Concerto II: SIR
Non-profit organisation
All communities of Salzburg are members
Competence in:urban planning/ geograficBuilding technique/architecture/ energy
Inge StraßlHelmut StrasserAlexander Brandl
SIR - Salzburger Institut für Raumordnung & Wohnen
Internet: http://www.sir.at
3
Kopenhagen (Valby) and Salzburg
Option area 1
Option area 2
New built area
retrofit area
retrofit area
4
Cooperations: Energy points in the Salzburg social housing funding system Danish experience with controlled air ventilation and PV common test bio gasification Thermal solar concept with housing International conferences in
Kopenhagen and Salzburg
5
Green Solar Cities
5 Partner in Valby/Kopenhagen (Koordinator Kuben)8 Partner in Salzburg 2 scientific partners: Uni Lund, OTB Delft2 associated partners
Ujpest – Ungarn
Eindhoven – Holland
Project time: 1. Juni 2007 – 31. Mai 2012
EU-funding:35% of the additional costs in demonstration50% for research, monitoring and dissemination100% for training and management
Total budget: eligible: 15,6 Mill €, EU-funding: 6,3 Mill €
EU money for Salzburg: about. 2.300.000 €
6
Salzburg Partners:
SIR: lokal coordination, research, dissemination
Builder:
Gswb, „Die Salzburg“ and HÖ: social housing and retrofit
Prisma: Investor for Science-center and renovation of the multi storey office building
Salzburg AG: owner of the area, will errect and run the solar-plant and the mikronet
Stadt Salzburg: Projektdevelopment, social economic aspects
Steinbeis Institut (Stuttgart): Conception, simulation, planning
8
Core-areal Salzburg
Core-areal: about 60.000m2 BGF new built, 10.000m2 renovation (Hochhaus)
Energy supply with micro.net
Gewerbeteil
Gemeinnütziger Wohnbau
Areal befindet sich in einem „problematischen“ Stadtteil
12
Siebenstätterstraße
Senior-residence 90 beds
32 apartments for elderly people
56 social dwellings
13
Main topics
Focus on raising the energy efficiency and use of solar energy
300 new built dwellings in passive house or lowest energy standard About 440 new dwellings
Refurbishment concept for the area: 300 dwellings thermal and, 450 dwellings with a new energy supply
About 100 thermal renovations, 100 new energy-supply, office building
Totally energy concept for the area with focus on solar: Thermal solar plant with 2.000m² collector and 200.000 l puffer tank and 250m² PV – distribution system with micro-net
2.000m² collector, 200.000 l puffer tank, 500m² PV, additional 580m² collector
Concept for raising the living quality of the whole area: quality of the green areas, traffic, social themes and integration
14
Project proposal:Sept 2005: first contact Danmark
Search for project in Salzburg
Conception and look for strong partners
proposal December 2005
Info of positive Evaluation June 2006
negotiations October 2006
Contract start 1st June 2007
16
Green Solar Cities: Salzburg
Concerto Projektmanagement Salzburg(Stadt Salzburg, GSWB, HÖ, Die Salzburg, Salzburg AG, PRISMA, Steinbeis Transferzentrum)
Coordination: SIR
Steering-groupe
Management Gesamtprojekt
Concerto Qualitätssicherung
Working groups Concerto (Solar &
Mikronetz, Bauphysik,..)
Other Working groups
(Quartiersmanagement, Soziales, Freiraum,..)
implementation
Monitoring and
Quality controll
Concerto Projektmanagement EU
Koordinator Kuben (DK) – Management team
17
Steering-group
Meilensteine - Zeitplan
Steering-group (once a month, chaired by the city):
- Project development (timetable, main actors,..)
- project management
- controlling
- Interdisciplinary team
- several themes (with Concerto)
18
Special working groups
0
500.000
1.000.000
1.500.000
2.000.000
2.500.000
Übersicht StadtwerkearealStrom bis
2012: CONCERTO Ziele
Übersicht StadtwerkearealStrom bis
2012: Normal
Strom für WW- BereitungStrom für übrige Haustechnik (Pumpen,..)Strom für Ventilation/LüftungStrom für Beleuchtung
- 90%
1. Building performance
2. Energy – Solar & micro-net
3. Energy – PV & electricity efficiency
4. retrofit
5. Participation und Quarter-management
6. Design of free areas
19
RTD – research
Integration of a heat pump in the solar circle of the thermal solar plant to increase the efficiency
Test new heating system for fresh air in passive-house
Air ventilation in existing buildings
Facade- system in renovation
integrated PV and solutions for use in social dwellings
20
Status Quo
1. First year finished reports
2. Ammendmanet to contract necessary (new contract partner, budget shifts,…)
3. First demo-project finished (passive-house detailled monitoring)
4. New Buildings in planning phase – building start middle 2009.
5. Problems renovations & Quarter-management (who is responsibel for what?)
6. „Option Areas“ additional in realisation Budget !!
7. International conference im autumn in Salzburg- Partnermeeting.
21
International conference
Do 23th October 2008 in Salzburg
„Stadt im Umbau – neue urbane Horizonte“
Themes: Revitalisation of old living areas – quality of public and halb public areas – Energy-conzepts for sustainable cities - changes in society and how the react in urban planning
22
Barriers / problems
1. long-term project conception for many partners
2. Political opinions are sometimes hard to handle (elections in spring 2009)
3. Many actors in new rolls – new ways of working – motivation necessary!!
4. Praxis relevant information for management missing (Budget shifts, change of contracts, EU-funding,…)
5. EU reports and calculations and accounting system
6. Funding not always clear and sometimes not really motivating (passive house)
23
Lessons learned
1. Complex problems needs interdisciplinary teams and structures
Steering-group
Concerto as impulse for innovations (Quality agreement, working groups,..)
2. Good structure for information
3. Strong local partners
4. Climate of confidence and clear rules
3. Builder and politicians are not used to work in the rules and ways of a EU project conferences & meetings as „Icebreaker“, personal contacts
4. Important are the acting persons!! – identification