PARKS VICTORIA ALTONA PIER DATE JOB NO. DRAWING NO ISSUE landscape architecture urban design environmental management 27.04.2020 V191484 5 SK-AL-01 PIER STREET ESPLANADE WATER DEPTH 0 - 1m 1 - 2.8m 2.8 - 4.5m (Water depths are approximate) SCALE 1:500 @ A1 0 10 20 30 50m SCALE 1:100 @ A1 0 2 4 6 10m NORTH RESPITE SEATING PROVIDED ALONG LENGTH OF PIER RAMP DOWN TO DDA COMPLIANT FIXED LOW LANDING EXISTING PIER HEAD TO BE REINSTATED ALIGNMENT OF PIER TO REMAIN THE SAME AS THE EXISTING CONCRETE ABUTMENT TO ADJOINING SEAWALL DEVELOPMENT NEW STEPS DOWN TO FIXED SWIMMING PLATFORM RESPITE SEATING PROVIDED ALONG LENGTH OF PIER RAMP DOWN TO DDA COMPLIANT FIXED LOW LANDING APPROXIMATE LOCATION OF ARTIFICIAL REEF ADDITIONAL ARTIFICIAL REEF MODULES AWAY FROM PIER DDA COMPLIANT FIXED LOW LANDING WITH CAPPING BOARD TO EDGE FOR SAFETY EXISTING PIER HEAD TO BE REINSTATED DDA COMPLIANT FIXED LOW LANDING WITH CAPPING BOARD TO EDGE FOR SAFETY MOTION SENSOR LIGHTING AT 30M SPACING TO MINIMISE IMPACT ON WILDLIFE WHILE ENSURING SAFE PEDESTRIAN ACCESS. APPROXIMATE LOCATION OF NO BOATING ZONE CONCEPT DESIGN - OPTION ONE - REPAIR PLAN 1:500 SECTION 1 1:100

CONCEPT DESIGN - OPTION ONE - REPAIR · concept design - option one - repair (detail plans) esplanade water depth 0 - 1m 1 - 2.8m 2.8 - 4.5m (water depths are approximate) direct

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CONCEPT DESIGN - OPTION ONE - REPAIR · concept design - option one - repair (detail plans) esplanade water depth 0 - 1m 1 - 2.8m 2.8 - 4.5m (water depths are approximate) direct

PARKS VICTORIA ALTONA PIER

DATEJOB NO. DRAWING NO ISSUE

landscape architectureurban design

environmental management 27.04.2020V191484 5SK-AL-01

PIER STREET

ESPL

ANAD

E

WATER DEPTH

0 - 1m

1 - 2.8m

2.8 - 4.5m

(Water depths are approximate)

SCALE 1:500 @ A1

0 10 20 30 50m

SCALE 1:100 @ A1

0 2 4 6 10m

NORTH

RESPITE SEATING PROVIDED ALONG LENGTH OF PIER

RAMP DOWN TO DDA COMPLIANT FIXED LOW LANDING

EXISTING PIER HEAD TO BE REINSTATED

ALIGNMENT OF PIER TO REMAIN THE SAME AS THE EXISTING

CONCRETE ABUTMENT TO ADJOINING SEAWALL DEVELOPMENT

NEW STEPS DOWN TO FIXED SWIMMING PLATFORM

RESPITE SEATING PROVIDED ALONG LENGTH OF PIER

RAMP DOWN TO DDA COMPLIANT FIXED LOW LANDING

APPROXIMATE LOCATION OF ARTIFICIAL REEF

ADDITIONAL ARTIFICIAL REEF MODULES AWAY FROM PIER

DDA COMPLIANT FIXED LOW LANDING WITH CAPPING BOARD TO EDGE FOR SAFETY

EXISTING PIER HEAD TO BE REINSTATED

DDA COMPLIANT FIXED LOW LANDING WITH CAPPING BOARD TO EDGE FOR SAFETY

MOTION SENSOR LIGHTING AT 30M SPACING TO MINIMISE IMPACT ON WILDLIFE WHILE ENSURING SAFE PEDESTRIAN ACCESS.

APPROXIMATE LOCATION OF NO BOATING ZONE

CONCEPT DESIGN - OPTION ONE - REPAIR

PLAN1:500

SECTION 11:100

Page 2: CONCEPT DESIGN - OPTION ONE - REPAIR · concept design - option one - repair (detail plans) esplanade water depth 0 - 1m 1 - 2.8m 2.8 - 4.5m (water depths are approximate) direct

PARKS VICTORIA ALTONA PIER

DATEJOB NO. DRAWING NO ISSUE

landscape architectureurban design

environmental management 27.04.2020V191484 5SK-AL-02SCALE 1:200 @ A1

0 4 6 12 20m

CONCEPT DESIGN - OPTION ONE - REPAIR (DETAIL PLANS)

ESPL

ANAD

E

WATER DEPTH

0 - 1m

1 - 2.8m

2.8 - 4.5m

(Water depths are approximate)

DIRECT ABUTMENT FROM PIER TO ADJOINING PATH

RAMP DOWN TO SINGLE DDA COMPLIANT FIXED LOW LANDING

EXISTING PIER HEAD TO BE REINSTATED

RAMP DOWN TO SINGLE DDA COMPLIANT FIXED LOW LANDING

ADDITIONAL ARTIFICIAL REEF MODULES AWAY FROM PIER

MOTION SENSOR LIGHTING AT 30M SPACING TO MINIMISE IMPACT ON WILDLIFE WHILE ENSURING SAFE PEDESTRIAN ACCESS.

DETAIL PLAN - ABUTMENT1:200

DETAIL PLAN - PIER HEAD1:200