 6 0.0005) than SH-PEX-P. SH-PEX-P makessignificantly fewer backtracks, commitments, and heuristic commitments than PCP-PEX-P which in turn makes significantly fewer backtracks, commitments, andheuristic commitments than LJ-PEX-P.• VH-PEX-NP, SH-PEX-NP, and PCP-PEX-NP each make significantly fewer back-

tracks, commitments, and heuristic commitments than LJ-PEX-NP. In addition, VH-PEX-NP makes significantly fewer backtracks (p 6 0.005) and heuristic commit-ments (p 6 0.005) than SH-PEX-NP. The only other significant differences are in theoverall commitments, where VH-PEX-NP makes significantly fewer than (p6 0.005)SH-PEX-NP which in turn makes significantly fewer than PCP-PEX-NP (p6 0.005).• With each heuristic, the use of PEX-edge-finding results in significantly fewer

backtracks and heuristic commitments (p 6 0.0005 when PCP-PEX is the heuristic).In terms of total commitments, LJ-PEX-P is not significantly different from LJ-PEX-NP, while the difference is significant for the other three heuristic commitmenttechniques (p 6 0.005 for PCP-PEX-P versus PCP-PEX-NP).

7.1.3. SummaryExperiment 1 indicates that:• The LJ-PEX heuristic when used with or without PEX-edge-finding performs

significantly worse than the other heuristics across all the problem sets.

Page 27: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 237

Table 6The characteristics of the problems in Experiment 2

Problem set Number of activities per problem

(Size of underlying jobshop problem) Minimum Mean Maximum

5× 5 36 61.7 85

10× 10 172 204.7 251

15× 15 356 430.9 524

20× 20 652 738.8 857

• While there is no significant difference in terms of the number of problems timed-outamong SH-PEX-P, VH-PEX-P, and PCP-PEX-P, all other search statistics indicateVH-PEX-P and SH-PEX-P perform significantly better than PCP-PEX-P.• There is little performance difference among VH-PEX-NP, SH-PEX-NP, and PCP-

PEX-NP.• PEX-edge-finding improves scheduling performance when used with the VH-PEX,

SH-PEX, and LJ-PEX heuristics. No such improvement was found with PCP-PEXheuristic.

7.2. Experiment 2: Scaling with problem size

The purpose of Experiment 2 is to examine the scaling behavior of the algorithms as theproblem size gets larger, but the number of alternatives remains fixed.

7.2.1. ProblemsThe problems used in this experiment are generated in the same way as the problems

in Experiment 1. The difference is that rather than changing the maximum number ofalternatives in different problem sets, we hold that parameter fixed at five while varyingthe size of the underlying job shop problem. All problems in Experiment 1 had a 10× 10underlying job shop problem. For this experiment, we look at problems whose underlyingjob shop problems are of sizes 5×5, 10×10, 15×15, and 20×20. The problem set fromExperiment 1 with five alternatives is used again in Experiment 2. As with Experiment 1,we use the job lower bound and varying makespan factors to create six sets of 20 problemseach at each problem size.

Due to the problem generation, different problem instances of the same size problemhave slightly varying numbers of activities. Table 6 shows the characteristics of the problemsets.

7.2.2. ResultsThe proportion of problems timed-out for each algorithm is shown in Fig. 12. SH-

PEX-P and VH-PEX-P time-out on significantly fewer problems than PCP-PEX-P whichin turn times-out on significantly fewer problems than LJ-PEX-P. Without PEX-edge-finding, the results are slightly different as PCP-PEX-NP times-out on significantly(p 6 0.001) fewer problems than SH-PEX-NP which in turn times-out on significantly

Page 28: Constraint-directed techniques for scheduling alternative activities

238 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

Fig. 12. The fraction of problems in each problem set for which each algorithm timed-out.

fewer problems than LJ-PEX-NP. VH-PEX-NP times-out on significantly fewer problemsthan LJ-PEX-NP, but there are no significant differences between VH-PEX-NP and SH-PEX-NP, or between VH-PEX-NP and PCP-PEX-NP. PCP-PEX-P shows no significantdifference when compared to PCP-PEX-NP while SH-PEX-P, VH-PEX-P, and LJ-PEX-P time-out on significantly fewer problems than their respective non-PEX-edge-findingalgorithms.

Turning to the mean CPU time results, the overall results are shown in Fig. 13. SH-PEX-P and VH-PEX-P each incur significantly less CPU time than PCP-PEX-P whichin turn incurs significantly less CPU time than LJ-PEX-P. Without PEX-edge-finding,however, PCP-PEX-NP uses significantly less CPU time than SH-PEX-NP (p 6 0.0005)which in turn uses significantly less CPU time than LJ-PEX-NP. There are no significantoverall differences between VH-PEX-NP and SH-PEX-NP, or between VH-PEX-NP andPCP-PEX-NP. Evaluation of PEX-edge-finding shows, overall, that using it results insignificantly lower CPU time with SH-PEX, VH-PEX, and LJ-PEXP, but not with PCP-PEX.

Other search statisticsA summary of the other search statistics is as follows:• SH-PEX-P and VH-PEX-P each make significantly fewer backtracks, commitments,

and heuristic commitments than both PCP-PEX-P and LJ-PEX-P. There are nosignificant differences in these statistics between PCP-PEX-P and LJ-PEX-P, orbetween SH-PEX-P and VH-PEX-P.

Page 29: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 239

Fig. 13. The mean CPU time in seconds for each problem set.

• VH-PEX-NP makes significantly fewer backtracks (p 6 0.001) and heuristic com-mitments (p6 0.005) than SH-PEX-NP while making significantly fewer backtracks,commitments, and heuristic commitments than either PCP-PEX-NP or LJ-PEX-NP.SH-PEX-NP and PCP-PEX-NP each make significantly fewer backtracks and heuris-tic commitments than LJ-PEX-NP. In addition, SH-PEX-NP makes fewer commit-ments than either PCP-PEX-NP or LJ-PEX-NP. There are no other significant differ-ences among the non-PEX-edge-finding algorithms.• The algorithms using PEX-edge-finding all make significantly fewer backtracks and

heuristic commitments than their counterparts that do not use the propagator. In termsof total commitments, however, the only significant difference is that PCP-PEX-Pmakes significantly fewer than PCP-PEX-NP.

7.2.3. SummaryThe results of Experiment 2 indicate that:• With PEX-edge-finding, the algorithms using the VH-PEX and SH-PEX heuristics

outperform the one using PCP-PEX which in turn outperforms the one using LJ-PEX.• Without PEX-edge-finding, however, the relative performance changes: PCP-PEX

outperforms SH-PEX which in turn outperforms LJ-PEX. VH-PEX shows few signif-icant differences with either SH-PEX or PCP-PEX while significantly outperformingLJ-PEX.• PEX-edge-finding typically results in better overall performance when used with SH-

PEX, VH-PEX, and LJ-PEX. There is little difference between PCP-PEX-P and PCP-PEX-NP.

Page 30: Constraint-directed techniques for scheduling alternative activities

240 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

8. Combining alternative process plans and alternative resources

In our final experiment, we look at problems containing both alternative process plansand alternative resources.

8.1. Experiment 3: Scaling with the number of alternatives

8.1.1. ProblemsAll problems for this experiment are transformations of the problems used in Exper-

iment 1. In those problems, each activity has only one resource alternative and a singlepossible duration.

Alternative resources were added to each activity by randomly generating the totalnumber of resource alternatives following the distribution shown in Table 7. The originalresource requirement and duration on that resource are preserved in the new problem.In addition, the new resource alternatives (if any) are randomly chosen with uniformprobability from among all the other resources in the problem. The duration of the activityon each new alternative resource is generated by multiplying the activity’s original durationby a randomly chosen factor in the domain[1.0,1.5] and then rounding to the nearestinteger value. Note that an activity that is specified to have one alternative resource hasonly one resource on which it can execute: the original resource from the job shop problem.

These transformations result in problems such that:• The original job lower bound calculated in Experiment 1 is still a valid lower bound.

All alternative resources require the activity to have at least as large a duration as in theoriginal problem; therefore, the shortest path in a job, including resource alternatives,remains the same.• There is likely to be widely varying expected PEX values between activities. The

theoretical range on the expected PEX value of an activity,A, at the beginningof a problem with seven alternatives is shown in Expression (5). The minimumexpected PEX value is possible for an activity that represents one of six possibleresource alternatives while the original activity (without resource alternatives) wasnested inside the seven process plan alternatives. Widely ranging expected PEX valuesrepresent non-uniformities in problem structure: an activity with a high expected PEX

Table 7The distribution of alternative resources for theproblems in Experiment 3

Number of alternative Probabilityresources per activity

1 0.03125

2 0.5

3 0.25

4 0.125

5 0.0625

6 0.03125

Page 31: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 241

Fig. 14. The fraction of problems in each problem set for which each algorithm timed-out.

value is far more likely to execute than an activity with a low expected PEX value.We would predict, therefore, that heuristics that reason explicitly about the expectedPEX value (i.e., SH-PEX and VH-PEX as opposed to the other heuristic commitmenttechniques) will be able to make higher quality commitments.

13 × 2−86APEX6 1. (5)

8.1.2. ResultsThe fraction of problems in each problem set that each algorithm timed-out on is

displayed in Fig. 14. These results indicate, regardless of the use of PEX-edge-finding, thatSH-PEX outperforms VH-PEX which is better than LJ-PEX which in turn outperformsPCP-PEX. In addition, each heuristic times-out on significantly fewer problems whenusing PEX-edge-finding than without it.

The results for mean CPU time are displayed in Fig. 15. These results are consistentwith the timed-out results on all accounts. Comparing heuristics shows that SH-PEX has asignificantly lower mean CPU time than VH-PEX. VH-PEX incurs significantly less CPUtime than LJ-PEX which in turn has a significantly lower mean CPU time than PCP-PEX.The PEX-edge-finding results indicate that each heuristic incurs a significantly lower meanCPU time when PEX-edge-finding is used.

Other search statisticsThe other search statistics evaluated (number of backtracks, number of commitments,

and number of heuristic commitments) agree in the relative ranking of the performanceof each heuristic: regardless of the PEX-edge-finding condition, SH-PEX significantly

Page 32: Constraint-directed techniques for scheduling alternative activities

242 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

Fig. 15. The mean CPU time in seconds for each problem set.

outperforms VH-PEX which significantly outperforms LJ-PEX which in turn significantlyoutperforms PCP-PEX. The only exception to this pattern is in comparing the numberof heuristic commitments made by LJ-PEX and PCP-PEX where there is no significantdifference.

All heuristics exhibited significantly fewer backtracks and fewer heuristic commitmentswhen used with PEX-edge-finding. Interestingly, VH-PEX, PCP-PEX, and LJ-PEX allmade significantly more overall commitments when using PEX-edge-finding than whennot using it. There is no significant difference in overall commitments between PEX-edge-finding conditions when SH-PEX is the heuristic commitment technique.

8.1.3. SummaryExperiment 3 strongly indicates that, independent of the propagator condition, SH-PEX

outperforms VH-PEX which outperforms LJ-PEX which in turn outperforms PCP-PEX. Inaddition, PEX-edge-finding results in better performance regardless of the heuristic used.

9. Discussion

The problem structure hypothesis that we set out to investigate in the paper states thatas a scheduling problem becomes more complex, a deeper understanding of the problemstructure is necessary for successful heuristic search [41]. Overall our results supportthis hypothesis as it was the heuristics that exploited the PEX information that achievedsuperior performance. Support for the problem structure hypothesis is especially clearwhen the results of Experiment 3 are contrasted with those of Experiments 1 and 2. While

Page 33: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 243

the PEX-based heuristics (SH-PEX and VH-PEX) achieved performance that equaled orbettered all other heuristics in the first two experiments, in the final experiment, theirperformance was dramatically superior. The central manipulation to produce the differentproblem structure in Experiment 3 was the more widely ranging expected PEX values.Because this added complexity is represented in the expected PEX values and because SH-PEX and VH-PEX take the expected PEX values into account in their problem structureanalysis, the PEX-based heuristics achieve significantly better performance: as the problemcomplexity increases, knowledge of the problem structure is increasingly important forsuccessful heuristic search.

9.1. Heuristics

Overall, while SH-PEX and VH-PEX outperform PCP-PEX with PEX-edge-finding,especially in Experiment 3, their comparison without PEX-edge-finding is less clear-cut.In Experiment 1 there are few differences; in Experiment 2, PCP-PEX is superior to SH-PEX; in Experiment 3 SH-PEX is superior to VH-PEX which is superior to PCP-PEX.LJ-PEX is outperformed by all other heuristics (regardless of the use of PEX-edge-finding)in Experiments 1 and 2, but outperforms PCP-PEX (again regardless of the use of PEX-edge-finding) in Experiment 3.

Experiment 3 clearly demonstrates the result of exploiting the extra informationrepresented by the expected PEX values in the texture measurement upon which theheuristic commitment technique is based. The widely ranging expected PEX valuesrepresent a non-uniformity in the problem structure that is successfully exploited by theSH-PEX and VH-PEX heuristics. In the other experiments, though the range of expectedPEX values is not as wide, SH-PEX-P and VH-PEX-P are still the best schedulingalgorithms of the ones tested.

The comparison between PCP-PEX and SH-PEX is interesting:• Experiment 1 shows no difference regardless of the use of PEX-edge-finding.• Experiment 2 shows that PCP-PEX is better than SH-PEX without PEX-edge-finding,

but worse with PEX-edge-finding.• Experiment 3 shows that PCP-PEX is much worse than SH-PEX both with and

without PEX-edge-finding.These results demand an explanation both for why PCP-PEX performs so poorly in

Experiment 3 and why it performs so well in Experiments 1 and 2.We know, based on the results of [10], that on some job shop scheduling problem sets

without resource-level non-uniformities, PCP is able to outperform SumHeight. No suchnon-uniformities were examined in this paper as our primary interest was the evaluationof reasoning about alternatives. A possible explanation for the good performance of PCP-PEX is that no resource-level non-uniformity exists for our experimental problem sets;therefore, the heuristic that does not specifically look for such non-uniformity achievesbetter overall performance.

A second explanation for the good quality of PCP-PEX is the quality of the underlyingbiased-slack heuristic. When there are no resource-level non-uniformities, a heuristic basedon the identification of minimum-slack activity pairs and the subsequent commitment tomaintain as much slack as possible has been shown to perform well in job shop scheduling.

Page 34: Constraint-directed techniques for scheduling alternative activities

244 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

Some of the quality of that heuristic is maintained when PEX is added. Again, in theabsence of resource-level non-uniformities, a heuristic that identifies the pair of activitieswith the smallest time in which they may be sequenced and seeks to maximize that time(through a PEX commitment or a sequencing commitment) seems to be a reasonableheuristic to establish both a selection of activity alternatives and a sequencing of activitiesthat satisfies the resource constraints.

Still the results of Experiment 3, especially the relative performance of PCP-PEX andLJ-PEX, demand explanation. We believe that these results are due to PCP’s degradedability to identify critical activity pairs in the presence of PEX values. In the original PCPheuristic, only activity pairs for which Constraint-Based Analysis (CBA) propagation hasnot inferred a sequence are examined to find the pair with minimum biased-slack [17,42].When at least one member of an activity pair has an unassigned PEX variable, however,the CBA propagator cannot infer a sequence and therefore, regardless of the activity timewindows, the biased-slack of the activity pair is evaluated. Activity pairs with little overlapwill tend to have a very low biased-slack and therefore the heuristic will tend to focus onsuch activity pairs. To take the extreme case of an activity pair with disjoint time windows,the activities are not actually competing with each other for a resource reservation and socan hardly be a truly critical pair, yet they have a very small biased-slack. Furthermore,the commitment to set the PEX value of one of the activities to 0 is made on the intuitionthat, if such a commitment is not made, there is a high likelihood that the two activitieswill later over-capacitate the resource. But this cannot be the case with disjoint activities,and the likelihood that an activity pair with a small overlap will lead to an over-capacityis relatively small. This reasoning points to a modification of the PCP-PEX heuristic tocalculate the biased-slack only for those activity pairs that would not have an impliedsequence if they both had a PEX variable assigned to 1. Such a modification remains asfuture work.

9.2. PEX-edge-finding

Through almost all experiments and experimental conditions, PEX-edge-finding wasshown to be beneficial to the overall problem solving ability of an algorithm. The onlyexception is when the PCP-PEX heuristic is used: little difference was seen between thePCP-PEX-P and PCP-PEX-NP except in Experiment 3 where PEX-edge-finding provedbeneficial.

In general, these results are as expected. Given the significant increase in theperformance of scheduling algorithms with the use of edge-finding propagators [31], weexpect that some gain is likely with the PEX-edge-finding variation. Our intuitions asto why PEX-edge-finding (and indeed propagation, in general) should improve searchperformance rests on two impacts of propagation. First, propagation techniques reducethe search space by removing alternatives that would otherwise have to be searchedthrough. Second, propagators improve the information upon which heuristics can bebased. PEX-edge-finding improves both the information represented in the expected PEXvalues (by pruning inconsistent activity alternatives) and the information represented inthe time windows of activities (because it infers unary temporal constraints on activitieswith unassigned PEX variables). SH-PEX and VH-PEX benefit from both improvements.

Page 35: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 245

Fig. 16. The mean percentage of commitments in each problem set made by the heuristic commitment techniquefor Experiment 1.

However, the PCP-PEX heuristic, because it does not use the expected PEX values, doesnot benefit from the extra information that they represent.

An additional, and not incompatible, explanation for the PCP-PEX results vis-a-visPEX-edge-finding is that PCP-PEX commitments tend to result in less propagation. Inthe job shop problems in [10], it was observed that a relatively large percentage of the PCPcommitments were heuristic commitments as compared to those for SumHeight. It wasargued that this arose from the fact that SumHeight tended to make a commitment wheremany activities were competing for a resource and time point while PCP simply looked forthe most tightly constrained pair of activities. The subsequent propagation from a heuristiccommitment therefore would tend to be higher when SumHeight is used. The same patterncan be seen here as shown in Fig. 16. Using the results from Experiment 1, we see that SH-PEX-P and VH-PEX-P make a significantly smaller percentage of heuristic commitmentsthan PCP-PEX-P. While a PCP-PEX-P incurs the computational cost, the benefits are notapparent because the heuristic commitments do not result in significant propagation.

10. Related and future work

Representation and reasoning about alternative activities opens a number of areas offuture research. While we have shown that the use of expected PEX values can lead tosuperior scheduling performance, there are a number of issues surrounding the scaling ofthe PEX approach that need to be addressed. In particular, the explicit representation of

Page 36: Constraint-directed techniques for scheduling alternative activities

246 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

each possible alternative activity results in scaling issues [19]. Investigation of methods toreduce the alternative activities that actually need to be represented forms important futuretasks. Given the positive impact of the PEX-edge-finding propagator, techniques to reduceits average and worst-case time-complexity will also contribute to overall schedulingperformance and help to combat scaling issues.

The PEX approach to alternative activities scheduling problems can be viewed as abottom-up approach. Alternative activities are fully represented in the scheduling problemand choosing alternatives is fully integrated into the scheduling algorithm. In contrast,a top-down approach to scheduling with alternatives can be seen in number of placesin the AI research literature [19,27,38,43,44]. In such systems, high-level and, in somecases, domain dependent, knowledge and heuristics are brought to bear on the problemof pruning alternatives before the actual scheduling takes place. While these techniquesavoid many of the scaling problems of the PEX approach, the heuristics are not informedby as much detailed information as the PEX heuristics. As a result, the quality of theheuristic decisions and overall solution tends to be inferior to the PEX solution in thoseproblems where the PEX approach is not overwhelmed by the size of the requiredrepresentation [19]. Obviously, there is a trade-off in terms of the effort required torepresent and reason about the detailed alternative information, and the quality of theheuristic decisions that can be made. Further research is required to better understand thistrade-off and, perhaps, to find ways to combine the top-down approach with the bottom-upapproach.

Reasoning about activity alternatives either with a PEX-based formulation or with amore top-down approach blurs the distinction between scheduling and planning. One ofthe major assumptions about the alternative scheduling problems addressed in this paperis that all activities are known before scheduling begins. Imagine, however, a problemwith demands for a number of finished goods and a number of process plans with whicheach can be produced. Each finished good process plan may require a number of otherinventories to be produced and these inventories, in turn, have alternative process planswhich themselves require further inventories to be executed. This cascade of process plansterminates eventually with raw material supply events. The problem now begins to lookmore like planning (with scheduling constraints) than scheduling. A set of goals must beachieved; however, actions to achieve goals potentially conflict with one another and mayintroduce further sub-goals. The combination of scheduling and planning techniques toaddress such problems has been begun in work such as [27,38,39]; however, much remainsto be investigated.

In this paper, we made the assumption that the expected PEX values are evenlydistributed among the paths between a pair of XorNodes. This is a “low knowledge”assumption: we assume we have no other information with which we can bias the expectedPEX values. In an application, we may have a preference for one alternative process planover another. Given such a preference, the overall problem then begins to look morelike a fuzzy or valued constraint satisfaction problem [20,34,40]. It would seem naturalto incorporate these preferences by biasing the expected PEX values and, therefore, theindividual texture curves. One difficulty with this approach, however, is the semantics ofthe individual demand curves. We have been interpreting these curves as a representation ofthe probability that an activity will demand a resource at a time point. It is not clear that this

Page 37: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 247

interpretation is well-founded if the individual curves are biased by preferences. At the veryleast, the heuristic commitment technique used here does not extend to biased curves. Theheuristic chooses, if possible,not to execute the activity with highest individual demandfor a critical time point and resource. If the individual demand is high because there is ahigh preference to execute the activity, choosing not to execute the activity is unlikely toquickly lead to high quality solutions.

Finally, it should be noted that the use of PEX variables to govern the existence ofactivities can be seen as an instance of a Conditional Constraint Satisfaction Problem(CCSP) [35] (originally called Dynamic Constraint Satisfaction Problem [30]). In sucha problem, only “active” variables need be assigned a value in a solution and “activityconstraints” define which variables become active depending on the values assigned tosubsets of other variables. Given an initial set of active variables, the assignment of avalue to a variable may cause new variables to become active and, therefore, to requirea value in order to solve the problem. Such a problem formulation is very natural forapplications such as configuration [30]. In the work presented here, the PEX variables andany activities not enclosed by XorNodes form the initial set of active variables. The onlytype of activity constraint is the one that links the value of the PEX variable with the othervariables in an Activity: if the PEX variable is assigned to 1, all the other variables in thatactivity are active, while if assigned to 0, the other variables are inactive. The link betweenour work and CCSP suggests that a possible area for future work is in generalizing thetechniques used here. To our knowledge no one has either attempted to extend advancedconstraint propagation techniques to CCSPs (such as we have done for PEX-edge-finding)nor attempted to incorporate the probability that a variable will be active into heuristicsearch techniques for CCSPs.

11. Conclusion

In this paper, we introduced the notion of the probability of existence (PEX) of anactivity and used it to expand constraint-directed scheduling representation and reasoningto account for alternative activities: an activity present in the original problem definitiondoes not necessarily have to be scheduled to achieve a solution.

The modeling of PEX required extensions to the constraint representation of activitiesand of the temporal network. Algorithms for the propagation of expected PEX values arepresented along with modifications to temporal propagation to account for the fact that anactivity might not exist in a final solution. In addition, heuristic commitment techniques andtwo edge-finding propagators are extended to account for the presence of PEX variables.

Experimental results indicated that incorporating expected PEX values into the texturemeasurements upon which the heuristic commitment techniques are based results in sig-nificantly higher quality commitments and better overall search performance. Performancedifferences are especially large when there is a wide range of expected PEX values in aproblem. Experimental results also validated the use of PEX-edge-finding which, in mostcases, leads to significantly better overall search performance.

Our primary theoretical motivation for the work in this paper is the investigationof the problem structure hypothesis which states that as a problem becomes more

Page 38: Constraint-directed techniques for scheduling alternative activities

248 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

complex, understanding its structure becomes increasingly important for successfulheuristic search [41]. The results in this paper support the problem structure hypothesis: asthe scheduling problems are made more complex by the addition of alternative activities,representation of the alternative information and heuristic reasoning that takes into accountthat information results in superior overall problem solving performance.

Acknowledgements

This research was performed while the first author was a Ph.D. student at the Departmentof Computer Science, University of Toronto. It was funded in part by the Natural SciencesEngineering and Research Council, IRIS Research Network, Manufacturing ResearchCorporation of Ontario, Baan Limited, and Digital Equipment of Canada. Thanks toAndrew Davenport and Angela Glover for discussion of and comments on previousversions of this paper.

References

[1] P. Baptiste, C. Le Pape, Disjunctive constraints for manufacturing scheduling: Principles and extensions, in:Proc. 3rd International Conference on Computer Integrated Manufacturing, 1995.

[2] P. Baptiste, C. Le Pape, Edge-finding constraint propagation algorithms for disjunctive and cumulativescheduling, in: Proc. 15th Workshop of the UK Planning and Scheduling Special Interest Group, 1996.Available from http://www.hds.utc.fr/ baptiste/.

[3] P. Baptiste, C. Le Pape, W. Nuijten, Incorporating efficient operations research algorithms in constraint-based scheduling, in: Proc. 1st Joint Workshop on Artificial Intelligence and Operations Research, June1995. Workshop proceedings available on world wide web from http://www.cirl.uoregon.edu/aior/.

[4] J.C. Beck, Texture measurements as a basis for heuristic commitment techniques in constraint-directedscheduling, Ph.D. Thesis, University of Toronto, 1999.

[5] J.C. Beck, A.J. Davenport, E.D. Davis, M.S. Fox, The ODO project: Toward a unified basis for constraint-directed scheduling, J. Scheduling 1 (2) (1998) 89–125.

[6] J.C. Beck, A.J. Davenport, C. Le Pape, Introduction to the special issue on industrial constraint-directedscheduling, CONSTRAINTS, in press.

[7] J.C. Beck, A.J. Davenport, E.M. Sitarski, M.S. Fox, Beyond contention: Extending texture-based schedulingheuristics, in: Proc. AAAI-97, Providence, RI, AAAI Press, Menlo Park, CA, 1997.

[8] J.C. Beck, A.J. Davenport, E.M. Sitarski, M.S. Fox, Texture-based heuristics for scheduling revisited, in:Proc. AAAI-97, Providence, RI, AAAI Press, Menlo Park, CA, 1997.

[9] J.C. Beck, K. Jackson, Constrainedness and the phase transition in job shop scheduling, Technical Report,School of Computing Science, Simon Fraser University, Burnaby, BC, 1997.

[10] J.C. Beck, M.S. Fox, Dynamic problem structure analysis as as basis for constraint-directed schedulingheuristics, Artificial Intelligence 117 (2000) 31–81.

[11] P. Brucker, O. Thiele, A branch & bound method for the general-shop problems with sequence dependentset-up times, OR Spektrum 18 (1996) 145–161.

[12] J. Carlier, E. Pinson, An algorithm for solving the job-shop problem, Management Sci. 35 (2) (1989) 164–176.

[13] J. Carlier, E. Pinson, Adjustment of heads and tails for the job-shop problem, European J. Oper. Res. 78(1994) 146–161.

[14] Carnegie Group Inc., Knowledge-based logistics planning system, Internal Documentation, 1994.[15] Y. Caseau, F. Laburthe, Improved CLP scheduling with task intervals, in: Proc. 11th International Conference

on Logic Programming, MIT Press, Cambridge, MA, 1994.

Page 39: Constraint-directed techniques for scheduling alternative activities

J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250 249

[16] Y. Caseau, F. Laburthe, Improving branch and bound for jobshop scheduling with constraint propagation,in: Proc. 8th Franco–Japanese Conference CCS-95, 1995.

[17] C.C. Cheng, S.F. Smith, Applying constraint satisfaction techniques to job shop scheduling, Ann. Oper. Res.(Special Volume on Scheduling: Theory and Practice) 70 (1997) 327–378.

[18] P.R. Cohen, Empirical Methods for Artificial Intelligence, MIT Press, Cambridge, MA, 1995.[19] A.J. Davenport, J.C. Beck, An investigation into two approaches for resource allocation and scheduling, in:

INFORMS, 1999.[20] D. Dubois, H. Fargier, H. Prade, The use of fuzzy constraints in job-shop scheduling, in: Proc. IJCAI-93,

Chambéry, France, 1993.[21] M.S. Fox, Constraint-directed search: A case study of job-shop scheduling, Ph.D. Thesis, Carnegie Mellon

University, Intelligent Systems Laboratory, The Robotics Institute, Pittsburgh, PA, 1983. CMU-RI-TR-85-7.[22] M.S. Fox, N. Sadeh, C. Baykan, Constrained heuristic search, in: Proc. IJCAI-89, Detroit, MI, 1989,

pp. 309–316.[23] M.R. Garey, D.S. Johnson, Computers and Intractability: A Guide to the Theory of NP-Completeness,

W.H. Freeman, New York, 1979.[24] I.P. Gent, E. MacIntyre, P. Prosser, T. Walsh, The constrainedness of search, in: Proc. AAAI-96, Portland,

OR, Vol. 1, 1996, pp. 246–252.[25] I.P. Gent, T. Walsh, The hardest random SAT problems, in: B. Nebel, L. Dreschler-Fischer (Eds.), Proc. KI-

94: Advances in Artificial Intelligence, 18th German Annual Conference on Artificial Intelligence, Springer,Berlin, 1994, pp. 355–366.

[26] D.W. Hildum, Flexibility in a knowledge-based system for solving dynamic resource-constrained schedulingproblems, Ph.D. Thesis, Department of Computer Science, University of Massachusetts, Amherst, MA,1994. UMass CMPSCI TR 94-77.

[27] A. Kott, V. Saks, A multi-decompositional approach to integration of planning and scheduling—An appliedperspective, in: Proc. Workshop on Integrating Planning, Scheduling and Execution in Dynamic andUncertain Environments, Pittsburgh, PA, June 1998.

[28] C. Le Pape, Using a constraint-based scheduling library to solve a specific scheduling problem, in:Proc. AAAI-SIGMAN Workshop on Artificial Intelligence Approaches to Modelling and SchedulingManufacturing Processes, 1994.

[29] O. Lhomme, Consistency techniques for numeric CSPs, in: Proc. IJCAI-93, Chambéry, France, Vol. 1, 1993,pp. 232–238.

[30] S. Mittal, B. Falkenhainer, Dynamic constraint satisfaction problems, in: Proc. AAAI-90, Boston, MA, 1990,pp. 25–32.

[31] W.P.M. Nuijten, Time and resource constrained scheduling: A constraint satisfaction approach, Ph.D. Thesis,Department of Mathematics and Computing Science, Eindhoven University of Technology, 1994.

[32] W.P.M. Nuijten, E.H.L. Aarts, D.A.A. van Arp Taalman Kip, K.M. van Hee, Randomized constraintsatisfaction for job shop scheduling, in: Proc. IJCAI-93, Chambéry, France, 1993, pp. 251–262.

[33] F.S. Roberts, Applied Combinatorics, Prentice Hall, Englewood Cliffs, NJ, 1984.[34] Z. Ruttkay, Fuzzy constraint satisfaction, in: Proc. 3rd IEEE Conference on Fuzzy Systems, 1994, pp. 1263–

1268.[35] M. Sabin, E.C. Freuder, Detecting and resolving inconsistency and redundancy in conditional constraint

satisfaction problems, in: Proc. CP-98 Workshop on Constraint Reformulation, 1998.[36] N. Sadeh, Lookahead techniques for micro-opportunistic job-shop scheduling, Ph.D. Thesis, Carnegie-

Mellon University, Pittsburgh, PA, 1991. CMU-CS-91-102.[37] N. Sadeh, M.S. Fox, Variable and value ordering heuristics for the job shop scheduling constraint satisfaction

problem, Artificial Intelligence 86 (1) (1996) 1–41.[38] N.M. Sadeh, D.W. Hildum, T.J. Laliberty, J. McA’Nulty, D. Kjenstad, A. Tseng, A blackboard architecture

for integrating process planning and production scheduling, Concurrent Engineering: Research andApplications 6 (2) (1998).

[39] V. Saks, Distribution planner overview, Technical Report, Carnegie Group, Inc., Pittsburgh, PA, 1992.[40] T. Schiex, H. Fargier, G. Verfaillie, Valued constraint satisfaction problems: Hard and easy problems, in:

Proc. IJCAI-95, Montreal, Quebec, 1995.[41] H.A. Simon, The structure of ill-structured problems, Artificial Intelligence 4 (1973) 181–200.

Page 40: Constraint-directed techniques for scheduling alternative activities

250 J.C. Beck, M.S. Fox / Artificial Intelligence 121 (2000) 211–250

[42] S.F. Smith, C.C. Cheng, Slack-based heuristics for constraint satisfaction scheduling, in: Proc. AAAI-93,Washington, DC, 1993, pp. 139–144.

[43] T. Wagner, A. Garvey, V. Lesser, Design-to-criteria scheduling: Managing complexity through goal-directedsatisficing, in: Proc. AAAI-97, Providence, RI, 1997.

[44] T. Wagner, A. Garvey, V. Lesser, Criteria directed task scheduling, Internat. J. Approx. Reason. 19 (1998)91–118.