35
PRESENTATION BY NATALIA KULICHENKO SENIOR ENERGY SPECIALIST JUNE 28, 2012 Concentrating Thermal Solar – lessons from different countries

Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

  • Upload
    dokhanh

  • View
    221

  • Download
    4

Embed Size (px)

Citation preview

Page 1: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

PRESENTATION BY NATALIA KULICHENKO

SENIOR ENERGY SPECIALIST

JUNE 28, 2012

Concentrating Thermal Solar –

lessons from different countries

Page 2: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Currently Installed CST Capacity (2012)

2

Country Total Operating Total under Construction

or Commissioning Total Announced

USA

(CA, NV, AZ, NM, ID, FL) 524.5 MW 1,447 MW 23,091.5 MW

Spain 1,081.4MW 673.5 MW 1,101.48 MW

Morocco 20 MW - 500 MW

Algeria 25 MW - 215 MW

Australia 6.8 MW 47.2 MW 250 MW

China - 31 MW 453 MW

South Africa - - 250 MW

Mexico - 12 MW -

Italy 5 MW 5 MW -

Egypt 20 MW - 100 MW

France - 13.4 MW 50MW

Jordan - - 100 MW

UAE - 100 MW -

Iran 17.3 MW - 72 MW

India 2.5 MW 10 MW 700 MW

Portugal - - 13 MW

Page 3: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Incentive Systems and Financing

Schemes

Page 4: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Regulatory Challenges with regard to CST promotion

4

• Provide sufficient incentives to developers to balance high up-front investment costs against savings in fuel and O&M costs and cost-reduction potential

Effectiveness

• Limit societal cost of the particular regulatory mechanism

• Avoid overpriced incentives resulting in investment bubbles and high societal costs

• Consider cost-reduction potential of different technologies

Efficiency

Page 5: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Current Instruments and Frameworks

5

Instruments available:

Feed-in tariff

Quota (Renewable Portfolio Standard – RPS; Green Certificate System – GCS; etc.)

Subsidy/tax incentive

Voluntary renewable energy scheme

Renewable energy fund

Differs among Market Structure

Spain:

Feed-In Tariff Framework (FIT)

United States:

Renewable Portfolio Standard Framework (RPS)

Page 6: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Feed-In Tariff Frameworks

6

•.

Set at a predefined level or as premium above market-wholesale price

Preferential grid access and specified tariff rate over extended period

Utilities required to off-take output but can pass cost difference on

Incentive for cost-reduction: tariffs reduced every year

PROS/CONS depends on mix of RE generation created by FIT and actual design of FIT

Pros:

reduced spot market prices, GHG emissions, need for fossil

fuel imports

Cons:

increases the overall price of electricity for customers

Page 7: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Renewable Portfolio Standard Frameworks

7

RPS combined with tax incentives, loan guarantees, voluntary purchases of RE power

Retailers obliged to reserve increasing percentage of RE to supply mix every year

Retailers can draw upon own facilities, purchase RE power, trade Green Certificates (GCs)

GCs reflect incremental cost of marginal capacity need to fulfill RPS requirement

Pros:

Trading GCs should create strong incentive to meet demand for GCs in

the least-cost fashion

Lower societal cost

Cons:

Once quota is reached, incentive to operate cost-efficiently vanishes

High administrative costs for retailers and developers

Page 8: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Choice of a Tariff Scheme in a Developing Country

Competitive Bidding Market determines price

… minimizes rent (no windfall profits for developers)

… allows choice between pre-selected or dev. selected sites

… allows transmission planning & optimization (MA, QC examples)

… not a problem who pays for transmission and other elements

… transparent scheme, no need for special tax incentives etc.

Feed-in Tariff (FIT) Market determines MW volume

… hard to estimate efficient pricing model in advance

… developers select sites, not suitable w/concentrated resource

… puts pressure on transmission planning, grid congestion queue?

… must plan who pays for any cost element including grid

… incentives important, zoning issues critical, corruption prone

IMPORTANT POLICY CONSIDERATIONS PART 1

Page 9: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Choice of a Tariff Scheme in a Developing Country

Competitive Bidding 2 … incomplete regulation (e.g. grid code) can be solved ad hoc by »regulation by contract«

… public land lease can be integrated in process and can be non-exclusive (QC example)

… permitting process (must be) integrated in RFP and quasi-automatic

... MW volume is controlled

Feed-in Tariff (FIT) 2 … requires complete and transparent regulatory scheme

… competition for scarce physical resources (transmission grid, public land leases)

… competition for regulatory resources (permits) –resource lock-up by unqualified bidders

… if tariff scheme is profitable queuing or quasi-market rationing develops

IMPORTANT POLICY CONSIDERATIONS PART 2

Page 10: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

INDIA NATIONAL SOLAR MISSION (source: NVVN)

10

• The National Solar Mission is major initiative of the Government of India –

–To promote ecologically sustainable growth;

–Addressing India’s energy security challenge.

• The Mission is set in three phases-

–Phase-I (up to 2012-13) – 1000 MW

–Phase-2 (2013-17) – 4,000 MW

–Phase-3 (2017-22) – 20,000 MW

Page 11: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

INDIA NATIONAL SOLAR MISSION – Bundling Scheme(source: NVVN)

11

Page 12: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

INDIA NATIONAL SOLAR MISSION - Implementation (source: NTPC)

12

• In order to facilitate grid connected solar power generation in the first phase, a mechanism of “bundling” relatively expensive solar power with power from the unallocated quota of the Government of India (Ministry of Power) generated at NTPC coal based stations, which is relatively cheaper.

• This “bundled power” would be sold to the Distribution Utilities.

• For each MW of installed capacity of solar power for which a Power Purchase Agreement (PPA) is signed by NVVN, the Ministry of Power (MoP) shall allocate to NVVN an equivalent amount of MW capacity from the unallocated quota of NTPC coal based stations and NVVN will supply this “bundled” power to the Distribution Utilities.

Page 13: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

CST COST REDUCTION

STRATEGIES

Page 14: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

The purpose is to assess cost efficient and cost effective approaches to reduce Levelized Cost of Electricity (LCOE) for CSP plants in India

Assumptions are key - used physical data inputs from both available bid data and US DOE database, and actual incentives provided by GoI to solar projects

Assessments are done for 1) parabolic trough & power tower; and b) wet and dry (air) cooling methods

With scaling up of CSP in India, majority of future plants will be air-cooled – need to be accounted as an input for cost analysis

Cost Reduction Strategies for CSP in India

14

Page 15: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Assessment Methodology

15

Sensitivity Analysis – Cost Impact for Government

Impact of regulatory/financial incentives and storage eligibility on government cost burden

Sensitivity Analysis – Cost Impact on Developers

Impact of variations in DNI and local conditions on LCOE

Impact of different financial and regulatory incentives on

LCOE

Impact of different technical eligibility criteria

on LCOE

Current Scenario – Parabolic Trough and Power Tower

LCOEs under current scenario using

NREL’s Solar Advisory Model and DNI data for Jodphur (one of the best on DNI resource)

Page 16: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Main Financial and Regulatory Assumptions

Analysis Period 25 years Loan Term 12 years

Inflation Rate 5.5% Loan Rate 11.75%

Real Discount Rate 15% Debt Fraction 70%

Minimum Alternative Tax

18.5% ROE 19%

Property Tax 0% Min required IRR 15%

VAT+ Excise Duties 5% on 100% of

Direct Costs Min required DSCR 1.5

Depreciation Schedule

7% first 10 years | 1.33% afterwards

EX Rs/US$ 45.0 Rs/$

Financial Modeling Exercise

16

Page 17: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Current Scenario in India

17

10

15

20

25

30

35

40

45

50

Air-cooled Wet-Cooled

Parabolic Trough Power Tower

CERC FIT

Page 18: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

10152025303540455055606570

Current Scenario Lower DNI Scenario

Parabolic Trough (Air-Cooled) Power Tower (Air-Cooled)

CERC FIT

DNI Sensitivity Analysis

– Cost for Developers

18

25% decrease in DNI causes LCOE to increase by 25-35%

Page 19: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

10

15

20

25

30

35

40

45

50

Current Scenario Lower Labor Cost Provision of "Free" Land

Parabolic Trough (Air-Cooled) Power Tower (Air-Cooled)

CERC FIT

Local Conditions Sensitivity Analysis

– Cost for Developers

19

Page 20: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

10

15

20

25

30

35

40

45

50

Longer LoanTerm 20

years

ConcessionalFinancing

lowers loanrate to 8%

Higher D/ERatio 75/25

AcceleratedDepreciationwithout FITreduction

GBIs at1.0Rs/kWh

granted

All incentivescombined

Parabolic Trough (Air-Cooled) Power Tower (Air-Cooled)

CERC FIT

Cost Impact in India – Air Cooling

20

Page 21: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

10

15

20

25

30

35

40

45

50

Current Scenario w/ Financial & RegulatoryIncentives

w/ Financial & RegulatoryIncentives and 6 hours of

storage

Parabolic Trough (Air-Cooled) Power Tower (Air-Cooled)

CERC FIT

Financial & Regulatory Incentives and Storage

Eligibility – combined

21

Page 22: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Incentive granted Reduction in

LCOE Cost Effect

Cost Impact for 500 MW

US$ per -1% LCOE

Current scenario + Concessional Financing

-9.5% Cost of guarantees

Not quantifiable

but likely to be very low

Not quantifiable

but likely to be very low

Current scenario + Accelerated Depreciation

-6.5% Lower tax revenues

$ 184 m $28 m

Current scenario + GBIs at 1.0 Rs/kWh

-4.3% Additional

Expenditures $ 464 m $ 108 m

All three of the above

-20.3%

Lower tax revenues + cost of

guarantees + expenditures

6 hrs of Thermal Storage

-13.8% Additional

expenditures $ 2,480 m $ 180 m

Sensitivity Analysis Parabolic Trough -

Cost Impact for Government

22

Page 23: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Incentive granted Reduction in LCOE

Cost Effect Cost Impact for 500 MW

US$ per -1% LCOE

Current scenario + Concessional Financing

-9.4% Cost of guarantees Not quantifiable

but likely to be very low

Not quantifiable

but likely to be very low

Current scenario + Accelerated Depreciation

-6.4% Lower tax revenues $ 148 m $ 23 m

Current scenario + GBIs at 1.0 Rs/kWh

-5.1% Additional Expenditures

$ 457 m $ 90 m

All three of the above

-21.0% Lower tax revenues + cost of

guarantees + expenditures

6 hrs of Thermal Storage

-29.3% Additional expenditures

$ 3,151 m $ 108 m

Sensitivity Analysis Power Tower -

Cost Impact for Government

23

Page 24: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

DNI accuracy matters – LCOE is very sensitive to DNI changes

LCOE much less sensitive to cost of labor and land

Current LCOEs are too high to allow for cost recovery and meeting

financing constraints

Financial and regulatory incentives combined with payment for

electricity generated through storage can lower LCOEs

Allowing for storage is most effective but least cost-efficient way

Concessional finance is still effective and likely to be cost-efficient

Conclusions on Cost reduction strategies on CSP

24

Page 25: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

LOCALISATION OPPORTUNITIES

Page 26: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Localization of Manufacturing Supply Chain (Source eSolar)

26

Assumes 92MWe Direct Steam Plant (w/ 600,000 heliostat ST3, 24 receiver towers)

Notes : High end scenario is dependent on ability to justify installing local manufacturing factory, NRE cost not included Partial items : Drive – excludes gearbox, Camera & Towers – excludes camera specialty parts

LOW END SCENARIO HIGH END SCENARIO

BOMValue at Current

Supply Source

%

Contribution

Estimated

Localization

Value of

Localization

Activities

%

Contribution

Estimated

Localization

Value of

Localization

Activities

%

Contribution

Heliostat

RM frame $6,024,000 3.9% Yes $6,024,000 3.9% Yes $6,024,000 3.9%RM Tape $588,000 0.4% No - No -

Reflector Mirror $10,182,000 6.6% No - Yes $10,182,000 6.6%Drive $54,876,000 35.8% No - Partial $27,438,000 17.9%PCBA $8,785,714 5.7% Yes $8,785,714 5.7% Yes $8,785,714 5.7%Cable $3,514,286 2.3% Yes $3,514,286 2.3% Yes $3,514,286 2.3%Structure $15,891,429 10.4% Yes $15,891,429 10.4% Yes $15,891,429 10.4%

Cleaning System $1,390,000 0.9% Yes $1,390,000 0.9% Yes $1,390,000 0.9%Sensors $164,850 0.1% No - No -

Installation Tools $35,700 0.02% Yes $35,700 0.02% Yes $35,700 0.02%Cameras & Towers $4,707,744 3.1% No - Partial $2,353,872 1.5%FECs $4,588,770 3.0% Yes $4,588,770 3.0% Yes $4,588,770 3.0%

Receivers $28,800,000 18.8% No - Yes $28,800,000 18.8%

Receiver Towers $13,776,000 9.0% Yes $13,776,000 9.0% Yes $13,776,000 9.0%

Total $153,324,492 100% $54,005,898 35.2% $122,779,770 80.1%

Ex-works

Page 27: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

27

Local Installation: Jobs Created (Source eSolar)

Assumptions

Construction and installation of an entire power plant

92 MW solar direct steam facility. Timing is one year.

Location is MENA.

Baseline is USA with efficiency and cost adjustment factors for MENA

Materials and support services job creation is not included Job Class Example

Jobs (site only)

$/Hour Salary

Management supervisor 8 $40 $632,000

Skilled electrician, pipefitter 226 $20 $9,405,000

Unskilled heliostat assembly 523 $10 $10,871,000

Total 756 $20,908,000

Page 28: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

28

Power Plant Operations: Annual O&M (Source eSolar)

Plant Labor Example Jobs

(plant only) $/Hour Salary

Management plant manager 6 $40 $499,000

Skilled electrician, technician 34 $20 $1,414,000

Unskilled heliostat maintenance 27 $10 $561,000

Total Labor 67 $2,474,000

Plant Operations & Maintenance Annual Spend

Solar collector system repair & maintenance (w/o labor) $800,000

Power plant repair and maintenance (w/o labor) $5,500,000

Total Power Plant O&M (includes labor) $8,774,000

Page 29: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

29

Summary: Direct Localization

One Time Impact Jobs Value

Local manufacturing jobs 1,161 $25,396,000

Local construction jobs 756 $20,908,000

Local mfg. material & services – high range

$122,779,000

Total (mfg jobs value included in material & services) 1,917 $143,687,000

Ongoing Operations - Annual Impact Jobs Value

Local Jobs (plant only) 67 $2,474,000

Power Plant O&M (less labor) $6,300,000

Total Annual Impact 67 $8,774,000

(Source eSolar)

Page 30: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Support Job Created

Assumptions

Construction investment multiplier = 1.78

Permanent job multiplier for the power generation industry = 4.21

30

One Time Impact Direct Jobs

Multiplier Support

Jobs Value

Local manufacturing 1,161 1.78 x 2,067 $45,206,000

Local construction 756 1.78 x 1,346 $37,219,000

Total One Time 3,412 $82,425,000

Ongoing Operations - Annual Impact

Direct Jobs

Multiplier Support

Jobs Value

Local Jobs 67 4.21 x 282 $10,420,000

Total Permanent 282 $10,420,000

(Source eSolar)

Page 31: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

31

Localization Summary (Source eSolar)

One Time Impact Jobs Value

Local manufacturing jobs 1,161 Included in material &

services

Local construction jobs 756 $20,908,000

Local support jobs 3,412 $82,425,000

Local material & services – high range $122,779,000

Total 5,329 $226,112,000

Ongoing Operations - Annual Impact Jobs Value

Local plant permanent jobs 67 $2,474,000

Local plant permanent support jobs 282 $10,420,000

Power Plant O&M (less labor) $6,300,000

Total Annual Impact 349 $19,194,000

Page 32: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Local manufacturing readiness in India

Page 33: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Cost reduction potential due to local manufacturing for components

considered for 100 MW PTC plant without thermal storage in India

Page 34: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

Local Content Requirements

All countries want to do this – and develop a base for exports(!)

Requires a critical mass of about 1000 MW (average across several start up markets

Requires that all orders go to a single manufacturer to incentivize investment in a local market and secure a market share

Requires a stable, long pipeline of orders, min. 5 years

Time horizon beyond 2-3 years requires bid price indexation

ISO 9000 series certification of supply chain required

Foundations, roads, electrical works: Locally procured anyway

Apertures/towers: Economic to manufacture locally anyway (>100 MW)

TYPICAL ISSUES – WHY IT RARELY HAPPENS IN FIRST STAGES

Page 35: Concentrating Thermal Solar – lessons from different countries · Concentrating Thermal Solar – lessons from different countries . ... parabolic trough & power tower; ... Concentrating

JUNE 28, 2012

Thank you for your attention

Merci pour votre attention [email protected]