16
Concept Summary Client: Monaghan Project: Garage Apartment Address: 2107 Central Ave, Ortley beach 1 Management $17,500.00 1 Permits $2,053.30 1 Design $6,900.00 2 Site $20,530.00 3 Concrete $7,467.84 4 Masonry $3,236.00 5 Metals $957.50 6 Carpentry $26,423.98 7 Thermal & Moisture $8,175.34 8 Doors & Windows $7,410.00 9 Finishes $16,859.60 10 Specialty $3,173.00 11 Cabinetry $2,058.00 12 Equipment $4,550.00 15 Plumbing $25,580.00 16 Electric $10,465.40 Total $163,339.96 Material & Equipment $ 54,365.26 Construction Labor $ 82,521.40 General Conditions $26,453.30 Building $100,841.26 1.50% $1,513 Plumbing $25,580.00 1.50% $384 Electric $10,465.40 1.50% $157 Contingency (5% of construction only) $6,844.33 Grand Total $170,184.29 Mngt/ Construction % $26,453.30 18% $143,730.99 84% Permit Allowance C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

  • Upload
    vuduong

  • View
    220

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Concept Summary

Client: Monaghan

Project: Garage Apartment

Address: 2107 Central Ave, Ortley beach

1 Management $17,500.00

1 Permits $2,053.30

1 Design $6,900.00

2 Site $20,530.00

3 Concrete $7,467.84

4 Masonry $3,236.00

5 Metals $957.50

6 Carpentry $26,423.98

7 Thermal & Moisture $8,175.34

8 Doors & Windows $7,410.00

9 Finishes $16,859.60

10 Specialty $3,173.00

11 Cabinetry $2,058.00

12 Equipment $4,550.00

15 Plumbing $25,580.00

16 Electric $10,465.40

Total $163,339.96

Material & Equipment $ 54,365.26

Construction Labor $ 82,521.40

General Conditions $26,453.30

Building $100,841.26 1.50% $1,513

Plumbing $25,580.00 1.50% $384

Electric $10,465.40 1.50% $157Contingency (5% of

construction only) $6,844.33

Grand Total $170,184.29

Mngt/ Construction %

$26,453.30 18%$143,730.99 84%

Permit

Allowance

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 2: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 1

General Conditions

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Design -$ -$ -$ -$ -$ -$

Conept Design 4 hrs -$ -$ -$ 125.00$ 500.00$ -$ 600.00$

Construction Documents 4 dys -$ -$ -$ 1,000.00$ 4,000.00$ -$ 4,800.00$

Construction phase support 10 hrs -$ -$ -$ 125.00$ 1,250.00$ -$ 1,500.00$

Management -$ -$ -$ -$ -$ -$

Preconstruction due dilagence 8 hrs 125 -$ 1,000.00$ -$ -$ -$ -$

Concept Budget 4 hrs 125 -$ 500.00$ -$ -$ -$ -$

Construction Budget 20 hrs 100 -$ 2,000.00$ -$ -$ -$ -$

Subcontractor qualification 60 hrs 100 -$ 6,000.00$ -$ -$ -$ -$

Construction phase support 80 hrs 100 -$ 8,000.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals -$ 17,500.00$ -$ 6,900.00$

Grand Tot 17,500.00$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 3: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 2

Site Work

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Demo Existing garage Inc slab -$ -$ -$ -$ -$ -$

Dumpsters 3 ea 650 1,950.00$ -$ -$ Pizz Plumbing 500.00$ 1,500.00$ -$ 1,800.00$

2 laborers 16 hrs 45 -$ 720.00$ -$ Pizz Plumbing 52.00$ 832.00$ -$ 998.40$

Back hoe & operator 8 hrs 50 100 -$ 400.00$ 800.00$ Pizz Plumbing 125.00$ 1,000.00$ -$ 1,200.00$

Stockpile stone 4 hrs 50 100 -$ 200.00$ 400.00$ Pizz Plumbing 125.00$ 500.00$ -$ 600.00$

New driveway 1200 sf 3.75 9 4,500.00$ 10,800.00$ -$ Hardscape -$ 15,000.00$ 15,000.00$

-$ -$ -$ -$ -$ -$

Landscaping -$ -$ -$ -$ -$ -$

Grade &Seed 2000 sf 0.05 0.33 100.00$ 660.00$ -$ TBD -$ 700.00$ 700.00$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 6,550.00$ 12,780.00$ 1,200.00$ 20,298.40$

Grand Tot 20,530.00$

Estimated Cost Bid Cost

Unit Total

Work sheet Work sheet

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 4: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 3

Concrete

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Excavate footing -$ -$ -$ -$ -$ -$

Backhoe and Operator 4 hrs 50 100 -$ 200.00$ 400.00$ -$ -$ -$

Labor 8 hrs 35 -$ 280.00$ -$ -$ -$ -$

Rebar& forms -$ -$ -$ -$ -$ -$

Place rebar hor 8 hrs 50 -$ 400.00$ -$ -$ -$ -$

Place rebar vert 16 hrs 50 -$ 800.00$ -$ -$ -$ -$

Rebar material 300 lbs 0.75 225.00$ -$ -$ -$ -$ -$

Forms 1 ls 250 250.00$ -$ -$ -$ -$ -$

Pour footing -$ -$ -$ -$ -$ -$

Mason 4 hrs 50 0 -$ 200.00$ -$ -$ -$ -$

labor 4 hrs 35 -$ 140.00$ -$ -$ -$ -$

Concrete 7 cy 87 30 609.00$ -$ 210.00$ -$ -$ -$

Slab and aprons -$ -$ -$ -$ -$ -$

Grade (BH &Op) 4 hrs 50 100 -$ 200.00$ 400.00$ -$ -$ -$

Labor 4 Hrs 20 -$ 80.00$ -$ -$ -$ -$

Stone (spread Inc in grade) 10 tns 35 50 20 350.00$ 500.00$ 200.00$ -$ -$ -$

Wire mesh 476 sf 0.34 161.84$ -$ -$ -$ -$ -$

Slab Concrete 9 cy 93 25 837.00$ -$ 225.00$ -$ -$ -$

Mason 16 hrs 50 -$ 800.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 2,432.84$ 3,600.00$ 1,435.00$ -$

Grand Tot 7,467.84$

Estimated Cost Bid Cost

Unit Total

Work sheet Work sheet

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 5: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 4

Masonry

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Foundation Walls -$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Mason 40 hrs 60 -$ 2,400.00$ -$ -$ -$ -$

CMU 280 pcs 1.2 336.00$ -$ -$ Pizzalato 10.50$ 2,940.00$ -$ 3,528.00$

Misc supplies 1 ls 500 500.00$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 836.00$ 2,400.00$ -$ 3,528.00$

Grand Tot 3,236.00$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 6: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 5

Metals

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Specialty Framing Fasteners -$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Sill Anchor bolts 35 4.5 157.50$ -$ -$ -$ -$ -$

Steel columns 4 200 800.00$ -$ -$ Arnold Steel 250.00$ 1,000.00$ -$ 1,200.00$

120 MPH strapping 0 ls 128 -$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 957.50$ -$ -$ 1,200.00$

Grand Tot 957.50$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 7: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 6

Carpentry

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Sill plate 8 hrs 50 -$ 400.00$ -$ Brown -$ 21,000.00$ 21,000.00$

2X6 Sill plate Mat 134 lf 0.87 116.58$ -$ -$ -$ -$ -$

1st flr walls -$ -$ -$ -$ -$ -$

1st flr walls Carp 16 hrs 50 -$ 800.00$ -$ -$ -$ -$

1st flr walls Lab 16 hrs 35 -$ 560.00$ -$ -$ -$ -$

2X4X14' wallstud 20 pcs 7 140.00$ -$ -$ -$ -$ -$

2x4X8' Wall stud 20 pcs 2.9 58.00$ -$ -$ -$ -$ -$

2X4X12' cap 12 pcs 5.5 66.00$ -$ -$ -$ -$ -$

4X4X8' posts 0 lf 10 -$ -$ -$ -$ -$ -$

3-1/2" X 11-7/8" LVL 23 lf 20 460.00$ -$ -$ -$ -$ -$

1-7/8" X 11-7/8" LVL 68 lf 16 1,088.00$ -$ -$ -$ -$ -$

Flr jsts Carp 16 hrs 50 -$ 800.00$ -$ -$ -$ -$

Flr jsts Labb 8 hrs 35 -$ 280.00$ -$ -$ -$ -$

Flr jsts Mat (9-7/8 TJI) 442 lf 8 3,536.00$ -$ -$ -$ -$ -$

1st flr decking carp 8 hrs 50 -$ 400.00$ -$ -$ -$ -$

1st flr decking Lab 8 hrs 35 -$ 280.00$ -$ -$ -$ -$

1st flr decking Mat 20 shts 30 600.00$ -$ -$ -$ -$ -$

1st flr decking Glue/ nails 1 ls 150 150.00$ -$ -$ -$ -$ -$

2nd flr walls Mat -$ -$ -$ -$ -$ -$

2nd flr walls Carp 24 50 -$ 1,200.00$ -$ -$ -$ -$

2nd flr walls Lab 16 35 -$ 560.00$ -$ -$ -$ -$

2X4X8" Wall stud 170 pcs 2.9 493.00$ -$ -$ -$ -$ -$

4X4x14' posts 0 pcs 20 -$ -$ -$ -$ -$ -$

4X4x8' posts 1 pcs 10 10.00$ -$ -$ -$ -$ -$

2X4X10' sill plate 30 pcs 4.5 135.00$ -$ -$ -$ -$ -$

2X4X10' Cap 30 pcs 4.5 135.00$ -$ -$ -$ -$ -$

1-7/8" X 11-7/8" LVL 15 lf 7.5 112.50$ -$ -$ -$ -$ -$

2X8 double headers 40 lf 1.5 60.00$ -$ -$ -$ -$ -$

Loft deck Carp 4 hrs 50 -$ 200.00$ -$ -$ -$ -$

Loft Deck Lab 4 hrs 35 -$ 140.00$ -$ -$ -$ -$

Loft floor jsts 5-1/2 X 3-1/2 LVL 0 lf 3 -$ -$ -$ -$ -$ -$

Loft decking 0 shts 30 -$ -$ -$ -$ -$ -$

Loft glue/ nails 1 ls 100 100.00$ -$ -$ -$ -$ -$

Deck Ceiliing 1 ls 300 -$ 300.00$ -$ -$ -$ -$

Roof support framing Carp 0 hrs 50 -$ -$ -$ -$ -$ -$

Roof support framing Lab 0 hrs 35 -$ -$ -$ -$ -$ -$

Roof jsts Carp 16 hrs 50 -$ 800.00$ -$ -$ -$ -$

Roof jst Lab 16 hrs 35 -$ 560.00$ -$ -$ -$ -$

Roof sheathing Carp 8 hrs 50 -$ 400.00$ -$ -$ -$ -$

Roof Sheathing Lab 8 hrs 35 -$ 280.00$ -$ -$ -$ -$

4X4X8 posts 4 pcs 10 40.00$ -$ -$ -$ -$ -$

2X10 lvl ridge pole 26 lf 0.75 19.50$ -$ -$ -$ -$ -$

2x4X8' Wall stud 0 pcs 3.5 -$ -$ -$ -$ -$ -$

2X10X14 roof jst 56 pcs 15 840.00$ -$ -$ -$ -$ -$

Ext Sheathing walls (1/2 " CDX) 51 shts 15 25 765.00$ 1,275.00$ -$ -$ -$ -$

Ext sheathing roof (5/8" CDX) 20 shts 21 30 0 420.00$ 600.00$ -$ -$ -$ -$

Glue/ nails 1 ls 500 500.00$ -$ -$ -$ -$ -$

Contiingency 0.10 % 9844 984.40$ -$ -$ -$ -$ -$

Lifting Equipment Rental 2 wk 1200 -$ -$ 2,400.00$ -$ -$ -$

Hurricane strapping 1 ls 500 500.00$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Trim -$ -$ -$ -$ -$ -$

Doors 7 ea 60 100 420.00$ 700.00$ -$ -$ -$ -$

Windows 6 ea 40 100 240.00$ 600.00$ -$ -$ -$ -$

Base 200 lf 3.5 1 700.00$ 200.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 12,688.98$ 11,335.00$ 2,400.00$ 21,000.00$

Grand Tot 26,423.98$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 8: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 7

Thermal Moisture

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Roofing -$ -$ -$ -$ -$ -$

Roof 8 sqr 160 1,280.00$ -$ -$ GDS Roofing 265.00$ 2,120.00$ -$ 2,544.00$

Roof install 24 hrs 35 -$ 840.00$ -$ -$ -$ -$

Misc mat 1 ls 200 200.00$ -$ -$ -$ -$ -$

Gutters 50 lf -$ -$ -$ Pace 6.50$ 325.00$ -$ 390.00$

Wall insulation 960 sf 0.33 0.25 316.80$ 240.00$ -$ Interstate 0.55$ 528.00$ -$ 633.60$

Floor/ ceiling insulation 1200 sf 0.33 0.33 396.00$ 396.00$ -$ Interstate 0.75$ 900.00$ -$ 1,080.00$

Siding -$ -$ -$ -$ -$ -$

Tyvec 1522 sf 0.07 106.54$ -$ -$ -$ -$ -$

Vinyl Siding 13 sqr 75 100 975.00$ 1,300.00$ -$ Martin -$ 4,200.00$ 4,200.00$

Trim 1 ls 1000 1125 1,000.00$ 1,125.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 4,274.34$ 3,901.00$ -$ 8,847.60$

Grand Tot 8,175.34$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 9: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 8

Doors Windows

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Doors -$ -$ -$ -$ -$ -$

Entrance 3 Pcs 150 150 450.00$ 450.00$ -$ Home Depot -$ 4,500.00$ 4,500.00$

Bath Rm 1 Pcs 75 65 75.00$ 65.00$ -$ Brown (Instal) -$ 2,500.00$ 2,500.00$

Passage Pcs 200 -$ -$ -$ -$ -$ -$

Bed Rm 1 Pcs 75 65 75.00$ 65.00$ -$ -$ -$ -$

Closet slider 1 Pcs 75 65 75.00$ 65.00$ -$ -$ -$ -$

6' Ext slider 1 Pcs 1200 450 1,200.00$ 450.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Windows -$ -$ -$ -$ -$ -$

36" window 3 Pcs 255 100 765.00$ 300.00$ -$ -$ -$ -$

5'Bay 1 Pcs 760 400 760.00$ 400.00$ -$ -$ -$ -$

Stair/ kit window 1 Pcs 275 100 275.00$ 100.00$ -$ -$ -$ -$

Gable 1 Pcs 75 75 75.00$ 75.00$ -$ -$ -$ -$

Garage doors 2 ls 450 200 900.00$ 400.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Hardware (locksets) 6 sets 65 390.00$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 5,040.00$ 2,370.00$ -$ 7,000.00$

Grand Tot 7,410.00$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 10: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 9

Finishes

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Walls & Ceilings -$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Drywall 1552 sf 1.1 3 1,707.20$ 4,656.00$ -$ Nagy Drywall -$ 5,500.00$ 5,500.00$

Paint 1552 sf 0.2 1 310.40$ 1,552.00$ -$ -$ -$ -$

Flooring -$ -$ -$ -$ -$ -$

Wood Flooring 560 sf 4.5 9 2,520.00$ 5,040.00$ -$ -$ -$ -$

Tile flrs 40 sf 4.5 10 180.00$ 400.00$ -$ -$ -$ -$

Mud Rm vinyl flr 65 sf 2.6 5 169.00$ 325.00$ -$ -$ -$ -$

Carpet 0 sf -$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 4,886.60$ 11,973.00$ -$ 5,500.00$

Grand Tot 16,859.60$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 11: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 10

Specialties

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Exterior Fiberglass Deck 36 sf 9 9 324.00$ 324.00$ -$ DecKing -$ 650.00$ 650.00$

-$ -$ -$ -$ -$ -$

Ext. Stairs 0 ls -$ -$ -$ -$ -$ -$

Interior Spiral Stairs (14 risers) 1 ls 1250 850 1,250.00$ 850.00$ -$ -$ -$ -$

Bathroom Vanity 1 ls 325 100 325.00$ 100.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 1,899.00$ 1,274.00$ -$ 650.00$

Grand Tot 3,173.00$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 12: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 11

Casework/ Cabinets

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Kitchen Cabinets (upper & lower) 10 lf 100 75 1,000.00$ 750.00$ -$ -$ -$ -$

Counter top 14 sf 12 10 168.00$ 140.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 1,168.00$ 890.00$ -$ -$

Grand Tot 2,058.00$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 13: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 12

Equipment

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

Furnace 1 pc 1500 1,500.00$ -$ -$ -$ -$ -$

Fridge 1 pc 450 450.00$ -$ -$ -$ -$ -$

Stove 1 pc 500 500.00$ -$ -$ -$ -$ -$

Dish Washer 1 pc 500 500.00$ -$ -$ -$ -$ -$

Washer/ dryer 1 pc 1000 1,000.00$ -$ -$ -$ -$ -$

HWH 1 pc 600 600.00$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 4,550.00$ -$ -$ -$

Grand Tot 4,550.00$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 14: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 13

Fire Protection

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals -$ -$ -$ -$

Grand Tot -$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 15: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 15

Mechanical

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Sanitary 175 lf -$ -$ -$ Pizz Plumbing 28.00$ 4,900.00$ -$ 5,880.00$

Service connections in Road (Road permit/

asphalt/ bond) 1 ls -$ -$ -$ Aldo Asphalt -$ -$ 10,000.00$ 10,000.00$

Plumbing permit 1 ls -$ -$ -$ -$ -$ -$ -$

Bath Rm 1 ls -$ -$ -$ Pizz Plumbing 2,000.00$ 2,000.00$ -$ 2,400.00$

Kitchen 1 ls -$ -$ -$ Pizz Plumbing 500.00$ 500.00$ -$ 600.00$

Water service (inc in San) 1 ls -$ -$ -$ -$ -$ -$ -$

Heating (inc furnace) 1 ls -$ -$ -$ Ace Heating 1,000.00$ 1,000.00$ -$ 1,200.00$

Gas 1 ls -$ -$ -$ Pizz Plumbing -$ -$ -$

Fixtures/ Equipment 1 ls 2500 2,500.00$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Ductwork 1 ls -$ -$ -$ Ace Heating 2,500.00$ 2,500.00$ -$ 3,000.00$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 2,500.00$ -$ -$ 23,080.00$

Grand Tot 25,580.00$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off

Page 16: Concept Summary - Construction Sidekickconstructionsidekick.com/.../3145799/garage_apt._concept_take-off.pdf · Concept Summary Client: Monaghan Project: ... \Construction Sidekick\Templates\Garage

Division 16

Electrical

Date: 8/25/2012

Description Qty Unit Mat Lab Equip Mat $ Lab $ Equip$ Sub Unit $ Total Est $ Total+Profit Notes

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Electrical service upgrade 1 ls -$ -$ -$ 2,200.00$ 2,200.00$ -$ 2,640.00$

Sub panel 1 ls -$ -$ -$ 1,500.00$ 1,500.00$ -$ 1,800.00$

Outlets 16 pcs -$ -$ -$ 75.00$ 1,200.00$ -$ 1,440.00$

Switches 12 pcs -$ -$ -$ 50.00$ 600.00$ -$ 720.00$

Ceiling fans 2 Pcs -$ -$ -$ 150.00$ 300.00$ -$ 360.00$

Hi hats 12 pcs -$ -$ -$ 86.00$ 1,032.00$ -$ 1,238.40$

Appliance hook up 4 pcs -$ -$ -$ 150.00$ 600.00$ -$ 720.00$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Fixture Allowances -$ -$ -$ -$ -$ -$

4' Florescents 6 Ea 40 240.00$ -$ -$ -$ -$ -$

Wall switch 20 Ea 5 100.00$ -$ -$ -$ -$ -$

Three way wall switch 4 Ea 15 60.00$ -$ -$ -$ -$ -$

Sub panel 100 amp 0 Ea 100 -$ -$ -$ -$ -$ -$

Main Panel 0 Ea 130 -$ -$ -$ -$ -$ -$

Duplex wall outlet 20 Ea 5 100.00$ -$ -$ -$ -$ -$

GFCI 3 Ea 4 12.00$ -$ -$ -$ -$ -$

Exterior surface mount light Ceiling 4 Ea 25 100.00$ -$ -$ -$ -$ -$

Exterior surface mount light Wall 1 Ea 40 40.00$ -$ -$ -$ -$ -$

6" hihat 6 Ea 50 300.00$ -$ -$ -$ -$ -$

4" hihat 4 Ea 50 200.00$ -$ -$ -$ -$ -$

Ceiling fan 2 Ea 175 350.00$ -$ -$ -$ -$ -$

Fart fan 1 Ea 25 25.00$ -$ -$ -$ -$ -$

Vanity light 1 Ea 20 20.00$ -$ -$ -$ -$ -$

Fixture allow 1 ls -$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$

Totals 1,547.00$ -$ -$ 8,918.40$

Grand Tot 10,465.40$

Work sheet Work sheet

Estimated Cost Bid Cost

Unit Total

C:\Construction Sidekick\Templates\Garage Apt. Concept Take-off