Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
COMPLIANCE REPORT
October 2018 – March 2019
Trivandrum, Kerala.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 2
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 3
COMPLIANCE REPORT
TO
THE CONDITIONS
OF
ENVIRONMENT CLEARANCE ORDER
(1085/EC1/SEIAA/2016)
FOR THE PERIOD OF
October 2018 – March 2019
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 4
INDEX
Sl. No. Particulars Page No.
1. Introduction 06
2. Compliance Report – Specific condition 07
Compliance Report – Green conditions 11
3. Compliance Report – General conditions 15
4. Compliance Report – Specific conditions –
Construction Phase
25
5. compliance Report – Specific conditions – Operational
Phase
36
6. Compliance report – Post Operational Phase 43
8. Annexure 45
9 Plate 60
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 5
LIST OF ANNEXURES
Annexure No. Particulars Page No.
1. Copy of consent from PCB 46
2. Copy of Building permit 51
3. Copy of Environmental Clearance 53
4. Copy of NOC from Fire and Rescue Service 56
5 Copy of monitoring results of Air 57
6. Copy of monitoring results of Sound 58
7. Copy of monitoring results of Water 59
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 6
INTRODUCTION
M/s KIMS Health Care Management Ltd. is an expansion of exist ing
Hospital project at Survey Nos. 1486/1-4-3-2,1486/1-4-3 and others in
Kadakampil ly Vi l lage, Trivandrum Taluk, Trivandrum Distr ict, Kerala . The
construction project was accorded Environmental Clearance for 41,509 sq.mtr of build up
area on 17-03-2018 vide order No. 1085/EC1/SEIAA/2016 by State Environment Impact
Assessment Authority, Kerala.
The half yearly compliance report needs to be submitted as part of general
condition No.22 of Environmental Clearance order by the project proponent.
The compliance report to conditions of the Environmental Clearance for the
period of October 2018 – March 2019 (Second half) is being submitted.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 7
COMPLIANCE REPORT
SPECIFIC
CONDITIONS
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 8
SPECIFIC CONDITION
01 Enhance total car parking facility for 648 cars which will
include mechanical, multilevel and conventional car parking
Will be
complied
At present the instant building is under construction stage. The project Proponent
will provide multilevel, mechanical and conventional parking facility for 648 cars in
its operational phase. The project will execute all possible facilities to
accommodate 648 cars in the project site.
02 Parking facilities for 650 two wheelers Will be
complied
The Parking facility for 650 two wheelers will be provided in its operational phase.
At present the piling is under progress.
03 During construction stage proponent agreed to provide
parking facility in a space away from the site with free to
and fro shuttle service.
Being
complied
The project proponent has identified a place near to the existing hospital to park
the vehicles. The project proponent will ensure hassle free movement and parking
of vehicles those who come to hospital.
04 Rain water storage capacity shall be increased to 3500 KL complied
The capacity of rain water tank has increased in its final drawing which will
construct in the proposed hospital building to face water shortage and harvest the
rain water. this will be constructed during civil work phase.
05 The sewage will be treated and recycled within the site itself Will be
complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 9
The total domestic water requirement of the hospital building will be about 272
KLD. The sewage generated from the proposed hospital project will be treated in
Sewage Treatment Plant having tertiary treatment. The recycled water of about 122
KL will use for the toilet flushing and other recycled water will be used for
horticulture, cooling tower with HVAC system.
06 Exit and entry will be as per revised plan submitted Being
complied
As per the direction of State Environment Impact Assessment Authority, the
project proponent has submitted a revised plan regarding entry and exit. This will
be scrupulously followed in construction and operational phase.
07 Emergency assembly points as shown in the revised
conceptual plan should be provided.
Complied
The project proponent has earmarked an area for emergency assembly at project
site as marked in the conceptual plan. The project proponent is intending to
provide mock drill as part of their Risk and hazard management plan.
08 Adequate safety measures shall be ensured to prevent slop
failure of steep cutting
complied
To prevent the slop failure of steep cutting the project proponent has provided soil nailing
and hillock system at project site. The systematic extraction of earth can provide
necessary slope stability. The degree of slope will be 7.13. The project will give utmost
care to prevent sliding by adopting all possible slope stabilization measures.
09 Excess earth excavated shall be disposed off without
causing environmental problem.
Complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 10
Compliance:
The project proponent is having excess earth in the project site. The excess earth will be
utilised for road construction and similar activities. The project proponent will assure that
the earth is not transporting for filling of wet land and paddy land. The work order has
given to PMK.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 11
COMPLIANCE REPORT
GREEN
CONDITIONS
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 12
GREEN CONDITIONS
01 Adequate rain water harvesting facilities shall be arranged
for
Noted
Compliance:
In construction phase the project proponent is going to arrange Portable tanks for
Rain water harvesting. The project proponent will construct a rain water harvesting tank
with a capacity of 3500 KL for its operational phase.
02 Technology and capacity of STP to be indicated with
discharge point (if any) of the treated effluent.
Noted
Compliance:
The project has installed an STP in the existing hospital. The tertiary treatment of
STP can remove nitrogen, phosphorus, additional suspended solids, refractory organics,
heavy metals, and dissolved solids. The technology intending to adopt is activate sludge
process followed by UASB. The treated water is using for flushing and gardening. One
STP is proposed for the instant hospital building for treating generated sewage water
03 Effluent water not conforming to specifications shall not be
let out to water bodies.
Noted
Compliance:
The sewage generated from the construction site will be channelized to STP. The
project is conscious to prevent letting out effluent water to water bodies. The treated
water will be used for gardening, cooling tower and flushing purpose. Only water
confirming to specification will let out to the public drain system.
04 Maximum reuse of grey water for toilet flushing and
gardening and construction work shall be ensured.
Noted
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 13
Compliance:
The treated water will be used for flushing and gardening. The project proponent
will install dual plumbing system in the project site. The project will reuse the grey water
in operational phase for toilet flushing and gardening with the help of STP.
05 Dual plumbing for flushing shall be done Noted
Compliance:
To reuse grey water the project proponent will install dual plumbing and all WC’s
will be dual flushing this can save water. The gray and black water can be recycled and
reused as domestic purpose by STP.
06 Provision for disposal of e – waste, solid wastes, non-
biodegradables and separate parking facilities for the
building shall be provided.
Noted
Compliance:
There will be suitable provisions for handling of all type of waste in the project site.
The project proponent will follow the rules framed in 2016 for Municipal solid wastes, e
waste and hazardous waste for handing and management. An ample parking space will
be provided for vehicles.
07 Generation of solar energy to be mandatory for own use
and/ or to be provided to the grid
Noted
Compliance:
The project proponent will install solar panel to generate renewable energy. This
initiative can reduce the use of conventional energy.
08 There shall be no compromise on safety conditions and
facilities to be provided by the project proponent, which
shall be ensured for occupation, regularisation or consent
to operate.
Noted
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 14
Compliance:
The project proponent will provide much thrust to safety conditions. The project
proponent has got initial NOC from fire and rescue service. The project will provide prior
concern to safety aspects. The project has a pre planned evacuation plan in case an
emergency situation arises. The project will get final NOC from Fire and rescue services
once all the fire safety equipments installed. The copy of initial NOC form Fire and rescue
service is provided as Annexure No.4.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 15
COMPLIANCE REPORT
GENERAL CONDITIONS
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 16
GENERAL CONDITIONS
01 Rain Water Harvesting capacity should be installed as per
the prevailing provisions of KMBR / KPBR, unless
otherwise specified elsewhere.
Will be
complied
Compliance:
As part of water conservation, the project is planning to construct rain water harvesting
tank with a capacity of 3500 KL in the project site. The project is intending to harvest roof
run off to the Rain water harvesting tanks.
02 Environment Monitoring Cell (EMC) as agreed under the
affidavit filed by the proponent should be formed and made
functional.
complied
Compliance:
The project proponent has constituted an Environmental Monitoring Cell (EMC)
under the chairmanship of Mr. Biju S A (General Manager). The EMC meeting convene
regularly to evaluate and monitor compliance towards the conditions stipulated in the
Environmental Clearance (EC) order.
03 Suitable avenue trees should be planted along either side of
the tarred road and open parking areas, if any, inclusive of
approach road and internal roads.
Noted
Compliance:
To reduce air and noise pollution during the time of transportation of vehicle, the
project will plant various native species as avenue trees and shrubs at either side of the
road. This can prevent PM10 and 2.5 in some extent. The landscape plan will be
submitted along with this report once it is finalised.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 17
04 The project shall incorporate devices for solar energy
generation and utilization to the maximum possible extent
with the possibility of contributing the same to the National
grid in future
Will be
complied
Compliance:
As part of energy conservation, the project is intending to generate and utilize
energy from solar by installing solar panels in the project site. This will help to reduce the
consumption of energy from conventional sources.
05 Safety measures should be implemented as per the Fire and
Safety regulations
Will be
complied
Compliance:
As per norms and guidelines of Fire and Rescue services of Govt. of Kerala, the
project will implement all possible safety measures for the safety of workers. The project
has got NOC from the department for the same and it is attached as Annexure.
06 STP should be installed and made functional as per KSPCB
guidelines including that for Solid Waste Management.
Noted
Compliance:
SEWAGE TREATMENT PLANT
During the operational phase of the project, the expected quantity of waste water
generated from the project will be more than 200 KLD which can be treated in the STP.
The maintenance of STP will be done by an approved agency. The treated water will be
used for flushing and gardening purpose in the project site.
SOLID WASTE MANAGEMENT
The estimated solid waste generation during construction phase will be be collected
separately as Bio – degradable waste and non Bio - degradable waste as per Municipal
Solid Waste Management & Handling Rules,2016. The Bio degradable waste is managed
with bio gas plant. Non bio degradable and recyclable waste will be sold to the vendor.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 18
07 The conditions specified in the Companies Act, 2013 should be
observed for Corporate Social Responsibility (CSR).
Noted
Compliance:
Since KIMS hospital is corporate in nature, constituted CSR committee consists of 3
directors. AS part of CSR (Corporate Social Responsibility) the project proponent is being
executed in the field of health care, Education and Environment.
08 The proponent should plant trees at least 5 times of the loss
that has occurred while clearing the land for the project.
Will be
complied
Compliance:
Eco – restoration is an important part in this residential project. The project
proponent is intending to plant maximum number of tree saplings in the proposed project
site for enhancing vegetative area and bio diversity.
09 Consent from Kerala Pollution Control Board under water
and Air act(s) should have been obtained before initiating
activity
Complied
Compliance:
The project has obtained consent for establishment from Kerala State Pollution
Control Board under Water and Air Act(s) before initiating the activity. The consent to
establish is attached as Annexure No.1.
10 All other statutory clearances should have been obtained, as
applicable, by project proponents from the respective
competent authorities including that for blasting and storage of
explosives.
Complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 19
Compliance:
The project proponent is a renowned hospital group therefore obtained all
necessary approvals from various Government departments and statutory authorities. To
enhance safety and promote environment sustainability, all the conditions stipulated in the
approvals will scrupulously follow. The important approvals are mentioned below.
Annexure No 1 - Consent to Establish - Kerala State Pollution Control Board
Annexure No 2 - Building Permit
Annexure No 3 - Environmental Clearance - State Environmental Impact Assessment
Authority (SEIAA)
Annexure No.4 – NOC form Fire and Rescue Department.
11 In the case of any change(s) in the scope of the project, the
project would require a fresh appraisal by this Authority.
Noted
Compliance:
At present there is no plan to change the scope of project. The proponent will apply
for fresh appraisal to get the Environmental Clearance, in case of any change(s) in the
scope of the project.
12 The Authority reserves the right to add additional safe guard
measures subsequently, if found necessary, and to take action
including revoking of the environment clearance under the
provisions of the Environmental (Protection) Act 1986, to ensure
effective implementation of the suggested safeguard measures
in a time bound and satisfactory manner.
Noted
Compliance:
To improve safety of labours, building, community and environment, the project is
happy to add additional safe guard measures subsequently if the authority found
necessary.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 20
13 The stipulations by Statutory Authorities under different Acts
and Notifications should be complied with, including the
provisions of Water (Prevention and Control of Pollution) Act,
1974, the Air (Prevention and Control of Pollution) Act 1981, The
Environment (Protection) Act, 1986, the public liability
(Insurance) Act, 1991 and EIA notification, 2006.
Noted
Compliance:
To implement all relevant directions and guidelines, the stipulated orders and
directions under different act and notification including EIA notification will be scrupulously
followed. A brief list of various Acts and notifications which are followed by the proponent is
given below
1. The Environment Protection Act,1986
2. The Water (Prevention and Control of Pollution) Act, 1974
3. The Air (Prevention and Control of Pollution) Act, 1981
4. The Public Liability (Insurance) Act,1991
5. The Solid Waste Management Rules, 2016
6. The Construction and Demolition Waste Management Rules, 2016
7. The Hazardous and Other Wastes (Management and Transboundary Movement )
Rules, 2016
8. The E – waste (Management) Rules, 2016
9. The Plastic Waste Management Rules, 2016
10. Kerala Municipality Building Rules, 1999 as amended up to 2013
11. The Companies Act, 2013.
12. Bio Medical Waste Management Rules 2016
14 The environment safeguards contained in the EIA report
should be implemented in letter and spirit.
Will be
complied
Compliance:
The project proponent will execute all safeguards suggested in the EIA report for the
conservation of environment. The EMP will implement in its letter and spirit.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 21
15 Provision should be made for supply of kerosene or cooking gas
and pressure cooker to the labours during construction phase.
Noted
Compliance:
The all provisions such as cooking gas and pressure cooker or hygienic food is
given by the labour contractor. There are nearly 200 labours working in the site and the
labour camp is set up at 200 meter away from the project site. The project proponent make
sure that the labours are provided with good housing, fuel for cooking facilities etc, by the
contractor.
16 Officials from the regional office of MoEF&CC would be
monitoring the implementation of environmental safeguards
should be given full cooperation, facilities and documents/data
by the project proponents during their inspection. A complete
set of all entire document submitted to MoEF&CC should be
followed to the CCF, Regional office of MoEF, Bangalore.
Noted
Compliance:
The project proponent will assure to execute all possible measures for environment
protection. The project proponent is keeping a set of files for MoEF & CC and
environmental conservation activities. The project will extend all support to the officials
from the regional of MoEF&CC for their monitoring on environmental safeguards
implemented in the project site.
17 These stipulations would be enforces among others under the
provisions of Water (Prevention and Control of Pollution) Act,
1974, the Air (Prevention and Control of Pollution) Act 1981, The
Environment (Protection) Act, 1986, the public liability
(Insurance) Act, 1991 and EIA notification, 2006.
Noted
Compliance:
The project proponent will scrupulously follow the condition stipulated in the
Environmental Clearance order.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 22
18. Environmental clearance is subject to final order of the Hon’ble
Supreme Court of India in the matter of Goa Foundation v/s
Union of India in Writ Petition (Civil) No. 460 of 2004 as may be
application to this project.
Noted
19. Any appeal against this clearance shall lie with the National
Environment Appellate Authority, if preferred, within a period of
30 days as prescribed under section 11 of the National
Environment Appellate Authority Act.1997.
Noted
20 The project proponent should advertise in at least two local
news papers widely circulated in the region, one which (both
advertisement and the newspaper) shall be in the vernacular
language informing that the project has been accorded
Environmental Clearance and copies of clearance letters are
available with the Department of Environment and Climate
Change, Govt. of Kerala and may also be seen on the website of
the Authority at www.seiaakerala.org. The advertisement
should be made within 10 days from the date of receipt of the
Clearance letter and the copy of the same signed in all pages
should be forwarded to the office of this authority as
confirmation.
Complied
Compliance:
As per the condition in Environmental Clearance issued by State Environment
Impact Assessment Authority (SEIAA),Kerala an advertisement in two local daily
newspapers (English and Malayalam) regarding Environmental Clearance accorded to the
construction project.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 23
21 A copy of the clearance letter shall be sent by the proponent to
concerned Grama/District Panchayath / Municipality /
Corporation / Urban Local Body and also to the Local NGO, if
any from whom suggestions / representations, if any were
received while processing the proposal. The Environmental
Clearance shall also be put on the website of the company by
the proponent.
Complied
Compliance:
A copy of the Environment Clearance letter was submitted to the Local self
Government. The project proponent did not receive any suggestions / representation from
anywhere while processing the application therefore did not give copy of clearance latter to
any NGO or personal. The project proponent will upload the Environmental Clearance (EC)
Order in the website of the company soon.
22 The proponent shall submit six monthly reports on the status of
compliance of the stipulated EC conditions including results of
monitored data (both in hard copies as well as by e-mail) and
upload the status of compliance of the stipulated EC conditions
including results of monitored data on their website and shall
update the same periodically. It shall simultaneously be sent to
the respective Regional Office of MoEF, Govt. of India and also
the Directorate of Environment and Climate Change, Govt. of
Kerala
Complied
Compliance:
The compliance report is being submitted to the State Environmental Impact
Assessment Authority, (SEIAA), Kerala and the Regional Office of MoEF&CC, Govt. of
India, Bangalore with the results of monitored data both in hard copy as well as mail. The
compliance report and results of monitored data has uploaded in the company’s website.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 24
23 The details of Environmental Clearance should be
prominently displayed in a metallic board of 3 ft x 3ft with
green background and yellow letters of Times New Roman
font of size of not less than 40.
Complied
Compliance:
The project proponent has displayed board at project site containing the details and
validity of the Environmental Clearance as directed by State Environment Impact
Assessment Authority, Thiruvananthapuram. The photograph of the same is attached as
Plate No.1.
24 The proponent should provide notarized affidavit (indicating
the number and date of Environmental Clearance
proceedings) that all the conditions stipulated in the EC shall
be scrupulously followed.
Complied
Compliance:
An assurance in the form of affidavit was already submitted to SEIAA Kerala, states
that all the conditions stipulated in the EC order will be scrupulously followed.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 25
COMPLIANCE REPORT
SPECIFIC CONDITIONS
CONSTRUCTION PHASE
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 26
SPECIFIC CONDITIONS CONSTRUCTION PHASE
01 “Consent for Establishment” shall be obtained from
Kerala State Pollution Control Board under Air and water
Act and a copy shall be submitted to the ministry before
start of any construction work at the site.
Complied
Compliance:
The project proponent obtained consent for establishment from Kerala State
Pollution Control Board under Air (Prevention and control of Pollution) Act, 1981 and
Water (Prevention and Control of Pollution) Act, 1974. A copy was submitted to ministry
along with earlier report.
02 All required sanitary and hygienic measures should be
in place before starting construction activities and to be
maintained throughout the construction phase.
Complied
Compliance:
The project has constructed hygienic toilets and bathing area for the labours in
the construction site and labours camp. The project proponent provided all requires
sanitary and hygienic measures well before the commencement of construction activity.
These facilities will be maintained for labours and labour camp throughout the
construction phase.
03 A First Aid Room shall be provided in the project both
during construction and operation of the project.
Being
Complied
Compliance:
The First Aid facilities have setup as per the guidelines mentioned in BOCW
(Building and other construction Workers Act). The project proponent has been keeping
first aid box in the project site. A brief detail of First Aid Facility kept in the project site
during construction phase is mentioned below.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 27
1. Betadine gargle mint
2. Refresh eye drop
3. Spray – voline
4. Digital thermometer
5. Cotton and Bandage etc.,
Since it is an expansion of existing hospital project, the major cases can be treated in
the hospital.
04 Adequate drinking water and sanitary facilities should be
provided for construction workers at the site, provision
should be made for mobile toilets. The safe disposal of
waste water and solid waste generated during the
construction phase should be ensured.
Complied
Compliance:
. The project proponent has been providing adequate facilities for labours since
the commencement of the construction work. The project proponent ensures the
availability of safe drinking water to all labours. Hygienic toilets are provided with
adequate domestic water in construction phase. The disposal of liquid and solid waste
will be managed as per various rules on waste management and handling in 2016. The
proponent ensures all wastes are disposed with proper care.
05
All the top soil excavated during construction activities
should be stored for use in horticulture/ landscape
development within the project site.
Complied
Compliance:
Excavation and removal of top soil is inevitable in a construction project. A
portion of the top soil excavated during construction activities is stored in project site for
use in horticulture/ landscape development and for other activities within the project site.
A portion of excavated earth is used for construction of public roads. The proponent will
use the stacked topsoil for landscape and green belt development, back filling and
internal road construction in the project site.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 28
06 Disposal of muck during construction phase should not
create any adverse effect on the neighboring
communities and be disposed taking the necessary
precautions for general safety and health aspects of
people, only in approved sites with the approval of
competent authority.
Complied
Compliance:
The muck is an inevitable byproduct of construction. The project proponent could
ensure that the muck is not creating any adverse effect on the neighboring
communities. The muck disposed under necessary precautions for general safety and
health aspects of people. The muck disposed for land filling with the help of experienced
contractor.
07 Soil and ground water samples will be tested to ascertain
that there is no threat to ground water qualities by
leaching of heavy metal and other toxic contaminants.
Complied
Compliance:
To distinguish the quality of ground water in the area, monitoring tests has been
conducting in regular intervals by a private laboratory approved by the Kerala State
Pollution Control Board. The construction of building is for hospital project, therefore the
use of heavy metals and toxic contaminants will be very low. However, the project
proponent is bound to dispose all wastes including toxic contaminants as specified in
various Acts and guidelines of competent authorities. The project proponent is taking
extreme care to dispose all wastes in a good manner.
08 Construction spoils, including bituminous materials and
other hazardous materials, must not be allowed to
contaminate water sources and the dumb sites for such
materials, must be secured note that they should not
leach in to the ground water.
being
Complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 29
Compliance:
The project proponent is following the relevant rules formulated in 2016 for the
handling of construction and demolition wastes. The project proponent is cautious to
preserve the quality of natural resources like soil and water during construction phase.
Therefore the contamination of water due to the improper disposal of construction spoils
and other hazardous materials will not happen in the site. The construction spoils will
keep in a safe place and disposed under existing rules and guidelines. This precaution
can prevent leach in to the ground water. To check the ground water quality the project
proponent is regularly monitoring various parameters of ground water.
9 Any hazardous waste generated during construction phase,
should be disposed off as per applicable rules and norms
with the necessary approvals of the State pollution control
Board.
Being
Complied
Compliance:
All hazardous waste like used oil, oil filters, paint tins etc, generated during
construction phase is being disposed as per applicable rules and norms stipulated in
Hazardous waste management and handling Rules 2016. This will be done in
association with an agency having necessary approvals from the State Pollution Control
Board.
10 The diesel generator sets to be used during construction
phase should be low sulphur diesel type and should
confirm to Environmental (protection) prescribed for air
and noise emission standards
Complied
Compliance:
At present the project proponent is using 3 DG sets with capacity of 120KVA, 63
KVA and 45 KVA. To keep the parameters like Suspended Particulate Matter, Sulphur
Dioxide and Oxides of Nitrogen of ambient air in the vicinity if DG sets, the emissions
from DG set is keeping within the limits. To reduce air pollution and health risks of public
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 30
and residents, the project proponent will try to use DG sets, which emitting low
pollutions.
11 The diesel required for operating DG sets shall be stored in
underground tanks and if required clearance from Chief
Controller of Explosive shall be taken.
Noted
Compliance:
In construction phase, the diesel is keeping in the inbuilt tank of DG sets. If
required more which will store in appropriate Mild steel barrel with capacity of 200 liters
and keeping in a safe room.
12
Vehicles hired for brining construction material to the site
should be in good condition and should have a pollution check
certificate and should conform to applicable air and noise
emission standards be operated only during non – peak hours.
being
complied
Compliance:
To reduce air and noise pollution, the project proponent has instructed and
monitored the condition of all vehicles and a valid pollution check certificate from an
approved agency. In addition that, assured transportation of all vehicles will operate
only during day time and in non – peak hours. This helps to reduce traffic congestions.
13 Ambient noise levels should confirm to residential
standards both during day and night as per Noise
Pollution (control and Regulation) Rules, 2000.
Incremental pollution loads on the ambient air and noise
quality should be closely monitored during construction
phase. Adequate measures should be made to reduce
ambient air and noise level during construction phase, so
as to conform to the stipulated standards by
CPCB/KSPCB.
Being
complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 31
Compliance:
During the time of construction, to maintain the ambient noise level as residential
standard at day and night time, the project will implement various measures in project
site. The project site has already covered with aluminum sheets with height of 10 ft. to
regulate amplification. There will be no work at night time. All measure will help to keep
noise level as residential slandered. The project will implement the measures as per
Noise Pollution (Control and Regulation) Rules, 2000. Incremental pollution loads on the
ambient air and noise quality will closely monitor through an approved laboratory. Since
it is an expansion project of existing hospital the project proponent is taking care to
reduce the sound and its amplification as much as possible.
14 Fly ash should be used as building material in the
construction as per the provision of Fly Ash Notification
of September, 1999 and amended as on 27th August,
2003. (The above condition is applicable only if the
project site is located within the 100 Km of thermal Power
stations.)
Noted
Compliance:
As per the provision of Fly Ash Notification of September, 1999 and amended as on
27th August, 2003, the project proponent need not to use fly ash since it is not located
within the 100 Km of thermal power stations.
15 Ready mixed concrete must be used in building
construction.
Complied
Compliance:
To conserve water and to reduce wastage of construction materials (natural
resources), and air pollution, the project proponent uses Ready mixed concrete in the
site for construction. This will help to reduce the noise generated from the site.
16 Storm mixed control and its re- use as per CGWB and BIS
standards for various applications
Noted
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 32
Compliance:
As part of water conservation, the project is using storm water curing purposes. The
project will store rain water in portable water tank. The stored storm water can be used
inside of the building during rainy days for curing the building. The treated water from
STP can also use during operational phase for flushing, dust suppression and
gardening. The excess treated water from existing STP can also used for construction
purposes
17 Water demand during construction should be reduced by
use of pre - mixed concrete, curing agents and other best
practices referred.
complied
Compliance:
Pre mixed concrete is using in some extent for construction. The project is planning
to use curing agents during its civil work to reduce the water consumption. The project
proponent will execute various measures to reduce water demand during construction
phase. The project will place rain water harvesting tank to reduce the use of water in the
construction site.
18 Permission to draw ground water shall be obtained from
the competent Authority prior to construction/ operation
of the project.
Noted
Compliance:
As per the Central Ground Water Authority, the State of Kerala has not notified and
therefore there is no such procedure of taking permission for ground water abstraction.
As of now the project proponent did not dig a single well for the ground water extraction.
19 Separation of grey and black water should be done by the
use of dual plumbing line for separation of grey and
black water
Will be
Complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 33
Compliance:
The project will install dual plumbing lane in the project to reduce contamination of
water and to separate grey and black water from the source. This will help in the
recycling process of used water. The both line will lead to STP for recycling the water.
20 Fixture for showers, toilet flushing and drinking should
be of low flow either by use of aerators or pressure
reducing devices or sensor based control.
Will be
Complied
Compliance:
All the sanitary equipments will selected on the basis of its water consumption
efficiency. All WC’s will be fitted with dual flushing system to reduce water consumption.
All tapes and showers will be low flow high pressure or fitted with aerators. This
measure can reduce water consumption during its operational phase.
21 Use of glass may be reduced by up-to 40% to reduce the
electricity consumption and load on air- conditioning. If
necessary, use high quality double glass with special
reflective coating in windows.
Will be
Complied
Compliance:
Only high quality double glasses with special reflective coating will be used where it
is necessary. To reduce the heat from glass windows, the project will use curtain inside
in all air conditioned rooms. The project will reduce the use of glass to maximum extent
possible this can reduce load on air – condition.
22 Roof should meet prescriptive requirement as per energy
Conservation building code by using appropriate thermal
insulation material to fulfill requirement
Will be
complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 34
Compliance:
To reduce the effect of heat, the project proponent will install thermal insulation
materials on roof to fulfill the requirement.
23 Opaque wall should meet prescriptive requirement as per
energy Conservation building code which is proposed to
be mandatory for all air conditioned spaces while it is
inspirational for non air-conditioned spaces by use of
appropriate thermal insulation material to fulfill
requirement
Will be
complied
Compliance:
The project is a hospital building therefore most of the rooms will be separated by solid
bricks. This will reduce the load of air conditions installed in each houses. The opaque
wall may construct with solid cement bricks, wooden materials and glasses.
24 The approval of the competent authority shall be
obtained for structural safety of the buildings due to
earthquake, adequacy of fire fighting equipments, etc. as
energy Conservation building code protection measures
form lighting etc.
Being
Complied
Compliance:
The building design has good structural stability to face all situations including
natural disasters like earthquake in zone III , as stipulated under Part – 6 ( Structural
Design) of the National Building Code of India, 2005 and other relevant codes. Lightning
conductor will install on top of the project , electrically bonded using a wire or electrical
conductor to interface with ground or "earth" through an electrode. This will protect the
structure in the event of lightning strike. All fire fighting equipments will be provided in
the project to face an emergency situation.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 35
25 Regular supervision of the above and other measures for
monitoring should be in place all though the construction
phase, so as to avoid disturbance to the surroundings.
Being
Complied
Compliance:
The project proponent has constituted an Environmental Monitoring Cell (EMC). The
EMC meeting will convene regularly to evaluate and monitor compliance towards the
conditions stipulated in the Environmental Clearance (EC) order.
26 Under the provision of Environment (protection) Act,
1986, legal action shall be initiated against the project
proponent if it was found that construction of the project
has been started without obtaining environment
clearance.
Noted
Compliance: The project started its construction only after obtaining Environmental
Clearance from State Environment Impact Assessment Authority, Kerala.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 36
COMPLIANCE REPORT
SPECIFIC CONDITIONS
OPERATION PHASE
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 37
OPERATIONAL PHASE
01 The installation of Sewage Treatment Plant (STP) should
be certified by an independent expert and a report in this
regard should be submitted to the Ministry before the
project is commissioned for operation. Treated effluent
emanating from STP shall be recycled/reused to the
maximum extent possible. Treatment of 100% gray water
by decentralized treatment should be done. Discharge of
unused treated affluent shall conform to the norms and
standards of the state Pollution control Board.
Necessary measures should be made to mitigate the
odour problem from STP.
Will be
complied
Compliance:
To reuse the used water generated from the proposed residential project, The PP will
install an STP with adequate capacity. The treated water from STP will be reused for
flushing and gardening. odour problem from the STP will mitigate through the measures
mention below.
1. Proper design with the consultation of experienced STP suppliers
2. Regular cleaning of bar screen
3. Assure disused aeration in equalization tank
02 The solid waste generated should be properly collected
and segregated. Wet garbage should be composted and
dry/inert solid waste should be disposed of to the
approved sites for the land filling after recovering
recyclable material.
Will be
complied
Compliance:
Solid waste management is an important activity in its operational phase. The collection,
segregation, treatment and disposal will be in accordance with the Municipal Solid Waste
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 38
(Management & Handling) Rules, 2016. For the sustainable disposal of Municipal Solid
Waste to be generated from the proposed residential project, the following measures are
proposed:-
Segregation of Municipal Solid Waste (MSW)
The segregation of Municipal Solid Waste to Bio- Degradable and Non – Degradable is
proposed to be achieved by providing colour coded bins in appropriate areas. (Green
colored bins for Bio Degradable waste and Blue colored for the Non – Bio degradable
waste.) and one bin will be there for collection of domestic hazardous waste.
Bio- Degradable and Non bio degradable Municipal Solid Waste
Bio gas plant or bio bins will install in the project premises to handle the bio – degradable
wastes generated from the project. Non bio degradable solid wastes are sold to the local
vendors.
03 Diesel power generated sets proposed as source of back-
up power for elevators and common area illumination
during operation phase. DG should be of enclosed type
and conform to rules made under the Environment
(protection) act, 1866. The height stack of DG sets should
be equal to the height needed for the combined capacity of
all proposed DG sets. Use low sulphur diesel. The location
of the DG sets may be decided with in consultation with
State Pollution control Board.
Will be
Complied
Compliance:
. At present the use of DG set is low therefore the use of diesel is also low. The
proponent is tried to use low sulphur diesel but it is not available in the local market.
04 Noise should be controlled to ensure that it does not
exceed the prescribed standards. During the night time the
noise levels measured at the boundary of the building
shall be restricted to the permissible levels to comply with
the prevalent regulations.
Being
Complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 39
Compliance:
The main sources of noise will be from playing of vehicles, DG sets and other
construction equipments. The all machines are regularly maintains and no work at
night time. The residential project needs to reduce the noise maximum extent
possible for a healthy environment.
05 The green belt of the adequate width and density
preferably with local species along the periphery of the
plot shall be raised so as to provide protection against
particulars and noise.
Will be
complied
Compliance:
The project proponent is intending to develop green belt with adequate width and density
in its first phase. The proponent will plant more species in the landscaping area of project
which is under construction.
06 Weep holes in the compound wall shall be provided to
ensure natural drainage of rain water in the catchment
area during the monsoon period.
Will be
complied
Compliance:
To ensure natural drainage of rain water during the monsoon period, the project
proponent will provide weep holes in compound wall where ever it is needed.
07 Rain Water harvesting for roof run-off and surface run-off,
as plan submitted should be implemented. Before
recharging the surface run-off, pre- treatment must be
done to remove suspended matter, oil and grease. The
bore well for rain water recharging should be kept at least
5 mtrs. Above the highest ground water table.
Will be
Complied
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 40
Compliance:
As part of rain water harvesting, the project proponent will collect rain water from the
rooftop to the rain water harvesting tank.
08 The ground water level and its quality should be
monitored regularly in consultation with Central Ground
water Authority.
Noted
Compliance:
To assure the quality of ground water the project proponent regularly monitor ground
water samples with the help of private laboratory approved by Kerala State Pollution
Control Board.
09 Traffic congestion near the entry and exit points from the
roads adjoining the proposed project site must be
avoided. Parking should be fully internalized and no public
space should be utilized.
Will be
Complied
Compliance:
The proposed project has taken all measures for the easy movement of vehicles near the
entry and exit points from the roads adjoining the project site and provided enough
parking spaces for vehicles in the residential project. The drive way has also sufficient
width to move vehicles.
10 A report on the energy conservation measures confirming
to energy conservation norm finalize by Bureau of Energy
Efficiency should be prepared incorporating details about
building materials & technology, R & U Factors etc, and
submit the Ministry in three months time.
Noted
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 41
Compliance:
The report on energy conservation measures in line with Bureau of energy Efficiency and
the materials & technology will be prepared and submitted the ministry once it is finalize.
11 Energy conservation measures like installation of CFLs/
TFLs for the lighting the areas outside the building should
be integral part of the project design and should be in
place before project commissioning. Use CFLs and TFLs
should be properly collected and disposed off/sent for
recycling as per the prevailing guidelines/ rules of the
regulatory authority to avoid mercury contamination. Use
of solar panels may be done to the extent possible.
Will be
Complied
Compliance:
As part of energy conservation, the project proponent will install wide range of LED lights.
The project proponent will also instruct the allotters to use LED lights as possible. The
project will install solar panels for lightening in common area. The discarded
LEDs/CFls/TFLs will properly collect and dispose for recycling as per the prevailing
guidelines to prevent mercury contamination.
12 Adequate measures should be taken to prevent odour
problem from solid waste processing plant and STP.
Noted
Compliance:
The project proponent will appoint an experienced agency to install the STP. To prevent
odour problem from STP, the project proponent will sign an agreement with suppliers of
STP for proper maintenance and will adopt following measures
1. Proper design with the consultation of experienced STP suppliers
2. Regular cleaning of bar screen
3. Assure disused aeration in equalization tank
4. Regular maintenance of Sewage Treatment Plant
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 42
13 The building should have adequate distance between them
to allow movement of fresh air and passage of natural
light, air and ventilation
Complied
Compliance:
To allow proper movement of fresh air, ventilation and natural light, the project has
provided adequate distance between the first phase and constructing phase. The natural
light helps to reduce energy consumption.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 43
COMPLIANCE REPORT
POST
OPERATIONAL PHASE
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 44
POST OPERATIONAL PHASE
01 Environment monitoring committee with defined
functions and responsibility should foresee post
operational environmental problems e.g. development of
slums near the site, increase in traffic congestion, power
failure increase in noise level, natural calamities, and
increase in suspended particulate matter etc. solve the
problem immediately with mitigation measures.
Will be
complied
Compliance:
The Environment monitoring committee will function to execute the condition stipulated
in the Environmental clearance order and the suggestions mentioned in the EIA report.
The project proponent will start to execute the imitative measures when work of the
project starts.
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 45
ANNEXURE
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 46
Annexure No.1
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 47
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 48
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 49
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 50
Consent from PCB
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 51
Annexure No.2
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 52
Building Permit
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 53
Annexure No.3
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 54
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 55
Copy of EC order
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 56
Annexure No. 4
Fire NOC
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 57
Annexure No. 5
Copy of Air
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 58
Annexure No. 6
Copy of Noise
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 59
Annexure No. 7
Copy of Water
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 60
PLATE
Compliance Report KIMS Health Care Management Ltd.
October 2018 – March 2019 Page 61
Late No.1
EC board