Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

Embed Size (px)

Citation preview

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    1/20

    CONDITION ASSESSMENT AND CATHODIC PROTECTION OF REINFORCED

    CONCRETE COOLING TOWER

    Zia Chaudhary and Fahad M. Al-Mutlaq

    SABIC Technology Center Jubail

    P.O. Box 11669, Al-Jubail Industrial City 31961

    Saudi Basic Industries Corporation (SABIC)

    Kingdom of Saudi Arabia

    E-mail: [email protected],

    &Ali A. Al-Beed

    Saudi Petrochemical Company (SADAF)

    P.O.Box 10025, Al-Jubail Industrial City 31961

    Kingdom of Saudi Arabia

    ABSTRACT

    Investigations were conducted to assess condition and determine root cause of the ongoing concrete

    deterioration of the cooling tower. The beams, columns, wall panels of end walls, roof slab, bund wall,and louvers, were visually exhibiting severe concrete deterioration in many areas across the entire

    structure. In some areas, the concrete deterioration was very advanced and posing serious threat to

    integrity of the structure. Chloride had penetrated to full depth of the concrete cover in concentrations

    significantly higher than threshold level. Electrochemical measurements showed that the reinforcing

    steel was actively corroding under the sound concrete in >50% areas of the entire structure.

    The visual condition of the exposed steel and the survey results concluded that the deterioration of

    concrete resulted due to chloride-induced corrosion of the reinforcing steel. There was no risk of

    carbonation-induced corrosion of steel and sulfate attack on concrete. Patch repair and cathodic

    protection (CP) repair method was recommended to arrest the ongoing corrosion of the steelreinforcement. The CP system design, installation, and initial commissioning and monitoring results are

    also described and discussed.

    Key Words: concrete deterioration, delamination, chloride, sulfate, half-cell potential measurements,

    probability of corrosion, patch repairs, cathodic protection, titanium mesh anode.

    1

    Paper No.

    08301

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    2/20

    INTRODUCTION

    The cooling tower provides potable water supply (cooling system) for plants in a petrochemical

    company located in Jubail industrial city, Saudi Arabia. The cooling tower structure comprises pre-cast

    concrete units mounted on a reinforced structural frame. The cooling tower structure is 27.45 m long, 24

    m wide and 18.22 m in height. The cooling tower was built in 1981.

    Major parts of the structure are as follows:

    End Walls (north and south elevation), are comprised of reinforced concrete in-situ castcolumns and pre-cast beams and wall panels.

    Roof Slab, it contains pre-cast slab panels, fan plinths, and parapet walls. Bund wall, built all around the tower to contain the water (2.97 m high) Reinforced concrete Louvers units, (east and west elevation)

    A schematic illustration of the cooling tower with major components identified is given in Figure 1 and

    a view of south elevation is shown in Figure 2.

    The cooling tower was commissioned in 1981 and was showing signs of concrete distress in the form

    of cracking and spalling of concrete for the last few years, believed to be caused by corrosion of the

    reinforcement. In some areas, the extent of deterioration was very severe and posing a safety hazard to

    personnel and plant below. A condition survey was conducted to determine the cause and extent of

    deterioration and recommend appropriate repair methods for the rehabilitation of the structure. This

    paper describes and discusses the condition survey results, available repair options, and design,

    installation, and monitoring of the recommended patch repair and cathodic protection (CP) repair

    method.

    CONDITION SURVEY

    Standard condition survey techniques were employed throughout this investigation, which includes

    the following:

    Visual Inspection & Hammer tapping survey of concrete surface Chemical Analysis for chloride and / or Sulfate content determination Cement content & compressive strength analysis Depth of carbonation & reinforcement Half-cell potential & Corrosion rate measurements

    Visual Inspection

    South & North End Walls (External):-The extent of concrete deterioration on south elevation was

    relatively more significant than on other parts of the structure. The cracking, delamination, and spalling

    of concrete was visible and noted at many locations. At some locations, the condition of concrete

    elements was posing safety hazard threat to personnel working in that area. Several water leaks were

    also visible.

    2

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    3/20

    Large and wide cracks were visible on many reinforced concrete beams. At some locations,

    propagation of cracks had already converted into spalling of concrete and exposing the steel bars, which

    were severely corroded, hence confirming the cause of concrete cracking & spalling. Whitish salt

    deposits were found on beams. Several columns were also exhibiting signs of cracking of concrete. At

    some locations, the cracks were very long and extremely wide as shown in photo 3. The crack pattern

    appears to be in line with reinforcing steel. Water leaks were noted on column / beam joints at many

    locations, particularly on the central row of columns. Rust staining and longitudinal as well as horizontal

    cracks in concrete were found in some areas of columns close by the leakage points. Scale deposits werenoted at many locations.

    Wall panels were showing by far the highest degree of concrete deterioration. Large sections ofconcrete repairs were also visible on many panels. Extensive cracking and delaminated concrete was

    visible on about 12 panels out of the total of 20.

    On the north elevation, visible signs of concrete deterioration were relatively less and few in

    numbers. However, where visible the extent of deterioration was quite advanced and had already led to

    spalling of concrete. Beams and columns on top east side of the elevation were exhibiting extensive

    cracking and at some points spalling of concrete. Water leakage was also underway at many locations. It

    was occurring either at the beam/wall panel joint or beam/column joint. The exposed steel bars were

    severely corroded hence confirming that deterioration of concrete is associated with corrosion of the

    reinforcing steel.

    East & West End Walls (External):- The top beams on both east and west elevations were showing

    signs of concrete distress. At some locations, the cracking was highly advanced and had already resulted

    in concrete spalling. The exposed rebars were severely corroded. Cracking and delamination was also

    visible on both columns and wall panels, but relatively at less no. of locations.

    Louvers:- Several louvers from both east and west elevations are showing advanced concretedeterioration. At many locations, the cracks were very long and extremely wide (>5 mm). The

    delaminated concrete was also visible. At some points, spalling of concrete had already occurred and

    rebars were exposed. The exposed rebars were extensively corroded and had significant section loss.

    End Walls Internal :- Internally, the visual condition of columns, beams, and wall panels was

    generally good except the top and upper wall portion, which was subject to frequent wet and dry cycles.

    Cracks were visible on beams and wall panels located in the uppermost chamber of the tower, just under

    the fans. The beams were exhibiting advanced stage of concrete cracking. Long and very wide

    longitudinal cracks were visible on many beams, which were in line with the reinforcing steel andappear to resulting due to corrosion of steel. The jointing mortar between the beams and top roof slab

    was also broken out.

    Roof Slab (Top & Soffit):- The roof slab top and fan plinth foundations were generally in good

    condition. The edges of the roof slab panels were repaired throughout the entire roof slab top, whichwere also visible on the soffit side as well. Some cracks and delaminated concrete sections were visible

    on parapet walls. Old repairs were also noted at several locations. The slab panel soffit was severely

    cracked and delaminated around the opening points and also in areas close by these openings. Exposed

    bars were severely corroded. The jointing mortar between the slab panels and between the slab and

    beams was either eroded or broken out at several locations. Most of the beams, which are supporting theroof slab panels, were severely cracked. The cracks are very long and generally wider than 2 mm. The

    3

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    4/20

    exposed steel showed that cracks were in line with the reinforcing steel. The exposed steel was severely

    corroded hence confirming that cracking has resulted due to corrosion of the reinforcing steel.

    Bund Wall:- The coating on external side of the bund wall was severely deteriorated and peeled off

    throughout the wall length. However, the concrete underneath was visually in good condition except the

    top of the wall, which was cracked at many locations.

    In summarizing the visual inspection records, the reinforced concrete elements of the cooling tower

    are exhibiting advanced stage of concrete deterioration on the external side of the structure. At manylocations, it has already resulted in spalling of concrete and posing safety hazard to personnel at number

    of other locations. The exposed rebars are severely corroded and confirm that deterioration of concrete

    is associated with corrosion of the reinforcing steel.

    Chloride Contents

    Concrete powder samples were taken from each concrete element for chloride content analysis. The

    acid soluble chloride content of concrete powder samples was determined in the laboratory usingconventional titration method by BS 1881: Part 124. The results are given in Table 1 below.

    South & North Elevations (Beams, Columns, & Wall Panels):-The average chloride content andprofile is shown in Figure 6 below. The chloride contents showed a decreasing profile with depth, which

    is indicative of ingress from an external source. The results show that chloride had penetrated into each

    concrete element beyond the external steel reinforcement depth and its chloride concentration at the

    external rebar level was well in excess of the threshold limit (0.03%) for chloride-induced corrosion in

    OPC concrete1-3

    .

    Bund Wall:- The chloride content profile is shown in Figure 6 below. The results show that chloride

    content at the external steel depth is 0.21%, which is significantly (7 times) higher than the threshold

    limit (0.03%). The profile also indicates that the chloride penetration was mainly from the external side

    of the bund wall, however, some penetration from the internal side could also be possible and the

    chloride content could also be higher at the internal steel depth.

    Roof Slab:- The chloride profile is shown in Figure 7 below. The chloride content at the top and

    bottom reinforcing steel depths (0.17% and 0.06% respectively) are higher than threshold level. The

    profile shows that chloride penetration was mainly from the external top of the slab, however, it appears

    that chloride penetration might also be from the soffit side as well though at relatively much less rate

    and in quantity.

    Roof Slab Beam:-The chloride profile is shown in Figure 7 below. The results show that chloride

    penetration had been from both sides of the beam and their concentration at the steel depth on both sides

    is significantly higher than threshold level.

    Louvers:- The average chloride content profile is shown in Figure 7 below. The results show that

    chloride content at the external steel depth is 0.25%, which is significantly (8 times) higher than the

    threshold limit (0.03%). The profile also indicates that the chloride content was higher on the external

    side of the both louvers.

    4

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    5/20

    Sulfate Content

    The acid soluble sulfate content of concrete powder samples was determined in the laboratory using

    conventional titration method by BS 1881: Part 124. The results are given in Table 3 below. Most of the

    results from all different elements showed that sulfate content was generally less than the threshold limit

    of 0.6% sulfate by weight of concrete1. Only one result value from south elevation column (2% at 0-20

    mm depth) was significantly higher than the threshold limit and some 6 results from 5 different locations

    were slightly higher than the threshold limit and ranged between 0.65% and 0.77%. Each profile has

    shown that sulfate penetration into the concrete was from the external side of each element.

    Cement content & Compressive Strength

    The cement content and compressive strength of concrete was determined from three cores CM1,

    CM3, and CM4, extracted from south elevation beam, column and roof slab respectively. The testing

    was carried out using CaO method in accordance with BS 1881: Part 124. The cement content in each

    core was >16.4% and the compressive strength was >35 N/mm2. These results suggest that both the

    cement content and the compressive strength of the concrete were sufficient.

    Carbonation

    The carbonation depth was determined using phenolphthalein solution spray on three cores CM1,

    CM3, and CM4, extracted from south elevation beam, column and roof slab respectively. No colorless

    zone was found in all three samples, which suggests there was no carbonated concrete at all.

    Half cell potentials

    The free corrosion potential of the reinforcing steel was measured in selected areas on the concrete

    surfaces of two beams and wall panels, one column and roof slab using hand held Ag/AgCl reference

    electrode. The half-cell survey results are summarized in Table 4 below. The interpretation of half-cell

    survey results was carried using the Van Daveer criteria and in accordance with ASTM C876-91standard.

    The results indicated 90% risk of corrosion of the reinforcing steel in 19%, 50% and 100% areas of

    the north & south elevations and top of the roof slab respectively. Whereas, 50% risk of corrosion was

    also evident in 61% and 50% areas of north and south elevations. This implies that risk of corrosion ofthe reinforcing steel was very high throughout the entire cooling tower structure and widespreadcorrosion activity is occurring underneath the sound concrete areas though this has not yet transpired as

    visible damage. .

    Corrosion Rate

    The corrosion rate of the reinforcing steel was measured in selected areas using Gecor 6 linear

    polarization device. The interpretation of the results was carried out in accordance with the following

    criteria4:

    Low to moderate corrosion: Icorr 0.1 to 0.5 uA/cm2Moderate to high corrosion Icorr 0.5 to 1.0 uA/cm

    2

    High corrosion rate Icorr >1.0 uA/cm2

    Using the above criteria, the summary of corrosion rate results is given in Table 5 below. The results

    showed that >50% of the reinforcing steel in south elevation concrete elements and in roof slab was

    5

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    6/20

    actively corroding at moderate to high corrosion rates. At north elevation, the corrosion rate in most of

    the areas (~66%) is in low range.

    DIAGNOSIS

    Cause of Concrete Deterioration

    There are five classes of concrete deterioration that are recognized by ACI Committee 2014

    . In theArabian Gulf environment, most commonly reported

    5causes of concrete deterioration are; a) Corrosion

    of the steel reinforcement and b) sulfate attack. Corrosion of steel in concrete occurs due to chlorideattack and/or carbonation of concrete6. Carbonation of concrete is not very common in the Gulf

    environment.

    It is evident from the visual condition of the exposed steel bars (resulted due cracking and spalling of

    concrete at many locations throughout the structure) that deterioration of concrete is associated with

    corrosion of the reinforcing steel. Corrosion of steel in concrete occurs due to either chloride attack or

    carbonation of concrete.

    The chemical analysis of concrete samples has shown that the carbonation depth of concrete wasnegligible, and the sulfate content was mostly lower than threshold level of 0.6% by weight of concrete.

    Extensive chloride penetration was, however, found in all test samples from all different concrete

    elements. This confirms that the cause of concrete deterioration is chloride-induced corrosion of thereinforcing steel.

    The chlorides profile in all different elements shows that chloride penetrated into the concrete

    externally. Since the deterioration has occurred in areas that are well above the grade level the source of

    chloride ions appear to be the cooling tower water, i.e. being sprayed onto the concrete from top of thecooling tower. The chloride concentration in the cooling tower water varies between 300 and 500ppm.

    The continuous water spray and subsequent evaporation due to high temperatures can result in gradual

    build-up of chloride concentration in the concrete.

    Extent of Damage

    It is evident from the chloride profiles that chloride penetration was very deep and its concentration

    at all depths was significantly higher than the threshold limit. This shows that not only external steel

    layer but also the internal steel layer would also be subject to chloride attack. According to the half-cell

    potential data, the risk of corrosion appears to be greater than 95% in about 50% area of the entire

    structure, whereas in remaining areas, likelihood of corrosion is between 5% and 50%. The corrosion

    rate data has confirmed that steel is actively corroding at moderate to high corrosion rates in about 50%

    areas of the structure. This implies that the extent of concrete deterioration is well spread and deep

    across the whole structure and therefore there is an urgent need for remedial works to arrest this ongoingconcrete deterioration.

    Based on the above-mentioned observations, it was diagnosed that deterioration of the concrete has

    resulted due to chloride-induced corrosion of the reinforcing steel. The reinforcing steel is also activelycorroding in several other areas of the structure where concrete apparently is in good condition.

    6

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    7/20

    SELECTION OF APPROPRIATE REPAIR METHOD

    The pros and cons and feasibility of the following three options were compared in selecting the most

    appropriate and durable repair method for the cooling tower structure.

    Option 1 Local Patch Repairs

    Option 2 Re-Skinning or Traditional Repairs

    Option 3 Patch Repairs and Cathodic Protection

    The option 1 was very economical, as this method would involve breakout and removal of only

    delaminated concrete and reinstatement. However, past experience has shown that in chloride-

    contaminated structures this method provides only a temporary or short-term solution since it deals withonly the damaged areas and not the cause6. It could result in enhancing the corrosion activity and/or

    developing incipient anodes in the adjacent un-repaired areas. By comparison, the re-skinning of the

    structure (option 2) would provide durable and well-extended service life, as it involves removing all

    delaminated and chloride-contaminated concrete. But it would require extensive concrete breakout (20

    mm beyond the main external reinforcement), which was not desirable considering the operations

    constraints and the time required. Due to extensive concrete breakout/removal and also concrete coating

    for durable repairs, this method was not likely to be an economical option when compared with option 3,

    which would involve patch repairs of the delaminated areas and installation of cathodic protection (CP)

    system to the concrete surfaces. Since, only delaminated concrete would be broken out and removed,

    risk of operational constraints would also be minimum or negligible. The ongoing chloride-induced

    corrosion of the reinforcing steel would be arrested or controlled when the steel is sufficiently

    cathodically polarized. Hence, it was concluded that option 3 method, would provide a durable and long-term solution for rehabilitation of the cooling tower structure.

    Therefore, for overall repairs of the structure, patch repair and impressed current cathodic protectionrepair method was recommended. The major and minor defects of different elements and recommended

    repairs are summarized in Tables 6-7 below.

    CATHODIC PROTECTION SYSTEM

    Design

    Based on literature guidance8-10and exposed condition of the reinforcing steel in different elements

    of the structure, a design current density of 20 mA/m2of steel surface area was used in calculating the

    current requirement for the protected steel in the cooling tower structure. The selected anode system

    comprised expanded titanium mesh anode with cementitious overlay. This selection was based on

    extensive and good track record of mesh overlay anode system in Middle East region. The overlaythickness was limited to 25-30 mm in order to keep the dead load onto the structure within acceptable

    levels.

    For effective performance, assessment, and control, the whole protected area of the structure was

    split into 16 CP anode zones, which both current and voltage outputs can be controlled independently.Multiple anode feeder and current return (steel) connections were allowed for each anode zone to

    7

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    8/20

    acquire good and uniform current distribution and also ensuring 100% redundancy. The precise number

    and positioning of these connections was based on design calculations that ensured minimum and

    acceptable level of voltage drops across the anode current distributors and mesh. About 2 to 5

    embeddable reference electrodes (Ag/AgCl / 0.5M KCl) were allowed for different anode zones to

    monitor the system performance. More design details are given in Table 8 below.

    Installation

    All concrete surfaces of all different elements of the structure that were to be protected, were

    hammer tapped in order to identify the delaminated areas. Subsequently, all delaminated concrete was

    removed. In some areas, particularly upper elements of the south elevation (extending down to 3-5

    meters from top of the structure, extent of damage was very significant and deep. The reinforcing steel

    was severely corroded with a section loss of >10-20%. Therefore, a lot of steel replacement was made in

    such areas.

    As the structure was made up of pre-cast elements, a comprehensive electrical continuity testing was

    conducted. All exposed steel was utilized for this testing and additional concrete breakouts were also

    made where needed. The reinforcing steel bar was considered electrically discontinuous when any

    individual resistance reading; was greater than 1 ohm or it changed more than 1 ohm in 15 seconds orwhen the instrument leads were reversed. In general, the reinforcing steel in all different elements, i.e.

    wall panels, columns and beams, was not electrically continuous. Similarly, the steel in top slab panelsand parapet walls was also electrically discontinuous. The testing also identified about 150-200

    discontinuous steel rods in the bund wall that were probably used to hold the scaffolding platform

    during the construction. The electrical continuity of all different elements within each anode zone was

    established using welded rebar links as shown in Figure 9.

    Double junction Ag/AgCl /0.5 M KCl reference electrodes (REs) were installed preferably at sites

    where risk of corrosion was high or steel was already actively corroding. In general, REs were located ina manner that whole area within each zone would be appropriately represented. Some REs were also

    embedded close to the rear layer of the steel reinforcement. All steel connections were made and then allexposed areas were repaired using cementitious material to the original concrete profile. All cables were

    secured and repaired areas were cured using wet hessian for a minimum period of 7 days. After curing,

    pull-off tests were conducted using 50 mm diameter dollies to determine bond strength between the

    repair material and the parent concrete. The pull-off tests were carried out at a rate of 1 set (3 no. per

    set) for the first 50 m2 and then 1 set per 100 m

    2. The repair approval criteria was that the point of

    fracture should occur within the substrate or if it occurred at the repair / substrate interface it should

    exceed the mean value of 1.5 N/mm2with no individual value below 1 N/mm

    2.

    The reinstatement of expansion and mortared joints was also completed at this stage. Two part poly-

    sulfide flexible sealant was applied to both type of joints using gun. Following this concrete surfaces

    were cleaned and abraded by mechanical scrabbling (using hatching tool) to acquire roughened surfacefor good bond between the substrate and CP overlay. Prior to overlay placement, electrical continuity

    testing was conducted to ensure all components of the anode system are electrically continuous within

    each zone and also there are no short circuits between the anode and the steel. All connection cables

    were appropriately tied to the mesh anode and carried to terminate in the nearest junction box. The

    overlay was installed in small sections to keep the shrinkage cracking under control and minimum.

    Special attention was given to the joint locations between the columns and walls and beams. The

    overlay was cured using wet hessian for a minimum period of 14 days. After curing pull-off tests were

    8

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    9/20

    carried out (as described above) to determine bond strength between the substrate and overlay.

    Commissioning & Monitoring

    Four transformer rectifiers (T/Rs) enclosures were installed, each containing multiple independentoutputs (T/Rs) and placed at four different locations around the structure. All dc output and monitoring

    cables were run between the associated T/Rs and junction boxes. Prior to energizing of the CP system,

    steel natural potentials were established at the location of all embedded reference electrodes and pre-commissioning checks were conducted to verify the circuit wiring and steel polarization in negative

    direction. The CP system was powered after the completion of 28 day curing of the overlay. All zones

    were initially energized at a steel current density of 5mA/m2and then current was gradually increased to

    achieve a current-on potential shift of 100-200 mV. After 7 days of system operation, instant-off steel

    potentials were measured and the applied current was increased in each zone to a level of 15 mA/m2of

    steel surface area.

    The natural and instant off steel potentials, and potential decay measurement results are summarized

    in Table 9 below. In general, the polarization growth in the negative direction increased steadily with

    increase in applied current and time and was noted quite uniform in all areas within each anode zone

    and also overall in all zones.

    After 9 months operation of the CP system, the monitoring results have shown that 100 mV decay

    criterion was met at all the 50 monitoring locations except at two, i.e. RE-8-4 and RE-14-2. These two

    reference electrodes appear to have gone faulty, as the potential readings were not stable. This implies

    that the CP system is affording the required protection and reinforcing steel is adequately protected.

    Based on these results it can be inferred that the CP system has been successfully commissioned and

    operating satisfactorily, and meeting its design objectives in controlling the chloride-induced corrosion

    of the reinforcing steel of cooling tower structure.

    CONCLUSIONS

    1. The deterioration of the cooling tower concrete occurred due to chloride-induced corrosion of thesteel reinforcement. The chlorides are present in the concrete cover in excess of the threshold limit

    of 0.03% by wt. of concrete, which poses a very high risk of corrosion of the reinforcing steel. The

    chloride penetration was from the external side and resulted due to continuous cooling tower water

    spray.

    2. There was no risk of carbonation-induced corrosion of steel and sulfate attack on concrete.3. The electrochemical measurements showed that the reinforcing steel was actively corroding under

    the sound concrete in >50% areas of the entire structure. Therefore, repair works should not be

    limited to the damaged areas only.

    4. Patch repairs and CP repair method offer durable, long-term & economical solution with no ormuch less installation constraints for rehabilitation of the structure. Therefore, this method wasrecommended.

    5. The CP system has been successfully installed and commissioned. The 9 month system operation& monitoring results have shown that the 100 mV day criterion was met at 48 monitoring locationsout of the total of 50. This shows that CP system is affording required protection to all protected

    areas and meeting its design objective in controlling the ongoing corrosion of the reinforcing steel.

    9

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    10/20

    ACKNOWLEDGEMENT

    The author would like to thank the management of SABIC Technology Center and SABIC R & T forthe encouragement and approval for the preparation and presentation of this paper.

    REFERENCES

    1. M.S., Eglinton, Concrete and its Chemical Behaviour Pub. Thomas Telford Ltd.1987

    2. ACI 224, Causes, Evaluation, and Repair of Cracks in Concrete American ConcreteInstitute, Detroit, USA, 1987.

    3. BS 8110: Part 1, The Structural Use of Concrete British Standards Institution, 1985.4. ACI 201, Guide to Durable Concrete American Concrete Institute, Detroit, USA,

    1987.

    5. O.S.B. Al-Moudi, Durability of Reinforced Concrete in Aggressive SabkhaEnvironments ACI Materials Journal, May-June 1995.

    6. J.P. Broomfield, Corrosion of Steel in Concrete Pub. E & FN Spon, 1997.7. Rasheeduzzafar, S.E. Hussain, and S.S. Al-Saadoun, Effect of tricalcium aluminate

    content of cement on chloride binding and corrosion of reinforcing steel in concrete

    ACI Materials Journal, January-February, 1992.

    8. Concrete Society/CEA Technical Reports No. 36. Corrosion Engineering Association,1989. U.K.

    9. NACE Standard RP0390-90, Item No. 53072, Cathodic Protection of ReinforcedSteel in Atmospherically Exposed Concrete Structures.

    10. European Standard BS EN 12696, Cathodic Protection of Steel in Concrete Atmospherically exposed concrete 2000.

    10

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    11/20

    TABLE 1:- Chloride content analysis results.

    Dust sample increment depths (mm)

    170-220120-17080-12060-8040-6020-400-20

    Chloride concentration % by Wt. of concrete sample

    Element/Face

    0.060.070.060.060.060.070.09Beam/South Elev.

    0.060.060.070.1Beam/Nort Elev.

    0.070.110.240.69Column/South Elev.

    0.070.060.070.09Column/North Elev

    0.080.120.21Wall/South Elev.

    0.160.160.21Wall/South Elev.

    0.070.090.10Wall/North Elev.

    0.130.120.150.180.210.230.28Bund Wall/East Elev.

    100-15080-10060-8040-6020-400-20

    0.060.050.070.110.170.18Roof Slab

    0.130.110.090.120.150.18Roof Slab Beam

    0.190.210.25Louver/East Elev.

    0.260.290.38Louver/East Elev.

    TABLE 2:-Sulphate content analysis results.

    Dust Sample increment depths (mm)

    170-220120-17080-12060-8040-6020-400-20

    Sulfate content % by wt. of concrete sample

    Element/Face

    0.470.410.380.400.430.450.47Beam/South Elev.

    0.360.390.500.56Beam/Nort Elev.

    0.440.530.772.00Column/South Elev.

    0.400.390.400.44Column/North Elev

    0.540.530.58Wall/South Elev.

    0.420.470.58Wall/South Elev.

    0.330.360.49Wall/North Elev.

    0.360.320.340.370.470.550.64Bund Wall/East Elev.

    100-15080-10060-8040-6020-400-20

    0.410.380.320.430.510.68Roof Slab Beam

    0.660.550.400.490.600.73Roof Slab

    0.510.530.57Louver/East Elev.

    0.450.550.65Louver/East Elev.

    11

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    12/20

    Table 3:- Cement content and compressive strength test results.

    CM4CM3CM1CORE IDENTIFICATION

    16.416.816.6Cement Content (%)

    38.547.246.6Corrected Compressive Strength N/mm

    TABLE 4: Summary of half cell potentials

    North Elevation South Elevation Roof Slab

    Half-cell

    potentials

    (mV)

    -351 -351 -351

    %of values within each potential range

    Beam 0 60 40 0 30 70 - - -

    Column 0 0 100 - - -

    Wall 36 63 1 0 65 35 - - -

    Roof Slab - - - - - - 0 0 100

    Total* 20 61 19 0 50 50 0 0 100

    * Totals are based on all data from each elevation

    TABLE 5:- Summary of corrosion rate results.

    North Elevetion South Elevetion Roof Slab

    Corrosion

    RateLow Moderate High Low Moderate High Low Moderate High

    % of values within each corrosion rate range

    Beam 100 0 0 0 33 67

    Column 100 0 0

    Wall 34 33 33 17 17 66

    Roof Slab 33 67

    Total* 66 17 17 27 18 55 33 67

    * Totals are based on all data from each elevation.

    12

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    13/20

    TABLE 6:- Repair methods for End wall concrete elements.

    Defect Concrete repairsSupplementary

    protection

    A.

    External South & North Elevations and Top Suspended Walls on East & WestElevations (Beams, Columns & Wall panels).

    B. Internal South & North Elevations, (Only upper portion of beams, columns, &wall panels) and Internal West & East Elevations.

    Spalls and delaminated

    concrete.

    Cracks >0.3mm.

    Leaks.

    Old repairs.

    Weathering

    Cavities, and Cracked and

    broken mortar sealant in

    joints.

    Electrical discontinuity ofreinforcing steel in

    different concreteelements.

    Break out only delaminated

    concrete and patch repair (repair

    material to be suitable for CP

    repairs). Evaluate loss of steelsection, replace as required.

    Local breakout and inspect steel,inject or reinstate mortar.

    Replace mortar fillets externally

    and sealant internally.

    Breakout to remove existing

    repair material and reinstate

    using material suitable for CP.

    Apply a coating to reduce rate of

    weathering.

    Breakout old mortar at corner

    joints and reinstate mortar.

    Test and establish electrical

    continuity of reinforcing steel in

    all different concrete elements.

    Impressed current CPsystem (ICCP),

    comprising mixed metal

    oxide (MMO) coatedexpanded titanium mesh

    and cementitious overlay

    anode system.

    13

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    14/20

    TABLE 7: Repair methods for roof slab, louvers, and bund wall.

    Defect Concrete repairsSupplementary

    protection

    Roof Slab (Top & Soffit), Parapet walls & Bund wall.

    Spalls and delaminated

    concrete, Cracks >0.3mm,Old repairs.

    Cavities, and Cracked andbroken mortar sealant in

    joints.

    Cracked and peeled off

    coating

    Electrical discontinuity of

    reinforcing steel indifferent concrete

    elements.

    As recommended in table 6

    above.

    Breakout old mortar at corner

    joints and reinstate mortar.

    Remove coating from all

    concrete surfaces.

    Test and establish electrical

    continuity of reinforcing steel in

    all different concrete elements

    Impressed current CP

    system (ICCP),

    comprising mixed metaloxide (MMO) coated

    expanded titanium mesh

    and cementitious overlayanode system.

    Louvers units of East & West Elevations.

    Spalls and delaminated

    concrete, Cracks >0.3mm,Old repairs.

    Weathering

    Replace all damaged units with

    new units. New units shall have

    epoxy-coated steel.

    Apply a coating to reduce rate of

    weathering..

    All new units shall have

    polyurethane coating.

    14

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    15/20

    TABLE 8:- Summary of CP system design details

    Design

    Current

    Anode

    CapacityCooling Tower Area

    Anode

    Zone

    RE

    (Nos.)Amps

    TR Output

    Ratings

    Bund Wall North 1 2 2.04 2.47 3A, & 10V

    Bund Wall East 2 2 3.54 5.10 5A, & 10V

    Bund Wall South 3 2 3.40 5.10 5A, & 10V

    Bund Wall West 4 2 0.88 1.26 2A, & 10V

    Bund Roof Slab

    South5 2 5.15 6.56 7A, & 10V

    Bund Roof Slab

    North6 2 1.87 2.26 3A, & 10V

    South End Wall,

    Lower7 4 2.41 2.91 3A, & 10V

    South End Wall,

    Upper8 4 2.41 2.91 3A, & 10V

    North End Wall,

    Lower9 4 2.04 2.47 3A, & 10V

    North End Wall,

    Upper10 4 3.54 5.10 5A, & 10V

    West End Wall,

    Upper11 2 3.40 5.10 5A, & 10V

    East End Wall, Upper 12 2 5.15 6.56 7A, & 10V

    Upper- Inner Beams,Columns & Walls-

    North

    13 5 5.10 6.27 7A, & 10V

    Upper- Inner Beams,Columns & Walls-

    South

    14 5 1.87 2.26 3A, & 10V

    Roof Slab West 15 4 0.87 1.26 2A, & 10V

    Roof Slab East 16 4 5.10 6.27 7A, & 10V

    15

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    16/20

    TABLE 9:- Summary of CP system monitoring results.

    After

    3M

    After

    6M

    After

    9M

    After

    3M

    After

    6M

    After

    9MNatural

    Instant-off 24 Hour decay

    TR

    Encl.

    #

    Anode

    ZoneRE No.

    Steel Potential mV Ag/AgCl mVRE 1-1 -326 -578 -655 -496 232 298 178

    3 1RE 1-2 -259 -562 -617 -562 260 302 218

    RE 2-1 -318 -474 -286 -452 161 103 129

    4 2 RE 2-2 -364 -572 -574 -587 160 175 130

    RE 3-1 -351 -619 -543 -613 226 159 2111 3

    RE 3-2 -474 -734 -746 -790 183 217 206

    RE 4-1 -343 -567 -572 -524 188 187 1464

    RE 4-2 -307 -588 -609 -503 266 316 188

    RE 5-1 -147 -474 -539 -401 356 430 2635

    RE 5-2 -252 -289 -212 -290 120 91 109

    RE 6-1 -105 -407 -416 -328 335 351 236

    2

    6RE 6-2 -162 -233 -164 -406 186 97 296

    RE 7-1 -230 -396 -405 -372 216 243 220

    RE 7-2 -233 -513 -563 -516 184 204 155

    RE 7-3 -192 -485 -437 -441 352 299 3157

    RE 7-4 -187 -637 -692 -643 376 419 335

    RE 8-1 -248 -447 -429 -435 229 193 221RE 8-2 -188 -346 -322 -410 180 145 178

    RE 8-3 -292 -424 -593 -379 226 336 208

    1

    8

    RE 8-4 -131 -339 -179 -23 244 99 9

    RE 9-1 -259 -716 -783 -723 296 312 286

    RE 9-2 -351 -526 -513 -540 171 168 189

    RE 9-3 -352 -616 -657 -648 238 237 2539

    RE 9-4 -190 -538 -599 -604 353 396 406

    RE 10-1 -355 -467 -487 -557 272 320 126

    RE 10-2 -199 -454 -486 -466 196 189 193

    RE 10-3 -313 -658 -651 -557 219 394 166

    3

    10

    RE 10-4 -187 -414 -437 -403 294 299 265

    RE 11-1 -179 -315 -537 -505 190 302 325

    1 11 RE 11-2 -230 -443 -372 -347 374 119 216RE 12-1 -203 -361 -345 -326 250 247 215

    4 12RE 12-2 -174 -357 -331 -386 252 214 234

    RE 13-1 -185 -309 -338 -399 191 204 254

    RE 13-2 -238 -308 -304 -400 168 165 124

    RE 13-3 -151 -267 -267 -412 149 133 267

    RE 13-4 -166 -298 -269 -396 227 217 249

    3 13

    RE 13-5 -246 -375 -404 -396 174 178 145

    RE 14-1 -145 -536 -405 -447 408 302 224

    RE 14-2 -138 -409 - -86 260 - 32

    RE 14-3 -198 -351 -428 -510 246 248 254

    RE 14-4 -187 -314 -565 -476 182 330 251

    1 14

    RE 14-5 -359 -317 -457 -441 202 294 216

    RE 15-1 -269 -457 -463 -585 257 293 202RE 15-2 -262 -443 -577 -546 286 378 321

    RE 15-3 -445 -484 -578 -528 114 156 1213 15

    RE 15-4 -172 -402 -409 -473 302 325 274

    RE 16-1 -282 -392 -548 -523 231 329 320

    RE 16-2 -250 -338 -548 -550 170 343 296

    RE 16-3 -236 -323 -493 -527 122 268 2644 16

    RE 16-4 -289 -375 -578 -572 175 302 286

    16

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    17/20

    FIGURE 1:- A schematic illustration of cooling tower shows major components of end walls.

    FIGURE 2:- View of south elevation and east side of the cooling tower.

    17

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    18/20

    FIGURE 3: Large & wide cracks on beam, water leakage and corroded bar.

    FIGURE 4: Extensive cracking of wall panel and edge column (A safety hazard).

    FIGURE 5: Severe cracking of internal beam and roof slab soffit.

    18

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    19/20

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    0.3

    0.35

    0.4

    0.45

    0-20 20-40 40-60 60-80 80-120 120-170 170-220

    Concrete Powder Samples Depth (mm)

    ChlorideConc.(%byWt.ofCon

    crete)

    Beam (Aver.) Column (Aver.) Wall Panel (Aver.) Bund Wall Threshold Value

    FIGURE 6: Chloride profile in the End Wall elements and Bund Wall.

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    0.3

    0.35

    0-20 20-40 40-60 60-80 80-100 100-150

    Concrete Powder Samples Depth (mm)

    ChlorideConc.(%b

    yWt.ofConcrete)

    Roof Slab Roof beam Louver (Aver.) Threshold Value

    FIGURE 7:- Chloride profile in the Roof Slab, Beam and Louvers.

    19

  • 8/13/2019 Condition Assessment and Cathodic Protection of Reinforced Concrete Cooling Tower

    20/20