Zuhair Haddad/ Amr ElSersyCCC
Consolidated Contractors International Company, (CCC)
Building Information Modeling (BIM) CCC Group
First Digital Facility Modeling Conference in Kazakhstan
Zuhair Haddad/ Amr ElSersyCCC
Company Introduction
Building Information Modeling (BIM) CCC Group
Consolidated Contractors Company (CCC) was originally formed in 1952 in Lebanon
CCC, with it’s managing office based in Athens - Greece, currently employs approximately 114,000 people in its worldwide operations
CCC is an ISO 14001 and OHSAS 18001 certified company with the highest level of commitment to HSE
CCC is an ISO 9001:2008 certified company with the highest level of commitment to Quality
CCC is predominately a construction company, providing project management, engineering, procurement and construction services to the industry
Currently ranked 18th in ENR Top International Contractors (2011)
Ranked 1st in the Middle East
Zuhair Haddad/ Amr ElSersyCCC
Our CCC Family
Building Information Modeling (BIM) CCC Group
CCC is a family company with a unique set of family oriented values and traditions. They embody Trust, loyalty and hard work. Long term commitment Human Touch with our partners and workers. The
“Mu’allem” Concept Basic decentralized structures with strong central support
and audit functions (Matrix Structure). This resulted in: Maintaining an entrepreneurial attitude Localized touch, knowledge and relations Focus on quality and safety Commercial acumen. Long term oriented client relationship especially those working in multi location
Our family values and traditions contribute to our long term and successful mode of operations.
Zuhair Haddad/ Amr ElSersyCCC
HSE Certificates & Awards
Building Information Modeling (BIM) CCC Group
ExxonMobil Development Company (EMDC)
Safe Contractor HSE Award of the year 2009 for QGXII
Project in Qatar
75 million manhours worked without a Lost Time Incident at Pearl GTL Project in Qatar
Zuhair Haddad/ Amr ElSersyCCC
CCC Group
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
CCC Group
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
CCC Group
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
CCC Group
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
Engineering & Procurement
Building Information Modeling (BIM) CCC Group
Expertise
Buildings / Civil Works Oil and Gas Up Stream Gas Treatment Pipelines Seawater and Cooling Water Networks
Engineering Procurement & Support Office Facilities
Total of 400 Engineers, Designers, Expeditor Staff Office Area: 16,800 m2 in Mussafah Space for 600 plus staff & Client representatives
Current Annual Engineering Internal capacity
800,000 MHR
600,000 MHR ( Pure Engineering)
Zuhair Haddad/ Amr ElSersyCCC
CCC Plant & Equipment
Building Information Modeling (BIM) CCC Group
WORK/SURVEY BOATS& STANDARD FACILITIES
168
EARTHMOVINGEQUIPMENT
906
PIPELAYINGEQUIPMENT
201
WELDING MACHINES
8,131
AIRCOMPRESSORS
454
CIVIL ENGINEERING& CONSTRUCTION EQUIPMENT
1,345HEAVY DUTY
VEHICLES
2,319VEHICLES
& LIGHT TRUCKS
2,625CRANES977
ELECTRIC GENERATORS& LIGHTING TOWERS
675
TOTAL NO. OF EQUIPMENT:TOTAL VALUE OF EQUIPMENT:
17,801US$ 1,049 MILLION
Zuhair Haddad/ Amr ElSersyCCC
Heavy Lift Division
Building Information Modeling (BIM) CCC Group
CCC has been involved in the heavylift business since 1980 empoweredby a professional team consisting ofEngineers, draftsmen, specialists andsupervisors dedicated for this criticaloperation and following CompanySafety and Quality standards
The Heavy Lift Division provides thefollowing services: Heavy Lift turnkey project Heavy Lift Execution Heavy Lift Consultation Heavy Lift Management Heavy Lift Engineering
CCC owns over 978 cranes with acapacity ranging from 1600 to 5 tons.
Zuhair Haddad/ Amr ElSersyCCC
Fabrication Facilities
Building Information Modeling (BIM) CCC Group
CCC provides both mobile and permanent fabrication facilities.
Facility Type / Location Monthly Production
Mobile Facilities 40 Fabrication Shops
Pipe spool fabrication: 700 tons per fabshop
Steel structure fabrication: 300 tons per fabshop
ECG Facilities Permanent Facility in Equatorial Guinea
Pipe spool fabrication: 600 tons
Steel structure fabrication: 700 tons
NPCC Fabrication Facility
Permanent Facility in UAE
5,800 tons of fabricated steel structures for wellhead Jackets, Decks, Topsides, Modules, loading Terminals
Zuhair Haddad/ Amr ElSersyCCC
CCC Projects Highlights
Building Information Modeling (BIM) CCC Group
Dubai Mall
Dubai MallRas Laffan Common CoolingWater System - Qatar
Khursaniyah Gas Plant - KSA
Muscat International Airport - Oman
Zuhair Haddad/ Amr ElSersyCCC
CCC Projects Highlights
Building Information Modeling (BIM) CCC Group
Isomerization andRefinery Revamp - Oman
Baku - Tbilisi - Ceyhan Oil Pipeline Azerbijan
The Landmark Tower Abu Dhabi
Presidential PalaceAbu Dhabi
Sports Hall at Khalifa Sports City - Qatar
Zuhair Haddad/ Amr ElSersyCCC
CCC Projects Highlights
Building Information Modeling (BIM) CCC Group
Alba Phase II Expansion
Bioko Island, Equatorial Guinea
Komo Airport Papua New Guinea
Princess Noura - KSA
Nile Corniche Towers – Cairo Egypt
Pearl GTL Project - Qatar
Zuhair Haddad/ Amr ElSersyCCC
CCC Projects Highlights
Building Information Modeling (BIM) CCC Group
Qatargas II LNG
Ras Laffan Port Expansion - Qatar
New Port at Al Duqm - Oman
Barwa Commercial Avenue - Qatar
Karachaganak - Kazakhstan
Zuhair Haddad/ Amr ElSersyCCC
The BIM-5D Approach
Building Information Modeling (BIM) CCC Group
Conventional BIM-5D
vs.
Zuhair Haddad/ Amr ElSersyCCC
The BIM-5D Technology & Potentials - PLC
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D Challenges
Building Information Modeling (BIM) CCC Group
Challenges Psychological
(Traditional Methods, Resistance to Change, Accepting IT Solutions, Trust,
Complexity of the Construction Processes, Fast Increasing Demands of the Industry)
Challenges Technological
(SV competitions, Focus on Design, Interoperability, SW Pricing Strategies,
Lack of Efficient Solutions, Business Logic & Communicating Business
Needs)
Zuhair Haddad/ Amr ElSersyCCC
Interoperability an Infrastructural Challenge
Building Information Modeling (BIM) CCC Group
Different BIM Platforms Means
Disintegrated BIM (interoperability challenges)
How Can we Achieve An
Integrated BIM?
BIM1SV 1
BIM4 SV 4
BIM2 SV 2
INTEGRATED BIM
BIM3 SV 3
BIM1SV 1
BIM4 SV 4
BIM3 SV 3
BIM2 SV 2
DISINTEGRATED BIM
Zuhair Haddad/ Amr ElSersyCCC
Elements For Success Of BIM-5D Implementation
Building Information Modeling (BIM) CCC Group
Management Embracement of the 5D-BIM Methodology
Availability of Professional BIM Resources and Ensuring Their Commitment & Quality
Strong IT Infrastructure and Capabilities
Availability of Cost Effective Project Controls Solutions
Strong 5D Collaboration Platforms
Cultural Change & Transparency Building
Integrating BIM within Company’s/Project’s Workflows and Processes
Developing 5D-BIM Awareness & Training Strategies
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D requirements for further response
Building Information Modeling (BIM) CCC Group
BIM-5D is about access to rich integrated information
BIM-5D is a work process that streamlines your operation
BIM-5D is a management paradigm BIM-5D Enhances project delivery to
be more efficient and more effective
Towards BIM for Construction (5D)
Zuhair Haddad/ Amr ElSersyCCC
CCC BIM-5D History
Building Information Modeling (BIM) CCC Group
Engineering Workflows Automation Concept was the Entrance 1995 - CCC was awarded the first project to be delivered in Bentley Microstation Format 1996 - There was a need to find a solution that can enhance and automate the process of
quantification – 1996 (Traditional techniques are inaccurate and time consuming) 1996 - BRICS, Belgium SW, was proposed as a solution Bentley bought BRICS end of 1996 and called it Triforma Beginning of 1997 - CCC Bought three licensee of Triforma for testing After extensive testing by an Automation / Civil Engineer Triforma was to be an efficient &
promising 3D based (model based) quantification solution In three months, 1 senior engineer and two draftsmen were self trained on 3D Information modeling for buildings (BIM) using Bentley Triforma End of 1997 – The first challenge – Ritz Carlton Hotel – Doha – Qatar – First model based Estimation Project
First Success Story
Zuhair Haddad/ Amr ElSersyCCC
CCC BIM-5D Centers of Excellence
Building Information Modeling (BIM) CCC Group
Information System Department (ISD) has established professional BIM Centers (Centers of Excellence), where a group of specialized engineers have been recruited, then intensively trained to be able to develop efficiently quality BIM with the controls methodology in the background.
The main center is located in Cairo, another two branches already exist, one in Athens and the other one in Palestine, in addition to some BIM resources that are offering BIM services in several projects across the globe.
Zuhair Haddad/ Amr ElSersyCCC
CCC BIM-5D Services
Building Information Modeling (BIM) CCC Group
Contractual, Quantity Surveying and Material Take-off Services
Develop BOQs based on CSI coding or any other coding required by the client Develop summarized and detailed Material Take-Offs (MTOs) per BOQ (Bill of
Quantity) aggregated on any Work Breakdown Structure (WBS) level for planning and scope of work definition
Develop Material Take-off reports per BOQ per object (coded as per the unique project object coding system) to link the 3D BIM with in-house as well as other project controls system
Develop and implement a 3D BIM based Quantity Surveying (QS) system with automatically generated valuation sheets
Support procurement operations Change Management Support
Zuhair Haddad/ Amr ElSersyCCC
Model Quantities
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
Scenario Browser
Building Information Modeling (BIM) CCC Group
Change Management Control (Scenario Browser)
Zuhair Haddad/ Amr ElSersyCCC
CCC BIM-5D Services
Building Information Modeling (BIM) CCC Group
Engineering Services
Develop professional high quality presentations and photo-realistic images (Digital Mockups)
Support and automate the engineering production of design drawings
Act as an integrated system for design coordination and clash detection
Assist in value engineering studies
Zuhair Haddad/ Amr ElSersyCCC
BIM Drawings Development – 3D Model
Building Information Modeling (BIM) CCC Group
Power Plan
Zuhair Haddad/ Amr ElSersyCCC
BIM Drawings Development – 3D Model
Building Information Modeling (BIM) CCC Group
HVAC Plan
Zuhair Haddad/ Amr ElSersyCCC
BIM Drawings Development – 3D Model
Building Information Modeling (BIM) CCC Group
FFT Plan
Zuhair Haddad/ Amr ElSersyCCC
BIM Drawings Development – 3D Model
Building Information Modeling (BIM) CCC Group
ARCH. Plan
Zuhair Haddad/ Amr ElSersyCCC
BIM Drawings Development – 3D Model
Building Information Modeling (BIM) CCC Group
STR. Plan
Zuhair Haddad/ Amr ElSersyCCC
Composite 3D Model
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
Clash Detection
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
CCC BIM-5D Services
Building Information Modeling (BIM) CCC Group
Construction and Project Controls Services
Provide visual planning and visual progress monitoring functionalities Establish visual reporting and querying systems Establish 3D crane layouts and utilization studies Develop logistic plans, site accessibility & constructability studies Develop visual simulations for construction method statements Support and validate subcontractors’ work and integrate their systems
with CCC in-house systems using EDI procedures
Zuhair Haddad/ Amr ElSersyCCC
Site Planner
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
3 Week Look Ahead Meeting
Building Information Modeling (BIM) CCC Group
Site Engineer Work-packaging
ProjectEngineers
FormanUpdate Progress
Zuhair Haddad/ Amr ElSersyCCC
4D Planned vs. Actual
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D Based Visual Project Controls System
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D Projects at CCC
Building Information Modeling (BIM) CCC Group
AUC New campus (Egypt)
College of Business and Computer Science Esquissée (Algeria)
Aramco Hawiyah Gas Plant Control Room (KSA)
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D Projects at CCC
Building Information Modeling (BIM) CCC Group
Mubadala Erwda (UAE) Khalifa Sports Hall (Qatar)
Saudi Embassy (Egypt) Khartoum (Sudan)
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D Projects at CCC
Building Information Modeling (BIM) CCC Group
Ahmadi Hospital (Kuwait) Jumirah Island Heights (UAE)
Qatari Emiri Naval Forces Mubarak Al-hassawi - Medical Institute
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D Projects at CCC
Building Information Modeling (BIM) CCC Group
Novotel Resort (Jordan) West Bay Lagoon (Qatar)
Haradh Project Plant (KSA) Central Bank (Kuwait)
Zuhair Haddad/ Amr ElSersyCCC
BIM-5D Projects at CCC
Building Information Modeling (BIM) CCC Group
High Rise Office Building (Qatar) Presidential Palace (UAE)
Qatar Faculty Of Islamic Studies (Qatar) New Administration Building (USA)
Zuhair Haddad/ Amr ElSersyCCC
Deviation Analysis at QFIS
Building Information Modeling (BIM) CCC Group
The deviation analysis method aims to interpret sources, types, and magnitude of errors in different phases of the construction workflow by comparing the 3D laser scan points (As-Built) to the digital reference CAD model (BIM).
Zuhair Haddad/ Amr ElSersyCCC
Meeting European Construction’s BIM Requirements
Building Information Modeling (BIM) CCC Group
CCC is an ENCORD member www.encord.org The European Network of Construction Companies for Research and Development (ENCORD) is a network of active members from the construction industry, represented by decision-makers and executives working on research, development and innovation (R,D&I) and providing service to experts and the operational sites within the member companies
Zuhair Haddad/ Amr ElSersyCCC
Meeting European Construction’s BIM Requirements
Building Information Modeling (BIM) CCC Group
CCC is a founding member for the 5Di Group www.5d-initiative.com A group of international European contractors who emerged from the ENCORD organization with a
target Initiative to develop new IT tools for design, realization and operation of buildings and infrastructure
Zuhair Haddad/ Amr ElSersyCCC
The 5Di Response
Building Information Modeling (BIM) CCC Group
Founded in 1869 HQ in Netherlands
5,4 billion Euro 26.000 employees
Merged in 2006 HQ in Germany 12,8 billion Euro
73.600 employees
Merged in 1929 HQ in Germany 1,4 billion Euro
6.000 employees
Merged in 1969 HQ in Netherlands
1,4 billion euro 4.000 employees
5Di MEMBERS
Founded in 1952 HQ in Greece
5,3 billion Euro 165.750 employees
ENCORD and ENCORD VCP support 5D Initiative in which many of their members are actively involved
Zuhair Haddad/ Amr ElSersyCCC
Achievements – 5Di Use-Cases
Building Information Modeling (BIM) CCC Group
Building Process Integration – Systems Engineering and BIM / Client Requirements Processing
Manage Change – Change Δ Managed
Design to Fabrication
Model-based Estimation – QTO Processes
Progress Collection, Monitoring and Control
Zuhair Haddad/ Amr ElSersyCCC
Target 5Di Platform Should Answer
Construction Processes During Project Lifecycle
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
Target 5Di Platform – 5Di Solution Components
Building Information Modeling (BIM) CCC Group
5D Process Managementdirect communication on model and database
Oper
atio
nal D
ata
listin
gs /
anal
ysis
5D Modeller3D / object oriented / parametric
5D Viewernative interface to 2D/3D/database
5D Expert Systemsstatics / MEP / calculation /
simulation / scheduling /ERP / etc.
5D Data Management
2D D
rawi
ngs
arch
itect
ural
/ st
ruct
ure
/ etc
.
graphics-driven database-driven
Zuhair Haddad/ Amr ElSersyCCC
CCC – 5Di Use-Case
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
CCC – Progress Collection, Monitoring and Control
Building Information Modeling (BIM) CCC Group
Three Weeks Look Ahead Planning & What If Scenarios
Zuhair Haddad/ Amr ElSersyCCC
CCC – Progress Collection, Monitoring and Control
Building Information Modeling (BIM) CCC Group
Progress Visual Reporting
Zuhair Haddad/ Amr ElSersyCCC
5Di Partners with Major SW Vendors
Building Information Modeling (BIM) CCC Group
Zuhair Haddad/ Amr ElSersyCCC
Building Information Modeling (BIM) CCC Group
5Di Presentation by CCC ICE Conference, 19 October 2011 - London, UK
Zuhair Haddad/ Amr ElSersyCCCBuilding Information Modeling (BIM) CCC Group
CCC Sponsoring & Organizing First Middle East BIM Conference
Zuhair Haddad/ Amr ElSersyCCC
Building Information Modeling (BIM) CCC Group
CCC was granted a CETI Award in April, 2012 for its Outstanding Efforts & Leading Role in the EPC Industry
Zuhair Haddad/ Amr ElSersyCCC
Thank you