27
Concurrent delay – In Simple Terms Tuesday 18 th October 2016 DCC, Doha Andrew Woodward [email protected] 1

Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

  • Upload
    others

  • View
    15

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

 Concurrent  delay  –  In  Simple  Terms  

 Tuesday  18th  October  2016  DCC,  Doha  

 Andrew  Woodward  

[email protected]    

1  

Page 2: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

     Discussion  to  outline:  •  A  discussion  around  the  contenAous  topic  of  concurrent  delay.  •  What  is  Concurrent  Delay?  •  How  can  it  be  IdenAfied?  •  And  what  does  it  mean?    

2  

Concurrent  Delay  –  In  Simple  Terms  

Page 3: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

Typical  issues  in  the  GCC  include:  •  Projects  procured  in  a  hurry  –  scope  incomplete  at  the  outset  –  playing  catch-­‐up.  

•  40%  of  construcCon  scope  ill-­‐defined  –    extended  ‘Provisional  Sums’.  •  Change  flowing  from  incomplete  scope  and  a  lack  of  decision  making:    

•  lack  of  design,  lack  of  approval,  lack  of  third  party  requirements.  •  VOs  provided  late  or  not  provided  at  all.  

•  Lack  of  empowerment  –  the  PMC  not  the  decision  maker.  •  Third  party  interference  –  Lack  of  permits,  uAliAes  etc.  •  Culture:  

•  A  deal’s  a  deal,  where  Contractor’s  deemed  responsible  for  everything.  •  Strategy  to  defer  agreements  to  beyond  the  comple?on  date.  

•  Contractor  Poor  Performance  –  Lack  of  resource,  lack  of  engineering,  error-­‐strewn  delivery,  poor  quality  etc.  

3  

ConstrucCon  Projects  –  Issues  at  Hand  

Page 4: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

 What  does  this  all  mean?  

•  Projects  faced  with  significant  overruns:  •  Contractor  facing  cash  shor@all  and  threat  of  penal?es.  •  Employer  facing  late  handover  –  100%  overruns  not  uncommon.  

 So  in  the  interim,  what  does  the  Contractor  do?  

•  The  Contractor  makes  his  claims:  •  The  Contract  Agreement  (CA)  compels  him  to  make  claims.  •  Claims  made  in  the  interim  –  project  on-­‐going.  •  Main  Claims  typically  for  EOT  and  Prolonga?on  Cost.  

4  

ConstrucCon  Projects  –  The  ParCes  Steps  

Page 5: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

In  reply  to  the  claims,  what  does  the  Employer  do?  •  Engineer/Employer  considers  the  claims:  

•  PMC  will  consider  the  claim.  •  Focus  usually  on  events  that  can  be  accepted.  •  Conten?ous  or  uncomfortable  events  put  to  one  side.  •  PMC  makes  recommenda?ons  to  Engineer/Employer.  

•  Offer  made  to  the  Contractor  for  an  Interim  EOT:  •  Time  offered  for  accepted  events.    •  Time  offered  with  no  Cost  –  So,  condi?onal  offer  ?  

•  ProlongaCon  Claim  Rejected:  •  Reason  –  Claim  not  dealt  with  issues  of  ‘Contractor  Concurrent  Delay’.  

5  

ConstrucCon  Projects  –  The  ParCes  Steps  

Page 6: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

From  the  Contractor’s  point  of  view:  •  Cost  and  Ame  pressures  –  project  account  in  the  red.  •  Claims  made  for  cost  and  Ame  –  believed  to  be  made  reasonably?  •  The  CA  imparts  a  sense  of  urgency  –  the  Ame  bars,  but  •  The  Engineer  takes  months  to  reach  a  decision  –  unreasonable?  •  Contract  says  negoAate  but  Employer  goes  for  his  most  favourable  opAon?  •  Decision  to  award  Ame  comes  with  no  cost  –  viewed  as  bad  faith?  

 From  the  Employer’s  Point  of  view:  

•  Arguments  and  claim  only  deal  with  Ame  –  So,  what’s  the  big  deal?  •  Contractor  ‘perceived’  to  be  performing  poorly,  so  why  should  the  Employer  

compensate  for  that  poor  performance.    The  ‘Contractor  Concurrent  Delay’.  

6  

Why  is  this  ContenCous?  

Page 7: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

       

So,  What  is  Contractor  Concurrent  Delay?    

7  

Page 8: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

Concurrent:  •  [Things]  occurring  or  exisAng  simultaneously  or  side  by  side.  •  AcAng  in  conjuncAon;  cooperaAng.  •  Having  equal  authority  or  jurisdicAon.  •  Tending  to  or  intersecAng  at  the  same  point.  Concurrency:  •  AcAng  together,  as  agents  or  circumstances  or  events.  Concurrence:  •  CooperaAon,  as  of  agents,  circumstances,  or  events.    

(merriam-­‐webster.com)  

8  

Start  with  DicConary  DefiniCons  

Page 9: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

9  

                                                                                                                                             Bridge  Scenario  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Longest  Path  

Page 10: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

 Delay  Analysis  is  not  about  P6:  •  P6  is  just  a  planning  tool.  •  P6  is  a  computer  model,  it’s  not  the  physical  works  out  on  the  ground.    Delay  Analysis  should  be:  •  Simple.  •  Establishing  what  is  the  ‘Compelling  Story’.  •  A  search  for  dominant  or  primary  causes    

–  the  CausaAve  Potency.  •  Based  on  a  common-­‐sense  approach.  

10  

Interim  Delay  Analysis  –  Before  We  Start  

Walter  Lilly  &  Company  Ltd  v  Giles  Patrick  McKay    Henry  Boot  (UK)  Ltd  v  Malmaison  Hotel  (Manchester)  Ltd      SCL  Delay  and  DisrupAon  Protocol  2002  

Page 11: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

•  ExcavaAon  –  looks  to  be  on  Ame.  •  Precast  deck  beams  –  started  on  Ame,  prolonged,  finished  same  Ame  as  Abutments.    •  Abutments  –  started  on  Ame,  prolonged,  finished  same  Ame  as  Precast.  •  InstallaAon  –  late  start  (driven  by  beams  and  abutments)  and  then  becomes  prolonged.    •  Landscaping  –  Prolonged  and  swapped  with  Deck  from  being  last  item  to  complete.  •  As  of  the  Analysis  Date  –  works  remain  incomplete.  

11  

Interim  Delay  Analysis  –  Big  Overrun,  What  Happened?  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Overrun  

Data  Date  

Page 12: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

       

Non-­‐CriCcal  Delay    

12  

Page 13: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

Non-­‐CriCcal  Delay  –  a  delay  NOT  HAVING  an  impact  on  the  CompleAon  date.    A  delay  being  parallel  to  the  criAcal  (longest)  path:  •  Landscaping  started  early  (too  early).  •  Out  of  sequence  –  a  miAgaAon?  •  Prolonged  but  complete  before  the  deck  installaAon.  

13  

Non-­‐CriCcal  Delay  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Overrun  

Data  Date  

Page 14: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

       

CriCcal  Delay    

14  

Page 15: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

15  

CriCcal  Delay  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Overrun  

CriCcal  Delay  –  a  delay  HAVING  an  impact  on  the  CompleAon  date.    A  delay  to  an  acAvity  residing  on  the  criAcal  (longest)  path.  •  InstallaAon  has  become  extensively  prolonged.  •  InstallaAon  of  deck  has  become  a  criAcal  item  and  is  now  driving  the  compleAon  date.  

Data  Date  

Page 16: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

       

Concurrent  Delay    

16  

Page 17: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

17  

Concurrent  Delay  

 Concurrent  Delay  –  some  key  guidance:    

...  Concurrent  delay  is  used  to  denote  a  period  of  project  overrun  which  is  caused  by  two  or  more  effecAve  causes  of  delay  which  are  of  approximately  equal  causaCve  potency.    

(KeaAng  on  ConstrucAon  Contracts,  SCL,  john  Marrin  ‘Concurrent  Delay  Revisited’)  

…  True  concurrent  delay  is  the  occurrence  of  two  or  more  delay  events  at  the  same  Ame,  one  an  Employer  Risk  Event,  the  other  a  Contractor  Risk  Event,  and  the  effects  of  which  are  felt  at  the  same  Cme.    

(The  Society  of  ConstrucAon  Law  Delay  and  DisrupAon  Protocol  2002,  guidance  at  1.4.4)    

Page 18: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

18  

Concurrent  Delay  –  In  Simple  Terms  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Overrun  

Concurrent  Delay  –  two  or  more  delays,  one  being  Contractor  AND  one  being  Employer:  •  Events  acAng  together  –  but  not  necessarily  at  the  same  Ame.  •  Events  coming  together,  converging  –  impact  is  merging.  •  Events  being  IndisCnguishable  in  effect  –  cannot  decide  between  the  events.  •  Equal  CausaCve  Potency.  

Data  Date  

One  Concurrent  Delay  containing  two  events  

Page 19: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

19  

Total  CriCcal  Delay  for  the  Bridge  Works    

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

•  Delay  X  Concurrent  Delay  

Delay  Y  Delay  X  

•  Plus  •  Delay  Y  

Cri?cal  Delay  

Data  Date  

Overrun  equals:  

Page 20: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

20  

Liability  

Note:    Discussion  so  far  has  been  about  idenAficaAon  of  the  delay.    

Now  what  about  Liability?  

Page 21: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

21  

Liability  –  CriCcal  Delay  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Overrun  

•  Employer  Event:  •  Contractor  receives  both  Time  and  Cost.  

•  Contractor  Event:  •  Contractor  receives  nothing.      •  Employer  recovers  his  PenalAes.  

Data  Date  

Delay  Y  

Page 22: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

22  

Liability  –  Concurrent  Delay  (SCL  Approach)  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Concurrent  Delay,  being  indisCnguishable  between  Employer  and  Contractor:  •  Contractor  receives  ‘Cme  but  no  money’:  

•  Contractor  gets  ?me  for  the  period  of  delay.  •  Contractor  does  not  get  compensa?on.  •  Employer  cannot  collect  penal?es  or  damages.  

Overrun  

Data  Date  

Delay  X  

Page 23: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

23  

Liability  –  Concurrent  Delay  (ApporConment  Approach)  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

Concurrent  Delay,  being  indisCnguishable  between  Employer  and  Contractor:  •  Liability  is  ‘ApporAoned’  between  the  parAes:  

•  Contractor  gets  some  EOT  and  some  Cost,  but  suffers  some  Penalty.  •  Employer  gives  some  EOT  and  some  Cost,  but  recovers  some  Penalty.  •  An  equitable  split?    

Overrun  

Data  Date  

Delay  X  

Page 24: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

24  

Liability  –  Non-­‐CriCcal  Delay  

ExcavaAon    Pre-­‐cast  Bridge  deck    Construct  Abutments    Install  deck    Complete  landscaping  

•  Employer  Event:  •  Contractor  enAtled  to  costs  –  disrupAon  claim  –  but  no  EOT.  

•  Contractor  Event:    •  Contractor  receives  nothing.  •  Employer  NOT  enAtled  to  relief  from  his  liability  for  Cost  arising  from  his  other  

accepted  delays.  

Overrun  

Data  Date  

Page 25: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

25  

Summary  

CriCcal  Delay:  •  Employer  Accepted  –  Contractor  to  receive  Ame  and  money.  •  Contractor  Accepted  –  Employer  receives  penalAes  /  LDs.    Non-­‐CriCcal  Delay:  •  Employer  Accepted  –  Contractor  enAtled  to  money  (disrupAon  claim)  but  no  Ame.  •  Contractor  Accepted  –  Employer’s  liability  to  ProlongaAon  cost  elsewhere  is  not  reduced  

by  the  presence  of  the  Contractor  non-­‐criAcal  delay.        Concurrent  Delay  (delays  indisCnguishable):  •  Employer  is  denied  the  right  to  recover  penalAes.  •  Contractor  is  provided  protecAon  from  penalAes,  but    •  Contractor  is  denied  right  to  recover  costs.  •  Alterna?vely  (in  GCC)  the  liability  may  be  ‘appor?oned’  between  the  par?es.  

Page 26: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

26  

Final  Thoughts  1.   There  is  no  such  thing  as  a  Contractor  Concurrent  Delay  –  it’s  a  Contractor  Delay  

acAng  concurrently  with  and  indisAnguishable  from,  an  Employer  Delay.  

2.   Contractor  must  make  his  claims  for  both  Cme  and  cost  –  must  be  reasonable,  fact-­‐based,  sensible  and  consistent  with  common  sense.  •  Equally,  the  Employer  should  not  demand  nth  levels  of  detail.  

3.   For  Concurrent  Delays,  Contractor  gets  Cme  but  no  cost  –  the  SCL  Approach,    •  But  beware  that  GCC  may  allow  ApporAonment  approach  to  split  liability.        

(ArAcle  257  CompensaAon  decreased  if  Creditor  parAcipated  in  damage)    

4.  If  the  Employer  accepts  a  criAcal  delay,  he  accepts  liability  for  both  Cme  and  cost.  •  But  should  the  Employer  consider  there  are  other  delays  that  relieve  him  of  his  

liability  to  cost,    it  is  for  the  Employer  to  prove.    (ArAcle  211  of  Law  13  of  1990  under  the  Civil  and  Commercial  Procedure  Law)    (ArAcle  256  CompensaAon  decreased  if  Debtor  was  not  responsible  for  the  delay)    

Page 27: Concurrent!delay!–In!Simple!Terms...Delay!Analysis!is!not!about!P6:! • P6!is!justaplanning!tool.! • P6!is!acomputer!model,!it’s!notthe!physical!works!outon!the!ground.!! Delay!Analysis!should!be

27  

Concurrent  delay  –  In  Simple  Terms  

       Any  QuesCons?        Quantum  Global  SoluCons  950  lbn  Seena  Street  Al  Muntazah  PO  Box  22521  Doha  Qatar  T:  +974  4431  2826  W:  www.qgs.global